2
SpanWright Case Study Hollowcore Flooring for T Chambers & Son (E) Ltd Contract CLIENT: T Chambers & Son (E) Ltd CONTRACT: Rockcorry National School LOCATION: Rockcorry Village, Co Monaghan, Eire COMPLETION DATE: Mid October 2010 SECTOR: Educational ABOUT THE PROJECT Spanwright UK were approached by the main contractor for this project - T Chambers & Son (E) Ltd- to provide the best cost solution on a hollowcore flooring package for a local 3 Classroom National School on a split level site. PROJECT CHALLENGES Spanwright’s main challenge was that the site required large amounts of filling and so a suspended floor was required. The Spanwright design team in conjunction with T Chambers contracting team progressed the design, production and installation of the product seeking to minimise the requirement for foundations and blockwork below slab level. They selected and re designed 250mm prestressed concrete flooring to produced significant cost savings for T Chambers & Son (E) Ltd.

Spanwright Hollowcore Flooring Case Study - T Chambers Project

Embed Size (px)

DESCRIPTION

Spanwright UK were approached by the main contractor for this project - T Chambers & Son (E) Ltd- to provide the best cost solution on a hollowcore flooring package for a local 3 Classroom National School on a split level site.

Citation preview

Page 1: Spanwright Hollowcore Flooring Case Study - T Chambers Project

SpanWright Case Study

Hollowcore Flooringfor T Chambers & Son (E) Ltd Contract

CLIENT:T Chambers & Son (E) Ltd

CONTRACT:Rockcorry National School

LOCATION:Rockcorry Village,Co Monaghan, Eire

COMPLETION DATE:Mid October 2010

SECTOR:Educational

ABOUT THE PROJECT

Spanwright UK were approached by the main contractor for this project - T Chambers & Son (E) Ltd- to provide the best cost solution on a hollowcore flooring package for a local 3 Classroom National School on a split level site.

PROJECT CHALLENGES

Spanwright’s main challenge was that the site required large amounts of filling and so a suspended floor was required.

The Spanwright design team in conjunction with T Chambers contracting team progressed the design, production and installation of the product seeking to minimise the requirement for foundations and blockwork below slab level.

They selected and re designed 250mm prestressed concrete flooring to produced significant cost savings for T Chambers & Son (E) Ltd.

Page 2: Spanwright Hollowcore Flooring Case Study - T Chambers Project

PRODUCTS & SERVICES PRECAST CONCRETE FLOORING 150mm PRECAST CONCRETE FLOORING 210mm

PRESTRESSED CONCRETE FLOORING 150mm

PRESTRESSED CONCRETE FLOORING 150mm High Density PRESTRESSED CONCRETE FLOORING 200mm

PRESTRESSED CONCRETE FLOORING 250mm 4

PLATE FLOORING

CONCRETE STAIRS

DESIGN 4

INSTALLATION 4

BESPOKE PRODUCT DESIGN

PRODUCT DETAIL PRESTRESSED/PRESCAST finishes to BS 8110. Available in a range of depths and sizes and manufactured to comply with the recommendations of the PRECAST FLOORING FEDERATION.

Windmill Hill Business Park, Whitehill Way, Swindon SN5 6QR

Tel: 01793 441474Fax: 01793 441401Mob: 07543 180455Email: [email protected]

www.spanwright.co.uk

The Board had been aware of Spanwright as a local quality supplier for a long time. We were delighted to have the opportunity to partner with them on this project.

Sammy Wilkin, Chairman of the Board of Management for Rockcorry NS