332
PROPOSED PARKCITY HANOI CLUBHOUSE AT LE TRONG TAN STREET, HANOI, VIETNAM Mechanical & Electrical Installation Specification and Drawings March 2015 THAM & WONG M&E (VIETNAM) CO., LTD No.6, 2nd alley, Pham Tuan Tai street, Cau Giay District, Hanoi Tel: +84 43748 0327 Fax: +84 43755 8903

Specification for Park City-clubhouse-Rev 0

Embed Size (px)

Citation preview

  • PROPOSED PARKCITY HANOI CLUBHOUSE AT LE TRONG TAN STREET, HANOI, VIETNAM

    Mechanical & Electrical Installation Specification and Drawings

    March 2015

    THAM & WONG M&E (VIETNAM) CO., LTD No.6, 2nd alley, Pham Tuan Tai street, Cau Giay District, Hanoi

    Tel: +84 43748 0327 Fax: +84 43755 8903

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 2

    CONTENTS Page

    1.0 PROJECT TEAM ......................................................................................................................... 3

    2.0 GENERAL REQUIREMENTS ..................................................................................................... 4

    3.0 SCOPE OF WORK .................................................................................................................... 22

    4.0 RESPONSIBILITIES OF CONTRACTOR ................................................................................. 27

    5.0 ELECTRICAL SERVICES ......................................................................................................... 29

    6.0 AIR-CONDITIONING & MECHANICAL VENTILATION SERVICES ..................................... 142

    7.0 PLUMBING & SANITARY....................................................................................................... 191

    8.0 FIRE PROTECTION SERVICES ............................................................................................. 212

    9.0 SWIMMING POOL SERVICES ............................................................................................... 242

    10.0 SCHEDULE OF UNIT RATE ................................................................................................... 258

    11.0 SCHEDULES OF TECHNICAL DATA .................................................................................... 310

    12.0 SCHEDULE OF SUB-CONTRACTOR ................................................................................... 331

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 3

    1.0 Project Team

    Owner Vietnam International Township Development Jsc (Parkcity)

    No.8, Quang Trung Road, Ha Dong - Hanoi, Vietnam Tel +84 4 3355 3366 Fax +84 4 3355 3365

    Architect Archicentre (Vietnam) Co.,Ltd.

    31 Phan Boi Chau Street, Ward 14, Binh Thanh District Ho Chi Minh City, Viet Nam Tel: +603 5633 2455 / +84 83841 3883 Fax: +603 5633 8213 / +84 83841 8516

    Structural & Civil engineer

    Tham & Wong VN Co.,Ltd.

    4th

    Floor, Packsimex Building, No.52 Dong Du, District 1 Ho Chi Minh City, Viet Nam Tel: +84 8 3821 7737 Fax: +84 8 3821 7736

    M&E Consulting Engineer

    Tham & Wong M&E (Vietnam) Co.,Ltd.

    No.06, 2nd

    Alley, Pham Tuan Tai street, Cau Giay District Ha Noi, Viet Nam Tel: +84 43748 0327 Fax: +84 43755 8903

    Landscape Designer

    Site Concepts International (Vietnam) Company Limited Landscape Architecture

    9th Floor WMC Tower, 102 A-B-C Cong Quynh Street, Pham Ngu Lao Ward, District 1, Ho Chi Minh City, Vietnam. Tel: (84) 8 3920 9895

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 4

    2.0 General Requirements

    2.1 General

    This Specification describes the standards, performance, materials, manufacture, supply, installation, testing, commissioning, operation and maintenance of all systems described in this document and shown on the Drawings.

    The intent of the Contract is to provide for the completion in every detail of the Contract Works, and unless otherwise stated, the Contractor shall furnish all labour, superintendence, materials, tools, equipment, storage, permits, certificates, drawings, temporary work, inspection, testing and all accessories, auxiliaries and incidentals necessary to complete the Contract Works in a proper, safe, thorough and skilful manner to the satisfaction of the Employer/Engineer.

    2.2 Site of the Contract Works

    The site is located as shown on the Tender Drawings.

    2.3 Climatic Conditions

    The Contractor is deemed to be familiar with climatic conditions prevailing in Vietnam and to be aware of the high temperature (up to 40

    0C) and the high relative humidity.

    The Contractor in submitting a tender will be assumed to warrant that all materials and items of equipment are suitable for continued use and/or operation in the various climatic conditions encountered.

    2.4 Standards

    The Contract Works shall fully comply with all statutory obligations and regulations together with any amendments made thereto as required. The Contractor shall arrange for all submissions, liaisons and pay the cost of all statutory inspections and certificates. The payment to the Authorities shall be paid well in advance so as to meet with the construction programme. Where applicable, the Installation shall comply with the statutory obligations and regulations and consistent with good practice in Singapore to satisfy the Engineers requirements.

    Singapore Code of Practices;

    British Standards Institution or other approved international standards;

    Chartered Institution of Building Services Engineers;

    Air Conditioning and Refrigeration Institute;

    American Society of Heating, Refrigeration and Air Conditioning Engineers;

    The Regulations for the Electrical Equipment of Buildings published by the Institution of Electrical Engineers (London);

    Environmental Protection Department;

    Pollution Control and Drainage Act and Regulations;

    Environmental Public Health Act and Regulations and Codes;

    Building Control Act and Regulations;

    Fire Safety Act and Regulations;

    Factories Act and Regulations;

    Public Utilities Act and Regulations;

    Fire Precautions for Building;

    Handbook on Energy Conservation in Building and Building Services;

    Handbook on Application for Electricity Supply;

    Code of Practice for Info-Communications Facilities in Buildings;

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 5

    NPQS

    Any other local authority having jurisdiction; and

    All other requirements from Authorities having jurisdiction over the installation.

    Viet Nam Standard

    The work shall be carried out by a registered Licensed Worker approved by the relevant authority for each particular category of work. The Contractor shall submit for approval the following within one month of award of Contract for approval: Licensed Water Service Plumber

    Sanitary/Sewerage Registered Licensed Plumber

    Licensed Electrical Worker

    Where the materials or equipment offered comply with other standards, the Contractor shall demonstrate they meet the requirements of the Specification and details shall be provided to the Architect for approval.

    The Contractor shall provide and perform all necessary inspections and maintain quality and workmanship in his works to ensure compliance with the Specification.

    2.5 Building Provisions

    Certain provisions will be made in the existing Building for the accommodation of the Contract Works. These provisions shall include space allocation, holes / openings through structural slabs, walls and beams, plant bases, inserts etc. The modified building layout incorporating basic M&E Installations are shown in the tender Documents. The Contractor shall provide comprehensive builders work requirements for approval prior to the execution of works. It shall be the Contractors responsibility to ensure that all the required holes/openings and inserts and their setting out dimensions are incorporated in the structure prior to the formation of openings. Where additional holes/openings are required after concrete has been poured, such holes shall be provided at the Contractors expense, unless they are covered on a duly authorized basis by the Employer on an instruction issued by the Engineer. The Contractor shall also be responsible to ensure that these holes are correctly reserved and protected during construction. The floor and wall openings shall be provided by the Contractor. The Contractor shall take the responsibility to ensure the opening is technically sound and approved by their employed structural engineers if necessary. Infill and repairs around openings in the building structure for the passage of building services shall be carried out by the Contractor. Where pipes and services pass through walls, floors, etc.(including floors in ducts), the Contractor shall provide pipe sleeves and in fill between the sleeves and pipe/services. Concrete bases and/or foundations required for the support or anchoring of equipment shall be provided by the Contractor except where otherwise specified. The Contractor shall provide the dimensions and locations for all bases to be provided or set in the structure. The Contractor shall furnish the bolts to the Builder for setting the bolts in position. Anchor bolts in concrete bases shall be securely fixed in position before concrete is poured. Templates shall be furnished by the Contractor. All structural and supporting steelwork required for the installation of the Contract Works shall be supplied and fixed by the Contractor, except otherwise specified.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 6

    2.6 Limited Access

    The Contractor shall note the limited access available in ceilings, pipe and duct shafts. All cables busbars, duct work and pipework should be installed in the correct sequence to ensure that all services shall be accommodated. Where works by other trades are to occupy the same pipe and duct space, care must be taken to leave clear access for sequential or future provision of these services within builders work shafts, plant rooms and false ceilings, etc.

