Sponsored Project Training ProgramSponsored Project Training Program
Post Award Grant Lifecycle and Post Award Grant Lifecycle and ToolsToolsOctober 12, 2011October 12, 2011Jennifer Gagnon & Sudha RamaswamiJennifer Gagnon & Sudha Ramaswami
Sponsored Project Training Program 1
ObjectivesObjectives• Recommend effective and efficient
post-award grants management practices
• Ensure all grants are ready to be closed and reported on by 30 days after grant end date
• Reduce compliance risks related to cost transfers and late reports• Promote use of advance accounts • Proactive PurCard management
Sponsored Projects Training Program 2
ObjectivesObjectives• Recommend PeopleSoft reports,
queries, and pages (tools) for effective grants management
• Review best practice of how and when to use these tools
• Discuss resources available for interpreting the data
Sponsored Projects Training Program 3
Grant lifecycle topicsGrant lifecycle topicsBrief overview of general grants
management topicsBest Practices in post award
◦Setup◦Management◦Closeout
Sponsored Projects Training Program 4
Post-Award Best PracticePost-Award Best PracticeAward SetupAward Setup• Choosing the advanced account route• Upon the setup of the chartstring
SPA will notify the PI, department administrator, and Dean’s Office
• Department administrator should meet with the PI to discuss the following: Start date of research and Pre-award spending Personnel expending effort on the grant
Compare committed effort to actual effortEnsure there are no reductions in effort greater than
25% or absences of more than three months Must make changes to any applicable distribution forms
• Grant cost share requirements Use faculty workload form/routing form to determine the
funding source for cost share commitment Change applicable distribution forms Contact Dean’s Office for budget transfer to cost share
chartstringSponsored Projects Training Program 5
Advance Accounts (AA)Advance Accounts (AA)Formerly called Guaranteed FundingPolicy drafted & circulated for public
commentNew policy & process training in DecemberDevelop advance account memo upon
notification of funding from sponsor Collaborative effort between the PI and department
administrator Allows SPA to create a chartstring in PeopleSoft
AA requests must be routed through InfoEd prior to set up in PeopleSoft
Sponsored Projects Training Program 6
Pre-Award SpendingPre-Award Spending• Some sponsors allow for pre-award
spendingSpending up to 90 days prior to award start date
• Pre-award spending memoMust obtain and complete a pre-award spending
memoWork with appropriate post-award administratorhttp://www.uvm.edu/spa/?Page=formslibrarychart.h
tml
Sponsored Projects Training Program 7
Post-Award Best PracticePost-Award Best PracticeAward ManagementAward ManagementKey considerations in award
managementPerform on a monthly basis:
Run the Project Monthly Budget Report for all departmental grants
Monitor for overdrawn or over encumbered projectsReview expenses for allowabilityProvide PIs with a copy of the reportsReview and resolve all budget checking errors
Use either the Closeout Report or query “UV_GM_KK_ERRORS_ALL” (financial module)
Review and submit all journal entries awaiting submission or posting Use either Closeout Report or query
“UV_RC_GL_JE_NOT_SUBMITTED” (financial module)
Sponsored Projects Training Program 8
Award Management Award Management (cont.)(cont.)• Perform on a quarterly basis:
Run the Closeout Report for all departmental grantsEnsure personnel are not distributed past end date of
grant Use query “UV_DIST_PAST_PROJECT_END_DATE”
(HR module)Compare committed effort to actual effort
For both the PI and key personnel Ensure no reductions of greater than 25% or
absences of more than three monthsMeet with PI to review grant budget status, effort,
and upcoming quarter plansMake prospective distribution changes as necessaryRun Cost Share Summary
• Ensure cost share commitments are met (including third party)Sponsored Projects Training Program 9
PurCard ManagementPurCard Management• Ensure departmental PurCard holders
Understand and apply specific award, sponsor, and federal regulations and University policy
Reallocate only allowable costs to sponsored project chartstrings
Reallocate PurCard expenses to the correct chartstring by the University deadlines to avoid future cost transfers
Change the default chartstrings for PurCards at the time of closeout of a grant.
