Ilhtninating lives,,,
SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED
Registered office: vidyutBhawan, Bailey Road, Patna -2L,A Govt. Of Bihar Undertaking
cr N-u40109BR2012SGC018890
Director (Proiect) reviewed the progress of Special Plan (BRGF) scheme and found that
none of the firms has executed work on the basis of approved BAR Chart/PERT Network
& are lagging behind the target.
1. Districts: Patna & Bhoipur NIT NO: 03 (M /s Supreme-VP|L JV')
(i) Managing Director of M/S Supreme-VPIL JV Participated in the meeting'
Schedule piogrus of agency was review .The detail is given below, on the basis of
aPProved BAR Chart/Part network:-
(a) 33 KV Line: To complete 107 Ckm by 31't September, 2015. But till date
stringing not started.(b) LL KV Line: To comPlete 1277 Ckm by 31't September, 2015. But till date 25
CKM stringing comPleted.(c) New LT Line: To complete 934 Ckm by 31't September, 2015' 25 CKM Pole
erections completed but till date stringing not started.
(d) R&M of 11 KV Line: To complete L6 Ckm by 31't September, 2015' But till date 6
iJ. ;tlffi:f ffil*:Ti.omprete 141 ckm by 31't septembe r,2o15.But tilr date 4
CKM stringing comPleted.(f) lnstalled of DT: To complete erection 210 nos. DT 63KVA, 239 nos' DT 100KVA
and t47 nos. DT 2oOKVA but DT not supplied till date.
(ii) Agency raised the issue regarding railway crossing of 33KV line from Hathidah GSS
to Mokama pSS. lt was directed to Sr.S.P.Mandal, EEE (BRGF) to visit the site and
finalize the route.(iii) Director (project), reviewed the achievement against submitted work plan in
month of May,2015 by agency and found that achievement Zero percentage in
33KV Line and 24%in lLKV Line'
(iv) As per approved bar chart /PERT network agency has to supply 100% materials but
achievement is nearlY l5%'
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna - 21'
E-mail-esebrgf.sbpdcl @gmai l.com; Contact Nos' : - 77 63874004
2. Districts: Gaya" Naw4da & Jehanabad NIT NO: 196 (NtUs GKC -APL
ioint venture, Hvderabad)
(i) Agency has informed that construction of new control room at existing
33111, KV PSS Nawada old not started due to public hindrance .Sri
prakash kumar, AEE (BRGF) was directed to visit the site and resolve
the issue.
(ii) Dakhshini Jehanabad PSS Complete in all respect with its associated
33KV & 11KV lines. Pending for energization due to railway crossing
which will be obtained in two weeks'time. Meanwhile the PSS may be
energized on no load by the 33KV line passing close to this new 33KV
line.(iii1 Sri Prakash Kumar, AEE (BRGF) was directed to inspect R&M work of
PSS in Nawada District.(iv) Agency has committed to complete :-R&M work of all PSS in Nawada
district up to 1-5th Sept,2015,
3. Districts: Arwa! & Auraneabad NIT NO: 203 (M/s Supreme & co.-
Utkal Galvanizers JV Kolkata)The progress of work is far from target committed by Agency during CMD
meeting.
The Agency was directed to accelerate execution of work and achieve
committed target.
4. Districts: Patna& Natanda NIT NO: 209 (M East lndia UdvoH Limited.
Ghaziabad)
(i)_ Agency raised the issue regarding handing over & taking over of
electrical work completed against R&M of PSS by the Agency. The issue
will be resolved after proper analysis.
(ii) Agency raised the issue regarding cable laying arrangement inside the
campus of Sampatchak GSS behind its boundary wall for energization
of punpun PSS. The issue is to be settle with the help of transmission
Officer.
5. Districts: Bhagalpur. Banka & Munger NIT NO: ?07 (M Baiai Ele-ctricals
Limited: Mumbail
(i) Agency raised the issue regarding railways crossing in 04 nos.
feeders(11KV line Narayanpur PSS to Navtoliya in Bhagalpur District,
11KV line Nehru colony PSS to Dudhari and 11KV line Nehru colony
PSStoAmarpurRuralinBankaDistrictsand33KVlineSafiabadGSSto
Nandlalpur PSS in Munger District)'
(ii) lt was directed to issue a letter to agency for Poor quality civil work
executed by agency against R&M of PSS. The painting of control room
buildings,structurenotproper.GravellingnotdoneasperTS.(iii) All the rail poles stringing done without painting of poles as per TS'
(iv) very slow work of new PSS at shankarpur & Nehru colony Banka'
(v) Stringing of 11KV lines not proper at many places'
6. Districts: Nalanda, Nawada & Banka NIT NO:02 (M/S Gopikrishna
lnfrastructure Pvt. Ltd')
(i) Agency raised the issue regarding Time extension' After analysis of
submitted document in support of time extension, needful action will
be taken as Per norms of RFP/LOA'
(ii) Agency raised the issue regarding approval of non-scheduled item in
BOQ. Rate of non-schedule item will be decided through variation
committee.
7. All Agencies were directed to speed up work and achieve committed target
during CMD review meeting held on 18'08'2015'
Memo nos. I 6l\ Date:- dl * 3 _.,JI-
copy forwarded to M/s Feedback infra Pvt. Ltd, M/s GKC-APL Joint Venture'survey
Nos. 9(P), cll Green Building Lane, Hitech city, Kondapur, Hyderabad- 5ooo84' M/s' sHlRDl
SAt ELECTRICALS LIMITED, 13182, INDUSTRIALESTATE,KADAPA- 516004' M/s Viiai
Electricals Ltd. 6-3-64 BIL&2, off Rajbhavan Road, somajiguda, Hyderabad-500082, e1an1a
pradesh, M/s supreme & co. Pvt. Ltd.-M/s Utkal Galvanizers Ltd' Joint venture'S3'Justic
Chandra,MadhavRoad,Kolkata.20,M/sEastlndaiUdyogLtd.l45,G.T.Road,Sahbabad,Ghaziabad , Pin-201005,Uttar Pradesh' M/s Bajaj electricals
i;il;; ttr"rOil iroo,. Rustomjee Aspire, 8ol-,10th Floor Rustomjee Aspire' Bhanu Shankar
YagnikMarg, off eastern express highway, ion (E),Mumbai.400022, M/s. Sri
Gopikrishna lnfrastructure Pvt. Ltd.corporate office: 3o/B (8-3-1971162)' Vengalrao Nagar'
Hyderabad-500038,M/sSUPREME-VPIL(Jv),EcospaceBusinessPark'ActionArea-ll'BuildingNos.2A,5thFloor,UnitNos.50lB,NewTown,Rajarhat,Kolkata-70:1t"tr^,Yl:il#r," ni;r't;r; Ltd., Kolkata, M/s Energo Engineering , New Delhi ' M/s Laser cable &
Lumino JV, Kolkata, M/s Cabcon lndia Pvt. Ltd. Kolkata for information & necessarv action'-r-)s. -/
(?.t'
CE (Project-l)