Upload
vannguyet
View
214
Download
1
Embed Size (px)
Citation preview
Project Report on
Study of Price Variation Clauses in long term Contracts in Procurement
Submitted by
Sri Rakesh Gupta CMM/CR
Facilitated by
Sri Ravij Seth FA & Sr. Professor (Finance & PPP)/IRITM/Lucknow
Administrative support by
Sri Kishor Mehta CMI/IRITM/Lucknow
1 April 2013
© Indian Railways Institute of Transport Management, Lucknow (Uttar Pradesh)
2
C M M ( C e n t r a l
R a i l w a y )
I n d i a n R a i l w a y s
9 9 8 7 6 4 0 7 5 2
4 / 1 / 2 0 1 3
Author: Rakesh Gupta
Four Cases of Price Variation Clauses have
been studied and a set of guidelines has been
evolved to be used while creating long term
contracts
Study of Price Variation Clauses in long term contracts for Procurement
3
TABLE OF CONTENTS
Declaration ...................................................................................................... 4
Introduction ..................................................................................................... 5
Price Variation Clauses ..................................................................................... 7
How it is useful to government .................................................................................... 7
Indexes used in PVC’s ...................................................................................... 8
Wholesale price index ............................................................................................... 8
All India CPI for Industrial Worker: ............................................................................... 8
Published raw material price: ...................................................................................... 8
PV Clauses Generally Used In Railways ............................................................... 9
Based on cost of raw material cost .............................................................................. 9
P.V. Clause for GRSP’s in Engineering Contracts ............................................... 10
Precautions ................................................................................................... 11
Some Interesting Cases .................................................................................. 12
Case 1: D.A. Gas ............................................................................................ 13
Major lapse on the part of SPC ................................................................................. 15
Case 2: Battery .............................................................................................. 16
Case 3: Cable ................................................................................................. 18
Case 4: Nickel Battery ..................................................................................... 20
What should be done .............................................................................................. 21
Concluding Remarks & Recommendations ........................................................ 21
DO’S ..................................................................................................................... 22
DON’T s ................................................................................................................ 22
References .................................................................................................... 23
4
Declaration
“I declare that the project on “Study of Price Variation Clauses in long term contracts
for Procurement” is submitted by me on completion of course on the 1st April 2013 to
the Indian Railways Institute of Transport Management (IRITM), Lucknow.
My report may be used by Indian Railways/ IRITM for official purpose.”
Date Signature
Place Name
Designation
5
Introduction
Indian Railways is procuring large quantity of material for its maintenance of rolling stocks in
Railway workshops and for execution of various types of works involving laying of track, signaling
cables, over head equipment, railway electrification etc.
The material procured is used over a spread of time extending from few months to more
than a year. Optimizing the timing of procurement is not possible & even if we procure large
quantity of material at a time and achieve economy of scale, carrying large inventory and risking
obsolescence, damage, and pilferage may lead to be uneconomical. There for it is best to get
material when it is required and keep minimum inventory. In order to get economy of scale and to
award a good quantity to contractor to make it more attractive it is best enter into a long term
contract with flexible provisions of delivery schedules or ordering under a rate contract valid for
longer period of time.
In order to make such contracts successful these contracts should have enough safe guard
against inflation which some times goes even beyond 10% and make the contracts financially
unviable. This leads to failures and avoidable arbitrations and risk purchases besides delaying the
completion of projects. On Indian Railways Price variation clause and statutory variation clause are
made part of contract condition to safeguard against general inflation and any statutory variation
due to changes in duties and taxes.
P.V. Clause is also very useful in comparing the last purchase rates of same or other
Railways for the purpose of justifying the rate proposed to be accepted.
However ample precautions should be taken whenever a P.V. Clause is used in any
contract, as its application at lower level is sometimes not very clearly understood. Some
instances have come to notice that large amount of money is siphoned out to some greedy and
shrewd contactors in connivance or out of ignorance due to scrupulous Price variation clauses.
The amount of PVC claims sometimes exceeds the value of contracts itself.
6
In this project the various types of price variation clauses and precautions to be observed
while operating price variation clauses will be discussed in detail with help of actual case studies.