Sponsored Projects Training Program 10
Prior ApprovalPrior ApprovalSponsor prior approval is often required for
the following situationsPI or key personnel reduction of committed effort
by 25% or more Ex. If committed effort was 20% but the actual effort is 12.5%
this represents a deviation of 37.5%
The 3 month absence of a PI or key personnel from grant
Change in scope of the projectSignificant changes in the project budget
See individual award documents for specific guidance
Deviation from award terms and conditionsAll sponsor requests for prior approval
should be routed through Sponsored Project Administration
Sponsored Projects Training Program 11
RebudgetingRebudgetingMay request rebudgeting as needed
See award document or contact post-award administrator to determine if prior approval is required by sponsor
Department administrator should contact post-award administrator for rebudgeting in PeopleSoft
Sponsored Projects Training Program 12
Budget Checking ErrorsBudget Checking Errors
Sponsored Projects Training Program 13
Budget Checking Error Name
Ledger Group
When does this occur?
Budget Date out of Bounds SP_CHILD2 In salary, fringe, and operating transactions that are budget checked more than 30 days after the end date of a project period.
No Budget Exists SP_CHILD2 In salary, fringe, or operating transactions when the chartstring used in the transaction is not set up in Commitment Control.
Exceeds Budget Tolerance SP_PARENT When a project is overdrawn or over encumbered.
Budget is Closed SP_PARENT Only if a project is closed in budget definitions in KK. The project is closed in KK upon completion of the final financial report.
Budget Checking ErrorsBudget Checking Errors
Sponsored Projects Training Program 14
Budget Checking Error Name
Process to resolve errors
Budget Date out of Bounds
Verify you are charging the correct chartstring. If so and expense was incurred before the grant ended and the final financial report has not yet been submitted, please provide backup documentation to the post award administrator. Error will be overridden if appropriate.
No Budget Exists Verify you are charging the correct chartstring. If the chartstring is valid and the expense is appropriate and allowable, ask the post award administrator to create a $0 budget. If the chartstring is invalid or the expense is unallowable, correct the chartstring and budget check the transaction again.
Exceeds Budget Tolerance
Review award and work with the post award administrator to determine best course of action if future funding is expected or encumbrances are incorrect. In most cases, the transaction should be allocated to a different chartstring and budget checked again.
Budget is Closed This error should occur only on projects that have already been reported to the sponsor. The chartstring should be changed on the transaction.
Post-Award Best Practice Post-Award Best Practice Award CloseoutAward Closeout• SPA will notify departments of grants ending
within 90 days on a monthly basis Department administrators meet with PIs to discuss:
Closeout process Cost share activities Assist with a no cost extension if needed
Sponsored Projects Training Program 15
Award Closeout (cont.)Award Closeout (cont.)Closeout Timeline:
30 days prior to grant end date: Run Closeout Report Review expenses to ensure they are allowable Review all salary expenses for allowability, allocability,
reasonableness, consistency Use query “UV_PAY_ERN_DIST” (HR module)
Notify internal billers of any chartstring changes Change default chartstring for relevant Purcards and expense
reports Resolve budget checking errors
Use either the Closeout Report or query “UV_GM_KK_ERRORS_ALL” (financial module)
Contact Procurement Services to close all operating encumbrances
Ensure cost share commitments will be met (including third party)
Sponsored Projects Training Program 16
Award Closeout (cont.)Award Closeout (cont.)Closeout Timeline (cont.):
20 days after grant ends: Run Closeout Report and resolve any remaining issues
30 days after grant ends: Confirm with SPA that grant is ready to close and the final
report is ready to be completed
• Sponsored Project Administration prepares and submits final financial report to sponsor and soft closes award to prevent additional transactions from posting
Sponsored Projects Training Program 17
PeopleSoft ToolsPeopleSoft ToolsWhat you should know . . . What you should know . . . Basic understanding of sponsored
