SOFTWARE PROJECT MANAGEMENT MS PROJECT 2010

SPM MS PROJECT 2007

Embed Size (px)

DESCRIPTION

Software Project Management - Microsoft Project 2007

Citation preview

Page 1: SPM MS PROJECT 2007

SOFTWARE PROJECT MANAGEMENT

MS PROJECT 2010

Page 2: SPM MS PROJECT 2007

• Add tasks/Subtasks• Add resources (team members)• Add costs for resources• Assign resources to tasks• Establish dependencies• Refine and optimize• Create baseline• Track progress

The MS-Project Process

Page 3: SPM MS PROJECT 2007

Task AreaGantt Chart Area

View Bar

Enter Tasks/Subtask here Tool Bar Time Scale

OVERALL SCREEN LAYOUT

Page 4: SPM MS PROJECT 2007

Set the start date

Page 5: SPM MS PROJECT 2007

Entering Major Tasks

Page 6: SPM MS PROJECT 2007

Subtasks

Page 7: SPM MS PROJECT 2007

Setting the task predecessors

Task Predecessor

Page 8: SPM MS PROJECT 2007

Reading Gantt Chart

Page 9: SPM MS PROJECT 2007

Task Information Form

Page 10: SPM MS PROJECT 2007

Task Information Form

Page 11: SPM MS PROJECT 2007

Task Information Form

Page 12: SPM MS PROJECT 2007

Task Information Form

Page 13: SPM MS PROJECT 2007

Task Information

Page 14: SPM MS PROJECT 2007

Resource Sheet

Work (people)Material (expenditures)Cost (hourly rate or cost of hardware)

Page 15: SPM MS PROJECT 2007

Critical Path

Critical Path

Page 16: SPM MS PROJECT 2007

Logical Task Relationships

Page 17: SPM MS PROJECT 2007

Constraint Type

• As Soon As Possible (ASAP) • As Late As Possible (ALAP) • Finish No Later Than (FNLT) • Start No Later Than (SNLT) • Finish No Earlier Than (FNET) • Start No Earlier Than (SNET) • Must Start On (MSO) • Must Finish On (MFO)

Page 18: SPM MS PROJECT 2007

• As Soon As Possible (ASAP) With this constraint, Microsoft Project schedules

the task as early as it can • As Late As Possible (ALAP) With this constraint, Microsoft Project schedules

the task as late as it can • Finish No Later Than (FNLT) This constraint indicates the latest possible date

that you want this task to be completed

Page 19: SPM MS PROJECT 2007

• Start No Later Than (SNLT) This constraint indicates the latest possible date

that you want this task to begin. • Finish No Earlier Than (FNET) This constraint indicates the earliest possible

date that you want this task to be completed • Start No Earlier Than (SNET)This constraint indicates the earliest possible

date that you want this task to begin

Page 20: SPM MS PROJECT 2007

• Must Start On (MSO) This constraint indicates the exact date on which a

task must be scheduled to begin

• Must Finish On (MFO) This constraint indicates the exact date on which a

task must be scheduled to be completed

Page 21: SPM MS PROJECT 2007

Resource Types

• WHAT -> WHEN -> WHO• There are three types of resources:

– Work– Material– Cost

Page 22: SPM MS PROJECT 2007

Resource Types

Page 23: SPM MS PROJECT 2007

What is Resource?

• A resource is the person(s), equipment, or materials used to complete a task in a project.

• The Resource Sheet is commonly used for entering the resources.

Page 24: SPM MS PROJECT 2007

Resource Sheet View

Page 25: SPM MS PROJECT 2007

Resource Sheet View

Page 26: SPM MS PROJECT 2007

Using The Resource Information Dialog Box

• The Resource Information dialog box is a comprehensive collection of all of the data stored for a single resource.

• You can make changes to:– Email– Notes– Resource Availability Dates– Holidays– Costs– And many more!

Page 27: SPM MS PROJECT 2007

Resource Information Dialog Box

Page 28: SPM MS PROJECT 2007

Assigning Resources

Page 29: SPM MS PROJECT 2007

views

• VIEWS– SINGLE– COMBINATION

• TABLES– CUSTOMS

• OVERALLOCATION

Page 30: SPM MS PROJECT 2007

Single ViewPress New

Page 31: SPM MS PROJECT 2007

Over Allocation

• Over Allocation is when a project calls for more time than a team member has.

• Over Allocation can be solved by number of ways for example:– Changing the relationships i.e. (SS, FS, SF, FF)– Changing lag to “zero” or change it to lead – Changing working time– Changing Units – Adding extra overtime hours to that particular

resource

Page 32: SPM MS PROJECT 2007

Shortening Critical Paths

• Critical Path– the critical path is the sequence of tasks that is

nothing but back-to-back work, with no slack, which you can subtract to reduce the duration

• How to shorten the Critical Path

– Adding more resources– Changing relationship type

Page 33: SPM MS PROJECT 2007

Splitting Tasks

• Either you want to interrupt some work with an other (By You)

• Or by leveling the resource to maintain the work balance (By the system) Split Button

Page 34: SPM MS PROJECT 2007

Setting Public Holidays

Page 35: SPM MS PROJECT 2007

Resource Levelling• Resource leveling can help project managers

resolve over allocations by delaying or splitting up tasks.

Page 36: SPM MS PROJECT 2007

Resource Levelling

Page 37: SPM MS PROJECT 2007

Resource Levelling

Page 38: SPM MS PROJECT 2007

Resource Levelling

Page 39: SPM MS PROJECT 2007

Resource Levelling

Page 40: SPM MS PROJECT 2007

Baseline

• The baseline is nothing else than a frozen picture of your project at a certain point time.

• In Microsoft Project 2007 you are able to have up to 11 different baselines in a project.

• You should only re-baseline when you have major changes in your project such as; delays, overrun of budget or loss of key resources.

Page 41: SPM MS PROJECT 2007

Baseline

Page 42: SPM MS PROJECT 2007

Baseline

Page 43: SPM MS PROJECT 2007

Tracking

Page 44: SPM MS PROJECT 2007

Variance

Page 45: SPM MS PROJECT 2007

Reports

Page 46: SPM MS PROJECT 2007

KEY POINTS

1. Critical Path2. Slack3. Mile stone4. Task types5. Constraint types6. Relationship types7. Interim plan8. Summary Task9. Dependency types

Page 47: SPM MS PROJECT 2007

KEY POINTS

10.Recurring task11.Deadlines12.Resources Type13.Cost Type14.Views15.Tracking16.Baseline17.Over allocation/ crashing

Page 48: SPM MS PROJECT 2007

KEY POINTS

18.Resolving Scheduling Conflicts19.Accrual methods