    2.7 Co-ordination Between Trades

    The acquisition and checking of all documents and drawings from the Engineer to be provided under the Contract and to ensure the compatible integration of all the work. Such co-ordination shall include recommending to the Engineer for approval design solutions to eliminate any conflict between elements of the work, and to provide adequate space between elements of the work for subsequent maintenance of the various installations in accordance with good practice.

    All checking, co-ordination and where necessary proposal to overcome conflicts in accordance with the above shall be executed well in advance of the programme for carrying out the works.

    The provision of co-ordinated working drawings incorporating all design solutions approved by the Engineer and showing the integration of all services to be executed by the Contractor.

    The establishment of a detailed sequence of work to enable the expeditious completion of the Works. The Contractor shall closely monitor the work progress and conflicts resolved in an expeditious manner.

    Liaison and co-ordination of works upon receipt of site instruction by the Engineer throughout the duration of the Contract.

    Co-ordination of government submission, testing and inspection of various building services works in a timely manner to comply with building construction programme and building occupation requirements.

    Liaison and co-ordination regarding training requirements to be provided to the Employer and handing over of the building services systems. Particular emphasis shall be given to the co-ordination of testing of various building services systems which require interface between different Contracts. Testing and commissioning shall be carried out within the Contract Period and only by agreement will the Engineer allow certain tests to be carried out within the Defects Liability Period.

    Receipt of lists of defects/outstanding work and liaise with the Builder for the rectification of defects within the Defects Liability Period. Co-ordination is deemed to include liaison for access and the ensure that rectification work is carried out in a expeditious manner.

    2.8 Metric Units The Contractor shall provide all information, drawings, manufacturers data and materials in metric (S.I.) units and dimensions or include a conversion table which must be printed on or within data sheets produced by the manufacturers. Separate locally produced, e.g. duplicated typed conversions or conversion tables within the written offer will not be acceptable.

    2.9 Notations

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 7

    Notations and symbols used throughout the tender documents area as listed on the abbreviations and symbols sheet of the Drawings. All other notations used shall have their normally accepted meaning and where any doubt or ambiguity is found, then the Contractor must seek clarification in writing form the Engineer at the time of tender

    2.10 Submissions Unless otherwise stated, all submissions to the Engineer for approval must be made at the times stated in the various Sections of this Specification. For material/ equipment submission, detail form of submission information and statement of compliance with this specification shall be provided for checking. All submissions must be made early enough in the Contract to enable the Engineer to fully check each item prior to giving approval. The Contractor shall ensure that submissions are made at least two months before any equipment is required to be ordered to meet the Builders contracts construction programme. The Contractor shall supply full drawings of all equipment to a scale suitable for the fullest understanding by the Engineer of the design details but in any event not less than a scale of 1:50, within the time required by the Engineer that they may be incorporated into other elements of works and as instructed by the Engineer, together with the fullest particulars and details of positions where power for any elements is required. The Contractor shall be responsible for ensuring that the works are carried out in strict accordance with the distributed working drawings. A schedule of submissions for individual, working drawings and equipment shall be submitted for checking within one week after award of Contract. Drawings showing locations of structural openings for services shall be submitted for consideration at least one month prior to erection of formwork or reinforcement at the affected area. No claims for extensions of time or additional costs shall be entertained as a result of the Contractors failure to make submissions in adequate time. If, in the opinion of the Engineer, the Contractors failure to make his submissions in adequate time may result in a delay in the completion of the project as a whole, then the Engineer shall have the authority to instruct the Contractor to order materials and or equipment from a source approved and nominated by the Engineer at no increase to the Contract Sum. If the Contractor subsequently fails to place such orders within a period of two weeks from receipt of the Engineers instruction, then the Employer shall have the right at his sole discretion to order the materials and/or equipment directly from the manufacturer(s). The cost of all such orders, including freight, shipping, insurance, handling and administrative charges shall be deducted from the Contract Sum or recovered in any other method at the discretion of the Employer. The Contractor shall on request, or where specified elsewhere, submit to the Engineer samples of materials and/or workmanship. Such samples shall be approved in writing before the appropriate equipment or installation work is carried out. Such samples shall be retained by the Engineer as the criteria of the workmanship or material to be supplied and any items not so complying may forthwith be rejected by the Engineer and shall be replaced by the Contractor without increase to the Contract Sum.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 8

    2.11 Sizes of Plant and Equipment The Contractor shall be required to demonstrate that the duties required of the equipment by the Specification are attainable by the Contractors proposed plant or equipment. Physical sizes of all plant and equipment are to be suitable for the spaces allocated for the accommodation of such plant and equipment, taking into account the requirement of access for maintenance purposes. Before ordering equipment, the Contractor shall provide the Engineer with full details of the weights of the equipment for purposes of determining floor loadings, etc.

    2.12 Makes and Types of Equipment The Contract has been drawn up in such a manner as to allow firms tendering to submit proposals incorporating their particular types of equipment and installation techniques while at the same time ensuring that that building services comply fully with the basic requirements and fit into the Building, having regard to the Engineering and planning requirements and to the provisions which are being arranged in the structure for the accommodation of the Contract Works. The Employer reserves the right to reject any tender which disregards the basic requirements or intentions of this Contract, or which seeks to vary the scope of the Contract Works, the Contract Conditions or any other requirements of the Tender Documents. In selecting makes and types of equipment, the Contractor shall ascertain that facilities for proper maintenance, repair and replacement can be provided without such a delay as could cause inconvenience or loss to the Employer.

    2.13 Working Drawings

    The Contractor is to note that the contract Drawings issued for the installation indicated the general design intent. The Contractor shall be responsible for the preparation and co-ordinating his working drawings with the services installations of other trades and with the fabric and the building structure, and for co-ordinating working drawings to facilitate co-ordination of the installation of all services in the correct sequence and position. All working drawings must be submitted to the Engineer and his confirmation must be obtained that such drawings comply with design intent prior to execution of the respective building services installation works. Co-ordination working drawings shall be submitted at the same time as the individual services working drawings to allow the Engineer to satisfy himself that co-ordination of the Works has been implemented. These drawings shall be based on the Contract Drawings and shall take into account any modification either to the Building or to the installation which may have taken place during the course of the works and shall be correctly related to the details of the actual items of plant and equipment installed. The Contractor shall prepare all equipment schedules and all necessary wiring diagrams, including internal wiring diagrams for items of electrical equipment and diagrams showing the interconnections and interface between different equipment and services. Five copies of all such drawings, schedules, diagrams, shall be submitted to the Engineer for approval before any work is commenced. After receiving written approval, six copies of all stamped approved drawings, schedules, shall be supplied by the Contractor, free of charge, for distribution. The Contractor is to allow in his programme for amendment and/or resubmission of drawings and schedules to the Engineer and this time shall include the periods necessary for co-ordinating with the Builder and other Contractors for the preparation of the aforesaid drawings

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 9

    and schedules and periods required by the Engineer for checking same. The Engineer shall endeavour to reply to the contractors Submissions within in a period of 2 weeks. No claim will be entertained nor extension of time be granted arising out of any amendment or resubmission required. The Contractor shall be fully responsible for updating the installation drawings based on any changes to the general plans which may from time to time be required. Checking of working drawings by the Engineer shall not relieve the Contractor of his responsibility for the technical, dimensional and co-ordination content of these working drawings, in accordance with the Engineers design drawings and specification and in observation of all relevant standards, codes and ordinances whether referred to in the specification or of a statutory nature.

