Construction Manager Architect
SPRINGFIELD TOWNSHIP MUNICIPAL CAMPUS
PROJECT
Springfield Township DEI Project No. 12069
Monthly Progress Report No. 08 May 2017
P a g e | 2
Springfield Township Municipal Campus Project
Phase 2
Phase 2: Buildings and Adjacent Site Work
Start: March 7th, 2016
Completion of Phase: June 23rd, 2017
WORK COMPLETED
Public Works:
Public Works main building, equipment
building, exterior storage building, and fuel
system complete.
Interior main building punch list work
near completion.
Owner is operating from new facility.
Amended soil placed and seeded.
Landscape plantings complete for this phase
1 and cedar fencing constructed. Remainder
to be completed following salt shed and
removal of topsoil stockpile.
Owner training 90% complete.
Pre-existing public works building vacated.
Utility terminations in progress.
Public Works
Exterior Storage Building
ss
P a g e | 3
WORK COMPLETED
Library:
Library retaining wall placement complete.
Forms and form liner stripped.
Metal panel installation in progress.
Interior GWB placement and finishing
complete. Ceiling grid installation began.
Mechanical, electrical and plumbing fixtures
and devices in progress. Fixtures are being
placed in ceiling grid as ceiling work
progresses.
Installation of storm sewer in progress.
Water and gas service to building complete.
Gas meter set scheduled for second week of
June.
Exterior canopy lighting rough in complete.
Placement of tongue and groove cedar in
progress.
Police/Admin:
Final cleaning in progress.
Hardwood paneling at lobby and board room
complete.
Cooling start up in progress. Remainder of
equipment start up complete.
Fire alarm testing and fire suppression testing
complete.
Topsoil placed and seeded along papermill
road frontage.
Access control rough in and devices
complete. Programming in progress.
Architect punch list in progress. Punch list
work will follow in June.
Police/Admin. Police Corridor
Library Adult Print Material
P a g e | 4
Library Ceiling Grid Installation Library Ceramic Tile Installation
Police/Admin.
Board Room
Library Retaining
Wall Placement
P a g e | 5
Site Layout: