Upload
manhnguyen
View
216
Download
0
Embed Size (px)
Citation preview
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 1/148
Defence
Works
Functional Standard
Design
&
Maintenance
Guide 08
Space requirements
for
plant
access,
operation
and
maintenance
INDUSTRIALGROUP
(IND GP)
DEFENCE ESTATE
ORGANISATION
(WORKS)
Ministry
ofDefence
London: HMSO
document
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 2/148
©Crown
Copyright
1996
Applications
for
reproduction
should
be
made
to
HMSO,
The
CopyrightUnit,
St Clements
House,
2—16
Colgate,
NorwichNR3
1BQ
ISBN
0
11 772785
7
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 3/148
Space Requirements
Foreword
Thisdocument
provides guidance
on the
provision
to bemadeforaccess to
plant
andthe
space requirements
ortheeffectiveand
safe maintenanceand
operation
of
mechanical/electrical
engineering
ervices
in
buildings
and
facilities.
Thedocument
highlights
he relevant
statutoryobligations
which must be
considered in
planning
he
provision
of
access
and
space
allowanceforservices.
It
sets
out
he
normal principles
whichare usedby
Project Managers
and
Designers
to address their
duty
of
careunder these
statutory
obligations.
TheGuide
should
be
considered asa
design
aid. Due
o
the diverse
natureof
services installations andmanufacturer's
equirements,
itmustnotbetakenas
giving
definitive
guidance
on
spatialrequirements.
This Guide
does notrelieve
Project
Managers
or
Designers
from their
duties ofcare
to
embodystatutory
obligations
and
goodengineeringpractice. Project Managers
have
a
duty
to
ensurethat
building
facilities are fit for
purpose, including maintainability.
Whilst
hisGuide
was
commissioned
by
DEO(W)
or
the
MOD
Estate,
it is
acknowledged
hat itcould be
usefully applied
outside
he Estate.
TheGuide has been reviewedand endorsed
by
theChartered Institutionof
Building
Services
Engineers.
1f
\
CIBSE
Acknowledgement
This
guide
hasbeen
produced
for the Industrial
Group, DEO(W),by
consultant
authorsOve
Arup
& Partners.Comments
and
contributions
by
others in
DEO(W)
and
in
the
building
services
industry
are
gratefully acknowledged.
This
guide
has
been
sponsored by
the
Chief
Safety
Officer,
MOD
and the
lead
TLBHs for works.
This Guide
has
been devised or
the use of he
Crownand
its
contractors
ntheexecution
of
contracts or theCrown. The Crown
hereby
excludesall
liability
other
than
iability
for death or
personal njury)whatsoever
and
howsoever
arising
(including,
but
withoutlimitation,
negligence
on
the
part
of he
Crown
ts
servants
or
agents)
for
any
loss
or
damage
howevercausedwhere
theGuide sused for
any
other
purpose.
Frontcover:
By
kind
permission
of heInternationalConvention
Centre,
Birmingham
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 4/148
Space Requirements
Abbreviations
ACOP
Approved
CodeofPractice
AHU Air
Handling
Unit
ANSI American
NationalStandards Institute
ASHRAE American
Society
of
Heating,Refrigerating
and
Air
Conditioning Engineers
BRECSU
Building
Research
Energy
Conservation Unit
BS British
Standard
BSI British Standards Institution
BSRIA
Building
Services Research Information Association
CIBSE
CharteredInstitution of
Building
Services
Engineers
CHP CombinedHeat and Power
COSHH ControlofSubstances Hazardous to Health
CV Constant
Volume
DEO(W)
Defence
Estate
Organisation
Works)
DWS
Defence Works Services
FD Fire
damper
FCU FanCoilUnit
HSE
Healthand
Safety
Executive
HSC
Health
and
Safety
Commission
HSWA
Health
and
Safety
at
Work
Act
HV
HighVoltage
HVAC
Heating,
Ventilation andAir
Conditioning
HVCA
Heating
and
Ventilating
Contractors' Association
HWS Hot
Water
Service
LTHW Low
TemperatureHot Water
lEE InstitutionofElectrical
Engineers
LV Low
Voltage
MCC
Motor Control Centre
M&E MechanicalandElectrical
MOD
Ministry
of
Defence
NALM National AssociationofLiftManufacturers
NHS National HealthService
O&M
Operating
and
Maintenance
UPS
Uninterruptible
Power
Supply
VAV Variable Air Volume
VCD Volume Control
damper
WSM Works Services
Manager
iv
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 5/148
Space Requirements
Contents
FOREWORD
iii
ABBREVIATIONS iv
CONTENTS
v
1.0 INTRODUCTION
1
1.1 SCOPE
OF THE
DOCUMENT
2
1.2
USE
OF THE
GUIDE
3
1.3 DEFINITIONS 4
1.4 KEY 4
2.0
LEGISLATION
AND
GOOD
PRACTICE
GUIDANCE
5
2.1 HEALTHAND
AFETY
5
2.2
STATUTORY INSTRUMENTS 6
2.3 GUIDESTOGOODPRACTICE 16
2.4
DEO(W)/DWS
TECHNICAL PUBLICATIONS 18
3.0 PHILOSOPHY OF PLANTROOMDESIGN 19
3.1 MAINTENANCE
AND
OPERATION ISSUES AFFECTING SPACE 19
ALLOWED
FOR PLANT
3.2
ACCESS,
MAINTENANCE FREQUENCYAND DURATION OF TASK 24
3.3
LOCATION
AND
LAYOUT OF
PLANT
ROOMS
26
3.4 DEVELOPMENT OF
PLANT
SPACES
28
4.0 SYSTEM
REQUIREMENTS
33
4.1 MECHANICAL SERVICES ISTRIBUTION SYSTEMS 33
DATA HEETS
Dl
Accessto Distribution Ducts and Shafts
35
D2 Ductwork 36
D3 Pipework
.
37
D4 Mechanical Services Risers 38
D5 Horizontal Services Ducts 39
D6
Pipework
Access
-
Common Problems
41
D7
Ductwork Access
-
Common Problems
42
D8 False
Ceilings
and Raised Floors 43
D9 Cross-overs 44
4.2 ELECTRICAL SERVICES DISTRIBUTIONSYSTEMS 45
DATA HEETS
D1O Controlanels nd Distributionoards 47
Dli
Electrical Services
-
Vertical Risers 48
5.0 COMPONENT REQUIREMENTS 49
5.1
CENTRAL STATION PLANT
-
MECHANICAL
50
DATA SHEETS
JULY1996 V
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 6/148
Space Requirements
5.1.1
LTHW
BOILERS 50
M1.1
Modular Boilers
Space Requirements
52
M1.2 Cast Iron Sectional and Steel Boilers
Space Requirements
53
Ml
3
Modular Boilers
Space
Details
54
Ml 4 Cast Iron Sectional and Steel Boilers
Space
Details 55
Ml
5 Fuel
Oil Storage
Space
Requirements
56
Ml
6 Fuel Oil
Storage
Tanks
Space
Details 57
5.1.2 LIQUIDCHILLERS
58
M2.1
Summary
of
Space Requirements
60
M2.2
Packaged
Air
Cooled Chillers
Space
Details
61
M2.3 Water Cooled Chillers
Space
Details 62
M2.4 Hermetic
Absorption
Chillers
63
5.1.3 PUMPS 64
M3.l
Circulating Pumps Space
Details 66
M3.2 Booster Sets: Fire Protection, Drinking and Domestic Water 67
Space
Details
5.1.4
PRESSURISATION UNITS
68
M4.1 Pressurisation
Units
Space Requirements
69
M4.2 Pressurisation
Units
Space
Details 70
5.1.5 WATER
TREATMENTAND WATERSOFTENING 71
M5.1 Water Treatment
andWater
Softening Space
Details 72
5.1.6 WATERSTORAGE 73
M6.1
Summary
of
Space
Requirements
75
M6.2 Cold Water Storage Space Details 76
M6.3 HotWater
StorageSpace
Details 77
5.1.7 AIR HANDLINGUNITS 78
M7.1
Summary
of
Space Requirements
80
M7.2
AHUs General Points 81
M7.3
AHUs
Space
Details 82
M7.4 Floor
by
FloorAHUs
Space
Details 83
5.1.8 FANS 84
M8.1
Summary
of
Space Requirements
86
M8.2
Centrifugal
and Axial Fans
Space
Details 87
5.1.9 HEATREJECTION
88
M9.1
Summary
of
Space Requirements
90
M9.2
Cooling
Towers
Space
Details 91
M9.3 Air Cooled
Condensers
Space
Details 92
5.1.10 LIFTS 93
vi
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 7/148
Space Requirements
5.2 CENTRAL
STATIONPLANT
-
ELECTRICAL
95
5.2.1 HV EQUIPMENT
95
El
1
HV
Switchgear
-
Indoor:
Space
Details and
Summary
of
97
Space Requirements
El 2 Cast Resin and
Dry Type
Transformers
Space
Detailsand
98
Summary
of
Space Requirements
El 3 IndoorSubstationswith Cast Resinor
Dry Type
Transformers
100
Space
Details and
Summary
of
Space Requirements
El.4 Oil Filled Transformers and Transformer
Compounds Space
102
Details and
Summary
of
Space Requirements
El 5 Substationswith Oil Filled Transformers
Space
Details and
104
Summary
of
Space Requirements
El 6
Ring
Main Units
Space
Details
106
El
7
Packaged
Substations
Space
Details and
Summary
of
Space Requirements
107
5.2.2 LV
SWITCHGEAR
AND
COMPONENTS
109
E2.1 Main
LV
Switchboards
-
Front Access:
Space
Details
110
and
Summary
of
Space Requirements.
E2.2 Main LV Switchboards
-
Rear access:
Space
Details
and 112
Summary
of
Space
Requirements.
E2.3
LV Switchboardsand MotorControl Centres
Space
Details 114
5.2.3 UNINTERRUPTIBLE
POWER SUPPLIES 115
E3.1 Static UPS
Space
Details and
Summary
of
Space Requirements.
116
E3.2
Rotary
UPS
Space
Details and
Summary
of
Space Requirements.
117
E3.3
Battery
Rooms
Space
Detailsand
Summary
of 119
Space
Requirements.
5.2.4 ROTATING MACHINERY 121
E4.l Diesel
Generating
Sets
-
Basic Generator Room: 122
Space
Details
and
Summary
of
Space Requirements
E4.2
Diesel
Generating
Sets
-
Generator Room withAcoustic Louvres: 124
Space
Detailsand
Summary
of
Space Requirements
E4.3 Diesel
Generating
Sets
-
Generator Room withAcoustic Enclosure: 126
Space
Details
and
Summary
of
Space Requirements
E4.4
Rotary Frequency
Convertors
Space
Details and
Summary
of 128
Space Requirements
6.0 DESIGN CERTIFICATES
129
6.1 CHECKLISTS
129
ANNEX A INSTALLATION CHECKLISTS
131
ANNEX B CHANGE SUGGESTION FORM 138
JULY1996 Vii
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 8/148
Space Requirements
1 Introduction
Space,
and
the
cost of
providing space,
for
plant
and
building
services
distribution soften ata
premium.
Pressuretoreduce he
spatial
requirements
for
building
services installations s hereforean understandable element of he
overall
design
process.
However,
considerable
care
is
required
f
building
servicesare
to be
designed
and
nstalled to
provide
adequate
pace for
the
safe
and
efficient
maintenanceof
the installations.
Difficultiescan
arise with
meetingstatutory
levels
of
accessto
safely
maintain
the installation f
pace
is
inadequate.
In
extreme
cases a
significant
amountof
additional work
may
have
to
be undertaken
after
completion
of he
building
to
ensure
compliance
with
statutoryrequirements.
Even whensafeaccess is
provided,
accessto
component
parts
can
be so restricted
that the costof
maintaining
hese
parts
imposes
a
significant
additional
operating
cost on the maintenance of he
building, e.g.
if
part
of
he
system
or
plantroom
enclosurehas to bedismantled.
Where
a
component
needsregnlar
replacement
duringthe
life
of
he
building,
consideration must be
given
to how
this
is to be achieved without
ncurring
excessive cost
in the
dismantling
of
arge
sectionsof he installationor
building
fabrictofacilitateremoval.
Given theabove
considerations,
the
purpose
of
hisGuide
is
to
provide
a
checklist
for
designers
and installers norder
that
these
problems
can be addressedand
mitigated against
atthe
design/construction stage.
To
provide
a
systematic
method of
assessing
the
provision
of
space
andaccess in
a
nstallation,
Design
Certificates are
proposed
in thisGuidewhichoffera
framework tocheck the
adequacy
of
space
allowances. These
Design
Certificates
are,
in
essence,
a
formal
wayof
checking
and
recording space
and
access
provision
at
key stages
of the
designdevelopment through
tohandover.
The Guide s
primarily
concernedwith
provision
of
pace
and
access which will
affect
the
health
and
safety
ofstaff
operating, maintaining, epairing
and
replacing
elements of
building
services.
However,
itdoes not address all
design
issues or all healthand
safety
considerations
relating
tothose
services. (For
example,
the Guidedoes
not address he
requirements
o
supervise persons
working
alone n
plant
ooms,
nordoes itaddress heneedto
provide
a route to
plant
rooms sheltered rom weatherextremes.
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 9/148
Space Requirements
Section 1 Introduction
1.1 SCOPE OF THEDOCUMENT
The
aim of
hisGuideisto
provide:
-
guidance
and
a
checklist
at
theoutline
designstage;
-
a checklistat
detail
designstage;
-
a
final
checklist
at
snagging/completionstage
to
minimise
the risk
of
acceptance
of
building
servicesthat cannotbe
efficiently
and
safely
maintainedor
replaced.
Due to the
diversity
in
type, configuration
and
possible
locationof
plant,
it is
not
possible
forthisdocument to
give
definitive
guidance
for all installationsand
therefore he
designer/installer
in
complying
with
this
Guide
snotrelieved from
complying
with all relevant
statutoryrequirements,
British Standardsand he
specific
recommendations
of
manufacturers.