7
Price Variation Clauses
Why do we need Price Variation Clauses? The purpose of price variation clauses is to
compensate to the contractor for the inflation in the input costs, be it labour, raw material,
exchange rate etc. However it does not generally compensate the full escalation in input cost but
only partly. The fixed component of the cost such as infrastructure or installation cost is not
compensated. Sometimes even all the components of raw material are not compensated. (IEEMA)
How it is useful to government
1. The biggest benefit of price variation clause is ,it acts as guaranty to the successfully
execution of contracts.
2. Avoid retendering, risk purchase, arbitrations.
3. Avoid delays in completion of work and help implementing the project in time and to get the
revenue earning started early.
8
Indexes used in PVC’s
Wholesale price index
• Published by Ministry of commerce & industries, office of economic adviser.
• Consists of mainly three component
� Primary articles 20.12% (Food articles i.e. Cereals, rice pulses, non food articles, fibers,
minerals, oils etc.)
� Fuel & Power 14.91 % (Petrol, diesel & petroleum gas)
� Manufactured products 64.9 % (Food products, sugar beverages, textiles, minerals,
metals, machinery & plant)
All India CPI for Industrial Worker:
• Published by Ministry of Labour. It represents the average cost of industrial worker
throughout India.
Published raw material price:
In some PVC,s direct price of raw material published by a nominated agency is also used. For
example, in case of batteries the price of lead published by Hindustan Zinc Ltd a GOI undertaking
is used for escalating prices of batteries.
For items made of predominantly steel, steel prices published by M/s SAIL is used, i.e. supply of
rails or its fittings such as fishplates, steel sleepers, E.R. Clips etc.
9
PV Clauses Generally Used In Railways
Based on cost of raw material cost
Example: Batteries
P1 = P0 + (Pbi - Pbo ) * F
Pi : Price of battery to be paid.
Po : Price of battery contracted in AAL.
Pbi: Lead price one month prior to the date of offeringmaterial for inspection.
Pbo: Lead price one month prior to the date of opening of tender.
F : Factor of lead content in the battery.
Example: Signaling cables
The PVC formula generally used for signaling cables in generalized form is produced below. The
variation factors will change depending upon the size of cable and the quantity of particular raw
material used for manufacturing a particular size of cable.
P = Po + Cuf ( Cu – Co ) + Ccfu ( Cc – Cco ) + Fef ( Fe -Fo)
Cuf : Copper variation factor
Ccfu : PVC compound Variation factor
Fef : Ferrous variation factor
Cu/Cuo : Copper prices one month prior to the date of offering of material for inspection
and that of opening of tender respectively
Cc/Cco : PVC compound prices one month prior to the date of offering of material for
inspection and that of opening of tender respectively
Fe/Feo : Ferrous prices one month prior to the date of offering of material for inspection
and that of opening of tender respectively
10
P.V. CLAUSE FOR GRSP’S IN ENGINEERING CONTRACTS
P = Po/100 *( 20 + 46Ci/Co +14Ii/Io + 10Li/Lo + 10Fi/Fo )
Where,
P0 /P = Accepted rate /Updated rate per no.(Net of all CENVAT Credits available)
Ci /Co = Average month price of natural rubber (RSS-4) as circulated by Indian Rubber Board as
prevalent during the month just preceding the month of inspection/ TOD
Ii /Io = WPI for “Basic Inorganic Chemical” prevalent during the month just proceeding the month
of inspection/TOD, as per Economic Advisor, Ministry of Industry web site http://eaindustry.nic.in
as per series 2004-05.
Li /Lo = All India Consumer Price Index for Industrial Workers for the month just preceding the
month of inspection/TOD, as per Labour Bureau, Ministry of Labour web site
http://labourbureau.nic.in .
Fi/Fo = WPI for Fuel and Power as prevalent during the month just proceeding the month of
inspection/TOD, as per http://eaindustry.nic.in as per series 2004-05.
11
PRECAUTIONS
• Scrupulous PVC could lead to siphon out huge money through PVC claims.
Always use standard PVC based on published Prices or Indexes by Government
agencies or well-reputed agency, which has no chances of manipulation.
• Incorrect or no updating of pries quoted by tenderers could lead to wrong
decisions.
• Base date for raw material price while seeking quotes should be defined in the
tender and it should be as close to TOD as possible.