projectsFamiliarity with basic and mid-level
PeopleSoft (monthly budget reports, journal entries, expense reports, PurCards, Time & Labor)
Basic Excel usageFinancial forecasting and analytical skillsAttended previous sessions in this
Sponsored Projects Training ProgramSponsored Projects Training Program 18
PeopleSoft ToolsPeopleSoft ToolsReports
◦Monthly Budget Reports - Projects
◦Closeout Report◦Cost Share Summary◦Budget Transaction Detail Report
Sponsored Projects Training Program 19
PeopleSoft ToolsPeopleSoft ToolsQueries
HCM:◦UV_PAY_ERN_DIST◦UV_DIST_PAST_PROJECT_END_DATEFINANCIALS:◦UV_GM_KK_ERRORS_ALL◦UV_RC_GL_JE_NOT_SUBMITTED◦UV_GM_FINDINGAWDTHRUREFAWD◦UV_GCA_PROJ_RESOURCE
Sponsored Projects Training Program 20
PeopleSoft ToolsPeopleSoft ToolsPages
FINANCIALS:◦Budgets Overview◦Award Profile
Sponsored Projects Training Program 21
MONTHLY BUDGET REPORT – MONTHLY BUDGET REPORT – PROJECTS (PMBR)PROJECTS (PMBR)Navigation: UVM Reports > Budget
Reports > Monthly Budget Rpt – Projects
General use◦ Review monthly for budget vs. actuals,
encumbrances, and possible unallowable expenses
The report can be run to excel and therefore the data may be manipulated for personal reports
Sponsored Projects Training Program 22
PMBRPMBR
Sponsored Projects Training Program 23
PMBRPMBRRecommended use
◦ Check the ‘Financial Data in XLS’ option and in the output filter for Possible unallowable expense categories Expenses that require possible prior approval
Equipment Foreign Travel
◦ Review for possible rebudgeting See NGA for restricted items Work with PI and PAS administrator for those items
requiring prior approval◦ Check salary distributions and fringe
Review PI and key personnel committed effort Work with PI and PAS administrator for those items
requiring prior approval
Job Aid - http://www.uvm.edu/hrs/?Page=skills/manuals/financialreporting.html Sponsored Projects Training
Program 24
PMBRPMBRReport use frequency - monthly It is important to note that the payroll
encumbrances are through UVM’s fiscal year-end (June 30) only, which typically does not match the award end date.◦ Payroll expenses should be projected through the
award end dateThis report captures only those transactions
that have been posted to the General ledger (GL). ◦ Any transaction that has been budget checked but not
posted will not be reflected here. SPA prepares interim financial reports and
invoices based on actuals posted to the GL at the end of a specific accounting period◦ PMBR will reconcile to these reports and invoices
Sponsored Projects Training Program 25
CLOSEOUT REPORTCLOSEOUT REPORTNavigation: UVM Reports>Closeout
Report
General use◦The best tool to get a comprehensive snap shot of the project
◦It provides sponsored and cost share budget balances, lists all the exceptions that need to be addressed and much more
Sponsored Projects Training Program 26
CLOSEOUT REPORTCLOSEOUT REPORTPossible parameters
Sponsored Projects Training Program 27
CLOSEOUT REPORTCLOSEOUT REPORT Recommended use
◦ Review the demographic information (in the header of the report)
◦ Compare budget to actuals for both sponsored and cost share chartstrings
◦ Review salary encumbrances◦ Journal Entries/Expense Reports/Vouchers/Purchase Orders
stuck in budget checking errors◦ Purcards/Expense Reports with a default chartstring tied to
the project◦ Open Purchase Orders and Requisitions – check to see if
encumbrances are still needed◦ Upcoming Reporting Milestones
Any Interim Reports due Final report due dates
Job aid - https://www.uvm.edu/hrs/?Page=skills/manuals/financial reporting.html
Sponsored Projects Training Program 28
CLOSEOUT REPORTCLOSEOUT REPORTReport use frequency
◦ Run quarterly for all department grants◦ Run 30 days prior to grant expiration and
both 20 and 30 days after grant ends
Sponsored Projects Training Program 29
COST SHARE SUMMARY COST SHARE SUMMARY Navigation: UVM Reports>Cost Share
Summary
General use◦ A snap shot of the mandatory cost
share requirements, budget, and actuals for ongoing monitoring
Sponsored Projects Training Program 30
COST SHARE SUMMARY COST SHARE SUMMARY Possible parameters
Sponsored Projects Training Program 31
COST SHARE SUMMARYCOST SHARE SUMMARYRecommended use
◦ Cost share budget, actuals, encumbrances, and budget balances compared to project start and end date
◦ Ensure commitments will be met by the end of the project period, including third party
◦ Resolve potential overdrafts in cost share chartstrings prior to the end of the project period