    2.14 Builders Work Drawings The Contractor shall submit to the Engineer for approval and subsequent distribution showing details for all builders work required in connection with installation of all services. In case where preliminary builders work information has already been given on the Drawings, such information is to be checked and verified by the Contractor for incorporation in his own drawings. It is the intention that all holes, inserts and chases, shall be incorporated within the structural work as it proceeds and not cut out subsequently, except in so far as may be necessary due to subsequent authorized variations to the Contract Works. The Contractor shall acquaint himself throughout the period of the Builder Works with the Builders detailed construction programme and shall prepare the builders work drawings in such order and at such times as to enable them to be checked and approved and subsequently issued to the Builder not less than four weeks before the actual construction is planned to take place. No claims will be entertained in respect to additional holes, inserts and chases, that may be required after the structure has been erected unless these are necessary due to authorized variations to the Contract Works.

    2.15 Maintenance and Operation Manual Prior to the issuance of the Completion Certificate, the Contractor shall submit in triplicate full operation and service and maintenance manuals for the complete installation. These manuals shall be typed on good quality paper and neatly bound into a manual having rigid covers with good lettering, giving the names of the Employer, Project and M&E Contract and approximate date of completion. A sample shall be submitted to the Architect for approval before final submission.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 10

    The manuals shall contain and be set out as follows : Section 1 Maintenance Personnel

    List to include name, address, fax and telephone number for normal and emergency use separately.

    Section 2 System Summary & General Description & Operating Instruction

    Each system, separately, shall commence with the relevant Design Criteria, comprehensive functional description of equipment.

    Instructions for operating each items of plant, including adjustment of controls, etc

    Section 3 Emergency/Re-Start Instructions

    Each items of plant to be listed in the same order as for Section 2.

    Instructions to procedures after a fault, and for Plant production.

    Section 4 Equipment List & Schedules & Manufacturers Literatures & Spare Parts

    Include manufacturers' and suppliers' contact and serial numbers.

    Literature clearly designating the relevant item(s) of equipment, including detailed specification. Order as per Section 2, each with its own sub-file divider. Catalogue listing, including source of supply.

    Section 5 Maintenance Schedules & Maintenance Instructions

    Proforma copy detailed schedules of periodic checks and maintenance and replacement procedures.

    Include description of each items of equipment or component in order as per Section 2 listing, and with a complete phases and procedures preventative maintenance.

    Section 6 Commissioning Data

    Include schedule of control and cut-out settings, copies of test certificates and progressive test data obtained during construction and installation.

    Section 7 Guarantee, Liabilities, Warranties

    Section 8 Drawings

    List all working drawings produced for the works.

    Note: In order that each set of volumes for each of the M&E installations are uniform, where one of these sections is not relevant to a particular Service, the Contractor shall note against that section in the main index: "Not Applicable".

    2.16 As-Built Drawings

    Upon completion of the M&E Contract Works and as a condition precedent to the certification that the work is complete, the Contractor shall furnish to the Engineer one set of reproducible

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 11

    transparencies and two sets of prints and one set of electronic files in CD Rom and in such detail as to enable the employer to maintain, dismantle, reassemble and adjust all parts of the M&E Contract Works. The As-built drawings must be drawn in a format that is suitable for submission to all relevant Authorities and FSB in particular. a) As-built drawings may be folded and accommodated in the Operating and

    Maintenance Manual if appropriate.

    b) As-built drawings should include a diagrammatic layout of the complete installation with major items of plant suitably referenced to the schedules and combined services drawing.

    c) A set of the as-built drawings should be provided for each copy of the Operating & Maintenance Manual required to be provided. In addition, one set of AutoCAD soft copy burned in CD-ROM/DVD should be provided.

    The as-built drawings shall comprise the following:- A) Electrical Installation

    1. Lighting layout plan and lighting control layout plan (including surface and

    concealed cable, trunking/conduit routes on floor, wall and ceiling). 1. Power layout plan (same as above). 2. Telephone layout plan (same as above). 3. Data outlet layout plan (same as above). 4. Security layout plan (same as above). 5. Main single line diagram. 6. Switchboards, sub-switchboards, distribution boards, consumer units single

    line diagram, general arrangement. 7. Schematic diagram for various systems like Telephone System, Cable TV

    System, Security System, Audio / Video Colour Intercom System, etc.

    B) Air-Conditioning and Mechanical Ventilation Installation

    1. Technical data/equipment schedule and brand of all A/C equipment and MV fans.

    2. A/C layout plan include any concealed pipings and conduits clearly demarketed on plan and elevation. The cooling capacity of each system/ outlet to be indicated.

    3. MV layout showing ductwork sizes, air quantity, guide-vane control and accessories.

    4. Control panels location, size and circuit diagrams. 5. Details of all equipment, model and capacity. 6. Schematic diagram. 7. Operational procedure of selected equipment clearly indicated.

    C) Sanitary and Drainage Installation

    1. Inspection chamber c/w pipework connection and gradient, all invert and top levels indicated.

    2. Sanitary pipework layout plan, including sump pump detail (if any) 3. All models of sanitary fittings: wc, basin, sink, shower, tap, etc. 4. Soil waste pipe and vent pipe riser duct details. 5. Schematic diagram of sanitary installation. 6. Catalogues of all sanitary wares (where applicable), pipes and pipe-fittings. 7. Operational procedure of selected equipment clearly indicating the model and

    capacity. 8. Control panels location, size and circuit diagrams.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 12

    9. Manhole c/w pipework connection and gradient, all invert & top levels indicated

    D) Water Supply Installation

    1. Water reticulation layout plans. 2. Detail for Water meter kiosk layout, pump and tank 3. Schematic diagram.of Cold and Hot water supply systems 4. Operation procedure of pump, electric water storage heaters. 5. Control panels location, size and circuit diagrams. 6. Valve chamber c/w pipe work connection, all invert & top levels 7. Detail of bulk water meter c/w valve chamber

    2.17 As-new Condition At the time of hand over of the Contract Works, the whole installation shall be in as-new condition. The Contractor shall, during the course of the Contract, protect all plant and equipment, and shall restore/repaint as necessary before completion of the Contract.

    2.18 Guarantee The Contractor in providing a specified piece of equipment or apparatus, whether specified herein by name or whether of a make selected by the Contractor, shall be deemed to warrant its satisfactory performance under all working conditions which may be encountered. Unless otherwise stated in this Specification, the Contractors guarantee for the Contract Works shall extend for a period of one year from the expiration of the Defects Liability Period or the date of issue of the Certificate of Making Good Defects whichever is the later for the Contract Works. In the event that any manufacturers guarantees are still within their term of validity at the end of the Guarantee Period, then all such manufacturers guarantees shall be assigned to the Employer. All subsequent rights under the manufacturers guarantees shall be the Employers. In the event of anything described in the Specification or shown in the Drawings being, in the Contractors opinion, unsuitable or inconsistent with his guarantee or responsibilities, the Contractor shall draw attention to such items at the time of tendering. Neither the time limit imposed on the Contractors guarantee, nor the Certificate of Making Good Defects issued by the Engineer, nor the acceptance of the installation by the Employer, nor the approval by the Engineer of any material or method shall in any way absolve the Contractor from his responsibility for any latent defects in the Contract Works which may become apparent in the future and which are, in the opinion of the Engineer, due to the Contractors failure to use materials and methods complying to this Specification and Drawings.

    2.19 Materials and Workmanship All materials supplied and work carried out shall be the best of their respective kinds and to the approval of the Engineer. All materials and work shall comply with British Standards where available. No substitution for approved materials will be permitted except by permission of the Engineer in writing. Any cost savings which result from such substitution shall be credited in full to the Employer. Any extra costs incurred shall be borne in full by the Contractor.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 13

    The phase or other Approved is deemed to be included whenever materials are specified by proprietary name. Materials of different manufacture but of equal quality may be substituted if prior Approval has been obtained but the rates and prices will not be changed from those submitted at the time of tender. The standard of equal quality, together with consideration of design suitability and appearance, will be strictly applied and the Contractor will be required to pay for independent testing to demonstrate equal quality prior to seeking Approval for any alternative to the proprietary brand specified. Where a choice of manufacturer is permitted for any material, advise the Engineer of that choice early enough to allow deliveries to be arranged in compliance with the construction programme. No change in the source of supply will be approved after deliveries have commenced.

