http://floridawaterdaily.com. On 6/8/2015, the St. Augustine City Commission reviewed the City's Capital Improvement Plan.
Citation preview
June 8, 2015 City Commission Special Meeting
Utility Fund
Agenda
2015 Baseline Assessment
City of St. Augustine Report Card Grade
Assisted by: Applied Technology & Management, Inc.
Grade C
Replacement Value $36,000,000 Refurbishment Cost $15,350,000
WTP Capacity: 6.5 mgd Lime: 4.5 mgd RO: 2 mgd Supply: 7 Deep Wells + 1 Surficial Well Storage: 3.5 Million Gallons
Water Treatment Plant
Grade C Replacement Value $26,500,000 Rehabilitation Cost $11,600,000
Wastewater Treatment Plant
Capacity: 4.95 mgd Secondary Treatment Surface Water Discharge Permit 2019
Grade
C
Gravity Mains 79 Mi
Force Mains 61 Mi
Manholes 2100 Ea
Lift Stations 75 Ea
Replacement Value $176,900,000 Rehabilitation Cost $32,354,000
Sewer Collection
Grade C
13,000 Accounts 200 Miles of Pipelines 30% Cast Iron Pipe
Replacement Value $182,600,000 Replace Cast/Galvanized $59,855,000
Water Distribution
Water Meters 13,000 Accounts
>2,000 Meters Over 20 Yrs
41%
33%
26%
Meter Age
20 years
Public Works Asset Condition Status (2015)
Service Asset Replacement
Value
Overall Asset Condition Grade
Estimated Asset Rehabilitation
Cost
Water Distribution
$182,600,000 C $59,855,000
Water Treatment $36,000,000 C+ $15,350,000
Sewer Collection $176,900,000 C $32,354,000
Wastewater Treatment
$26,500,000 C $11,600,000
Overall $389,600,000 $139,806,000
Accomplishments
$-
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
Water Sewer WTP WWTP
Utility Capital Investments
2011-Present
Reserves
2012 Bond
2011 Bond
$18.8 Million Completed or Underway
Summary Major Projects
Charlotte Street Reconstruction
Charlotte between King & Bridge 870 L.F. Replace watermain, sewer refurbishment Surface stormwater Base restoration and historic bricks
FY 2016 General Fund $ 629,290 Stormwater Fund $ 25,000 Utility Fund $ 425,000 Total $1,079,290
King Street
Bridge Street
San Marco Watermain Replacement
San Marco between Cinncinnati & Piccolata 6,000 LF 10-inch Cast Iron Replace with 12-inch PVC
FY 2016 Design $ 290,000 FY 2017 Construction $2,900,000 Total Project: $3,190,000
Water Conservation Pilot Area
Phase 1 FY2015/2016 $292,050 Total Project
Rate Study Conservation Rate Structure (FY14)
Meter Change-Out Pilot Area Heritage Park
SJRWMD Grant ($89,760)
City Cost $202,290
Questions/Discussion? .........Next.......
The Financial Plan