Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

Embed Size (px)

Citation preview

Page 1: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,
Page 2: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

Spares for Critical ItemsKickers

W. Weterings

SPS Consolidation Review

Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano,Remy Noulibos, Luc Sermeus, Viliam Senaj

Page 3: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

3SPS Consolidation Review

Talk Overview

• KFA71 Repair of 2 magnet modules

• KFA79 Build 2 magnet modules

• KFA45 Build 3 magnet modules and 1 vacuum tank

• MKDH Build 2 magnet modules and 1 vacuum tank

18/03/2015W. Weterings

Page 4: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

4SPS Consolidation Review

KFA71

18/03/2015W. Weterings

Ejection kicker magnet KFA71 Together with magnet KFA79, this device kicks the beam in the aperture of SMH16 for extraction.Installed in 1973.

• Configuration:• 1 tank with 9 magnet modules;• The magnets are of cellular,

closed aperture, C-ferrite loaded transmission line type, 15Ω impedance.

• 1 spare tank with 9 modules exist. (not operational for the moment)

• Current status:• All 3D CATIA models of magnet modules made and 2D drawings ready, but not checked.• 2 modules have been repaired;• Modules will be individually tested before assembly in the 9 modules spare tank.

WU status BC Activity   2014 2015 2016 2017 2018 2019 2020

Active 65261 Spare KFA71-79 modules + KFA45 tank kCHF 80 125 117 137      

      FTE   0.40 0.55 0.55 0.40 0.25  

Page 5: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

5SPS Consolidation Review

KFA79

• Configuration:• 1 tank with 3 magnet modules;• The magnets are of cellular,

closed aperture, C-ferrite loaded transmission line type, 15Ω impedance.

• 1 spare tank with 1 module exists.

• Current status:• All 3D CATIA models of magnet modules made, 2D drawings ready (but not checked).• At least 2 modules to be built;• No supplier for ‘shiny’ laminated AlMg3 plates known, possibility of electro polishing to be

investigated.

18/03/2015W. Weterings

Ejection kicker magnet KFA79 Together with magnet KFA71, this device kicks the beam in the aperture of SMH16 for extraction.Installed in 1977.

WU status BC Activity   2014 2015 2016 2017 2018 2019 2020

Active 65261 Spare KFA71-79 modules + KFA45 tank kCHF 80 125 117 137      

      FTE   0.40 0.55 0.55 0.40 0.25  

Page 6: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

6SPS Consolidation Review

KFA45

18/03/2015W. Weterings

Kicker magnet KFA45.Used to inject protons into the PS.Installed in 1979.

• Configuration:• 1 tank with 4 magnet modules;• The magnets are of cellular, closed aperture,

C-ferrite loaded transmission line type,characteristic impedance of 26.3Ω.

• Originally designed to inject 800MeV proton.• 1 spare module exists.

• Current status:• All 3D CATIA models of magnet modules

made, 2D drawings ready (but not checked). Drawings of the tank still to be made;

• At 2 GeV at the limit of saturation, operation with only 3 modules will be impossible.• 1 tank and at least 3 modules to be built, redesign for non-saturation to be considered.

WU status BC Activity   2014 2015 2016 2017 2018 2019 2020

Active 65261 Spare KFA71-79 modules + KFA45 tank kCHF 80 125 117 137      

      FTE   0.40 0.55 0.55 0.40 0.25  

Page 7: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

7SPS Consolidation Review

• Configuration:• 3 tanks with 2 magnet modules;• Different thickness of lamination

between the magnets.• No spare exist.

• Current status - Nothing has been done…….• Spare magnet with thinner lamination would be preferred, due to lower eddy currents;• Current magnets suffers from outgassing issues caused by the lamination oxidation;

Improvement by different lamination insulation or bake-out to be studied.

MKDH

18/03/2015W. Weterings

WU status BC Activity   2014 2015 2016 2017 2018 2019 2020

Draft 3 22081 Assemble MKDH spare kCHF  

      FTE  

Kicker magnet MKDH.Used to dump the beam in LSS1 of the SPS.

Bonus points for guessing the name

Page 8: Spares for Critical Items Kickers W. Weterings SPS Consolidation Review Laurent Ducimetiere, Patrick Faure, Luis Miguel Coralejo Feliciano, Remy Noulibos,

8SPS Consolidation Review

Conclusion• KFA71

3D CATIA models of magnet modules made and 2D drawings ready, but not checked. 2 modules have been repaired; Modules will be individually tested before assembly in the 9 modules spare tank.

• KFA79 3D CATIA models of magnet modules made and 2D drawings ready, but not checked. At least 2 modules to be built; No supplier for ‘shiny’ laminated AlMg3 plates known, possibility of electro polishing to

be investigated.

• KFA45 3D CATIA models of magnet modules made and 2D drawings ready, but not checked. Drawings of the tank still to be made. 1 tank and at least 3 modules to be built, saturation issue to be studied.

• MKDH Nothing has been done

18/03/2015W. Weterings