    2.20 Rejection of Unsuitable Materials The Engineer shall be at liberty to reject any plant, materials and workmanship not complying with the requirements of this Specification or which are in any way unsuitable and to order their removal and replacement, without increase to the Contract Sum. The Engineers decision as to what constitutes compliance with requirements and suitability shall be final and binding; the true intent and meaning of the Contract being that the whole of the Contract Works shall be completed to the satisfaction of the Engineer. No rejected item shall be considered as a reason for failure to meet the completion date of the project.

    2.21 Packing and Protection All plant, equipment, apparatus, materials and parts shall be delivered to the Site in a new condition, properly packed and protected against damage due to handling, adverse weather or other circumstances, and as far as practicable, they shall be kept in the packing cases or under protective coverings until required for use. Any items suffering damage in transit or on the Site shall be rejected and replaced without extra cost to the Employer. No item so rejected will be considered as a reason for failure to meet the completion date of the project.

    2.22 Vesting of Plant and Equipment The Contractor shall take reasonable measures to avoid damage, loss, etc., of material, plant or equipment to be incorporated in the completed Building during the progress of the Works.

    2.23 Samples The Contractor shall on request or where specified elsewhere submit to the Engineer samples of materials and/or workmanship and such samples shall be approved in writing before the appropriate equipment or installation work is carried out. Such samples are subsequently to be retained by the Engineer as the criteria of the standard of the workmanship or material to be supplied and any items not so complying may forthwith be rejected by the Engineer and shall be replaced by the Contractor without increase to the Contract Sum.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 14

    2.24 Silence of Operation The Contract Works as installed shall be reasonably silent in operation having regard to the conditions under and locations in which they will be called upon to operate. The Contractor shall take all necessary steps to ensure that the equipment supplied by him is silent as specified and shall include for such sound absorbing, or anti-vibration, material or devices as are necessary to ensure a satisfactory degree of silence and absence of vibration in the structure of the Building. The Engineers decision as to what constitutes satisfaction in this respect shall be final. If on completion the system is not, in the Engineers opinion, sufficiently silent, the Contractor shall, without additional charge, carry out such modifications or additions as may be required, until the system is made silent to the Engineers satisfaction. Octave band sound pressure levels in the various areas within the building and at certain positions outside the building due to the operation of the equipment included in this Contract shall not exceed the noise level ratings as set down from Government Authorities.

    2.25 Storage and Delivery of Equipment

    The Contractor shall, arrange storage and delivery of the equipment to suit the progress of the Works. Storage areas and siting together with routing to and from such storage areas of heavy equipment on Site in relation to structural loading restriction shall be submitted to the Engineer for approval.

    2.26 Contractors Programme

    The Contractor shall provide a bar chart programme giving realistic schedules or working periods to conform to the construction Programme for the Contract Works. The bar chart programme shall indicate how the various activities will be scheduled in order to complete the Contract Works within the Contract Period. Activities included in the Contractors programme shall take account of, without limitation, the following : -

    Submission for approval of all equipment;

    Ordering of equipment;

    Manufacture of equipment;

    Delivery of equipment;

    Installation of equipment and plants;

    Submission to and inspection by Authorities;

    Testing, balancing and commissioning;

    Submission of As Installed Drawings, operating, Maintenance Manuals and maintenance programme.

    The above list is indicative but not exhaustive of all factors required.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 15

    2.27 Origin of Materials

    The Contractor shall produce documentary evidence to verify the place of origin for the materials delivered to site or installed. Such documentary evidence shall be in the form of purchase orders to, and shipment/delivery orders or produce certificates from the manufacturers or the manufacturers agents in Singapore. The materials or the works employing such materials will not be certified for payment until the required evidence has been produced to the satisfaction of the Engineer. The Tenderer shall indicate in the Schedule of Information Supplied by the Tenderers the place of origin of the materials being offered at the time of tendering.

    2.28 Electricity Supply Unless otherwise specified, the complete electrical installation shall be suitable for operation under the supply system with nominal frequency of 50Hz and nominal voltage of 400V, 3 phases and 230V, single phase within the variation limits as declared by Authority.

    2.29 Radio and Television Interference

    All electrically operated equipment used by the Contractor for the execution of the works shall where applicable have suppressors fitted to prevent interference with radio, television in use in the neighbourhood. The above applies equally to all new items of equipment supplied and fixed by the Contractor. Means of suppression shall comply with B.S. 800. Equipment and materials used in determining the level of interference shall be in accordance with B.S. 727. Reference shall also be made to B.S. CP1006 for further guidance in order to meet the specified standards.

    2.30 Calculations

    The Contractor shall supply all calculations as may be required by the Engineer. Calculations shall be submitted in triplicate, and shall be based on equipment selected and offered by the Contractor. The checking of calculations for compliance with Design Intent, shall not relieve the Contractor from his responsibility or necessity of furnishing material or performing work as required by this Specification and/or Drawings.

    2.31 Safety Precautions The Contractor shall arrange for the provision of industrial safety helmets to B.S. 2826 for the use of all his personnel on site, including supervision staff. The Contractor shall ensure that helmets are worn, when necessary by all his personnel on site. The Contractor shall be responsible for ensuring that all works are carried out in a safe manner.

    2.32 Testing and Commissioning After having satisfied himself of the performance of the installation, the Contractor shall demonstrate to the satisfaction of the Engineer that the installation or part thereof as the case may be, complies with all the requirements of the Specification.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 16

    The Contractor shall provide all necessary facilities and instruments for the witnessing and checking of such tests, but this shall not relieve the Contractor of his responsibility for testing and satisfying himself of the adequacy of the installation before hand. The Contractor shall make complete records of the tests as carried out and when the tests have been successfully completed, he shall provide the Engineer with test records in triplicate on a form to be agreed upon. All tests shall be carried out at the direction of the Engineer. Should the test results indicate that the plant or equipment is not functioning in a satisfactory manner or complying with the requirements of the Specification, the Contractor shall carry out at his own expense any alteration, replacement or adjustment as may be required to correct the faulty work. The Engineers decision as to what constitutes a satisfactory test shall be final. All the equipment and systems shall be examined and tested after completion of the installation work. The Contractor shall furnish the Engineer with copies, in triplicate, of test certificates in respect of all plant, equipment, materials and accessories showing compliance with tests to British or any other comparable and acceptable standards, manufacturers instruction, applicable insurance company or Governments requirements, and with any additional tests specifically called for herein. The Contractor shall be responsible for and bear all the costs in connection with any inspection, tests and permits for the installation and shall make such tests as are called for by any regulations or authorities. These tests shall be made in the presence of the authorized representative of any such authority. The Employer may permit the Contractor to make use of the permanent facilities from the utility companies to perform functional checks, and commissioning tests on the plumbing & drainage equipment, provided that: All plant & equipment are maintained, to as-new condition at the time of handing over of the installation. Should there be any damage to any part of the installation, the Contractor shall undertake to repair and replace all damaged parts/components to the satisfaction of the Engineer. In particular, the Contractor shall note that all equipment for the use of future tenants shall be fully commissioned prior to hand over that is to say, All equipment/fittings shall be made to work to demonstrate that they are fully functional after installation. All Protection Installation and distribution equipment shall be tested for full performance. The Engineer shall be entitled at all reasonable times during manufacture to inspect, examine, and test on the Contractors premises the materials and workmanship of all equipment to be supplied under the Contract. Such inspection, examination, or testing, if made, shall not release the Contractors from any obligation under the Contract. All costs shall be borne by the Contractor. At least two months prior to testing or commissioning any system, the Contractor shall furnish the following information for each system or process to the Engineer for approval:-

    Type of instruments to be used;

    Manufacturer of instruments;

    Calibration methods for instruments;

    Operating instruction for instruments;

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 17

    Accuracy and tolerances of instruments; Proposed formats for testing and commissioning reports; and

    Complete schedule and programme of all testing and commissioning activities. All plant, materials and systems shall be tested, balanced and commissioned as specified in the Commissioning and Testing Section of this specification. All testing, balancing and commissioning procedures and documentation shall be approved by the Engineer prior to commencement. Four sets of all documents shall be provided for record purposes. All instruments shall have been recalibrated within six months of the start of commissioning or testing. Calibration of all instruments shall be certified by the instruments manufacturer or an approved calibration agency.

