Sprint 169 Review / Sprint 170 Planning Oct 19th – Nov 2nd 2015 – s169

Page 2: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint Resource Pages

• For past sprint, visit: https://connectopensource.atlassian.net/wiki/display/NHINProgress/Sprint+169+Progress+Summary

• For next sprint, visit:https://connectopensource.atlassian.net/wiki/display/NHINProgress/Sprint+170+Progress+Summary

• For complete information on the CONNECT 4.5 release visit: https://connectopensource.atlassian.net/wiki/display/CONNECT4/CONNECT+4.5

•2

Page 3: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint 169 Summary

3

Points completed in sprint (velocity) = 20

Page 4: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint 169 - Development

• Audit logging for specification compliance– Completed audit logging for Deferred DS and PD– Audit viewer – User story– Audit viewer design updated – design wiki

• Tasks for feature wrap-up• Audit logging configurability • Audit viewer and database table update• Complete testing on all application servers

4

Page 6: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint 169 - Partner/Community Support

• SSA- Open– Setting up CONNECT 4.5 in test WAS environment

• Access denied error, adapter ? (CONN-1625 Open)

• DoD - Closed– Setting up CONNECT 4.5 in test JBoss environment

• Setting up internal connection information files - (CONN-1623 Closed)• Review server logs to troubleshoot issues – Patient Discovery

configuration, policy engine – (CONN-1624 Closed)

• Forums• Supported community installation questions

6

Page 7: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint 169 - Partner/Community Support

• eHealth Exchange – Test team questions related to audit logging and checklists for

PD, QD and RD – Testing team wiki• eHealth Exchange Product Certification

– Kick off with eHealth Exchange– 6 smoke tests + 35 security tests– 52 provisional (optional)– https://

connectopensource.atlassian.net/wiki/display/CONNECTWIKI/eHealth+Exchange+Product+Testing+Information

7

Page 8: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint 169 - Partner/Community Support

• CONNECT Way Ahead– Discussion held with Agency SMEs, Technical Leads, and

FHA Managing Board on Oct 15th• Partners’ operational use of CONNECT and goals and

objectives for its future– FHA follow-up survey to be completed by Nov 13

8

Page 9: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint 169 - Managing Board update

• CONNECT – Planned activities until March 2016– Release 4.6

• Audit Trail and Node Authentication (ATNA) compliant audit logging across all Gateway services

– Audit Log events for PD, QD, RD, DS and X12 services– Search/view audit events using System Administration Module

• Performance testing • Release tasks - security and code quality testing, release testing,

external compliance validation, documentation– eHealth Exchange/Product certification– Support

• Partner / community – installation, upgrades, questions• Way Ahead Survey • HIMSS support

9

Page 10: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

CONNECT 4 -Partner and Community Support

• Current Partner Contacts (Partners please validate)

10

Agency Agency POCs

DoD

Lauren Thompson

Monica Farah-Stapleton

Crystal Baum

John Keane (SCQC Team)

Sean Miller (Dev Mgr, ManTech)

Steven Phillips (Dev Mgr, ManTech)

VA

Elaine Hunolt

Margaret Donohue

Paul Cartland

David Seitz

Todd Turner

Del Johnson

Dick Rickard

CMS

Melanie Combs-Dyer

Elaine Wigginton

Walter Dill

Walden D. Byers(CMS/OIS)

Aaron Walters (CMS/OFM)

Fatima Millar

Michael Azar

SSAMarty Prahl

Kitt Winter

Tom Davidson

Dave Arvin

Page 11: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

CONNECT 4 -Partner and Community Support

• Current Partner Supported Platforms in production

11

Agency CONNECT Version JVMApplication

ServerServer Platform

DoD 4.3.1 1.7 WebSphere 8.5.5Red Hat Linux

version 6.5 - 64 bit

VA 4.2.2.2 1.7 WebLogic 12.1.1Red Hat Linux

version 6.1 - 64 bit

CMS 4.2.1 1.7 WebSphere 8.5 Solaris Sparc 10 and x86

SSA 4.3.2 1.7 WebSphere 8.5 Sun Solaris Sparc 10

Page 12: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Sprint 170 - Proposed ThemesDevelopment / Community Support

