Upload
elzinga-volkers
View
215
Download
1
Tags:
Embed Size (px)
DESCRIPTION
The Cornerstone - Issue 10
Citation preview
Fun Fact
Moving from September to October here are some interesting facts that happened in October:
The first Ford “Model T” was put on the market – 10/1/1908
The Soviet Union launched the first artificial satellite – 10/4/1957
President Harry S. Truman made the first presidential telecast ad-dress from the White House – 10/5/1947
The Chicago Fire began and burned for 30 hours – 10/8/1849
U.S. Naval Academy opened at Annapolis, MD – 10/10/1845
The first transcontinental telegram was sent – 10/24/1945
The Statue of Liberty was dedicat-ed – 10/28/1886
Nevada became the 36th state – 10/31/1864
Project Update
With the space program finalized and the overall square footage of the
building set at 120,000SF, the project has moved in to the schematic de-
sign process. As we discussed in last week’s issue, schematic design is the
time where the overall layout and look of the building is estab-
lished. Randy Pease with Integrated Architecture has been working dili-
gently on getting each department located properly on their designated
floors and through this process the footprint of the building has length-
ened. This change was presented to the PDG Group last week, as well as
current department locations and the following items were brought up
and discussed at that meeting:
Women’s Health is now located on the first floor
Women’s Health and Urgent Care will co-utilize flex exam rooms
All private offices have been removed from the project because they do not
fit the Spectrum model of care
On the 3rd floor, the EEG rooms need to be located in a place where there
will be minimal noise and traffic
The team needs to determine the true needs of the loading area
Special attention needs to be given to the location of the MRI
It needs to be located away from any moving metal, such as the trucks in
the loading docks
Its relationship to phone triage needs to be considered due to the
amount of noise the unit will emit
The IS issues need to be addressed and communicated to the team
Issues include kiosks, check out process, need for nurse call and printers
in exam rooms
We have been inputting these comments, as well as others over the past
week. In addition to the schematic design going on, Elzinga & Volkers has
been working with The Concord Group to establish the preliminary budget
for the project. We have reached out to local subcontractors to validate
costs, as well as try to get inside information on if they project any fluctua-
tions in the market over the next year.
Volume 1, Issue 10
September 28, 2012
Created By:
Dustin Kuzee
Project Manager
October is National Breast Cancer Awareness Month!
Let’s all do our part to help find a cure, whether that’s a charity con-tribution, volunteering or having a “pink day” at the office. Every lit-tle bit helps.
Project Forecast
Plans will continue to evolve over the next couple of weeks. We will be meeting with each department next week to present the current documents. In these meetings will be discuss-ing adjacencies with other practices, provider work areas, location in the building, exam room lay-out, hospitality locations, and the overall building layout. From these meetings we will be looking for likes, dislikes, needs, and wants to help direct the design of the building to help suit each de-partment. After our first meeting there will be a follow up meeting to confirm if what was dis-cussed in the initial meeting was translated to the drawings properly. By the next issue of The Cor-nerstone we will be entering these second meetings, as well as getting closer to taking the next step in design.
Page 2
Programming Basis of Design/SD Design Documents Construction Documents
+
Track the Project’s Progress as the Forest Grows!