    2.33 Period of Notice A minimum of seven days notice shall be given to the Engineer before all testing and commissioning operations commence. A minimum of four weeks notice shall be given in the case of factory tests on major plant.

    2.34 Employers Instruction

    The Contractor shall include in the Tender a minimum period of one month for giving instructions training to the Employer regarding the operational details and maintenance requirements of the plants and equipment to be installed in this Contract. During this period, a full time engineer shall be assigned to co-ordinate training for the Employer. Training shall consist of work sessions to explain in details the installation followed by site training on the actual operation and maintenance of equipment. The Contractor shall allow in the Tender for operating all plant and equipment on behalf of the Employer for One (1) month following issue of the Certificate of Practical Completion.

    2.35 Free Maintenance and Service Apart from his contractual responsibilities for making good inherent defects, the Contractor shall furnish maintenance service free of charge on the entire equipment supplied and installed under this Contractor from the completion of the installation under this Contractor, until twelve months after the Practical Completion of whole of the Works. Maintenance shall include systematic and periodical examination, adjustment and lubrication of all equipment, details of which shall be submitted to the Engineer for approval. During this Free Maintenance and Service period, the Contractor shall also repair or replace electrical and mechanical parts of the equipment wherever this is required and shall be only genuine standard parts produced by the manufacturer of the equipment concerned. In the case if standard parts being not readily available, a substitute may be accepted for emergency use but must be replaced with the standard part as soon as possible all at the Contractors expense. Renewals or repair necessitated by reason of negligence or misuse of the equipment, or by reason of any other cause beyond the control of the Contractor, except ordinary wear and tear, shall not be the responsibility of the Contractor. All works under this maintenance provision shall be performed by competent personnel under the supervision and in the direct employ of the Contractor. At the end of the free maintenance period, a further test will carried out by the Contractor on the plant in the presence of the Employers representatives, and any defects shall be rectified by the Contractor without charge, to the satisfaction of the Engineer, as part of his normal contractual obligation.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 18

    2.36 Spare Items The Contractor is required to guarantee that sufficient spare items of the specified materials and goods are available to allow for the timely replacement of any defective ones during the free maintenance period.

    2.37 Maintenance Contract The Contract shall submit with his tender the yearly cost and terms for the periodical inspection, testing maintenance and repair of the whole installation and equipment to be installed under this Contract for 3 years after the first twelve months of free maintenance.

    2.38 Contractors Management and Site Organisation The Contractor shall provide an experienced and fully qualified management team under the overall direction and co-ordination of the Contractors Project Manager. The site organisation shall include a competent Site Engineer, together with the necessary back-up technical staff to supervise the work and to undertake co-ordination duties with the Engineer. The Project Manager and site engineer shall be English and Mandarin speaking. The management organisation and principle staff shall be provided to the satisfaction and approval of the Employer and the Engineer. The Project Manager shall be fully responsible for the timely completion of the entire Works to the quality and the standards specified. He shall be a corporate member of a recognised professional institute and must have a well demonstrated record in project management of satisfactorily completed commercial rise projects. He shall be supported by an extensive back up team to the satisfaction of the Engineer to ensure that the project is managed in a comprehensive and orderly fashion. The Contractor shall engage sufficient qualified and experienced site staff to execute the Contractor Works. Registered and licensed trades person shall be employed and under the direct employment of the Contractor and they shall be full time on site to supervise the works. When requested by the Architect, sufficient draughtsmen shall be kept on site to facilitate prompt preparation and issuance of shop drawings. The Site Engineer shall be constantly on the Works responsible to the Project Manager for the timely completion to the specified quality and standards. The Site Engineer is to be exclusively employed for this Contract and is to be constantly upon the Works from commencement of Works until the end of the Defect Liability Period.

    2.39 Method Statements Prepare and submit method statements for enabling works, installation, testing, commissioning, operation, demonstration, training and hand over procedures.

    2.40 Certification and Approval

    The Contractor shall be responsible for all technical submission, applications and liaison with government departments and supply authorities, whether they are new submission or following up of previous submission already made. The Contractor shall be responsible for obtaining all the necessary approvals and certificates for his installation and payments (excluding meter deposit, if any) for his applications.

    2.41 Design Requirement and System Description

    The contractor shall supply, deliver, install, test and set into perfect operating condition the automatic fire protection and fire alarm system required for the above premises as shown in

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 19

    the drawing. All equipment selected shall be of equivalent or higher standard to the existing installation. The Contractors particular attention is drawn to the items listed in this clause which will involve in design, specification and/or selection of items based on such designs and specification. The selection of manufacturers or suppliers, equipment, plant, components or materials against the requirement specified herein shall not be deemed to be the design or specification by the Contractor under this clause. The production of shop drawing by the Contractor for construction purpose shall not be deemed to be the design or specification by the Contractor under this clause. The items which will involve the Contractor in design or specification are as listed below: a. Supporting systems including brackets, suspension rods, fixing methods including

    builders work bases as necessary to support and secure the complete installation forming the Works.

    b. Modifications as necessary to designs indicated on the Contract Drawings to incorporate

    the specific items of plant and equipment and components selected to meet the requirements as specified herein.

    c. Adjustments to plant and equipment to allow for deviations between specified

    requirements or data and details of items selected for incorporation into the Works.

    d. Obtaining the Engineers prior approval on the equipment appearance, colour, finish and method of installation for those equipment exposed in the lobbies/corridors/shop etc.

    2.42 Performance Guarantee

    The system schematic, layout and the equipment data in the technical schedules is meant as guide. The Contractor shall be solely responsible for the complete design, supply, and installation of a complete operable system and shall guarantee the performance to meet the conditional criteria.

    2.43 M&E Painting, Colour Coding and Labelling General Except where otherwise specified the external surfaces of all conduits, apparatus, equipment, fittings and services including supports, hangers and brackets shall be painted. All sheet metal control cabinets, switchboards and distribution board enclosures and similar shall be painted internally and externally. All surfaces are to be painted and shall be cleaned, prime coated, undercoated and then finished with two finishing coats. Each coating (including priming, undercoating and the first finishing coat) shall be allowed to dry and shall be rubbed down before the next coat is applied. Surfaces Not to be Painted (i) Fibreglass and plastic surfaces. (ii) Chrome plate and stainless steel surfaces.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 20

    (iii) Bearing surfaces slides adjusting screws and any surface that is required to be unpainted for the correct operation for adjustment of the equipment.

    (iv) Hot dipped galvanised lamp holes.

    Paint Material All paint and other preparations shall be non-poisonous, lead-free prepared synthetic products of approved brand, conforming to the relevant British Standard, brought onto the site ready mixed in manufacturers sealed containers and used to the manufacturers Specification. Preparation of Surfaces and Prime Coating Metal surfaces shall be wire-brushed to remove loose rust and scale. Castings shall be either ground smooth or alternatively filled with approved filling compound and then rubbed to a smooth finish. Steel plate and all rolled steel sections including brackets and supports not galvanised, shall be given an application of cold phosphate compound before being prime coated with red zinc chromate primer. Steel pipes and conduits delivered to the site unpainted shall be prime coated as specified for steel plate. All galvanised or zinc sprayed steel surfaces and all non-ferrous surfaces shall be given an application of PVB / Zinc chromate self-etching primer before being prime coated as specified above. Machinery, apparatus, equipment and fittings delivered to the site already prime or finish painted shall be thoroughly cleaned down. Finishes Each finishing coat shall be of a different shade. The final coat shall be left smooth, even and free from the visible brush marks and other defects.