Cost Share Business Process & Summary Job Aid - http://www.uvm.edu/spa/?Page=costsharingcommitments.html
Sponsored Projects Training Program 32
COST SHARE SUMMARYCOST SHARE SUMMARY◦Report use frequency
Run and review quarterly
Sponsored Projects Training Program 33
BUDGET TRANSACTION DETAIL REPORTBUDGET TRANSACTION DETAIL REPORT
Navigation: Commitment Control>Budget Reports>Budget Transaction Detail
General use◦ Research a transaction that may have
posted during a prior accounting period◦ Used as back up for Journal entries◦ Secondary to the Monthly Budget Report -
Projects and should only be used for research
Sponsored Projects Training Program 34
BUDGET TRANSACTION DETAIL REPORTBUDGET TRANSACTION DETAIL REPORT Possible parameters
Sponsored Projects Training Program 35
BUDGET TRANSACTION DETAIL REPORTBUDGET TRANSACTION DETAIL REPORT
Ledger Group Detail KK will return transactions for all the types of projects◦ Ledger group is active effective 07/01/2008
Ledger Group Child2 will return transactions for the old Ledger Group Child1 as well
This report will give the details of transactions that have a valid budget status◦ This will differ from the monthly budget report in all
those cases where the journals/expense reports have not been posted to the General Ledger
Sponsored Projects Training Program 36
UV_PAY_ERN_DIST QUERYUV_PAY_ERN_DIST QUERY Navigation: HR module – Reporting Tools>Query Viewer>
Type in the query name General use
◦ Great tool to review the individuals and the salary on a project
Quick things that can be used to check using this query◦ People distributed to this project/chart string◦ Dollar amount per person◦ Type of pay received (vacation, overtime, etc)◦ Check against Monthly Budget Report – Projects
In order to reconcile with PMBR, the period has to be closed to ensure payroll is posted.
Link to the job aid: http://www.uvm.edu/hrs/skills/manuals/queries.pdf
Query can assist with trouble shooting information in PMBR
Sponsored Projects Training Program 37
UV_DIST_PAST_PROJECT_END_DATE UV_DIST_PAST_PROJECT_END_DATE
Navigation: HR module – Reporting Tools>Query Viewer> Type in the query name
General use◦ Lists all people across departments who are distributed to a specific
project past the project end date
Things to check◦ Useful at closeout of an award◦ Should be run at least quarterly to find out who is still
distributed to a project◦ Trigger to request a no-cost-extension◦ Trigger to remove people from project – possible
terminations involved (timing of notice, vacation calculations)
Sponsored Projects Training Program 38
UV_GM_KK_ERRORS_ALLUV_GM_KK_ERRORS_ALL Navigation: Finance module - Reporting Tools>Query
Viewer> Type in the query name General use
◦ Lists all budget checking errors as of a particular date
◦ Used by GCA in contacting you to clear certain budget checking errors
◦ Extremely useful during closeouts and at year end
◦ Use this query instead of the project closeout report to get a list of all budget checking errors for all grants in your unit
Can be run by transaction type – Salary journals, regular journals, expense reports or for a particular ledger group – SP_CHILD2 or SP_PARENT for grant related budget checking errors
Run monthly to review and resolve budget checking errors
Sponsored Projects Training Program 39
UV_RC_GL_JE_NOT_SUBMITTEDUV_RC_GL_JE_NOT_SUBMITTED
Navigation: Finance module - Reporting Tools>Query Viewer> Type in the query name
General use◦ Lists journal entries that have not been
submitted or posted◦ Used by Financial Reporting and Analysis
department during month end◦ This information is also available on the
closeout reportUseful during
◦ Month End ◦ Project close out
Sponsored Projects Training Program 40
UV_GM_FINDINGAWDTHRUREFAWUV_GM_FINDINGAWDTHRUREFAWDD
Navigation: Finance module - Reporting Tools>Query Viewer> Type in the query name
General use◦Used for locating awards using the
sponsor award number◦A quick way to locate any new
awards or awards that are on Guaranteed Funding/Advanced Account
◦Should be run as neededSponsored Projects Training Program 41
UV_PROJ_RESOURCEUV_PROJ_RESOURCENavigation: Finance module – Reporting
Tools>Query Viewer> Type in the query name
General use◦ Basically an expenses only version of the
Monthly Budget Report – Projects
Monthly Budget Report - Projects includes the details in this query plus budget information. We recommend that you use the PMBR in place of this query.