It should however allow
comparison
between he
proposed
plant
space
and
what
may
be consideredthe normal allowance for
a
similar nstallation.Where these
differ,
the
design
shouldbe
scrutinised
to ensure
hat
sufficientspace
has
been
allowed
to
adequately
maintain the installations.
This should be
completed by
reference to the check lists contained in thisdocument.
ThisGuide also
specifies
what is consideredtobe sufficient access
by
defining
levels
of
access
and
frequency
of
access
required
to
commonly
found
items of
plant
and
equipment, e.g.
clearand mmediate accessfor
plant
which s
maintained
requently.
At
the
completion
of
he
designstage
and
again
at
practical
completion stage
those
responsible
for the
design/construction
of the installationshouldconfirm
by
completion
of he forms included inAnnex Aof hisdocument that he
installation
has
been
designed
and installed
to
meet
the
requirements
of
he
Guide. The
project sponsor
wouldbe
responsible
for distribution
of he
Design
Certificates.
In
general
he
Guide
is intended
o be
applied
o
modern
buildings.
In the case
of
new
design
workforhistoric
buildings
the
recommendations
in this
Guide must
notbe
applied
unthinkingly
n
the contextof
building
conservation. For
example:
•
False
ceilings
and raised floorsare
very
often
inappropriate
n historic
settings,
orif
used
should
be of
an
appropriatequality.
•
Service ducts should
not
damage
historic fabric.
•
Siting
ofexternalservices features such as fuel
storage
anks should
respect he setting
of
historicbuildings.
For
specialised applications
such
as
hardened
facilities,
explosives storage,
etc,
space provision
is
required
which
is
beyond
the
scope
of
his
document. The
Designer
should seekadvice from therelevantWorks Technical
Authority
at
DEO(W).
2 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 10/148
Space Requirements
Section1 Introduction
1.2USE OF
THE
GUIDE
1.2.1 Structure
of
he Guide
The Guide s
divided
into
five
main
sections;
these
are:
SECTION2
Legislation
andGood Practice Guidance
Defines
the
statutory requirements
mbodiedinvarious health and
safety
regulations
and the
implications
on the
provision
of
space
andaccess for
installation,
maintenance
epair
and
replacement.
The
guides
o
good practice
which
provide
quantitative
ecommendations of
space
provision
are also
summarised.
SECTION3
Philosophy
of Plantroom
Design
Defines
the main hazards
that a
designer
should consider inariskassessment
exercise
when
considering
the
provision
of
space
andaccess
ina
plantroom.
The
principles
ofplantroom
ayout, location
and
connection
to
primary
distribution
routes are discussed. This section
pulls
together
he considerationsdetailed
n
Section
5
(Component Requirements)
to
illustrate
the
practical
issuesof
combining
main
plant
items with
ancillaryequipment,
e.g.
shared
space
for
maintenance
activities on different
plant
tems.
The variation
in the
requirement
for
access
due
to
frequency
of
maintenance
tasks and their duration s also
defined.
SECTION
4
SystemRequirements
Defines the access and
space requirements
of
distribution
ystems; pipework,
ductwork,
cabling,
ete,
invertical andhorizontal
distribution
arrangements.
The
requirements
of
co-ordinated services
in
false
ceiling
voidsand
raised
floors
are
defined. To assist the
designer
or thoseinvolvedwith
checking
of
existing
installations,
commonproblems
with
access
to
pipework
and
ductwork
are
discussed.
SECTION5
ComponentRequirements
Eachelementofcentral
plant
formechanicalandelectrical services
is considered
individually
and he access and
space
requirements
o
safely
install andmaintain
the installation are
defined.
Typicalranges
of
space requirements
are
quoted
and
the
disposition
of
hat
space
indicated
diagrammatically
in the
plant
datasheets.
The
risk
assessment ssues
which
affect
space provision
aredefined. Cross-
reference
is made
o
Health
and
Safety Regulations,
Codesof
Practice,
British
Standardsand
guides
to
good practice
for each
plant
item.
SECTION
6
Design
Certificates
The
Design
Certificate
is
to
be used
toconfirmthat the
design
conforms
with the
recommendations in thisGuide.
The
certificates will
be based
upon
a
series
of
checklistsfor various
stages
of the
procurement procedure;
outline
design,
detail
design
andhandover. The evel ofdetail of he checklists
will
ncrease as the
project proceeds through
hat
sequence.
JULY1996 3
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 11/148
Space Requirements
Section 1 Introduction
1.2.2
DataSheets
Thebulk of he
information
on
access
and
space
requirements
or distribution
systems
and central
plant
itemshasbeen
presented
ondatasheets.These data
sheets
present
information inaconsistent andconcisefashion.
The
commentary
which
accompanies
the data sheethasbeen streamlined o
impart
only
the basic
information
on
access
and
space
requirement, or installationand
maintenance
andassociated riskassessment.
If
further
details of
he
rationale
behind
a
particular
recommendation
is
required
these can be
found
by cross-referencing
to
Regulations,
Codes
of
Practice,
British
Standards,
and
guides
to
good practice given
in
Section 2.
Itis
not
expected
that the
plant
data
sheets will be read
by
the user in
sequence;
the Guide is more
likely
o
be used as a reference
document
selecting
datasheets
to
obtain
he
relevant
piece
of nformation on a
particular plant
item.
They
have therefore been made as
self
ontained as
possible
with some
duplication
of
nformation;
e.g.
reference
in
eachsub-section
to
pertinent
health and
safety
egislation.
1.3 DEFINITIONS
Designer
The
organisation responsible
to,
andwhohasadirect or indirect
contract with the
project
manager
for the
design
of he
building
services
installations.
Installer
The
organisation responsible to,
andwhohasadirect contractwiththe
project
manager
for
the
installationof
building services
plantand
equipment.
ProjectManager
PM)
An
official
of
heMOD
or commercial
representative esponsible
for the
purpose
of
management
and administrationofworks coveredwithinthisGuide. Forwork
within
the
remit of
he
WSM,
the
term
PM should
be
read
asWSM.
Outline
Design
The
stage
when the
disposition
and
approximate
sizeof
he
plantroom
and
distribution
pace
allowances are
being
determined.
Detail
Design
The
point
in
time when he
designdrawings
are
complete,
but
prior
to
the
commencement
of
nstallation/fabrication drawings.
Completion
When
practical completion
certificate is
being
sought.
1.4
KEY
The
followingsymbols
re used
hroughout
he
guide
fl
Shaded
areas around
plant plans
andelevations
to
show
space
allowance
for maintenanceand
access.
1100
AlL dimensions are inmm.
Allclearance dimensions shouldbeconsidered as minimaandshouldbe
checked
against
manufacturer's/installation
requirements
4
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 12/148
Space Requirements
2
Legislation
and
Good
Practice
Guidance
2.1
HEALTH
AND
SAFETY
There
is
a
significant
amount of
egislation
which affects the
provision
ofaccess
and
space
formechanicalandelectrical services.This
is
argely
embodiedin
Regulations flowing
from
the
enabling
Health and
Safety
atWork Act 1974.
The
principal Regulations
are as
follows:
•
Management
ofHealth
and
Safety Regulations
1992
•
Workplace (Health, Safety
andWelfare)
Regulations
1992
•
Provision
and
Use ofWork
Equipment Regulations
1992
•
Construction
(Design
and
Management) Regulations
1994
•
Manual
HandlingOperations Regulations
1992
•
Electricity
at
Work
Regulations
1989
•
Pressure
Systems
and
Transportable
Gas Containers
Regulations
1989
Whilst he
provision
ofaccessand
space
for safe maintenance and
operation
is
referred
to in
these
regulations
there
is a
dearthof
detailed guidance
on the
allowances which should be
made.
The
generalrequirement
of
"adequate"
or
"sufficient"
space
is
often
quoted
but
is
rarelyquantified.
Therearesome useful
guidance
documents and standardswhich
provide
some
quantitative
guidance, e.g.
BSRIATechnical
Notes,
BS
8313,
NHSPublications
etc. but
hese tend
to
be the
exceptions.
A
summary
of he
scope
of
he
relevant Health
and
Safety Regulations
is
given
in
sub-section 2.2.
Designers
arenot to
ignore
the actual
Regulations,
Codes
ofPractice
and
guidance
notes,
etc.
The
commentary
in theschedule
provides only
an
outline;
t is
essential
that
the relevant
Regulations,
Codes
of
Practice
and
guidance notes
are referred
to
before applying
this
information.
JULY1996
5
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 13/148
Space Requirements
Section
2
Legislation
and
Good Practice Guidance
2.2 STATUTORY INSTRUMENTS
A
summary
of
egislation
and
regulations
which
affect
the
provision
ofaccess and
space
is
shown in Tables 2.1-2.8. Inaddition
to
describing
the
statutory
instrument,
the
associated codes
of
practice,guidance
notes and
approved
documents
are
also noted.
To make
cross-referencing
easiera
coding
system
susedtoreference each
document:
-
Regulations
*
sequence
number
R*/ACOP
-
Approved
Code
of
Practice
R* GN
-
Guidance Note
*
sequence
number
R* AD
-
Approved
Document
6 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 14/148
Space Requirements
Section
2
Legislation
and
Good Practice Guidance
Table
2.1
Management
of
Health and
Safety
at
Work
Regulations
1992
REFERENCE STATUTORY NSTRUMENT
Ri
Management
ofHealth and
Safety
atWork
Regulations
1992.
Ref:
SI
1992
No.2051
These Regulations impose
a
dutyon
employers
to
develop
a
systematic approach
to risk
management
to ensure the
workplace
is
safe and
healthy
for their
Date:
1
Janua'
1993
employees
and
others
who
may
be
affected
by
their
activity.
It
provides
a
framework
to
carry
out a risk assessment
and
organise
measures
o
prevent
or
minimise those
risks,
and set
upsystems
for
on-going
surveillance.
As
part
of heirduties under these
Regulations,
the
employer
must
carry
out risk
assessmentof the variousactivities carriedoutatthe
workplace, including
maintenanceand
repair
ofmechanical and electrical
systems serving
the
workplace. Specificrequirements
are
amplified
in other
regulations
suchas
R2,
R3, R5,
R6.
These Regulations require:
•
risk
assessment
of
he
workplace
for the
employees
andothersaffected
by
their
activities;
•
preventative/protective
measures tobe
put
in
place arising
from therisk
assessment;
•
health surveillance
appropriate
o the
risks;
•
appointment
of
persons
esponsible
for
preventative/protective measures;
•
emergency procedures;
•
provision
of
nformation
for
those involvedin risk
assessment,
preventative/protective strategies,emergency procedures;
•
co-operation
between
employers
who
share
a
premises;
•
training
and
nstructions or use of
machinery, dangerous
ubstances,
etc;
•
provisions
for
temporary
works.
Ri/ACOP
Approved
Code
of
Practice.
Ref: HSC
-
L21 Provides clarification of he
Regulations
and
guidance
onhow
they
should be
implemented.
This
documentsetsout the
generalprinciples
ofrisk
assessment,
Date:
1992
healthand
safety arrangements,
health
surveillance,
etc.
JULY1996 7
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 15/148
Space Requirements
Section
2
Legislation
and
Good Practice Guidance
Table
2.2
Workplace (Health, Safety
&
Weltare) Regulations
1992
REFERENCE STATUTORY NSTRUMENT
R2
Ref:
SI
1992
No.3004
Dates:
1
January
1993for new
workplaces
in use after
31 December
1992
1
January
1996for
existing workplaces.
(Schedule
2 of the
Regulations
will
continue
to
apply
until that
date).
Workplace Health,Safety
and
Welfare) Regulations
992
These
Regulations replace
a
considerable
amount
of
existing
egislation contained
in the Factories Act
1961, Offices,
Shops
and
Railway
Premises Act 1963and
others.
They
are
applicable
to all
workplaces except
meansof
ransport,
construction
sites,
sites where mineral
resources
are extractedand
fishing
boats.
They
setoutthe
generalrequirements
or
the
working
environment,
safety
facilities and
housekeeping.
These focus
onthe
specific
issues which affect the
quality
of he
working
environment
suchas
temperature,
ventilation, lighting, cleanliness,etc.
The
Regulations impose
duties on the
employer
and
personshaving
control
of he
workplace
toensurethat the
workplace
is fit for
purpose,
witha
healthy
and
clean environment
and
he
equipment
and
systems
are
properly
maintained.
These
Regulations
require
the
workplace, equipment
and
devices
to be
maintained o
function
efficiently
(from
the
view-point
ofhealth and
safety).
In
this
process, provisions
should
be
made
o
permit
maintenance o
be
carriedout
properly
and atsuitable ntervals.Referenceismade
o
BS8210
(Guide
to
building
maintenance
management)
and also to other Health
and
Safety
Regulations.
The
Regulationsrequire
trafficroutes
to
be suitable
n
terms of
strength
and
stability
for
the
loads whichwill
be
mposed.
Hence there is a
requirement
o
assessthe
suitability
of
egress/ingress
routes for
replacement
of
majorplant
components.
The
Regulationsrequire
that
measures
are taken
to
prevent
fallsfrom
heights,
in
particular
work
platforms
and
addersabove 2m
in
height.
These
Regulations
require
health and
safety
issues
to be addressed or:
•
maintenanceof he
workplace
and of
equipment,
devicesand
systems;
•
theinternal
environment, ventilation, temperature,humidity,
lighting;
•
workstations and
seating;
•
sanitary
and
washing
acilities;
•
drinking
water;
•
minimum space for occupied rooms;
•
provision
of
safe and suitable rafficroutes
(includes themovement of
plant
and
equipment);
•
protection
from
falling
rom
heights.
R2/ACOP
Ref:
HSC L24
Date: 1992
Approved
Code
of
Practice.
Provides
clarification
of he
Regulations
and
guidance
for
their
mplementation.
The
duty
of
ensuring
he
workplace, equipment,
devices
and
systems
are
properly
maintained s
explained.