    For surfaces, which shall operate below 93C, the finishing coat shall be high-grade alkyd enamel. Piping, cable enclosures and conduits shall be painted to a gloss finish in colour or colours to conform to Schedule of Colours. The ground colour shall extend throughout the entire length of piping, cable enclosures and conduits installed in the following locations:

    (a) Plant rooms;

    (b) Piping in trenches;

    (c) Piping in basements underground floors and in vertical ducts; and

    (d) Wherever exposed to weather or to view.

    All piping, cable enclosures and conduits installed in ceilings and similar concealed spaces shall have the ground colour applied in 400mm wide bands spaced at 6m centres except that ground colour bands shall be provided adjacent to branches, junctions, valves, floors and walls (both sides).

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 21

    Labelling All instruments, gauges, indicators, control equipment contactors, circuit breakers, switches, starters, relays and cable terminals on switchboards, etc., shall be clearly labelled and identified with their associated function. Labels shall be of laminated plastic with engraved upper case black letters on a white background. Plastic labels shall be attached by screw or rivet-fixing. Punch machine type strip lettering and stick-on markings will not be approved. Lettering shall not be less than 12mm high. Lettering for items installed in switchboards and on control panels shall not be less than 9mm high. Schedule of Colours Equipment, conduit and trunking shall be identified in accordance with relevant standard and in accordance with the following schedule:

    Equipment / Services Finish / Colour Labelling / Identification

    Electrical Panel Labels Exterior / Grey Interior : Grey

    Engraved

    Electrical Conduit and Trunking Orange or Match surrounding Grey Band

    Speaker Conduit and Trunking White or Match surrounding Blue Band

    Telephone Conduit and Trunking Green or Match surrounding Orange Band

    Surface Light Fitting White

    Suspension Rod and Channels Potable /drinking water pipe

    White Green

    Black/flow direction

    Town Gas Yellow Black/flow direction

    2.44 Construction programme The Contractor shall provide the equipment and carry out the works based on The Practical Completion Date in this Document. The Contractor shall include the cost of the Contract to meet the construction programme requirement and project completion date. Detail programme shall be submitted by the Contractor for Engineers approval.

    2.45 External Noise Criteria The mechanical systems shall be such designed that noise generated will not be greater than 45 db(A) during daytime and 40 db(A) during night time when measured at 10 metres from boundary. Under no circumstance the noise generated shall exceed the values as stipulated in Environmental Protection Departments requirement. Acoustic treatment shall be provided by the Contractor when noise generated exceeds the above stated values and when the environment is affected.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 22

    3.0 Scope Of work

    The scope shall include but not limited to:

    3.1 Electrical Installation 3.1.1 Scope of work for external works

    a. Lead-in H.D. UPVC Pipes for Electrical, Telecom, Cable TV System from the Authority intake point (1000mm beyond existing open drain) to the meter compartment as shown.

    b. Lead-in H.D. UPVC Pipes for Electrical, Telecom, Cable TV & Security System c/w MCTs at both ends

    c. Outdoor distribution boards, and submains as shown.

    d. External/Landscape, wiring.

    e. Take delivery and installation of all light fittings.

    f. Supply labour for installation of equipments, and lay Data control cabling including all necessary termination works.

    g. Supply & install Cable TV System including cabling works & necessary equipments, accessories and concealed/exposed conduit.

    h. External/Landscape Lighting layout as per drawing.

    i. Testing & commissioning for all system.

    j. Attendance to Power supply application and submission, inspection by all relevant authorities including engagement of Licensed Electrical Worker (LEW).

    3.1.2 Scope of work for typical units.

    k. Lead-in H.D. UPVC Pipes for Electrical, Telecom, Cable TV System from the Authority intake point (1000mm beyond existing open drain) to the meter compartment as shown.

    l. Supply & install Meter Panel (MP-1) located at Gate Pillar c/w Authority metering facilities. Incoming supply sigle phase c/w necessary protection relay

    m. Lead-in H.D. UPVC Pipes for Electrical, Telecom, Cable TV c/w MCTs at both ends

    n. Distribution boards, and submains as shown.

    o. Small Power Distribution.

    p. Lighting points, Ceiling fan points and wiring.

    q. External/Landscape lighting and wiring.

    r. Take delivery and installation of all light fittings.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 23

    s. Supply labour for installation of equipments, and lay Data control cabling including all necessary termination works.

    t. Supply & install Telephone System including Key phone system Panel, cabling works, necessary accessories and UPVC concealed/exposed conduit/ metal trunking as shown.

    u. Supply & install Cable TV System including TV splitter, cabling works & necessary equipments, accessories and UPVC concealed/exposed conduit/ metal trunking.

    v. Lightning Protection System & Earthing System.

    w. Testing & commissioning for all system.

    x. Attendance to Power company application and submission, inspection by all relevant authorities including engagement of Licensed Electrical Worker (LEW).

    3.2 Air-conditioning & Ventilation Installation for typical units

    a. Take delivery and installation of the Air-cooled Split Air-Conditioning equipments.

    b. Supply and Installation of the Air Conditioning refrigerant pipes, drain pipes, electrical wiring & control, etc. as shown in the tender drawings.

    c. Toilet exhaust systems c/w fans, ductworks, grilles, external weatherproof louvres, etc. as shown in the tender drawings.

    d. Take delivery and installation of the Air-cooled Split Air-Conditioning equipments.

    e. Testing & Commissioning.

    3.3 Plumbing and Sanitary Installation

    3.3.1 Scope of work for external works

    a. Supply and install of external underground sewer drainage system.

    b. Supply and install of external plumbing & fire protection system.

    c. Supply and install of external storm water drainage system.

    d. Take delivery and fixing of all sanitary and plumbing fittings

    e. Testing & Commissioning.

    f. Attendance to PUB/ENV application and submission of water and sanitary plans, inspection by all relevant authorities including engagement of licensed plumber, Licensed Water Service Plumber and Qualified Person/Professional Engineer.

    3.3.2 Scope of work for typical units

    g. Supply and install of Internal underground sanitary drainage system.

    h. Supply and install of Internal plumbing system.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 24

    i. Supply and install of Internal aboveground sanitary drainage system.

    j. Supply and install of Waste water pumping system

    k. Supply and install of Rain water pumping system (if any)

    l. Supply and install of Cold and Hot water supply system.

    m. Supply and install of Complete domestic water hydro-pneumatic Booster pump, & storage tank system. The booster pump system inclusive pumps, pressure vessel, pipe work, fittings, VSD Drive, control panel complete with wiring, pump starters, water level sensors, controls, relays, trunking, conduit, pump automatic operation and change-over to standby pump and accessories.

    n. Supply and install of Electric water storage Heater system.

    o. Take delivery and fixing of all sanitary and plumbing fittings

    p. Electrical equipment and installation work.

    q. Testing & Commissioning.

    r. Attendance to Authorities application and submission of water (including booster pump system, pressure vessels and domestic water tank) and sanitary plans, inspection by all relevant authorities including engagement of licensed plumber, Licensed Water Service Plumber and Qualified Person/Professional Engineer.

    3.4 General Scopes

    a. Acoustic treatment and vibration control.

    b. All interfacing work with other trades.

    c. Painting and labelling of pipework and equipment.

    d. Provision of all hold down bolts, spigots struts and the like required to be built in during construction.

    e. Testing and commissioning.

    f. Provision of twelve (12) months operational maintenance and breakdown services for external services. The period shall commence immediately upon issuance of the Architects Completion Certification or handing-over date of the service to the authorities, whichever is later.

    g. Provision of operating instructions and maintenance manuals; as-fitted drawings.

    h. Application, Submission and Liaison with authorities to obtain all necessary certificates and approvals, including the completion of all submission drawings, forms and payment of any fees and charges. All the costs for all the tests as required by all relevant authorities shall be included.

    i. Take, delivery from site, installation, handling, commissioning and protection of all sanitary wares and fittings including all valves, accessories, taps, brackets, plugs, complete as specified.

    j. Provision of spare parts.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 25

    k. Training of the employer for proper operation of the entire systems.

    l. Provision of the necessary installation which include pipework, connection of water supply, conduit and control wiring, etc. to form a workable system as required.

    m. Attend to all authorities inspections regardless of whether this inspection is carried out after the defect liability period.

    n. All other works and systems as specified in the Contract document and or shown on the drawings.

    o. All M&E installation works shall be in accordance to the construction phasing programme which include the various completion dates, target dates etc. for the different areas in the development.