• While comparing the rates with the last accepted rates the PVC of last contract
should be clearly understood and its rates should be brought to the same level
for comparison.
12
Some Interesting Cases
Few cases are discussed here to make the understanding of P.V. Clause clear.
1. CASE GAS
By accepting a wrong P.V. Clause Railway had to pay Rs 4.77cr for PVC claim against a
contract valuing just Rs 28 Lakhs for supplying D.A.Gas to a Railway workshop in year
1986.
2. CASE BATTERY
By quoting at lower raw material base price the level tender committee was brought down
and high value tender case was decided at lower level. The quality of decision making
compromised.
3. CASE CABLE
By quoting at different base date of raw material the inter-se ranking changed.
4. CASE NICKEL BATTERY
While comparing the last purchase rates of other Railways PVClause was ignored as it was
not very explicitly indicated on the body of supply order. Other Railways kept placing orders
for many years justifying their rates with their own or other Railway without PVC.
13
Case 1: D.A. Gas
To tide over emergency situation on a Railway Workshop a Spot Purchase Committee (SPC) was
nominated to procure Dissolved acetylene gas on 13.10.86 for the monthly consumption of
November 86 quantity 13500CUM. SPC called quotations from 6 regular sources due to open on
25.10.86.
T1 T2 T3 T4 T5 T6
Basic
rate/100cum
4280 4875 4390 5500 5425 5443
D&C 50 125 215 0 200 292
Maintenance 75 0 0 0 0 0
L&Unl 15 0 0 0 0 0
ED 0 0 661 0 0 0
ST 0 0 202 0 217 218
Total rate
/100cum
4420 5000 5468 5500 5876 5953
Rent Free 7
days
Rs
1/cyl/day
thereafter
Rs0.6 for
7day and
Rs1/cyl
thereafter
Free
7days
Rs 1/cyl
thereafter
Free
7days
Rs 1/cyl
thereafter
Free 7days
Rs 1/cyl
thereafter
Free 7days
Rs 1/cyl
thereafter
Discount 0 2% for
8000cum
or more
15%for
4000cum or
more
Tenderers T2, T5, & T6 had quoted there prices with P.V. Clause and others quoted firm prices.
The comparative statement did not indicate the P.V. Clause quoted by tenderer nor was any other
comparative statement prepared duly considering the PVC.
The PVC quoted was not a standard PVClause issued by any agency and the base rate of calcium
carbide used for PVC was also neither same nor supported by any published document of the
calcium carbide manufacturer. It was different than the PVC used by DGS&D in their Rate
contract. One tenderer even insisted to believe the procurement price of calcium carbide certified
by his charted accounted.
14
The Price Variation Clauses quoted by the tenderers were as under.
1. PVC by T2: The prices of D.A gas will increase / decrease by Rs 6 per CUM for every
increase / decrease of Rs 15 PMT the average quarterly cost of procurement of calcium
carbide. The quoted prices are based on the calcium carbide procurement price of Rs 8600
PMT. Railways will accept the certificate of the Charted accountant furnished by us. The
average quarterly price will be determinded on April, July, Oct, and Jan.
2. PVC by T5: The price of Dissolved Acetylene gas are based on the calcium carbide price of
Rs 9248.57 PMT F.O.R. contractor’s factory at Faridabad as on 30.06.1986. The prices of
D.A. gas under this contract will revise quarterly based on the quarterly average cost of
calcium carbide and will increase/ decrease by Rs 6 per 100 CUM for every increase /
decrease of Rs 15 PMT on the cost of calcium carbide quoted above.
3. PVC by T6: The price of Dissolved Acetylene gas are based on the calcium carbide price of
Rs 9753 PMT F.O.R. contractor’s factory at Faridabad as on 30.06.1986.
4. The prices of D.A. gas under this contract will revise quarterly based on the quarterly
average cost of calcium carbide and will increase/ decrease by Rs 6 per 100 CUM for every
increase / decrease of Rs 15 PMT on the cost of calcium carbide quoted above.
Spot Purchase Committee recommended and competent authority accepted the recommendation
to place order on more than one source to take care of any eventuality of failure of any one source.
Order for 8100cum was placed on T1 and remaining 3500 cum D.A.gas was ordered on T2 as per
above comparative statement.