S
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 16/148
Space Requirements
Section
2
Legislation
and Good Practice Guidance
Table2.3
Provision and Use
ofWork
Equipment Regulations
REFERENCE
STATUTORY NSTRUMENT
R3 ProvisionandUse
of
Work
Equipment Regulations
1992
Ref:
SI
1992
No.2932
These Regulations combine
all
the
existing
statutory requirements elating
to
equipment
used
at
work.The
Regulations place
a
duty
on the
employer
to ensure
Dates:
thatwork
equipment
is
safein use
anddefines minimum
requirements.
The
1
January
1993
definitionofwork
equipment
is
wide;
from fork ift trucksto
portable
drills. The
General
requirements
definitionof use'covers the
starting,
stopping,
transporting,
epairing,
apply
to
existing
modiing,
maintaining,
servicing
and
cleaning
of
equipment.
equipment, specific
Employers'
general
duties
nclude:
requirements
only apply
to
new
equipment.
•
equipment
which
s
selected
is
safe
and suitablefor the
task and
he
working conditions;
1
January
1997
Specific
.
.
ensunng
that
equipment
s
properlymaintained;
requirementsapply
toall
work
equipment.
• providing raining and
information
on the
equipment.
Employers' specific
duties
include:
•
maintenance
of
equipment;
•
protection
from
dangerous parts
of the
equipment
andfrom
specific
hazards;
•
isolation of
equipment
from
power
sources;
Equipment
covered
by
these
Regulations
include:
•
equipment
which
operates
at
high
or low
temperatures,
•
controls
and
control systems;
•
stability
of
equipment.
R3/CN1
Work
Equipment.
Ref: HSE L22 Provides
guidance
on
the
Regulations; guidance
on
general
issues
such as
suitability
ofwork
equipment, maintenance,
information
and
instructions,
to
Date: 1992
specificrequirements
or
lighting, emergency stop controls,
isolation from
power
sources,
etc.
JULY1996
9
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 17/148
Space Requirements
Section 2
Legislation
and Good Practice Guidance
Table2.4 Construction
(Design
and
Management) Regulations
1994
REFERENCE
STATUTORY NSTRUMENT
R4 Construction
(Design
and
Management) Regulations
994
Ref:
SI
1994
No.3140
The
CDMRegulations impose
mandatoryduties on
clients, designers
and
contractors
to
minimise
risks to
construction
workers
and o
those
who
will
Date:
31
March
1995
eventually
maintainand
repair
the
building,
with
consideration also
of he
demolition
process.
Therefore
the
designer
must
avoid
causingany
foreseeable
health and
safety
risks
to
those
persons constructing,
maintaining,
cleaning
or
demolishing
the
building.
Hence
in the
planning
of
plant
ooms
and
he distributionofmechanical and
electrical services around
the
building
the
designer
has
duties to ensure there is
sufficient access
and
space provision.
The
designer
must
undertake
arisk
assessment
o
identify
hazards
in
construction
and
maintenance ctivities.
In
terms
of
access and
space
requirements
he
designer
must
consider
for
example:
•
space
needed forremoval
and
handling
of
plant
components.
Sufficient
space
must be
provided
for safe manual
handling
or to
facilitate
he
use of
mechanical
lifting
devices;
see
alsoR6.
•
provision
ofsafe access
to
plant
components
at
high
level
to
prevent
falling
from
height.
The
guidance
notes which
accompany
he
Regulations
(see
R4/GN1&
R4IGN2)
define the duties
of
he
designer,
contractor
and
client
and
provide
moredetailed
guidance
for the risk assessment
xercise.
However,
none
of
he
accompanying
guidance
to
these
Regulations provide explicit
information
on
space
allowances.
The aim of hese
Regulations
is
to
improve
the
health
and
safety
ofconstruction
workers
by
placing
newduties on
clients,
their
agents,
designers
and
contractors.
These
duties extend
from
the initial
conceptdesign hrough
o the
execution of
works
on siteand
subsequent
maintenance
and
repair.
A
new role is
defined,
that
of
Planning
Supervisor
(PS),
to
identify
he main hazards
and risk andco-
ordinate
he
designers
in the
process
of
risk
management.
Two documentsare
required
n this
process:
•
The Health
and
Safety Plan;
Thisdocument contains
he
Health
and
Safety
information related
to
the
desigupreparedby
the
design
team
and he
PS. This
will
alert
Tenderers
to
hazards and risks
associated
with
the
construction works.
•
The Health
and
Safety
File;
This
may
consist
of
as-built
specifications
and
drawings
and
can
be
considered
as an
enlarged operation
andmaintenancemanual
for
the
building.
The
file
will contain
nformation
on
operation
and
maintenance
of
plant
and
equipment,procedures
for
cleaning
and
repairing
he
fabric,
and
design
oadings
for structural elements.
The
Regulations require
a
more formal
approach
o risk
management
nthe
construction
process
from all thoseinvolved
in
the
procurement
procedure.
10
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 18/148
Space Requirements
Section
2
Legislation
and Good Practice Guidance
Table2.4
Construction
(Design
and
Management) Regulations
1994
(continued)
REFERENCE
STATUTORY NSTRUMENT
R4/ACOP
Approved
Codeof Practice.
Ref:
HSC L54 Provides guidance
on the
application
of
he
Regulations,
definesduties of
client,
designers, principal
contractorand
planning upervisor.
Provides methods for
Date:
1995
satisfying
the
requirements
of
he
Regulations
albeit
in
general
erms.
R4/GN1
Managing
Health and
Safety
n
Construction.
Ref:
HSE
C100 Provides
guidance
on how to
comply
withtheCDM
Regulations
forall thosewith
responsibilities
under the
Regulations
Itdefines when he
Regulations
are
Date: 1995
applicable.
The
design
process
is
tracked rom
concept
through
tohandover
identifying
the
duties ofeach of
he
main
members
in
the
design
and
procurement
teams.
Examples
are
given
as
tohowthe
Regulations
will be
interpreted
in
practice.
R4/6N2
Designing
for
Health
and
Safety
in
Construction.
Ref:
HSE Provides
guidance
to
theCDM
Regulations
for
designers
and
outlines
the
principles
of
designing
for health and
safety
in
construction work.
Guidance is
Date: 1995
given
on the
types
ofhazards and risks whichcanoccur in
construction,
maintenance and
repair
of
a
building
inorderto assist the
designer
nrisk
assessment.
JULY1996
11
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 19/148
Space Requirements Section 2
Legislation
andGood Practice Guidance
Table2.5
Electricity
at Work
Regulation
1989
REFERENCE
STATUTORY NSTRUMENT
R5
Electricity
at
Work
Regulations
1989
Ref:
SI
1989 No.635 These Regulations impose
duties on
employers
and
employees
to
minimise
risk
associatedwith the useofelectrical
equipment; fixed, portable
and self
powered.
Date: 1
Apnl
1990
The
Regulations require adequatespace
and
means ofaccess
to
be
provided
wherework is carried
out
on
electrical
equipment.
These
Regulations
supersede
he
Electricity
(Factories Act)
Special Regulations
1908& 1944.
They
are
applicable
to all
places
wherework is carried
out
using
electricity
andcover
all
electrical
equipment,
including
fixed,
portable
and
self-
powered.
Thereisnodistinction between
HighVoltage
and
Low
Voltage
installations.The
Regulations place
a
duty
on
employers
and
employees
and
detail the
principles
ofelectrical
safety
rather han
try
ocover
specific
cases. The
Regulations
fall into two distinct
categories
with
some
imposing
an
absolute
duty
and
others
allowing
a
so
far
as is
reasonably practical' interpretation.
These
regulations require:
•
systems
to
beconstructed
and maintained
o
prevent danger
to
persons;
•
equipment
to be
suitable
for
use
in its ocation
and
environmental
conditions;
•
all
conductorsto be
suitably nsulated,
protected
or located so as
to
prevent
danger;
•
systems
and
equipment
to
be
correctly
earthed;
•
systems
to have suitable
protection
against
overcurrent
anda
means
of
isolation;
•
precautions
to
be takenwhilst
working
on dead
equipment
to
prevent
t
becominglive;
•
no
person
shall be
engaged
in
any
work
activity
on
orso
near
a ive
conductor (other thanone
suitably
covered with
insulating
materialsoas
to
preventdanger)
that
danger may
arise.
(Note:
subject
to
a
number
of
exceptions
defined
in
the
Regulations);
•
adequate
working
space, lighting
and
means
ofaccess
to be
provided
wherework iscarried out on electrical
equipment;
•
persons
o be
competent
to
carry
out he work involved or be under
suitable
supervision.
R5/CN1
Memorandum
of
guidance
on the
Electricity
at
Work
Regulations.
Ref:
HSE
HS(R)25
Provides
guidance
onthe
Electricity
at
Work
Regulations 1989, excluding
the
Regulations applicable
to
mines and
quarries.
Provides
background
information
Date: 1989
explaining
the
reasoning
behind the
regulations
withmethods for
satisfying
the
requirements
of
he
Regulations
in
general
erms.
12
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 20/148
Space Requirements
Section 2
Legislation
and Good Practice Guidance
Table2.6 The
Manual
Handling Operations Regulations
1992
REFERENCE STATUTORY NSTRUMENT
R6
Manual
Handling Operations
Regulations
992
Ref:
SI
1992
No.2793
These Regulations impose
a
dutyon
employers
to
assess the manualhandling
procedures
carriedout
by
their
employees
inthe course of heir
workplace
Date: 1
January
1993
activities. This will extend to the installation
and
maintenance
of
M&E services
and
overlap
with other Health and
Safety Regulations.
Adequate pace
must be
provided
for
correct
manual
handling
of
plant
components
up
todefinedlimits. Thereafter heuseofmechanical
lifting
and
handling
devicesmust be
considered,
whichwill
havea
significant
influence
on
space provision
around the
plant
tem and
along
the route
of
egress
from
the
building.
TheGuidance
Note L23
clearly
defines
the limits on manual
handling
for
particular iftingheights
andmaximum loads
-
see
Section 3.1 which discusses
the
issues
in
more detail.
Duties
are
placed
on
employers
to assess risks
and
put
in
place
measures
o
minimise those
risks.
Employees
have
a
duty
to
make use
of hose measures
put
in
place
for
their
protection.
These
Regulations
should be
read
in
conjunction
with the
Management
ofHealth
and
Safety
atWork
Regulations
(Ri)
which
impose
a
general duty
on
employers
to
carry
outarisk assessmentof heir
employees
in the
workplace.
Where
the
possibility
of
risks to
employees
frommanual
handling
is dentified from therisk
assessment
xercise,
these
Regulations
should
then be
observed.
These Regulations
set
a
hierarchyof
measures:
•
avoid hazardous manual
handling
as far as
reasonably
practicable;
•
assess
any
hazardousmanual
handling
operations
thatcannotbe
avoided;
•
reduce riskof
njury
as far as
practicable;
R6/GN1
Manual
Handling
Guidance
on
Regulations
Ref:
HSEL23 Provides
guidance
to
satisfy
he
Regulations
intermsofmanual
handling
techniques
and limits on
safe
manageable
loads
for
different
reach
heights
and
Date.1992
postures.
The threshold wheremechanical
lifting
devices are usedisaddressed
and
he
types
of
devices which
can be used are
thscussed.
JULY1996
13
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 21/148
Space Requirements
Section 2
Legislation
and Good Practice Guidance
Table2.7 The
Pressure
Systems
and
Transportable
GasContainers
Regulations
1989
REFERENCE STATUTORY NSTRUMENT
Ri
Pressure
Systems
and
Transportable
Gas Containers
Regulations
989
Ref:
SI
1989
No.2169
These Regulations
replaceparts of he
Factories
Act
1961 which
relate to the
safety
of
pressure
systems
and heir
mechanical
integrity.They apply
o
Date: 1
July
1990
compressed
air
plant,
steam and
pressurised
hot
water
plant
and
various
pressurisedgassystems.
The
Regulations
call fora
regime
of
systematic
examination
and
esting
of
pressure
plant.
Awritten
scheme
of
examination
is
required
for all
protective
devices,
pressure
vessels
and
relevant
pipework.
Thusaccess and
space
mustbe
provided
to
permit
the
regular
inspection
of
hese
system
elements.
Furthermore,
or the
installation,
operation
and
maintenance
of
hese
systems
there
s
a
duty
to
provide
safe access
to
the
plant.
R7/ACOP
Safety
of Pressure
Systems
-
Approved
CodeofPractice
Ref:
HSC Provides
guidance
on
the
application
of he
Regulations.
This
Code
gives
a
broad
outline of he
principles
which
apply
to
pressuresystems.
There
are,
however a
Date: 1990
number of other
ACOPs
and
guidance
notesnot
cited
here
which offer
guidance
to the
duties under
the
Regulations;
these are listed
inthis
ACOP.
14 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 22/148
Space Requirements
Section
2
Legislation
and Good Practice Guidance
Table2.8
The
Building Regulations
1991
REFERENCE
STATUTORY
NSTRUMENT
R8 The
BuildingRegulations
1991: Part
Bi Means of
Escape
Ref: SI 1991No.2768 These
Regulations
make
provisions
for
public
health and
safety
in new
building
works
and
applyto new
build,
refurbishmentand
extensions. Section
Bi
requires
Date: amended 1992
that the
building
be
designed
and constructed
othat there
are
means
of
escape
inthe case of ire.
R8/AD
Approved
Document
B
Ref: DOE The
approved
document
provides
an
interpretation
of
he
general equirements
cited inthe
Regulations.
It
gives guidance
onthemaximum travel distances and
Date:
1992
number of
escape
routes fora
variety
of
building
types
and
plantroom spaces.
JULY1996
15
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 23/148
Space Requirements
Section
2
Legislation
and Good Practice Guidance
2.3 GUIDES TO GOOD
PRACTICE
There are
many guides
oactivities involved in
maintaining
mechanical and
electrical services
and theco-ordinationand
management
ofmaintenance
strategies.
However,
the references cited belowhavebeen limited to
thosewhich
provide
useful
quantitative guidance.
This
sub-section
provides
a
summary
of
those references
which
provide
a
quantitativeguideto the
provision
of
space
for
servicesandaccess.