    3.5 Servicing and Maintenance.

    General The works as described hereunder are for the servicing and maintenance of all the systems and ancillary plant, machineries and equipment supplied and installed under the works during and after the Maintenance Period and includes the supply of all materials, tools, apparatus, equipment and appliances, labour and necessary incidentals. During the Maintenance Period, the replacement and/or repairs of all defective plants, machineries and equipment and installations or any parts thereof shall be entirely free of charge to the Employer, if such repairs or replacements are necessitated by reason of defective design, materials or workmanship.

    Workmanship and Materials The servicing, maintenance and repair (or replacement) shall be performed by skilled and competent workmen and shall be executed in accordance with the best commercial, technical and engineering practice. All materials to be supplied shall be new and unused, and shall generally be of the best quality as regards manufacture and performance.

    Supervision The servicing, maintenance and repair (or replacement) works shall be under the charge of a Supervisor. For works required by local laws and regulations to be performed by licensed or registered personnel, the Supervisor shall deem to have the appropriate licence or registration. This Supervisor shall also be fully competent in supervising the servicing, maintenance and repair (or replacement) work and be acceptable to the Employer.

    Scope of Work

    All plant, machineries and equipment comprising the complete systems and ancillary equipment supplied and installed under these Works shall be serviced and maintained strictly in accordance with the requirements/recommendations as stipulated by all the plant and equipment manufacturers as well as in compliance with all by-laws, rules, regulations and requirements of the Local Authorities and shall also satisfy all appropriate Singapore Standards including all relevant Codes of Practice. The Works includes the preparation of a comprehensive servicing and maintenance schedule which shall be submitted to the Architect / Engineer for review after the award of the Work. The reviewed schedule shall then be included and shall form an integral part of the Operating and Maintenance Instructions and Parts List including monthly servicing.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 26

    The time and day for carrying out the servicing, maintenance and repair shall have agreement with the Employer. It is to be expected that working outside normal working hours (i.e. overtime) will be required. Also emergency repair services if so requested by the Employer shall be carried out at any time of the day (overtime included). It shall be contractually bound that the Employer be immediately advised of any defects or deterioration in any part of the equipment/materials observed during the routine inspection and servicing.

    The Works shall include the services of a Licensed Electrical Worker to take charge of the entire Electrical Installation of the entire Building including those related to all other building services, i.e. Air Conditioning & Ventilation, Fire Fighting & Alarm, Lifts, Sanitary and Plumbing, etc. for licensing purpose (if applicable). All costs connected therewith including fees payable to the Authorities are deemed to have been included during the Maintenance Period.

    The Works shall include routine inspections, servicing and maintenance of all the equipment, machinery and plant to be carried out outside the peak hours of the building of at agreeable time with the Employer. The routine inspections, servicing and maintenance schedule shall be so arranged that minimum inconvenience and interruption shall be caused to the occupants and Employer. During every regular inspection, the Works to be performed shall include but not limited to the following:

    (a) Check the performance of the complete Installation, including cleaning and adjusting all

    control devices as and when technically necessary.

    (b) Advise the Employer's operators/maintenance in respect of the emergency rescue, correct operation procedure etc.

    (c) Report in writing to the Employer any defects discovered, coming to light or observed in

    any part or parts of the Installation. Such reports shall state fully the cause(s) of such defect(s) and shall include, where applicable, an estimate of the cost of repairs or replacement of the defective part or parts required.

    (d) Record, in the log book for each element of the Installation, kept by the Employer,

    particulars of all maintenance or repair works carried out and initial all entries in the log book.

    (e) Tests as and when necessary, any part of the Installation.

    (f) Report in writing to the Employer all servicing & maintenance works carried out.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 27

    4.0 Responsibilities of Contractor

    The Contractor is to price for the followings:

    Provision of hoisting facilities.

    Provision of artificial lighting and temporary electricity supplies including power for testing and commissioning of air-conditioning and ventilation, lifts and electrical installation which will be from the permanent installations.

    Removal of rubbish from locations on each floor.

    Securing the building and building works in such a manner that it will not be subjected to damage by construction activities such as falling debris or water seepage during the progress of the Contract works.

    Protecting, casing up and accepting full responsibility for loss or damage to which have been fully, finally and properly incorporated into the Works.

    Additional costs incurred due to the working hour different from and extended hours to those worked by the Contractor.

    Provision of all setting out and survey information including giving all necessary dimensions and taking responsibility for their accuracy.

    Programming, co-ordinating and organising the contractors work to ensure the correct timing, sequencing and completion of all operations including preparing co-ordinated working drawings of all services.

    Ascertaining all particulars relating to the contract works in regard to sizes and positions of chases, holes and the like which are to be formed or left in the structure.

    Cutting and forming holes, recesses, etc. for ductwork, pipes, conduits and fittings through walls, floors, ceilings, roofs, etc. and making good after the contract works are sufficiently advance. Cutting holes through false ceilings and special partitions shall be by the respective specialist contractors. The contractor shall be responsible for chasing of walls for pipes, conduits and fittings and making good.

    Filling, grouting and making good under lift shaft entrance sills, around lift doorways and casings for buttons and indicators, etc.

    Building-in or casting-in of inserts, bolts, sleeves for pipes, ducts, trunking, guide rails, equipment, suspension systems etc. The contractor will provide the inserts, bolts, sleeves, etc. and will locate the correct position for these fittings. Sealing between the sleeve and the pipe, duct, trunking, etc. will be executed by the contractor, in addition, sealing between the sleeve and building structure (i.e. floors, walls) will also be by the Contractor.

    Marking the locations of any pre-stressing cables on the soffit of structural floors, face of walls etc.

    The formation of concrete bases, plinths, inertia blocks, etc. for plant and equipment, door louvres, exhaust discharge (external) grilles and fresh air intake louvres, unless otherwise stated in the specification or drawings.

    The provision, erection, maintenance and removal of all their temporary office and storage accommodation.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 28

    Connections to temporary power supplies made available by the Contractor. Supplying and running distribution cables, leads and electrical equipment as required.

    The provision of plant, equipment and generators for welding works.

    The provision, erection and removal of special scaffolding including altering and adapting from time to time as necessary.

    Removing of all existing equipment and associated equipment made redundant during A/A works from site. Depositing all rubbish, crates, drums, etc. at positions on each floor to be indicated by the maintenance.

    Full responsibility for loss or damage to their plant, tools, equipment and other property on the site.

    Protection and casing up of the contract works until such works have been properly completed and incorporated into the Works.

    Chasing of walls for pipes, conduits and fittings. The painting of pipes, conduits and equipment.

    Sealing between sleeves built-in by the Contractor and the pipe, duct, trunking, etc. using materials and methods of suitable fire rating and to the approval of the building Authority, Architect and Engineer.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 29

    5.0 Electrical Services

    This specification shall be read in conjunction with all other relevant drawings accompanying this document. The Contractor shall not be absolved from his responsibility for not carrying out the contract works in accordance with the requirements of the foregoing sections of this document and the detailed specification of work as outlined hereunder. a) Check phase loading and phase balance the circuits.

    b) Provision of proper ceiling Roses, Flexible Chords and connectors to every lighting point to comply to the requirements of S P Services Ltd.

    c) Provision of necessary cable trunking/trays for all services including Data, Telephone, and Security cables

    d) Supply and installation of new wall boxes and concealed conduit from the nearest down trunking in the wall/column.

    e) Ensure the accuracy of timers and reset.

    f) Record all services and replacement carried out.

    g) Contractors LEW to make all necessary application and to submit plans or drawings, endorsed forms and certificates to Authority

    h) Contractors LEW shall be responsible for Authority meter installation, turn-on and pay all fees including the Licensing Fee for the operation of the installation up to the expiry of the Maintenance Period.

    i) Test for the proper functioning of existing light fittings, control and protective circuits/devises and distribution boards.

    j) Modify existing circuiting of light fittings and distribution boards as required

    k) Testing and commissioning of all systems and equipment and hand over of those systems and equipment to the Client.

    l) Provision of twelve (12) months operational maintenance and breakdown services after practical completions.

    m) Provision of shop drawings as-built drawings, operating instructions and maintenance manuals.

    n) Liaise and co-ordinate with other trades for the interface requirements of the Electrical systems.

    o) Training of employers staff for proper operation of the entire system.

    p) Provision of spare parts and equipment

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 30

    5.1 General

    This Section specifies the electrical equipment and installation which shall form part of the Works as shown on the Drawings.