Similarly six such orders were issued over a period of six months because the DGS&D Rate
contracts for D.A. gas were not available for that period. The T2 tenderer could secure like this six
orders for supply of total 57100 CUM of D.A. gas to the workshop. Firm supplied the complete
quantity of gas within specified delivery period and submitted his bills for payments as per the
purchase order from 16.9.86 to 4.5.87. The total amount of the bill claimed was Rs 28 lakhs
without PVC claim.
Subsequently firm raised bills against each supply order for claiming price variation as per the
clause quoted by firm in their quotation and also accepted by Railway as the same terms &
conditions were attached with the PO as mentioned by supplier in their quotation. The total bill
claimed was Rs 2,30,68,832.25/-.
15
This bill was rejected by Railways on the plea that P.V. Clause mentioned in the quotation was
erroneous as variation of Rs 6 per CUM was mentioned instead of per 100 CUM. Railway also
issued a letter on 28.5.1988 withdrawing PVClause which was protested by supplier to General
Manager, and sought Arbitration.
The Arbitrator issued award in favor of Supplier for payment of claim with interest from 31.5.88 to
19.6.1999 at rate of 6% per annum Rs 1,26,35,399.43/- and total amount to Rs 3,57,23.531.68/-.
Railway challenged the award in District court and got the orders quashed. Firm appealed in High
court and got the decision in his favor on 25.2.2004 with additional interest charges and total
amount increased to Rs 4,77,52,189.51/-.
Now Railway appealed in Supreme Court where it has been admitted on the condition of
deposition of total amount with Supreme Court who accepted the plea that public money could not
be allowed to be siphoned out in such huge sum just for the mistake or connivance of few Railway
officials.
The Supreme Court bench ruled:
On perusal of the Divisional bench we find that while confirming award of the arbitrator the issue
was not examined in proper prospective and to its full extent.
In course of hearing of parties the council for the respondent was therefor directed to find out as to
whether he can come forward with a suggestion in order to put an end to this long drawn
legislation.
Having heard the councils of the parties we are convinced that the suggestion put forward by the
learned councils fair and reasonable and that by directing the appellant to pay Rs 25 lakhs toward
escalation along with sum of Rs 58 lakhs by way of interest roughly @ 9% as awarded by
Arbitrator and further sum of Rs 7.0 lakhs by way of litigation cost. In all a sum of Rs 90 lakhs is to
be paid by appellant to the respondent.
(Union of India & ORS. Versus M/S. Audhyogic Gases PVT. LTD., 2013)
Major lapse on the part of SPC
• The comparison of the rates should have been done on same level at same base price of calcium
carbide for determining the inter-se ranking of offers. After application of PVC at same base rate of
Rs 9753 pmt as on 30.06.88 the revised comparative ranking of offers will be like this.
Rates in Rs per 100 CUM
16
T1 T2 T3 T4 T5 T6
Original basic rate 4280 4875 4390 5500 5425 5443
Updated basic rate 4280 50995 4390 5500 5626.77 5443
Updated all inc
rate
4420 51120 5468 5500 6059.84 5953
Inter-se ranking L1 L6 L2 L3 L5 L4
• It will be appreciated that by applying P.V. Clause the whole ranking is changed. The T2 is now
highest bidder and therefore does not deserve any order.
• It was a Spot Purchase Case and material was required immediately. Quotations were opened on
25.10.88 for supply in November so no P.V. Clause should have been accepted as it was a very
short term contract which would not involve any change in input cost. Even if some firm had
quoted PVC the same should have been frozen after revising tabulation on the date of tender
opening and contract should have been placed without P.V.Clause.
• In case P.V. Clause was to be used it should made part of tender condition it should be a standard
clause, might be same as DGS&D rate contract and variation should based on the rate
published by a government agency or at least a agency with high credential.
Case 2: Battery
Tenders were called to procure VRLA batteries 2V/300AH quantity XXX no of sets. Tenderers may
quote P.V.Clause with base lead price published by M/s HZL one month prior to date of opening of
tender 17.7.2012.
Following offers were received as tabulated below with the base lead price as indicated by them.