In
addition,
information should be
sought
from manufacturers
as,
forcertain
plant items,
their
ecommendations willbe
governing
factors
affecting space
provision, e.g. separation
of air
cooled
chillers
rom
each
other
andfrom
enclosures.
Gi
Space
and
Weight
Allowances for
Building
Services Plant:
Inception Stage Design
-
Technical Note TN
9/92
BSRIA. 1993.
Space
requirements
are
given
for
various mechanical
and
electrical services
plantrooms.
General
plant
arrangements
are
given
forboiler
rooms,
chiller
rooms,
air
handlingplant
andelectrical
switchgear. Space
and
weight provisions
are summarised for
a
range
of
plant
capacities.
The
document
is
ntended
o
be
used
for
space
planning
at
the outline
stage
of
design.
G2
Space
Allowance
or
Building
Services:Detail
design stage
-
Technical Note
TN1O/92
BSRIA 1992.
Space
requirements
are
given
for the
purpose
of nstallation
andmaintenance of
pipework, ductwork, cabling
etc. The
guide
is
ntendedfor the detail
designstage
where
space provision
is
given for
various
pipework
types,
techniques for
insulating
he service etc.TheGuide
restricts itself
o
distribution
services.It
does
not
cover
detail
design
issues ofcentral
plant,
terminalunits or false
ceiling
and
raisedfloor co-ordinationoraccess.
G3
BS 8313-
Codeof Practice forAccommodation of
Building
Services in Ducts
(Formerly
CP413).
BSl. 1989.
Provides
recommendationson
the
design,
construction and nstallationof
ixed
ducts. This includes
pace provisions
for safe
access,
installationand
maintenance
of
service
ducts.The
influence
of
he
frequency
ofmaintenance
on
the
provision
of
access
is addressed
n the
Code
of
Practice. Anthropometric
data
is
given
for the
fundamental
analysis
of
space requirements
or maintenanceor
installationactivities. TheCodeofPractice concentrates
primarily
on
space
provisions
forair
ducts,
considering
methods of
ointing,
insulation
and
he
relationship
of
he
duct
toenclosure walls.
16 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 24/148
Space Requirements
Section2
Legislation
andGood Practice
Guidance
04 Health Technical Memorandum 2023
-
AccessandAccommodation
for
Engineering
Services NHS Estates 1995
Volume
1
Management Policy
-
provides
a
strategicguide
to
space
requirements
and
accessformechanical
and
electrical services for
chief
executives/general managers
whohave
responsibility
for
services
installations
and
maintenance. Reference
is made o
Health
and
Safety legislation.
Volume
2
Good Practice Guidance
-
provides
recommendation
on
space
requirements
of
central
plant
and
distribution
ystems
for
mechanical andelectrical
services.
The main thrust of hedocument is
understandably
directed to
hospital
applications,
although
some of
he
guidance
is relevant to
general
applications.
05
BS
8210
-
Building
Maintenance
Management.
BSl. 1986.
This
BS
provides guidance
on
a
systematic
approach
o
management
of
building
maintenance.
It
addressesboth fabric
and
engineering
services maintenance
requirements.
The issue
ofsafe access for
inspection
and maintenance
activities
isdiscussed
and how the health
and
safety
requirements
pertaining
at
that time
c1986)
influence that work.
Thedecision
to
make
provision
for
permanent
or
temporary
accessisconsidered
and he
standards whichneed
to
be adhered
to
when
using adders,scaffolding,
cradles,
mobile scaffold towers and
powered equipment
such as scissor
lifts,
etc.
G6
Designing
for
Maintainability
-
Application
Guide 11/92. BSRIA1992.
ThisGuidehasbeen
produced
in
conjunction
withG1andG2
and considers at
each
stage
of he
design process
what allowances should be ncluded for
maintenanceof he
building
services. Checklists are
given
toreview the
detail
design
oensurethat
provisions
are
in
place
to allowthe
system
o bemaintained
effectively.
07
Electricity
at
Work
and Related
Regulations
-
A
Handbook or
Compliance.
TE Marks. 1994.
Provides
explanation
of
he
Regulations
and outlines he
ways
of
meeting
he
requirements.
Particular
emphasis
s
placed
on the
difference between
regulations
mposing
absoluteduties
and
hose
which
must
be
followed
as
reasonably practical.
08
AJ Guide
o
the
Space
for
Services
-
Architects Journal
Reprint.
1986.
This
publication
s a
reprint
ofseveralarticles which
appeared
n the
Architects'
Journalin1986.Datais
given
for
space requirements
of
central
plant.
The
ayout
of
distribution
systems
around the
building
is
discussedwith
particular
attention
to
the
co-ordinationof
pipework,
ductwork
and
cabling
with
structure,
for
accessible
ierticaland
horizontal distribution
systems.
JULY1996
17
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 25/148
Space Requirements
Section 2
Legislation
and Good Practice Guidance
G9
Standard
Maintenance
Specification
or
Mechanical Services In
Buildings.
HVCA. 1991.
This
StandardMaintenance
Specification
was
produced
by
the
HVCA
n
conjunction
with CIBSE and BRECSUand
provides
a
contractual tandard for
maintenance work.
The
document
provides
schedules
ofmaintenance asks
requiredby
the
elements
of
he
building
services
systems,
the
frequency
of
maintenance
and
notes
on the
maintenance procedures.
There
are
five volumes:
Volume
1
Heating
and
Pipework Systems
Volume2
Ventilating
and
Air
Conditioning
Volume
3
Control,
Energy
and
Building
Management Systems
Volume4
Ancillaries, Plumbing
and
Sewerage.
Volume
5
Electrics
in
Buildings
GlO
Tolley's
Health
andSafety
at
Work
Handbook 1995.
This handbook
provides
a
useful
commentary
on most of the
legislation,
regulations
and
available
guidance
which affects
health
and
safety
and
welfare
at
the
workplace.
Thisversion
states
he law
as
at
30
September
1994
and
s
updated
o
accommodate
changes
n
statute law and
regulationsby
repeal,
revocations
and
enactment,
andin
cumulative case aw. The
guide provides
an
interpretation
of
ssues related
to
maintenance,
access
and
risk
assessment.
2.4
DEO(W)/DWS
TECHNICAL PUBLICATIONS
TheDEO(W)/DWS
"Technical Publications Index"
lists the extant
MOD
and
PSA
technical publications which
are
to be
used
in
management
and
construction
of
MOD's
built
Estate.
The
publication
"DefenceWorks
Safety
Rules
and
Procedures for
Working
at
Height"
is
to be
issued
shortly
and
s of
particular
relevence
to the
provision
of
safe
access.
18 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 26/148
Space Requirements
3
Philosophy
of
Plantroom
Design
3.1
MAINTENANCE
AND
OPERATION ISSUES AFFECTING
THE
SPACE ALLOWED
FORPLANT
3.1.1 BasicConsiderations
Riskassessment
and he
consequent provision
of
access
must be madeon the
basis
of
he
following
aspects
of
he
operating
and
maintenance
0
&
M)
taskand
the
specified
0
&
M
staff
which
are
the
major
determinants:
•
Task; type,
difficulty, frequency,
duration.
•
Hazards,
dentification
and
evaluationofrisks.
•
Staff;
type, supervision,
size of eam.
Task
type;
the maindivisionof asks is between
operation, monitoring,
inspection, servicing
andmaintenance. The
first wo of
hese
usually require
no
more thanobservation
and
operation
of
simply operated
controls.
The
last
three
involve
in-situ'work with or without
dismantling,
and/or
demounting/removal
for on- oroff-site overhaul.
Demounting requires
more local
space
and local
overhaul
requiresservicingbays.
Task
difficulty;
thisis
a
unctionof
he
type,
the
locationof
he
activity
and
he
physical
actions
required.
Cramped positions may
oftenbeacause ofaccidents.
Guidance on the
space
needed
is
given
inthe
anthropometric data,
see
Fig
3.1.
Numerical
guidance
onthemanual
handling
of
heavy objects
is
given
in
Appendix
1 of heHSE
guidance
booklet L23 to the Manual
Handling
Operations
Regulations
1992.
A
figure covering
lifting
and
owering,
is
reproduced
as
Fig
3.2.
Task
frequency
and
duration;
easieraccessformore
frequently performed
and
engthy
tasks
is
ustified
on
economicaswell as
safety
grounds.
Categorisation
of
frequency
is
given
in
Section
3.2.
Hazards;
must
be dentified
and
an
estimatemade of
he
risks
involved;
e.g.
falling
rom
heights, ripping,
explosive atmospheres, petroleum vapours,
methane,
etc.
There are various
approaches
to
the
evaluation of
risk
ranging
from
complex
fault
tree
analysis
and
reliability
studieswhere
a
single
event
could lead o death of
manypeople,
to
a
ess
complex qualitative approach
where
the
hazards
mayonly
lead ominor
njury.
Staff
type;
must
allowfor in-house' staff not familiarwith
equipment
and
external
specialists
not familiar with the
plantspace.
Staffsupervision
and
teamsize;
access
must make
allowance for
the
number
of staffneededtoundertake
a
particular ask, eg
a
pair
both committedto
a
task
element
simultaneously.
JULY1996 19
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 27/148
Space Requirements
Section
3
Philosophy
of
Plantroom
Design
Fig
3.1
Anthropometric
Data
(page
1of
2)
(e) Stoop
Alldimensions are
in
millimetres.
Extracts
fromBS8313:1989are
reproduced
with he
permission
of
BSI.
Complete
ditionsof he standards an be obtained
bypost
from
BSI
Customer
Services,
389 Chiswick
Road,
LondonW4 HAL
20 JULY1996
(a)
Prone
(b)
Kneel
(c) Crawl
Stand
Kneel
S
1500
1200
900
600
300
(f) Maintenance reach
evels
1200
(dl
Squat
550
absolute
minimum
750
preferred
minimum
2100
mm.
(g) Passageway
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 28/148
Space Requirements
Section
3
Philosophy
of
Plantroom
Design
FIg
3.1
Anthropometric
Data
(page
2
of
2)
Provide
back
guard
over
2250
height
0
90
750
Optimum
range
Ladder
width 380mm. 450
optimum
Distance between sidewalls600mm.
Rung
distance
c
225
to
250
Rung
diameter
d
20
to
40
(h)
Ladder
500
350
2O0
Optimum range
2100
Optimum
(j) Inclined ladder
All
dimensions are inmillimetres.
JULY1996
21
2100
mm.
150
mm.
Width or
one man
600
o750.
Width or
twomen 1100mm.
Riserb184 optimum
Treadc240
optimum
Ci)
Steps
1100 mm. at 750
1600 mm.
at
500
940
9O0
50°x 860
mum
range
Width530
to
600 with handrails
600
mm.between side walls
Riser
b
250maximum
Tread width
c
80
to
150
Incline
not to
exceed 20°
Width750mm. to 1100
optimum
(k)
Ramp
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 29/148
Notes
1 Full notesare
given
inHSE 23
see
able
2.1
-
R6/GN1)
2
Figures
n he boxed onesaremaximaor he
centres
of he
zones
3
Interpolate
values or otherpositions
n
he zones
4 It the
objectbeing
ifted
passes
through
more han one
zone,
use he lowest
igure
5 Reduce he
guideline
values
by
10% if he
body
s urned
up
o
45°
and 20%
up
to 90°
6
Figures pply
or
up
o 30 ifts/hr
Space Requirements
Section 3
Philosophy
of
Plantroom
Design
Fig
3.2
Lifting
and
Lowering
Full
height
Shoulder
height
Elbow
height
Knuckle
height
Mid lower
eg
25kg 15kg
4
20kg
10kg
5kg
22 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 30/148
Space Requirements
Section 3
Philosophy
of Plantroom
Design
3.1.2 BasicHazards
Allowancemust be made for at
least
he
following
hazards,
both
in
terms of
basic
access and inthe
provision
of"extra"
space
where hehazards cannotbe treated
or
avoided.
•
Hot
or
cold surfaces
not insulated to BS
5970.
•
Sharpedges
and
ends,
usuallyoccurring
on
equipment
or
supports.
•
Hazardous
atmospheres; explosive
dusts or
vapours, petroleum vapours,
methane,
etc.
(Note:
Special
consideration
may
be
required
for
these hazards
which
are
beyond
the
scope
of his
document; specialist
advice should be
sought.)
•
Projecting
parts
of
equipment,
particularly
athead and ankle
height,
allow for the
most extreme
protrusion
of
any component
of
an item.
•
Unprotected movingparts
-
no
go'
area delineation
may
be
required
n
addition
oaccess
space.
• The need to work on
live electrical
parts
in
accordance
with
the
Electricity
at Work
Regulations,
1989.
•
Flammable materials
-
handling space
or
liquid
and
gas
transfer.
Consider
plantrooms
within
plant spaces.
See3.3.
•
Toxic
materials
-
asforflammable materials.
•
Noise
-
acoustictreatment tothe wholeofa
plant
oom
occupies
significant space.
Consider
plant
rooms
within
plant
spaces,
oracoustic
hoods. See 3.3.
•
Heavy
andlor
awkwardly
shaped
objects
may require lifting
eyes
andlor
runways,
suitablefor standard
lifting
echniques, positioned
above
equipment.
The full
height
of the
plantspace
below
the
eye
or
runway
must remain free
of
other
services.
See also HSE
references
in
Section
2.
•
Falling
from
heights
-
walkways,
protected
ladders
etc.
(to
the
relevant
BSs)mustconnectwith accessroutesand mustnotobstruct
any
otheraccess.
•
Tripping
provision
of
step
overs
(with
or without
safety
railsetctothe
relevant
BS)
will affectthe
layout
of
services overhead.
The
following
basic
hazards are
normally
dealt with
by warningsigns,
which
must
not
be
obscured
by adjacent
ervices.
•
Insecurehand andfoot holds
-
provide
donot
walk',
'donot ean
on',
'do
not
use as
support' signs.
Consider
designing
all
hangers
for
equipment
loadplus
the
weight
of
wooperatives.
