7/23/2019 Specification.doc http://slidepdf.com/reader/full/specificationdoc 1/2 SPECIFICATION  1.1. GENERAL :  SCOPE: 1. The scope of work to be executed under this contract is for the item of works covered under the title. a. The entire electrical installation shall be carried out in accordance with latest indian electricity & relevant I.S standards up to date . The work shall also comply with all statutory regulations of supply agencies state inspection authorities & fire regulation.  b. The work scope includes but is not limited to the enclosed !ill of "uantity #rawings erection testing and commissioning as per specification. c. The contractor shall bear total responsibility of the work to be executed and shall not avail himself of any unintentional error or omission in the enclosed documents.  RESPONSIBILI TIES: 1.$ The contractor should work in consultation with consultants in the interest of the %ob.  is responsibilities include but are not limited to following: a. 'ommitting work schedule including dates of commencement and completion.  b. (ngaging and deploying ade)uate *o. of full time well )ualified and experienced skilled authori+ed personnel along with sufficient semi,skilled and unskilled labours. c. (nsuring safety and security of personnel materials and installations at site. d. 'o,operating with other agencies working at site.  Seeking prior permission from -wners for any type of cutting chasing drilling etc. for making  pocketsholes etc. in any /'' slabcolumnwall etc. f. 0aking good any other agencys work damaged by him if any.  Including the cost of material and labour.  #oing chasing the masonry walls for placing concealed conduits and #istribution !oard etc. and making them good with '0 21:$3 plaster including cost of materials and labour as well as making good pockets in /'' slab in 0 45 grade concrete 2material 6 labour3 'ost of materials supplied by -wners will be recovered at there landed cost at site. 1

Specification.doc

Embed Size (px)

Citation preview

Page 1: Specification.doc

7/23/2019 Specification.doc

http://slidepdf.com/reader/full/specificationdoc 1/2

SPECIFICATION

 

1.1.GENERAL

:

  SCOPE:

1. The scope of work to be executed under this contract is for the item of works covered under

the title.

a. The entire electrical installation shall be carried out in accordance with latest indian electricity& relevant I.S standards up to date . The work shall also comply with all statutory regulations of

supply agencies state inspection authorities & fire regulation.

 b. The work scope includes but is not limited to the enclosed !ill of "uantity #rawingserection testing and commissioning as per specification.

c. The contractor shall bear total responsibility of the work to be executed and shall not avail

himself of any unintentional error or omission in the enclosed documents.

  RESPONSIBILITIES:

1.$ The contractor should work in consultation with consultants in the interest of the %ob.

  is responsibilities include but are not limited to following:

a. 'ommitting work schedule including dates of commencement and completion.

 b. (ngaging and deploying ade)uate *o. of full time well )ualified and experienced skilledauthori+ed personnel along with sufficient semi,skilled and unskilled labours.

c. (nsuring safety and security of personnel materials and installations at site.

d. 'o,operating with other agencies working at site.

  Seeking prior permission from -wners for any type of cutting chasing drilling etc. for making

 pocketsholes etc. in any /'' slabcolumnwall etc.

f. 0aking good any other agencys work damaged by him if any.

 Including the cost of material and labour.

 

#oing chasing the masonry walls for placing concealed conduits and #istribution !oardetc. and making them good with '0 21:$3 plaster including cost of materials and labour

as well as making good pockets in /'' slab in 0 45 grade concrete 2material 6 labour3

'ost of materials supplied by -wners will be recovered at there landed cost at site.

1

Page 2: Specification.doc

7/23/2019 Specification.doc

http://slidepdf.com/reader/full/specificationdoc 2/2

g. 7orking out actual )uantities and details making of working drawings sketches conduit

layouts based on enclosed documents and other relevant drawings etc. for carrying out his

work smoothly and also making timely regular progress reports test reportsmeasurementreconciliation reports as built drawings etc.

h. Seeking clarifications on contradictions if there are any.

i. Seeking approvals on deviations if re)uired are any.

 %. Seeking clearances before starting any part of the %ob.

k. Timely arranging all necessary tools tackles duly testified testing instruments e)uipments

accessories etc.

l. Timely ordering out and procuring of materials.

m. 0aking optimum utili+ation and si+ing of materials so that wastages are minimum 2in any casewastage should not exceed $8 in any item3. owever all wastages shall be the contractors

account no compensation shall be paid by the 'lient.

n. Safe handling unpackingpacking checking transporting of materials to and fro sitestores.

 p. /epairing for any transit damage of e)uipments checking tightening fixing ofloose components and connections.

). /edoingmodifyingcorrecting any dis,approvedimproperdefectivepoor )ualitybad looking

work without any delay.

s. 9articipating in regular review meetings with ownerconsultants following

instructions and attending to priorities fixed.

t. -perating maintaining protecting the installation from any damage due to any cause till it is

taken over by the owner.

u. eeping the vendorconsultants well informed of all his activities and plans all the time.

v. Indemnifying the owner from any liabilities due to his not complying with any of hiscontractual obligations.

x. eeping site neat and clean all the time.

y. To inform the respective supply vendor to be present on site to assist for testing &

commisioning.

+. anding over the installation in working and perfect condition to the purchaser 2-wner3.

$