Name T1 T2 T3
PVC Base
Rs/MT
88000 88000 145900
Basic Rate 3675 3750 4364
ED % 12 12 12
Ed cess % 3 3 3
CST % 5 5 5
17
As per
tender
condition,
the price of
lead prevailing one month prior to TOD was to be used for the deciding the inter-se position. The
price of lead on 18.06.2012 was Rs 124600 PMT. The tabulation was revised as under. PV Clause
is with every increase/decrease of lead price by Rs 100 PMT the battery rate will
increase/decrease by Rs 1.27 each.
Up dated
Basic rate 4139.82 4214.82 4093.49
All inc rate 4884 4972.56 4829.42
Rank L2 L3 L1
This kind of quotes may have following implications which can even affect the decision making
process:
• The inter-se position of tenderers is changed after converting the basic rate to the base
rate of raw material as per tender condition. At lower level tender committee it is prone to
mistake.
• By quoting rates at lower base rate of the raw material, the value of tender will be lower and
the level of tender committee will be at lower level and the quality of decision could be
compromised.
• By quoting at higher base rate of raw material initial payment is released at higher rate and
firm never returns the PVC amount back to Railways. Railway seldom claims the same and
it leads to huge losses to Railways.
Freight 0 0 0
All inc rate 4335.69 4424.18 5148.76
Rank L1 L2 L3
18
Case 3: Cable
Tenders were invited to procure PVC insulated armored unscreened, copper conductor
underground Railway signaling, cable size 9core x 1.5 sq.mm.to IS S-63 2007. Total qty 235.48
km. Tender due date 1.4.2010 and tenderers to quote the rates on PVC as per IEEMA formula on
base rate dated 1.1.2010.
The tabulation statement as downloaded from IREPS website is as below.
Exhibit
Name T1 T2 T3 T4 T5 T6
Offered
Quantity 235 235 235 235 235 235
Basic rate/unit 78310 78000 86400 83148 84600 83000
ED % 10 10 10 10 10 10
Cess on ED % 3 3 3 3 3 3
CST % 5 5 5 4 4 5
Freight 1800 3000 3400 2500 1000 2500
Total
Ail incl. Rate 92494.73 93335.70 94120 97880.73 98046.35 98626.45
PVC Base dt 1.2.10 Firm 1.2.10 1.2.10 1.1.10 1.2.10
Rank L1 L2 L3 L4 L5 L6
The IEEMA P.V.Clause was as under
P = Po + Cuf ( Cu – Co ) + Ccfu ( Cc – Cco ) + Fef ( Fe -Fo)
Copper (Cuf = 0.117 ) PVC compound (Ccuf= 0.241 ) Ferrous (Fef =0.383)
The prices of three components at different stages were as under.
19
Material/dates 1.1.10 1.2.10 1.3.10
Copper 377834 353062 376792
PVC compound 92000 94500 96000
Ferrous 53000 53000 53000
The tender condition was, to quote PVC as per IEEMA formula on base date 1.1.2010 therefore for
deciding inter-se position, all the offers were converted to base 1.1.2010 as below
In this case the inter-se ranking position has changed by transforming the rates to the date
specified in the tender condition for PVC. This could lead to erroneous decision
Following deficiencies were noticed in this case:
1. The PVC quote date is normally the for which latest IEEMA rates/indexes would be
available on the date of tender opening. In this case it would be 1.2.2010. Specifying a different
date
might
have
lead to
some
tenderers quoting 1.2.2010 base date who ultimately stand looser of contract.
2. PVC formula was not defined in the tender condition.
3. The TOD should normally be after 7th of the month so that IEEMA circular of previous month
is available and tenderer may with latest rates available for workout its cost.
Updated
Basic 80605.8 78000 88695.8 85443.8 84600 85295.8
All Inc rate 95153.6 93335.7 96530.6 100514.3 98046 101285.3
Revised Rank L2 L1 L3 L5 L4 L6
20
CASE 4: NICKEL BATTERY
The Nickel Battery is used in 3 Phase Electric Locomotive having advantage of large service life
and less maintenance if comparison to Lead Acid Batteries used in Conventional Locomotives.
The Nickel Cd Battery Loco Set consists of 26 batteries of 3.6 V each. The total weight of battery
set is 748 kg (approx.)