•
Escape
routes
-
sign
all
escape
routes,
including
labelson
large
tems
whichobscure viewsofexits.
•
Chemical
storage
and
handling,eg
water treatment.
3.1.3
Facilities
or
Maintenance.
The
followinggeneral
principles
should
be
noted. Some will
tend to
minimise
the
area
required
for
access.
•
Routes to
plant
and
equipment
should be asdirectas
possible.
•
Standing
room
should
be
provided
at
the
end of
crawlways
and at/or near
equipment.
JULY1996
23
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 31/148
Space Requirements
Section3
Philosophy
of Plantroom
Design
•
Access
adders and
platforms
are
required
for
high plant
(heights
greater
than
2m),
permanent
or
frequent
access,
temporary
or
infrequent
access;
frequency
is defined in3.2.
•
Mobile access
gear
should be
capable
of
iftingequipment
as
well as
personnel,
and
may
beallowedto
temporarily
compromise
access butnot
escape
routes.As
a
generalrule,
escape
routes
should
neverbe
compromised
and
if
navoidable a
horough
risk
analysis
needs
o
be
completed.
•
Cranage unways
shouldbe
designed
to
allow transfer
to
trucks,
trolleys,
rollers,
skates or
airbags
close to the
point
of ift to minimise the
space
compromised.
•
Stepovers
shouldbe
designed
to
carry
the
weight
of
objects
likely
o be
carriedover
them,plus
that
of he
operatives.
Local
lifting gear may
be
required.
3.2
ACCESS, MAINTENANCE FREOUENCY
AND
DURATIONOF TASK.
3.2.1
Access
The
statutory
duties under
the
HSWA,
FactoriesAct
(requirement
until
1
January
1996)
and hemore
specific
duties inthe
Workplace Regulations
1992
require
an
employer
to
provide
safe
access/egress
to
anyplace
where
employees
have to work
and not
merely
their
normal
workplace.
Thedistinction needs
o be
madebetween
he
access route
to a
plant
tem and
the
space provision
around he
plantnecessary
to
safely
carry
out the
maintenance ask,
repair
or
replacement.
The
provision
ofaccess must
be
appropriate
o
the
frequency
at
which certain
taskswill be carriedout. Taskswhichneedto
be carriedoutona
dailybasis,e.g.
checks
on steam
boilers,
will need
open
and mmediate access.
Conversely
pipework
enclosed in
ariser
space
wouldnot
normally require regular inspection.
Fig
3.3 illustrates the
relationship
between he
frequency
ofmaintenenceand
the level
ofaccess
required.
Definitions
of
frequency
andaccess
are
given
in
Section 3.2.2
The
access/egress
route must be sufficient interms of
space provision
and
oading
capacity
toallow
the
safe movement
of
maintenance
staff,
the
handling
of
major
plantitems
and
he use
of
mechanical
lifting
devices
where
necessary.
In the considerationofaccess to
plant
above 2m above floor
level,
falls from
height
is
a
major
concern.Thereare two
aspects
to considerwheremaintenence
tasks
are
at
high
evel:
•
access
to the
working position (portable
ladder,
scaffold
owers,
powered
working platform).
•
the
working space
around the
plant
item
The
working platform
around he
plant
tem
may
be
permanent
for
frequent
accessor
temporary
or less
frequent
maintenance. The
Workplace Regulations
require
that
it is
protected o prevent
people
falling
and
objects
falling
on
to
people
below. This
may
be with the
provision
of
fencing,guard
rails and oe
boards see BS 5395.
24
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 32/148
Space Requirements
Section 3
Philosophy
of
Plantroom
Design
Fig
3.3
Access forMaintenance
1r
Occasional
Maintenance
JULY1996
25
Maintenance
Task
I
Frequent
Maintenance
I
Ir
Infrequent
I
Repair
or
Maintenance
I
Replacement
Clear
&
Immediate Access
I
L
Jr
Jr
II
Semi-Clear Access
Jr
Activities
Plant
requiring
frequent
ccess
(up
o
monthly)
or
nspection/
adjustment/testing/lubrication
/cleaning.
Eg chillers,boilers,
cooling
owers
dAcce
Activities
Yearly
maintenance activities.
Repair
or
replacement
of
plant
components, pipework,
ductwork.
Activities
Plant
requiring
maintenance
up
to
6
monthly
ntervals
inspection/ad ustment/testing/
lubrication/cleaning.
Eg
tank
rooms
Access
Clearand
mmediate
access to
andaround
plant
tems.
Itat
high
evel
Permanent
stairsand
catwalks
suitablyguarded
with
hand
rails
oBS5395
with sufficient
space
for
he
handling
or
removal of
major
plant
components.
U
Access
Access
through
clearly
marked
hatches,
panels
etc,
using
quick
elease fasteners.
Ifat
high
evel
Permanent ladders, scaffold
towers,
hydraulic powered
platforms.
Clear areas around
plant
temswithout
heneed
for
dismantling
ofservices or
building
elements.
Access
Access for
preventative
maintenance
gained
through
demountable
partitions,
nd
semi-permanent panels
which
canbe removed withoutneed
for
re-decoration.
Some
dismantling
of
plant acceptable.
Access
for
eplacement
of
ductworkand
pipework
in
riser
voids
hrough
panels
with
minor
re-decoration
requirements.
Ifat
high
evel
Temporary
access
equipment,
scaffolding,
taging,
ladders etc.
Lred
adder
ermanent
uarded
stair
andcatwalk
Permanent
guarded
adder
and
catwalk
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 33/148
Space Requirements
Section
3
Philosophy
of
Plantroom
Design
3.2.2 Definitions
of
frequency
and
level
ofaccess.
Frequency
As
frequency
ofmaintenance will influence the level
of
access thisis
clearly
definedfor each
plant
item insection 5. Forthe
purposes
of his
document,
frequency
is
categorised
as
follows;
•
Frequent;
lessthan
monthly
•
Occasional;
between
monthly
andhalf
yearly
•
Infrequent;greater
than half
yearly
Accessfor
Frequent
Maintenance
All
plant,
valves, controls,
terminal
units,
etcwhich
requirefrequent
maintenance
and
operation
should
have
permanent,
clear
and
immediate access
with
adequate
pace provision
to
carry
out he
particular
ask. If
enclosed,
a
hinged
door should
be
provided
which
opens
outward
hrough
180°.
Access
for
Maintenance
on
an
Occasional
Frequency
For maintenance askswhichare undertaken onanoccasional
frequency,
access
can
be
readily
achieved
by
removal
of
clearly
marked
hatches,
floor
traps,
panels/tiles
infalse
ceilings,
walls and
partitions.Quick-release
fasteners
(captive type)
are
preferred
o screwed
fixings.
Access for
Infrequent
Maintenance
Infrequent
maintenanceor
emergency
repair
and
replacement
of
ductwork,
pipework
and
terminal
units,
shouldbe
considered.
The
removal ofdemountable
partitions,doors, etc,
to
gain
access
may
be
appropriate.
The removal of
masonry
walls isnotconsidered reasonable.
The issue ofwhether
permanent
clear
access
is
necessary
for
emergencyrepair
needs
o
be
agreed
with the client. Provisions
should beallowedfor the removal and
replacement
of
pipework
lengths
in
a
service duct.
Duration
of
ask
Durationcannotbedefined so
specifically
because it isrelated to
operative
fatigue.
This is
dependent
not
only
on
the
dexterity
and
physical
exertion
required
butalso ontheaccess
provided
andenvironmental onditions.
In
general,
access should bereconsidered
for
any
ask,
other
than
observation,
whichoccurs abovehead level orbelow
hip
evel and lasts more
than
1minute.
Alternative
handlingprocedures
should
be
sought
fexertions
greater
than hose
of
Fig
3.2 are
required.
3.3 LOCATION
AND
LAYOUT
OF PLANT
ROOMS
The
following
properties
of
plant
and
equipment
and
characteristics ofnormal
building
construction limit
the
practical
ocationsof
plantrooms.
•
Plant
weight
-
structural
considerations,
nitial installation
and
removal
for
servicing
or
eplacement
•
Plantsize
-
removal for
servicing
or
replacement
•
Design
of loor
slabs
-
floor
slabs other than
ground
floors
are
not
usually
designed
to
supportheavy weightsparticularly
tems such
as
liftinggear
attached
o theirunderside.
If
he
slab is
required
o
bear
fully
oaded
lifting
devices
provision
should be
madein the structural
design.
•
Ingress
and
egress
-
loading
acilities for and
routes to
plant
roomsare
necessary.
Where the size or
weight
carrying
capacity
ofeither are
limited,
smaller
or
easily
dismantled
plant
must be
used.
26 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 34/148
Space Requirements
Section 3
Philosophy
ofPlantroom
Design
Escape
routes
-
the
options
or
escape
outesinbasementswill be limited.
The
followingbuilding
related
factors,
when
nadequate,
affect
possible
plantroom
location
by increasing
hefloororwall
areas
requiredbeyond
the
values that
would
be
expected.
•
Relationship
to
outgoingservices
-
here
must
be
links to
dedicated
electrical,
ductwork and
pipework
routes
of
adequatecapacity.
Also,
if
these links have
significantlength,
other
building spaces may
be
compromised.
•
Heights
of
plant
ooms
-
inadequate
height
increases
the
plant
room
floor
area. The
plant
room
areaat the
point
ofexit
ofservices
will be
congested,
which will
limit the number of
servicesthat
can exit
to
an
adjacent
iser
without
compromising
access.
•
Clear
plantspace
-
columns
may
obstructwithdrawal
space
or
access/escape routes;
beams
may
obstruct
cranage
or
cross-plantroom
service
routes;
imperforable
walls willhaveeffectssimilar o
plant
ooms
of
nadequate
height.
The
following
rules'
apply
generally
to
considerations
of
access.
•
Space
requirements
or O&M activities
may
not be
adequate
for functional
requirements e.g.
distance from
walls,
or other
plant,
of air cooledchillers
may
cause recirculation of
cooling
air).
•
Space required
for future
plant
must
not
be
compromised.
Thisincludes
access routes. The
space's
eventual
purpose
should
be
reserved
by
flooror
wall
markings.
•
Other itemsof
equipment
orthe
building
fabric mustnotbe affected
by
O&M activities on a
particular
itemof
plant.
If he
equipment
is
noisy
or
the
maintenance
s
otherwise dangerous, consider locating
duty
and
standby
equipment
in
separated
spaces.
•
Equipment
should be laid
out in
a
way
hat creates sharedaccess
space
between temswhich arenotmaintained
simultaneously.
•
Escape
routes must not be
blocked
by
O&M
activities.
The rule can be
relaxed
if
here
isan
alternative
escape
route.
However,
full risk
assessment hould
be
carried
out.
•
Allow for theeffects of
hinged components,
suchascontrol
panel
doors,
boiler
burners,
access
panels
ontheunderside of
plant
or
ducts,
particularly
when
positioning
adjacent
services.
•
Allow for the
furthest
projection
of
anycomponent
onan tem of
equipment.
•
Avoid
tripping
hazardsand ncrease
ow level access
space
by running
pipe
andductwork
at
high
level in
plantrooms
with
droppers
to
equipment.
•
Motor control
panels
shouldbe
close to
the
plantroom's
normal
entry
doors.
•
Large plant
shouldbeclose tothe mainaccess doors
(or
specialised
removable wall and roof
panels).
•
Consider
what items
of
plant
can be
located
inthe same
space
and
what
must
be
separated,e.g.
air
compressors
andboilers
from
chillers; larger
or
emergencyelectrical generators
(and
their
associated
equipment)
rom all
other
plant. Separateequipment
which
is
noisy,
andlor
contains oxic or
flammable
materials,
from other
plant.
This limits areas
affected,
eases
control and eases rescue
operations.
JULY1996
27
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 35/148
Space Requirements
Section 3
Philosophy
of Plantroom
Design
•
Allow
adequatespace
for items such
as
breathingapparatus
and
other
cumbersome
personal
protective equipment,
eye
washersand
dousing
showers close
to the
point
of
hazard.
•
Allow
space
for
emergency
ock-offcontrolsclose to
the
normal accessdoors.
3.4
DEVELOPMENT OF PLANTSPACES
3.4.1 Practical
space requirements
The
space
equirements
of ndividual items of
plant, pipes, ducts,
cables and
wiringdeveloped
from the
principles
described
above,
areshown nSections4
&
5.
The clearances
shownare
those that
are
required
if
he item is surrounded
by
walls or
equivalent
ixedbarriers. For several
plant
itemsin a common
space
there are therefore
wo
corollaries;
•
If
adjacent
tems are not maintained
simultaneously,
a
single
clearance
can be
shared.
•
The shared clearance must be
equal
o
the
larger(est)
of
hose
required.
Similarly only equipment
which
must
be ifted from soffit
mounted
eyes
or
runways requires
heclearances shown n
plan
for the full
plant
oom
height.
The
consequence
is
that the
sums ofvolumes
and
plan
areas
actuallyrequiredby
plant
andaccess
space
is
usually
lessthanthe sum of allof he individual items'
requirements.
Some
of
his
space
saving
soffset
by
the
space requirements
or
routingpipes
andductsand
cableways.
Further the
shape
of the
plantspace
is
unlikely
tobe
ideal for the
plant
it
eventually
is
to
contain,
bearing
n
mind standard
building
design
sequences
andtendering
procedures,
which
creates
ess
than
deal solutions.
The
optimum
use
of
any space
isdetermined
by
certain of
he
factors listed
in
the
previous
sub-section,
such
as the
relationship
of he
plant
space
to the
outgoing
service
routes,
externalwalls and accessroutes.Itmust also be
accepted
that
laying
out
plant spaces
is to
an
extentan
amalgam
of
experience,
skill
and
hree
dimensional visualisation.
The net
consequence
of
hese
conflicting
sets offactors is
that
the overall
area/volume
of
a
plantspace, including
wastage,
is
unlikely
to be ess than
the
sum of he
requirements
of he individual
components, neglecting overlaps.
