Upload
brian-gilligan
View
116
Download
5
Embed Size (px)
Citation preview
Space Savings Performance Contract Concept
Office of Federal High Performance Green BuildingsKevin Kampschroer - Brian Gilligan
IntroductionSpace Efficiency as an Energy Conservation Measure
• Employ workplace strategy to reconfigure space to house people and mission more efficienty; Space Savings Measures (SSMs) save energy by eliminating requirement for space and fixed energy loads
• OMB Memo M-12-21 requires meeting 4 tests to use ESPC authority:o Apply to a Federal Buildingo Improve energy efficiencyo Be life Cycle Cost Effectiveo Include permissible activities
• Pilot Project – GSA Staff Consolidation o Cost: $4.4M including ESPC costso 40% reduction in space yields 25% energy savingso Payback <25 years from energy and related operations cost savingso ~$30M (NPV) additional rent opportunity
IntroductionSpace efficiency - Alternative Workplace Strategies
• Consolidation of GSA functions
• 50,000SF Reduction in footprint
136,000 SF 83,000 SF
~40% Reduction in Space
Test 1Applied to Federal Space – Max Savings
• The project is a contraction within the JCK Federal Building:
o Space required at old space standards, less
o Space required at new space standards
o Equals total space reduced, multiplied by
o Energy and operating cost rate for JCK Bldg
o Maximum possible cost savings
136 KSF
83 KSF-
x $9.50/SF
= 53 KSF
= $503K / Year
Projected Total Energy UseEUI - Per SF Total Area Total Energy Energy Reduction
Scenario (kBTU/SF-Yr) (SF) (kBTU/Yr) (KBTU/Yr)
Current planning layout 77 136,000 10,472,000
Future planning layout 93 83,000 7,724,234 26%
Test 2 Improve Energy Efficiency in Federal Space
~26% Reduction in
Energy
Avoided capacity:• 53,000SF Space• Heating / Cooling • Lighting
That space may well be filled, but: • Savings for the base group
remain• New group is vacating space
somewhere
Test 2Efficiency – Space is an energy-consuming system
Test 2Efficiency – Space is an energy-consuming system
Bannister “Test Bed” Project, Kansas City, MO:• Doubled planning density & occupancy• Modeled energy with EnergyPlus v8.0• Per capita energy reduced 63%
M&V would use the same process in order to compare:
• Energy consumption at old space standards to
• Energy consumption at new space standards
• Estimate impacts of potential changes downstream
Test 3Life Cycle Cost Effective - Options to Reduce Risk
Full SSPC Alt 1 Alt 2 Alt 3100% Finance 90% Finance 75% Finance 50% Finance
Rent Revenue - NPV ($M) $30M $30M $30M $30M
Project Buydown $0M $0.5M $1.2M $2.2MDiscounted Payback 24 Years 20 Years 15 Years 9 Years
$0.0$0.5$1.0$1.5$2.0$2.5$3.0$3.5$4.0$4.5
0 5 10 15 20 25
Mill
ions
Alt 1 (90%) Alt 2 (75%) Alt 3 (50%)
Test 4Permissible Activity
• Must involve energy conservation, may include:o cogeneration facilities, o renewable energy sources, o improvements in O&M efficiencies, or,o retrofit activities (retrofit of space as an energy-consuming system)
Conclusion
• We believe SSPC projects meet OMB’s tests, however, a proof of concept is required to be certain - GSA’s Administrator approved a pilot for 2015
• We have worked with DOE - Contracts and General Counsel staff to understand the conditions that must be addressed to:o Conduct a proof of concept pilot using the ESPC IDIQo Have DOE support in executing the pilot project
• We hope you will support a pilot:o Cons: Resistance to ESPCs generally, fear of abusing authorization
specifically; while it seems a good bet it is still uncertaino Pros: GSA succes with workplace strategies, OMB interest in ESPC
authority for PPP projects, ESPC challenge requires new project sources
• We recognize Portfolio must set the pace and terms for a pilot project