    All electrical equipment including luminaires, switch socket outlet, switches, motors, starters, switchgear panels, cabling, wiring, etc., associated with the various mechanical systems or equipment shall fully comply with this Section.

    Manufacture

    All electrical equipment and materials of the same type shall be supplied by a single manufacturer to ensure uniformity of standards and composition.

    All equipment and accessories delivered to site shall be new and shall be clearly marked to identify different grades, materials and manufacturers.

    All switchgear, motors and starters must be the product of a manufacturer experienced in the design and construction of similar equipment and who have made electrical equipment for similar duties for at least five years.

    Submissions

    The information listed in this Clause must be provided for each electrical system at the times stated.

    At the time of tendering, the Contractor shall provide all information in accordance with the Form of Tender.

    Within two weeks of being notified of the Employer's intent to award the Contract and prior to ordering the equipment, the Contractor shall furnish the following information for each system to the Engineer for approval:-

    Manufacturer of all cables, wiring and accessories;

    Specifications and standards for all materials; and

    Certified list of recommended spare parts.

    Within two weeks of being awarded the Contract, the Contractor shall submit to the Engineer for approval complete working drawings of all electrical systems included in the Contract.

    Working drawings shall show all conduit runs and cable routings and shall clearly indicate the locations of all electrical installation, isolating switches and all plant and equipment to which the electrical system connects.

    Prior to ordering any motors, switchgear, control panels, instruments or any other electrical equipment or accessory, the Contractor shall submit to the Engineer for approval the manufacturer's data for each item and in the case of control panels, a detailed layout drawing of the panel face.

    Prior to ordering any motor starters, the Contractor shall submit for approval full technical details of the equipment including time/current characteristics for each motor/starter arrangement.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 31

    Prior to ordering any materials, the Contractor shall submit for approval samples of all cables, wiring, conduit, junction boxes, fittings, switches, hangers, cable trays and any other item as may reasonably be requested by the Engineer.

    Within two weeks of being awarded the Contract, the Contractor shall submit a draft copy of his proposed commissioning and testing procedures and report for approval.

    Within one month of the Date of Practical Completion, the Contractor shall provide as-built drawings for each system in accordance with the "General Requirements" Section of this Specification.

    Within one month of the Date of Practical Completion, the Contractor shall provide complete commissioning and testing reports for each system in accordance with the recommendations of the 16th Edition of the I.E.E. and in compliance with the "Commissioning and Testing" Section of this Specification.

    5.2 Equipment

    5.2.1 HV SWITCHGEAR & EQUIPMENT

    Scope of Work

    This Specification specifies the requirements for switchgear operating at voltages above 22

    kV a.c.

    This Specification specifies protective relays that are not integral to a circuit breaker or

    switching device and separately-mounted voltage and current transformers.

    This Specification specifies integrated protective relays and voltage and current transformers

    assembled as an integral part of a circuit breaker or switching device are covered in the

    relevant sections.

    Performance Criteria and Requirements

    Provide switchgear suitable for indoor use in tropical conditions

    Ensure all ratings, including the ratings of all fittings, accessories, CTs, VTs, instruments,

    relays etc, are for continuous operation under full load at the specified on-site conditions/

    Arc Fault Containment

    Provide switchgear certified to prove the suitability of the switchgear for accessibility Type A

    as specified in IEC 60298. Carry out Arc fault containment tests for:

    Busbar chambers

    Circuit breaker and switch chambers

    Cable termination chambers

    Submit certificates to the Engineer.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 32

    MATERIALS

    General Requirements

    Provide free-standing, modular, metal-enclosed indoor type switchboards to IEC 60298.

    Ensure switchboards are extensible at both ends.

    Provide switchboards that are able to withstand the prospective short-circuit current for 1

    seconds duration for 20 kA and fully type tested by an internationally recognised testing

    station such as ASTA, KEMA or any other testing station approved by the Engineer.

    Provide switchboards with electrical and mechanical interlocks so that multiple incoming

    feeders cannot be operated in parallel.

    Ensure switchboards have a minimum Index of Protection of IP4x in accordance with IEC

    60529.

    Provide switchboard assemblies with a continuous copper earth bar running the whole length

    sized for the prospective short-circuit current.

    Provide each switchboard section with anti-condensation heaters. Ensure anti-condensation

    heaters are individually fused.

    Protective Relays

    So far as it is practicable, ensure all CTs are of the ring type. Wound primary CTs will only be

    accepted when the rated primary current is so low as to make the ring type impracticable.

    Ensure all CTs for use at voltages exceeding 1000V are epoxy resin encapsulated, whether

    of the ring type or the wound primary type.

    DESIGN AND FABRICATION

    General

    Provide switchboard enclosures constructed from minimum 2mm steel sheet, with stiffening to

    all doors and covers.

    Internal Segregation

    Ensure busbars, circuit breaker or switch and cable terminals are segregated from each other

    by means of separate compartments. Provide a separate front opening compartment for all

    low voltage components.

    Pressure Relief

    Ensure pressure relief flaps are fitted to the top of the circuit breaker, busbar and cable

    chambers and discharge either from the top of the cubicle or from the rear of the cubicle via a

    duct to direct the gases up over the top of the cubicle. Fit dynamic flaps to all front facing

    vents.

    Ensure that gases cannot be transmitted from a faulted to a non-faulted compartment or

    cubicle.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 33

    Safety Shutters

    Provide busbar and circuit spouts devices provided with automatic metal safety shutters.

    Ensure the safety shutters are operated by the movement of the circuit breaker being racked

    between the 'Test/Disconnected' and 'Service' positions.

    Ensure shutters are individually driven open and positively re-closed.

    Provide shutters capable of being individually propped in the 'Open' position. Provide shutters

    capable of being closed manually or, on re-insertion of the circuit breaker to the 'Service'

    position, normal operation is automatically restored.

    Provide earthing for safety shutters when they are in the Open and Closed positions.

    Ensure shutters are capable of being individually padlocked in the Closed position.

    Ensure busbar and circuit shutters are clearly identified.

    Circuit Breaker Interlocks

    Provide full interlocking as follows:

    Ensure that it is not possible to insert the circuit breaker into the cubical unless the racking

    system interlocks are disengaged.

    Ensure that it is not possible to rack the circuit breaker from the 'Test/Disconnected' position

    to the 'Service' position unless:

    The racking system interlocks are engaged

    The circuit breaker is open

    The front door is closed

    The earth switch is open

    Ensure it is not possible to rack the circuit breaker from the 'Service' position to the

    'Test/Disconnected' position unless the circuit breaker is open

    Ensure it is only possible to close the earth switch with the circuit breaker in the

    'Test/Disconnected' or 'Withdrawn' position.

    Ensure it is only possible to close the circuit breaker in the 'Service' or

    'Test/Disconnected' position.

    Ensure it is not possible to open the cubicle door unless the circuit breaker is in the

    'Test/Disconnected' position.

    Nameplates

    Provide nameplates on the front of each section giving the circuit identification and the cable

    size.

    Provide on the front of each section a permanently fixed synoptic diagram indicating the

    busbars and any circuit breaker or switch, earthing switch and voltage transformers.

  • PARKCITY ` Clubhouse Facilities ParkCity at Le Trong Tan Ha Noi, Viet Nam Mechanical & Electrical Specification Rev 0

    Tham & Wong M&E (Viet Nam) Page 34