The
exceptions
are
most
likely
o
be
plant spaces
designed
after
equipment
hasbeen
selected
and
containing
either
a
single
type
of
equipment
or
a
wide
variety
of
smaller
tems.
There are two
types
of
plant
oom
for which hese
effects
are most
significant:
•
smalltomedium sized boiler
rooms,
which
conventionally
contain
HWS
calorifiers,
all related
pumps
and water treatment
equipment
inaddition
to theboilers.
•
smalltomedium sizedwater-chiller
rooms,
which
conventionally
contain
the
related
pumps.
Demonstration of heuse of
overlapping
access
spaces
andstatisticaldatafor
areas of hesetypes
of
plant
space
are
given
in
Figs
3.4
-
6.
28
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 36/148
Space Requirements
Section 3
Philosophy
ofPlantroom
Design
Fig
3.4 Boiler
Room
Space Planning
Key Space
requirements
Section
5.0
data
heets
Boilers M1.4
Pumps M3.1
N
Caloritiers
M6.3
Pressurisation
unit
M4.2
Circulation
oute
JULY1996
29
Pumps
Caloritiers
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 37/148
Space Requirements
Section 3
Philosophy
of Plantroom
Design
Fig
3.5 Boiler Room
Space Requirements
E
-a
ci)
a
a,
C,
0
0
E
0
0
C,
a-
Note
Space requirements
include or
ancillary
equipment,
see
fig
3.4
I
/
Thai
-___
/
///////
I.'
Range
I
—
500
1000
1500
2000 2500
Maximum
heating
capacity
kW)
30 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 38/148
Space Requirements
Section3
Philosophy
of Plantroom
Design
Fig
3.6 ChillerRoom
Space Planning
Key Space requirements
Section 5.0
data
heets
Watercooledchillers M2.3
77Z
Pumps
M3.1
j
Circulationoute
JULY1996
31
Possible
chilled water
pumps
Possible condenser
water
pumps
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 39/148
Space Requirements
Seclion
3
Philosophy
of
Plantroom
Design
Fig
3.7
Chiller
Room
Space Requirements
E
a,
a
,
C,
0
0
E
0
0
Ca
Note
Space requirements
include or
ancillaryequipment,
see
ig
3.6
32
JULY1996
-
-
/
/:
/
-___
—
Range
I
100
50
0
0
500 1000 1500
2000 2500
Maximum
coolingcapacity kW)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 40/148
Space Requirements
4
System Requirements
4.1
MECHANICAL SERVICES DISTRIBUTIONSYSTEMS
4.1.1
Plantrooms andDistribution Routes
The
designer
hould ensurethatductworkand
pipework
areco-ordinatedintheir
distribution hroughout he
building,
and hat
the central
plant
oom connects
logically
with the
vertical distribution
routes.The
designer
hould:
•
Position
a
plant
room
tobe as near as
possible
to the centre of he zone
whichitwill serve.
•
Consider the branches rom vertical risers
to
serve horizontal distribution
routes with
careas this is
likely
tobe themost
congested
areaof he
service core.
•
Co-ordinate the
mechanical services with other services in the
building
such as
electrical,
electronic
and
communications
distribution
systems;
e.g.
cable
trays
and
conduits,
seesection
4.2.
Sufficient space
must be
provided
forinstallation
and
maintenance
of he
systems
whichdistribute
heating,cooling, ventilation, electricity, etc,
around he
building. Very
often
the
horizontal
and
vertical distributionofservicescan be
more
problematic
than the accommodationofcentral
plant
whichserves those
systems.
In
false
ceiling
voids
or
riser
spaces
here are several
distribution
systems vying
forrestricted
space
whichwill needto be
carefully
co-ordinatedwith eachother
and with
the
structure
to
ensure ease of nstallation
andaccess
for
maintenance,
repair
and
removal of
system components.
Positioning
of he
plant
as closeas
possible
tothe centreof he zone
it
serves
will
reduce
the
amountof
horizontal
distribution
needed.
This
is
ofmajor
mportance
when
considering large
ventilation
ductwork which
needs
o
be
accommodatedin
a
false
ceiling
or withinaraised
floor.
Theconnectionofhorizontal ductwork or
pipework
with
vertical
risers
should
alsobe
carefully
considered.If
heservice core isenclosed
on three
sides
by
lift
shaft and external
walls,
horizontal distribution rom the service corewillbe
extremely
difficultand will
provide
little
space
for installation
access
and
maintenance.
Similarly,
the
structural
stability
(and
fire
integrity)
of he coreis
compromised
if
toomuch of
its
perimeter
area
(above
thefalse
ceiling
orona
single
level)
is
removed
for
service exits.
JULY1996
33
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 41/148
Space Requirements
Section 4
System Requirements
Theareaserved
by
a
single
riser willdictate the size of hehorizontal branch
ductor
pipework.
In
particular,
he
depth
selectedfor abranchair ductwill have
a
great
influence
on the
false
ceiling
or raised
floor
depth,
will affecttheoverall
floortofloor
heights
and hence have
significant
influence
on
building
costs.
The
depth
of hehorizontal element s a function of he numberofvertical
risers,
generally:
maximum vertical risers
=
minimum horizontal element
depth
minimum vertical
risers
=
maximum
horizontal
element
depth
4.1.2Access
The evelofaccess
required
will
depend upon
he
frequency
at
which
that task
needs to be carriedout. The levels
of
access
required
for
frequent,occasional,
or
infrequent
maintenanceare defined
in Section 3.2. Sections 4 and5 refertothe
following
maintenance intervals:
•
frequent
maintenance
clear
and mmediate access.
•
occasionalmaintenance access
through
emoval of
clearly
marked
hatches,panels
or
tiles with
quick
release fasteners
(captive type).
•
infrequent
maintenanceor
emergencyrepair
-
access obtained with the
dismantling
of
part
of he
installation,
demountable
partitions,
etc.
4.1.3
Mechanical
Services
Distribution
-
Data
Sheets
The
ollowing
data-sheets
summarise theaccess and
space
allowances for
pipework,
ductwork and
erminalunits.
Spacerequirements
are
given
for
vertical
and
horizontal
distributionand
the
co-ordination
in
false
ceiling
voids
and raised
floors.Theco-ordinationofservicesinthese
spaces
is
discussed, considering
the
accomodationofmechanical
distribution, lectrical,
electronicand
communication
systems.
Common
problems experienced
indistribution
system
accessare
also
noted.
34
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 42/148
Space Requirements
Section
4
System Requirements
Dl Access to DistributionDucts andShafts
Commentary
Good Practice
References
British Standards
Accessto ducts
largeenough
o be entered
by
maintenance taff should have
the
minimum dimensions shown above. Access should be increased if
breathing
apparatus
is
to
be
worn.
All
access doors should
be
capable
of
being opened
from
within the duct
with
double sided
handles
(cold room
type).
In verticalducts the hazard
from vertical
drops
should be
fully
assessedandmeasures suchas
guard
rails,
fixed
ladders,
etcshould beusedtominimise
risk,
see
Workplace Regulations
R2.
•
Space
allowances for
building
services distribution
systems
-
Detail designstage.
BSRIA. 1992.
•
BS8313. Code
ofPractice or theaccommodationof
building
services
in ducts. BSI. 1989.
JULY1996 35
——
%_
I
—
%%.
I
•1
— I
—
I
—
I
All
dimensions
nmm
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 43/148
Space Requirements
Section
4
System Requirements
D2 Ductwork
INSULATED DUCTS
Plan:
Vertical Riser
w w
x
IfW ess hanor
equal
o1000mm;
X=
200mm S
=
400mm
lfWgreater
han
1000mm;
X=400mm S=600mm
tfW less hanor
equal
o 1000mm;
X
=
100mm S
=
300mm
IfW
greater
han
1000mm;
X
=
300mm S
=
400mm
Commentary
Good Practice
References
British Standards
Accessto ducts
is
governed byspace required
to
install and
insulate the
ductwork;
this is
dependent
on the
clearance from firm
objects,
the
type
of
jointing
method
and
whether the ducts are
to
be insulated
after
nstallation,
see BS
8313
for
detail.
Duct
clearances can bereduced with
care,
providing
correct
jointing,
nsulation
and
maintenance
of
vapour
barrieris
achieved. Consideration
shouldalsobe
given
as to how the ductworkwill
be
tested or
eventually
eplaced.
•
Space
allowancesfor
building
servicesdistribution
systems
-
Detail designstage.BSRIA.
1992.
•
BS8313. CodeofPractice or the
accommodationof
building
services
in
ducts. BSI.
1989.
36
JULY1996
Ix
UNINSULATED DUCTS Plan:VerticalRiser
W
S1
W
Ix
All dimensionsnmm
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 44/148
Space Requirements
Section
4
System Requirements
D3
Pipeworic
VERTICAL RISER Uninsulated
t
50
Je
at
Joints
5
tor
pipes
ess han
50
m
or
equal
ol
50mm
0
than
in
mm
50
tor
pipesgreater
Commentary
Good
Practice
References
British
Standards
Accessto
pipework
is
governed
by
the
space required
o
install
and
nsulate
the
pipework. Although infrequent,
the
removal
of
a
pipework length
from the
riser,
service ductorfalse
ceiling
void should beconsideredand he
appropriate
space
allowed.
Consider the falls of
pipework
for
venting
and
draining; especially
steam or
compressed
airwith
trap
sets.Vertical
space
needs tobe
allowedforair
bottles,
automaticairvents and
drain
points.
•
Space
allowancesfor
building
servicesdistribution
ystems
-
Detail
designstage.
BSRIA.
1992.
•
BS8313. Code ofPractice or the
accommodationof
building
services
inducts.
JULY1996
37
PLAN
VERTICAL RISER Insulated
ELEVATION
Flanges staggered
Flanges staggered
VERTICAL RISER
Mechanically
Grooved EndJoints
Uninsulated
50mm
ELEVATION
PLAN
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 45/148
Space Requirements
Section
4
System Requirements
04
MechanicalServicesRisers
Risers
—ii•'
•÷tteiLn
x
j 69omin
X is
dependent
on he sizeand
type
ot
pipework
n
the riser
-
see
data
sheet
03.
V is
dependent
on
ype
and sizeof
pipework
and
whether
thereare
crossovers
orvalveswhiohcan
ncrease
clearances
considerably
seedata sheet 3.
Simple Pipework
Riser
One
rowof
pipes
oallow he nstallationor
emoval
trom he
ront
ot
iser
space
without
he needto remove
other
pipework except
cross-overs. Avoid double
banking
of
pipes
where the
op
rowwill
obstruct
ccess
to he bottom
ow. Stems
andwheelsof
valves
require
learance
tor
operation,
onsider
especiallyarger
alves
which
may
use
rising
stems.
Clear access is
required
in rontof he
iser,
hinged
door or
frequent
access, demountable
covers or
occasional access.
3
Sided Riser
See above notes
x
Walk-in Riser
Cupboard
(side entry)
Headroom clearance
minimum 1
0mm
All dimensionsn
mm
Good Practice
•
Space
allowances for
building
services
distribution
systems
-
References Detail
design
stage.
BSRIA.1992.
British Standards
•
BS
8313. Code
of
Practice
for he
accommodation
of
building
services
in
ducts.
38 JULY1996
Walk-in Riser
Cupboard
(tront entry)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 46/148
Space Requirements
Section
4
System Requirements
D5 HorizontalServicesDucts
ServiceTrenches
Access rom
above through
continuous overs
or
covers
at
junctions
and
changes
ofdirection.Provision hould be
made
for
drainage
ot he duct n he event ot
eakage;
eg grading
of
the loors
of
he duct
or
service
rench.
Crawlway
Access fromends or
hrough
removable covers. Dimensions
shown areforclearaccess
space
clearof alve
projections, pipe
supports,
etc.
Walkway
Access romendsof
walkway
or
through
emovable covers.
Walkways
tobe
adequately
ventilated.
Dimensions hownare or
clear access
space.
X
Dependent
on
pipework
sizeand
ype
-
seedatasheet
D3
All dimensionsn
mm
Good
Practice
•
Space
allowancesfor
building
servicesdistribution
systems
-
References
Detail
design stage.
BSRIA.1992.
British Standards
•
BS8313. Code
of
practice
for
the
accommodation
of
building
services
in
ducts.
JULY1996 39
1200
k I. •
x
900
8
2100
x 900
X
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 47/148
Space Requirements
Section
4
System Requirements
D5
HorizontalServices
Ducts
(continued)
Ductwork
one
Y
Services
one
2100
Main Services
Corridor
W
Sized
to
accommodate
pipework
in renchor
mechanical
lifting
and
handling
equipment
and heir
turning
radii
whichever
is
the
greater
X
Dependent
on
pipework
orductwork
type
andsize
-
eedatasheetD2orD3
Y
Dependent
on
pipework
or
ductwork
typeand
size
-
seedatasheetD2 or
D3
(All
dimensionsn
mm)
Commentary
Good
Practice
References
British Standards
Main services corridors
require
access tothe serviceswithinandallow clear
passage
for maintenance taffand
any
mechanical
lifting/handling equipment
they might
use
in
thecourse of heirwork.
If
he servicecorridor s the
egress
route for the
removal
of
majorplant,
the
clear
space
should be
large
forthe
plantcomponent
and ts mechanical
handling
device.
If
elevant the
turning
radiiof he
handling
device should
also
beconsidered.
•
Space
allowances
for
building
services
distribution
systems
-
Detail design
tage.
BSRIA.
1992.
•
BS8313. CodeofPractice for theaccommodationof
building
services
inducts.
40 JULY1996
w
—l
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 48/148
Space Requirements
Section
4
System Requirements
D6
Pipework
Access
-
Common Problems
loor__
Motorised
alve
IiiiiE-
Ih+2Smm
h
=
Withdrawal
space
L
=
Overall
length
of
sensor
L+25mm
JULY1996 41
V
Sensor
Fixedobstruction
MotorisedValves/
Sensors/Instrumentation
Removal
ot
actuator, sensor, etc,must not be
obstructed
by
sofft,
wall,
ductwork
or
other
pipework.