• Sprint 170 themes– Auditing

• Fix audit response timeout issue • Audit configurability – turning off by service• Update auditrepo.auditrepository schema

– Partner/Community support• Product certification – execution of test cases• Follow-up with test team on spec/checklist questions• Partner support CONN-1625 (SSA)

12

Page 13: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

CONNECT 4 - WildFlyDevelopment

• Open source application server – WildFly– Product team to use WildFly as development app server– https://connectopensource.atlassian.net/wiki/display/

CONNECTWIKI/Community+Application+Server+Migration– Oracle announced sun setting commercial support for future

major releases of GlassFish Server– WildFly is an open source Application server ( JBoss Community

version) • One federal partner (DoD) already testing with JBoss for future upgrade• FIPS configurable implementation• Strong community and Red Hat support• Clear support path from JBoss WildFly to EAP (Commercial version)• Ease of installation, configuring, and upgrade

13

Page 14: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

CONNECT 4 – WildFly Development

• Open source application server – WildFly– What this means?

• Development and new feature testing will be done on WebLogic, WebSphere, JBoss and WildFly only.

• Product team’s regression testing environment moving to WildFly• Installation testing at release time will be done on GlassFish for one more

release to provide time for the community to make any changes.• Federal partners are encouraged to communicate with their trading

partners about switching to WildFly to avail of new features in future and also to become aware of ‘Oracle/GlassFish sun-setting support’ announcements.

14

Page 15: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

CONNECT 4Community Announcements

• CONNECT Awareness – Open sprint review and planning updates

• Look for Sprint Summaries https://connectopensource.atlassian.net/wiki/display/NHINProgress/Progress+Summary+Page

• Ask questions and participate in discussions on the CONNECT forums

– CONNECT 4 Blogs and Forum posts• http://www.connectopensource.org/developer-resources/forums

– CONNECT 4.5 • https://connectopensource.atlassian.net/wiki/display/CONNECT4/

CONNECT+4.5

15

Page 16: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

CONNECT 4Custodial Agent and Community

Support• Ongoing Product Backlog work, CCB and CONNECT

Roadmap Updates– Finalized as of March 31st

• Top focus to be on projects that facilitates implementation, exchange partner testing/onboarding and lower operational burden

• The Roadmap can be found on the CONNECT wiki: CONNECT 2015 Roadmap

• Product Backlog– JIRA Product Backlog

16

Page 17: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

CONNECT 4 – Backup - Latest Release 4.5

• CONNECT 4.5 released on July 13• Release artifacts for CONNECT 4.5

– Interoperability Testing completed - passed• Interoperability Testing results

– Installation Testing completed - passed• Installation Testing results

– Regression Testing completed - passed• Regression Testing results

– Release notes are here – Installation instructions are here– Binaries are here – Source code is here

17

Page 18: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Questions or Discussions?

18

Page 19: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

FHA Overview

• Established by the Office of Management and Budget as an E-Government Line of Business (LoB) Initiative

• Supports federal activities related to the development and adoption of health IT standards and policies

• Ensures that federal agencies seamlessly and securely exchange health data with other agencies, government entities, and with other public and private organizations

19

Page 20: Sprint 169 Review / Sprint 170 Planning Oct 19 th – Nov 2 nd 2015 – s169

Stay Connected, Communicate and Collaborate

• Find out more about FHA on the ONC website: http://www.healthit.gov/FHA

• Schedule a meeting with me or send me your thoughts at: [email protected]

• Subscribe, watch, and share: • @ONC_FHA,• @CONNECT_Project• Federal Health Architecture• http://www.flickr.com/photos/federalhealtharchitecture/

20