Sponsored Projects Training Program 42
BUDGETS OVERVIEWBUDGETS OVERVIEW Navigation: Commitment Control>Review Budget
Activities>Budgets Overview General use
◦ Quick snapshot of the project budgets and expenses including cost share information at any point in time (live)
◦ Not used for reports or invoices to the sponsors or for University financial statements
Quick things that can be ascertained◦ Total budget of the award◦ Expense Categories◦ Chartstrings◦ Estimated budget balance
Can be run for sponsored or cost share chartstrings or both
Sponsored Projects Training Program 43
AWARD PROFILEAWARD PROFILE Navigation: Grants>Awards>Award Profile General use
◦ Provides award demographic information and other helpful details for effective grants management
Gives the demographic info of an award◦ PI name/Co-PIs
◦ Sponsor name
◦ Amount of Funding
◦ Start and End dates
◦ Milestones – Reporting and otherwise
◦ Grant Administrator link
The additional information link that gives a variety of info◦ Cost Share
◦ Related Awards
◦ Any other special terms
Sponsored Projects Training Program 44
Learning ResourcesLearning ResourcesHow to run reports/report
questions: Open Labs, Learning Services Classes, Footprints◦ http://www.uvm.edu/hrs/?Page=skills/develop_skills.html
Sponsored Project Training Program◦ http://www.uvm.edu/spa/?Page=sptp.html◦ Fall 2011 offerings:
Subawards and subcontracts F&A Costs and Cost Policy New UVM Policies Effecting Grants
Sponsored Projects Training Program 45
Award Management Award Management ResourcesResourcesResources: Basic Financial Reports Mini-Manual:
http://www.uvm.edu/hrs/skills/manuals/basicfinancialreports.pdf
Cost Share Summary job aid:http://www.uvm.edu/spa/?Page=costsharingcommitments.html
Advance Accounts:http://www.uvm.edu/spa/?Page=advancedaccounts.html
Electronic Salary Distribution Forms:http://www.uvm.edu/hrs/skills/manuals/electronicsalarydistributionform.pdf
Monthly Business Processes:http://www.uvm.edu/hrs/skills/manuals/monthlybusinessprocesses.pdf
Sponsored Projects Training Program 46
Process Questions/Contact Process Questions/Contact infoinfoDean’s Office
Sponsored Project Administration◦http://www.uvm.edu/spa/◦217 Waterman Building◦6-3360
Sponsored Projects Training Program 47
ConclusionConclusion Through pro-active award management and use of
advance accounts:◦ Virtually eliminate the use of departmental suspense for
actual salary/benefits expenses ◦ Significantly reduce retroactive salary distribution changes◦ Ensure all grants are ready to be closed out and reported
on by 30 days after grant end date◦ Reduce compliance risks related to cost transfers and late
reports
• Recommended PeopleSoft reports, queries, and pages (tools) for effective grants management
• Reviewed best practice of how and when to use these tools
• Discussed resources available for interpreting the data
Sponsored Projects Training Program 48