Ensuresufficient learance oallow
actuator/sensor
tobewithdrawn
without he disturbance
r removal of
other
services.
Strainers
The
emoval
ot he strainer
basket
mustnot be
mpaired
by
ixed
obstructions orother ervices-seeabovenotes.
Fixedobstruction
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 49/148
Space Requirements
Section 4
System Requirements
D7 DuctworkAccess
-
Common Problems
Fire
Dampers
Accesso ire
damper
must not be obstructed
by
other ervices.
Ensure all tire
dampers
have clear access
tor
nspection
and
esting
seealso data sheet 08.
Fire
damper
access
doorobstructed
bypipework
Fire
damper
access door
Teebarshouldnot obstruct
removal otaccess door
The
ceiling grid
immediately
beneath he erminalunit shouldbe demountable
to
acilitate ccess
tor
emoval
and
eplacement
ot
ilters, ans,
motors
or
he
complete
nit. Access hould be
provided
which
s
at east
the
ull
plandimensions
t
he unit(including ontrolandcommissioning alves)plus 100mmminimum
on
all
sides.
Fire
damper
FCU
or
VAV Terminal Unit
Ceiling
Mounted
Terminal
Units
Ceilinggrid
demountable for
access tor emoval ot
FCU
or
VAV terminal
42
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 50/148
Space Requirements
Section
4
System Requirements
D8 False
Ceilings
andRaised Floors
Structural zone
50mm
deflection+ ol
HVAC
ductor
erminal
unit
50mm
support
+
ol
Sprinkler
one
50
+
150
150
ighting
zone
Headroom
Raised
floor
Commentary
Good
Practice
References
Points to
watch:
1
Ensure clearaccess to all fire
dampers
or
inspection
and
testing.
2
Clearance
of
1.5
times
the
luminairedepth
to
facilitate
removal of
the
fitting.
3 Demountable
ceiling
grid
o
permit
access to the
ceiling
mounted
terminal unit andremoval.
4
Clear
accessto the
terminal
unit
for
removal
of
herecirculation air filter
(FCUs), cleaning
ofcoilandcondensate
tray.
5 Additional
vertical
space
to
beallowed
for
condensate
drains
and
heir
fall
(FCUs).
6
Access
to
raisedfloor shown for
the
situation where
all
floor
tiles
may
not
be
removable.
7
Provision should
be madeforpermanent
access
to all
commissioning
and
control valves.
•
AJGuide to the
Space
for
Services. Architect's
Journal
Reprint.
1986.
JULY1996 43
HorizontalDistribution
VAV Terminal
Unitor
FCU
Mainduct run-outs
Access
Sprinkler
Fire
Damper
I
ccess
600x
600
Floor
box
Cable
ray
Supply
ductfor loor
supply
system
orerminal
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 51/148
Space Requirements
Section 4
System Requirements
D9 Cross-oven
FalseCeilingCross-over
ones
For more
omplex ervicing
arrangements
provision
shouldbe madeor
cross-overs
ot
ductwork
and
pipework
n he alse
ceiling.
Dimension7willbe
governed normally
by
the
depth
of he branch
ducts.
Pipework
Branch
pipework
mustbe
planned
to
provide
sufficient
learance
from other
pipes
n
he
main run o
permit
access
to
langed joints,
etc and
space
to
nsulate.
Commentary
Riser
space
is
normally
at a
premium
and
absolute clearance dimensions
will
depend
on the actual
equipment
installed. The
drawings
indicatecritical areas
wheresufficient
space
must
be
allowed.
Good Practice
References
•
BSRIA.
Space
and
weight
allowancesfor
building
services
plant
inception
stage
design.
1994.
NHS
Estates. Health
Technical Memorandum 2023. Access
and
accommodation
for
engineering
services. 1995.
44
JULY1996
Cross-over
one
Section
Through
False
Ceiling
Uninsulated
pipework
Insulated
pipework
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 52/148
Space Requirements
Section
4
System Requirements
4.2
ELECTRICAL SERVICES DISTRIBUTIONSYSTEMS
4.2.1
Substations,
MainSwitcbrooms and DistributionRoutes
The
designer
hould ensure hat
HV,
LV
(power)
and datalcommunications cable
routes are
co-ordinated
in
their distribution hroughout he
building,
and hat
all
rooms with distribution
equipment
connect
logically
withtheverticaldistribution
routes.The
designer
should:
•
Position
main
switchroomsand
riser
cupboards
to
be
as near
as
possible
to
the
electrical
load
centre of
he
zonewhich
hey
serve.
•
Considerthebranches rom vertical riserstoserve horizontal distribution
routes. Care must be
takenwhererisers are locatednear lift shaftsor fire
stairsas these
may
mpede
horizontal routes.
•
Consider
the
number ofrisers
needed,
data/communications cables should
bein
separate
risersfrom
power
cables or busbarsif
possible.
If
not,
risers
must be
large
enough
to
permit adequate
separation.
•
Consideration should be
given
to
safety/electric
shock notices
addressing
location,
vision
ine and
ease
of
eading.
•
Co-ordinate with the mechanical distribution
ystems.
4.2.2
Access
Access toelectrical services formaintenance are
governedby
hesame
fundamental
equirements
as those formechanical
services;
accessis
argely
influenced
by
frequency
of he maintenance task. The evel ofaccess and
maintenance
requency
is detailed in Section
3.2;
to summarise:
Accessfor
Frequent
Maintenance
All
plant,
switchboards,
control
panels
andother units which
requirefrequent
maintenanceand
operation
shouldhave
permanent
clear and immediate access
with
adequate
pace provision
to
carry
out the
particular
ask. Where boardsare
enclosed,
locked
hinged
doors are
preferred
to
covers fixedwith
screws,
as these
often do not
get
replaced
after maintenancework.
AccessforMaintenanceon an Occasional
Frequency
For maintenance asks which are undertaken onan
occasional
frequency,
access
can be achieved
by
removal of
clearly
markedhatches or
panels/tiles
nfalse
ceilings. Quick-release
fasteners
(captive type)
are
preferred
o
screwedfixings.
Accessfor
EmergencyRepair
and
Replacement
Replacement
of
majorplant
items like
transformers,generators
or main
switchboards
units, althoughgenerally nfrequent,
shouldbeconsidered. The
removal ofdemountable
partitions,doors, ductwork,
etc to
gain
access
may
be
appropriate.
The removal of
masonry
wallsisnotconsidered
reasonable. The
issue ofwhether
permanent
clearaccessis
necessary
for
emergencyrepair
needs
tobe
agreed
with the client.Ifa
particular
tem of
plant
s essential othe
operation
of he
facility
sufficient
standby
capability
should be included inthe
basic
design.
JULY1996
45
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 53/148
Space Requirements
Section
4
System Requirements
4.2.3
Access
for
Replacement
or
Installation
of
Cables
Although
main
power
cables
are
generally eplaced
only
duringmajor
building
refurbishment
or
modification,
data andcommunications cable networks are
frequentlychanged
o suit he latest
developments
inInformation
Technology
(IT).
It s essential
hat
provision
ismadeatthe
designstage
to
allownewdata
and
communication cables
to
be installed
easily.
For
example,
cable
trays
on
gallows
brackets
or tree
hangers
allow
new
cables to be
laid on
more
easily
han
trays
on
trapeze hangers
where the
cable
needs
tobe threadedin.
4.2.4
Electrical
Services
Distribution
-
Data
Sheets
The
ollowing
data-sheetssummarise theaccess and
space
allowancesfor
cabling,
control
panels
and distributionboards.
Space
requirements
are
given
forvertical
and
horizontal distributionand
the
co-ordination
in
false
ceiling
voids
and
raised
floors.Theco-ordinationofservices
in
these
spaces
is discussed
considering
the
accomodation
of
mechanical
distribution, lectrical,
electronic
and
communicationssystems.
Common
problems experienced
indistribution
system
accessarealsonoted.
46
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 54/148
Space Requirements
Section 4
System Requirements
D1O
Control Panelsand DistributionBoards
In
general
for
ergonomic
easons front
panel
controlsshouldbe
located between
1200and 1800mmabove he
finished
floor or
operating
platform
evel.
All dimensionsnmm
Commentary
Good Practice
References
Front
panel
controlsand
ndicating
nstruments
should
be
easy
to
read and
operate
rom
a
normalstanding
position. Infrequently
used
controls
such
as
main
isolators
may
be ocatedoutside
this
range
but should be
readily
accessible.
Internal electrical terminations
or
pneumatic
connections
may
extendoutside
this
range
but should not
be
below 300
mm or
above 2000 mm.
Sufficient
space
must
beallowed for cable
bending
radius
above
and
below
panels.
Cables mustbe
straight
where
hey
enter
glands.
The
published
minimum
bending
adius foracable is he theoretical minimum to
prevent
cable
damage.
In
practice
it is
not
practical
to install
large
cables to
such
a
ight
bend.
A
straight length
ofaround
half
he
bending
adius is
recommended for
installationofcable
clamps.
•
BSRIA.
Space
and
weight
allowancesfor
building
services
plant
-
inception tagedesign.
1994.
•
NHSEstates. HealthTechnical Memorandum 2023. Access and
accommodation
for
engineering
services.1995.
JULY1996
47
Cables
Radius
1000 mm
for
arge
cables
Controlsand
nstruments 1800
Controls
and
nstruments
Wall-mounted
Floor-standing
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 55/148
Space Requirements
Section 4
System Requirements
Dli ElectricalServices
-
VerticalRisers
HorizontalBusbar
section Vertical Busbar
plan
Busbar
Tapoff
unit
C)C)OO
Cabletray
Door
hingeswrongway
Cable
ray prevents
ccess
Door
hingeswrongway
Rising
Busbar
Tapoff
unit
Door
ouling
wall
Typical
Electrical Risers
-
plan
Door hits
adjacent panels
ShallowElectrical
Cupboard
with
Style Hung
Doors
-
plan
Open
doorobstructs
egress
-
Styles
-,
Paneldoors oul
cupboard
door
styles
(styles
mustbe
demounfable)
Commentary
Riser
space
is
normally
at
a
premium
and
absolute
clearance dimensions will
depend
ontheactual
equipment
installed.The
drawings
ndicate critical areas
where
sufficient
space
must
be
allowed.
See also
clearances
given
for
mechanical
risers
in
D4.
Good Practice
•
BSRIA.
Space
and
weight
allowances for
building
services
plant
-
References inception
stage
design.
1994.
•
NHSEstates. HealthTechnical Memorandum 2023. Access and
accomodationfor
engineering
services. 1995.
48
JULY1996
Cables
inaccessible
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 56/148
Space Requirements
5
Component Requirements
Access
and
space requirements
forcentral
plant
are
considered
in
eachsub-
section for individual
plant types
and
he
spatial layout
nformation
is
given
in
the
accompanying
data
sheets.
Eachsub-sectiondeals
exclusively
witha
single
type
of
plant
or
tem
of
equipment
and
plant
oom
space
requirements
will be an
aggregation
of
individual
spatialneeds.
It
does
not contain
any
allowances
for
ancillary
equipment (pumps,
water treatment
plant, etc,
are
dealt with
individually
elsewhere
in
Section
5.1).
Eachsub-section
highlights
he main factors whichaffectaccess
and
space
requirements.
The nfluence
that
the Health
and
Safety Regulations
have
in
the
provision
of
space
to
minimise
riskin
maintenance
and
operation
is
discussed.
A
range
of
space
requirementsagainst
capacity
is
given
for
major
plant
tems.
This is
supplemented
with
diagrams
showing
the
disposition
of
hat
space.
JULY1996 49
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 57/148
Space Requirements
Section 5
Component Requirements
5.1 CENTRAL STATION
PLANT
-
MECHANICAL
5.1.1 LTHW Boilers
The
ypes
of
gas
andoil fired
LTHW
boiler
plant
considered
are:
•
Modular boilers Floor
standing
and
vertically
stacked ow water
contentmodularboilers.
•
Cast-iron sectional
•
Steelboilers Reverse flame
ype.
•
Fuel oil
storage
All
boilers
require
access
space
in
front
and
at
the
sides
of
he
plant
to
facilitate
maintenance.
Modular boilers
can
provide
a
compact
installationwith
minimum
space
requirements
consistent with the accommodationof
flue,
shunt
pumps,
flowand
return
headers,
and
valves.
Space
allowance
must
permit
the safe
withdrawal
of
burner bars or
combustion
compartment. However,
in the
planning
of
plantroom
space
it is
prudent
toconsider the
possible
subsequent eplacement
with
sectional boilers which
may require
a
greater space provision.
Cast iron sectional boilers
requirespace
in
front
of
he boilerfor
flue-way
cleaning,
access to
burner
and
fuel
feeds
plus
clear
access
forboiler
doors
to
open
with burner attached.
Space
is
required
atthe rearof the boilerfor flue
inspection, cleaning,
combustion
testing
and eakchecks.
Steelboilers have similar
requirements
o
cast ironsectional boilers
but
the
ingress/egress
routes
through
the
building
must be
considered
carefully
to
accommodate
the
full
size
and
weight
of
he
boiler.
The total
plant
areas shown n datasheets Ml.1 andM1.2 show
typical
ranges
requiredby
boiler
plant excludingancillaryplant).
This data should
be
used
as
a
preliminary
check
to determine
f
ufficient
space
has been
allowed.
Evenif here
is
compliance
with the
requirements
ndicated,
thisshouldbefollowed
up
to
ensure
that the
space
is
proportioned correctly
to allow
key
tasks to
be
carried
out;
e.g. space
for
cleaning
of
flueways.
Oil
storage
tanks:
•
Distillate fueloils
-
Access
is requiredall around he
tank
for cleaning,
paintingand
inspection. Space
needs obe
provided
at frontfor draw-off
piping,
filter
and valves.Tank
supports
o be
highenough
for
sample
draw-offand
draining.
Walls
andfloorto be
treated with
oil
resistant material to
a sufficient
height
ocontain ankcontents
plus
10%,
inthe eventof ankfailure.