The above item was introduced on Indian Railways in January 2006. Since then, it has been
regularly procured on yearly basis by Indian Railways (both by Production unit and Zonal Railways
as well). As most of the other items of Electric Loco this item is also restricted to be procured from
CLW approved sources wherein two sources are approved viz. i) M/s HBL, Bangalore – Part-I; ii)
M/s AMCO Soft, Bangalore – Part-II.
CLW finalized a purchase in early 2007 for this battery with following PVC formula:
“The prices are based on LME’s average price of Nickel prevailing in November 2006 which is
Rs.1626/- per kg (32.11$) inclusive of Custom duty @ 12.5%. Foreign Exchange Rs.45=1 USD.
The price will be subject to variation for every increase/decrease of Rs.100/- in LME Price of Nickel
by Rs.7500/- per Battery Set.
P = Po + ( Ni – No ) *7500/100
P/Po : Price of battery per set to be paid/ quoted in tender
Ni/No : Price of Nickle one month prior to the date of inspection/ TOD.
**75 Kg is the amount of Nickel used in one Battery Set (110V 199 AF) (75KPL 199P).
CLW purchase orders are still not issued on MMIS nor are they fully loaded on the IREPS. The
PVC clause is not very explicitly visible on purchase order on front page. Many Railways keep on
placing orders justifying their Rates with reference to this without application of PVC. In fact the
prices of Nickel fell to almost half @ 905.95 Rs/kg (16.457 $/Kg). With Exchange rate inflation
and change in custom tariff the actual price of battery to be paid would be much less.
21
Sr.
No.
PO No. & Dt. TOD Basic rate per
set
Basic rate per no.
1 Railway 1 PO dt.27.7.12 for 6
sets
9.5.12 Rs.4,75,000/- Rs.18.269.23(-)
Rs.654/- discount i.e.
=Rs.17,615/-
2 Railway 2 PO dt.13.6.12 for 2
sets
15.3.12 Rs.4,50,000/- Rs.17,307.70
3 Railway 3 PO dt.30.07.12 for
4 sets
27.03.12 Rs.4,50,000/- Rs.17,307.70
4 CLW PO dt.23.11.11 for 45
sets
19.7.11 Rs.4,36,500/- Rs.16,990/-
5 CLW PO dt.3.5.11 25.10.10 Rs.4,47,500/- Rs.17,21 1/-
CLW is still placing PO’s with same base of 2006 November price of Nickel with applicable PVC
and paying correctly as due to be paid.
Other Railways while justifying their rates, in comparison with CLW or other Railways rates should
first bring their rates at par and at same level before comparing them.
What should be done
Concluding Remarks & Recommendations
Whenever an order is placed with PVC, the base month of raw material price should be as
close to TOD as possible. It will have following advantages.
• Even if somebody commit mistake of not applying PVC the loss will be minimum
possible.
• The booking of funds will be less and reasonable. Excess booking of
expenditure may deprive Railways to procure valuable vital material.
A chance of taking wrong decisions is minimized.
22
While using P.V Clause utmost care should be taken at the time of framing tender conditions,
tabulating the offers at the same base date and formula and payment of final bill. For the
convenience of users following DO’s and DON’T s are prepared
DO’S
1. Give P.V. Clause only in long-term contracts extending to more than 6 months.
2. Always give your own P.V.Clause wherever necessary. Only standard P.V. Clause widely
used in the industry should be generally used. Prefer P.V.Clause published by IEEMA,
RDSO etc.
3. The base date of raw material price/index should be very clearly mentioned in tender
condition and all tenderers should be asked to accordingly.
4. Prefer to use P.V. Clause based on Indexes published by a Government agency rather than
direct price of raw material. The Indexes average out many factors viz geological factors,
local factors, short term fluctuations etc.
5. Tabulation of rates for the purpose of comparison of rates should be done after all the
tenderer’s quoted rates are brought to the same date as per tender condition.
DON’T S
1. Don’t use P.V. Clause in short term contracts that are likely to last for few months only.
Contracts finalized through Spot Purchase Committee or Local purchase to tie over
emergency situation should not have P.V. Clause as material is required very urgently.
2. Don’t allow tenderers to quote their own P.V. Clause as it will lead to complication for
comparison of rates as they all will quote different formula at different base rates of raw
material.
3. Don’t accept the prices of raw material based on an unpublished data. Try to use PVC
based on Indexes rather than prices.