•
Residual fuel oils
-
Accessis
required
all around
he tank as
for distillate
oil
tanks,
including
sampling
and
draining acility.
Space
for the withdrawalof heout-flowheater must
be
provided.
Isolating
valves must be locatedclear
of he
flowheater
to
allow its
removal
without
obstruction.
Walls
and
floorsof
any
bunds or
tankrooms to
be tanked
as
for
distillate
oil
tanks to
retain
contents
plus
10%,
in the
event of
ankfailure.
50 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 58/148
Space Requirements Section 5
Component Requirements
Risk
assessment
-
main
hazardswhich
influence
space provision:
•
Manual
handling
Sufficient
space
must be
provided
toallow
the
removal
and
handling
of
major plant components
such as burners and boilersections.On
larger
boilers
this
will
require he use
of
mechanical
lifting
and
handling
equipment.
•
Falling
from
height
On
large
boilers with
valves,
controlsand nstrumentation ocatedat
levels
above
2m
which
requirefrequent
nspection
or
adjustment,
permanent
safe access should be
provided protected
by guard
rails.Safe
access
is
also
applicable
tooil
storage anks,
e.g.
accessto
man-way
on
storage
anks. Bund
sumps
shouldbe
protected
with
open
plate
covers.
•
Hot surfaces
Sufficient access
space
shouldbe
provided
between
boilers,
other
plant
andfixed obstructions toavoid
contactwith
high temperature
surfaces.
Otherwise
insulate
and
finish
o
BS
5970.
Good
Practice
•
BSRIA.
TN
9/92
Space
and
weight
allowances
for
building
services
plant
-
References
inception
stage
design.
1992.
•
HVCA.
StandardMaintenance
Specification
for Mechanical Services in
Buildings.
VolI
-
Heating
and
pipework systems.
1990.
•
CIBSE.
Commissioning
code series:
B.
Boiler
Plant.
•
NHSEstates. Health
Technical Memorandum 2023. Access
and
accommodationfor
engineering
services.
1995.
Legislation and
• Healthand
Safety Regulations:
Regulations
References
-
Ri, R2, R3, R4, RB,R8,
see Section 2.2.
•
HSE. Guidance Note
PMJ5.
Automatically
controlledsteam and hot
water
boilers.
•
Gas
Safety Regulations
(Installation
and
Use) 1984.
British Standards
•
BS 799.
Oil
burningequipment
Part 5:
Specification
for oil
storage
anks.
•
BS2594.
Specification
for carbon steelwelded horizontal
cylindrical
storage
anks.
•
BS
5410. Code
of
practice
for
oil
firing:
Part2
Installations of
44kW
and
abovefor
space heating,
hot water and steam
supply purposes.
• BS
5970. Code
of
practice
for thermal insulation
(in
the
temperature
range
-100°C to
870°C).
•
BS6644.
Specification
forthe installationof
gas
firedhotwater
boilers of
rated
inputs
between 60kW
and2MW.
•
BS6880. Code
of
practice
for
low
temperature
hot
water
heatingsystems
of
output greater
than45kW.
•
BS8313. Code of
practice
for the accommodationof
building
services
inducts.
JULY1996
51
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 59/148
Space Requirements
Section5
Component Requirements
Ml 1 Modular Boilers
-
Summary
of
pace requirements
for
loor-standing
nd
vertically
stacked modular boilers
Modularboilers
1
FIoor-sg
/7'
1
—
Vertically-stacked
'*
I
Commentary
The
summary
aboveindicates
ypical space
requirements
orLTHWmodular
boilers anddoesnotallow for
ancillary
equipment
(dealt
with
separately
n this
document).
The load
expressed
in the
graphs
is he total installed
heating
capacityof
he
installation.
The
space
requirements
hown inthis
graph
are based
upon
heallowances
detailed in datasheetM1.3.
52 JULY1996
65
-C
a)
-
60
a
a
55
0
0
50
45
40
35
30
25
20
15
10
5
0
500
1000 1500
2000 2500 3000
Boiler
Capacity (kW)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 60/148
Space Requirements
Section
5
Component Requirements
Ml 2
Cast
Iron Sectionaland
Steel
Boilers
-
Summary
of
pace requirements
forLTHW boilers
E
0
0
0
0
-o
a
cc
Boiler
output kW)
Boiler
output kW)
Commentary
The
summary
aboveindicates
ypical space
requirements
orrelated
against
the
total
heat
output
of
heboiler
plant
or LTHW
cast iron
and
steel
boilers anddoes
notallow for
ancillary
equipment
(dealt
with
separately
n this
document).
The
load
expressed
in
the
graphs
isthe
total installed
heating capacity
of the
installation.
The
space
requirements
hown in this
graph
are based
upon
heallowances
detailed
n data
sheet
M1.4.
JULY1996 53
70
65
60
55
E
cI
00
-o
0
-o
=
a
U
E
t
,
ypil
20
_-
Compact
cast-iron
sectional oilers
500 1000 1500 2000 2500 3000
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 61/148
Space Requirements
Section
5
Component Requirements
Ml
3 ModularBoilers
-
Space
Details
Access
Requirement
Floormountedmodular
boilers
Frequent
1.1W
____________________
1.1W
750
3L
2(X) 3L
750
Vertically
tackedmodularboilers
690
W
50
690 L 690
Dimensions
W
Width 01
module
L
Length
ofa
single
module
(All
dimensionsn
mm)
Commentary
Access
space
is
required
forroutine
inspection, cleaning
and
adjustment
of he
boilers.
Space
is
required
atthe front of
he
boiler
fortheremoval ofcombustion
compartment
or
burner bars.
Accessis
required
at the rearof he setforaccess to
flue,
shunt
pumps,
flowand
return
headers,valves,
etc.
54 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 62/148
Space Requirements
Section 5
Component Requirements
Ml 4 Cast Iron Sectional andSteel Boilers
-
Space
Details
Access
Requirement
Frequent
1100mm
L
[+200mm
S W
S W
S W S
ll ll ll
4 4 4
••
2'
Dimensions
W
Width
ot
boiler
L
Length
ofboiler
S
Space
required
or
learance between
adjacent
boilers
=
1.5
n
burner ength
+
door
thickness)
=min
100
(All
dimensions
n
mm)
Commentary
Access
is
required
o
inspect
and
overhaul he burner
assembly,
check boiler
casing
or
damage
or leaks.Clearance must beallowedfortheboiler
door obe
opened
by
90°withouttheremoval of
he
burner. Burner
sizes
can
vary
and
specific
datashould
be
sought
from the
burner
manufacturer.
All
fluewaysrequire cleaning pace
which s needed forward of heboilerface
for
boiler brush
clearance.
Generally
brushes are
single piece
and
run the
full
length
of
he
flue-ways,
this
dimension
maybe
significant. This space
will also
allow for
thewithdrawal ofa ube onasteelboiler.
Space
is
required
for
accessto the flues for
cleaning, inspection,
andcombustion
tests
atthe rear
of
he
boiler.
JULY1996
55
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 63/148
Space Requirements
Section5
Component Requirements
Ml
5 Fuel Oil
Storage
-
Summary
of
space requirements
for
ylindrical
nd
rectangular
oil
storage
tanks
160
E
0)
-
40
Ct
C,
120
100
80
60
Space required
oroil
storage
anks
Oil
storage capacity m3)
Commentary
The
summary
above
indicates
ypical space
requirements
or
oil
storage
and
preheatingequipment
and
does
not
allow for
other
ancillary equipment
(dealt
with
separately
n this
document).
The
volume
expressed
in the
graphs
is the
total
storagecapacity
of the
installation.
56 JULY1996
3 tanks
—
cyl
horizontal
3 tanks
-
rectangular
-
—
—
—
—
— —
2tanks-cyl
—
—
- -
hzontal
I
2 anks
-
rectangular
I I
40
20
10 20 30 40 50 60 70 80 90
100
110
120
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 64/148
Space Requirements
Section 5
Component Requirements
Ml
6 Fuel Oil
Storage
Tanks
-
Space
Details
Access
Requirement
Frequent
Cylindrical
oil
storage
tanks
690
D
1000 D
690
I
—I
690 W
690
Bund
:>r-iZ
m'
SectionA-A
Dimensions
W Widthot
rectangular
tank
L
Length
of
ank
D Diameter
of
cylindrical
ank
Lh
Length
of
outf owheater
(All
dimensions
n
mm)
Commentary
Accessis
required
all
around
thetanks for
inspection,
painting,
insulationand
repairs.Space
is
required
alsofor
draining
water from
the
tanks andremoval
of
the
outflow
heaters.
The
space requirements
of
he
re-filling
tankershould
also be
considered;
access
to
the
point
of
filling, turning
circle
of
he
vehicle,
etc.
JULY1996
57
Access
ladder
6901
L
LflIA
690
L
1100
Rectangular
oil
storage
anks
A
1150
x
-s
Sump
Oil
storage
tank o
B5799:Part .
Rectangular
x
A-
Access
ladder
I-
4501
mm
SectionX-X
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 65/148
Space Requirements
Section
5
Component Requirements
5.1.2
Liquid
Chillers
This section
ives
he
space requirements
for both
vapourcompression
and
absorption
machines.
The
provision
of
clearances
and
access
is similar or
each
type.
Two common
groups
of
vapourcompression
machines
are
considered:
Packaged
air
cooled
type
The
single package
ontains
efrigeration
machineand heat
rejection
fans.
Normally
located outside the
building
to
facilitateheat
rejection hrough
its
air
cooledcondenser.
They
are
generally
available
up
toa
capacity
of
approximately
500kW
of
cooling.
Space requirements
are influenced
significantlyby
the need
to
allow free
movement
of air
through
the
machine
without
short-circuiting'
or
interacting
with other
machines.
However,
the
separation
dimension can
vary
considerably
betweenmanufacturersand lead toa similarvariation
in
space requirements.
Water
cooled
ype
-
Thesemachines useacondenser
water
circuit
as
a
means ofheat
rejection,
which
permits greater
flexibility
inits ocation.
As
a
consequence,
aheat
rejection
deviceisneeded to
dissipate
heat from the
condenser
circuit;
e.g. cooling
ower orairblast
cooler.
Typically,
they
are
usedfor
largercooling
dutiesfrom 50kWto in excessof
1MW
of
cooling.
The
space
forwater cooled machines is more
compact. However,
an
additionalallowance mustbemadeforthe
heat
rejection
device associated
with
this
type
of
machine,
see Section 5.1.9.
Space
and
entry
shall be
provided
for
the
replacement
ofa
compressor,
motor,
evaporator
or
condenser
tube without
disruption
to
other
services,
structure
or
fabric. These
tasks will have
a
significant
influence
on
space provision.
General
space
requirements
or
chillers
are based on the need
for
frequent
nspection,
cleaning
and
adjustment
andannualoverhaul.
Space
for
packaged
air
cooledchillers is
governedby
the same
requirements
as
cited
above,
but in
addition,
sufficient
space
mustbe allowedbetween ndividual
units in a
multiple
machine installation
o
prevent
he interaction
of air
flows.
The
required separation
between
machines,
or
from the
enclosure,
should
be
sought
from
the manufacturer's nstallationdata.
The
plant
areas
shown in
data sheet
M2.
1
show a
ypical
range
needed
by
chiller
plant
excluding
ancillary
plant).
This
datashould
be used as
a
preliminary
check
to
determine
f
ufficient space
has
been
allowed. Even
if here
is
compliance
with
the
requirementsndicated,
thisshouldbefollowed
up
to ensurethat the
space
is
proportioned correctly
to
allow
key
tasks
to
be carried
out;
e.g.
space
for
removal
of
tubes.
Risk assessment
-
mainhazards which
nfluence
space provision:
•
Manual
handling
Theremoval ofa
compressor
ormotor on the
majority
ofchillers will
require
the use of
amechanical
lifting
device. For
larger
screw and
centrifugal
chillers,
which
may
have
life
expectancies
in
excess
of
80,000
hours
run,
permanent
provision
for the
removal of
heavy
plant
components
will
be
necessary, e.g.
lifting
beam.
58
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 66/148
Space Requirements
Section 5
Component Requirements
Sufficient
space
must be
provided
not
only
in the
plant
oom
to lift and
manoeuvre
compressors,
motors, etc,
butalso ontheentire
egress
route
from the
building
whichmust be
capable
of
safely
bearing
he
weight
of
that
component
and ts
lifting
mechanism.
•
Hazardous substances
Some
of
herefrigerantsused
in
vapour
compressionmachines
have the
potential
o
cause suffocation
by
exclusion
of
air,
are
toxic andlor
flammable,
the
extent
varying
with the
refrigerant
ype. Replacements
for
CFCs
and
HCFCs are no
exceptions;e.g.
R134a
has
ow
flammability
and
toxicity
rating,
conversely
ammonia s
more
hazardous
n
both
respects.
Exposure
to
both
is
controlled
under the
COSHH
Regulations.
The size of
the
plant
room
and heventilation
trategy
should
be
considered
in
order
that
safe
exposure
levels
are
not exceeded
in
the event of
a
sudden lossof
refrigerant
rom
the
machine.
Toxicity,asphyxiation
hazards and
flammability
are
safety
issues
which
shouldbe dealt with
in
the
design
of he
system
in their
own
right.
The
influence
on
space
requirements
affects
the
selection
of
volume
of
he
chiller
space
(and
itsventilation
trategy).
If he
refrigerantcharge
s
catastrophically
lost into the
plant
oom
space
thehealthand
well-being
of
someone
in that
space
should
not
be
at
risk;
see BS
4434
and
COSHH
Regulations
for
specific
guidance
on
exposure
limits to
refrigerants.
Measures
o
minimise
this
risk
may
involve
the
provision
of
protective
equipment
and/or
a eak
detection
system.
•
Tripping
For
example,
low level
pipework
connections
to
evaporators
and
condensers,
see
Section 3.1.2
on basic
hazards.
•
Hot/Coldsurfaces
For
example,
hot
discharge
gas
pipework,
see
Section 3.1.2
on
basic
hazards.
Good Practice
•
BSRIA.
Space
and
weight
allowances for
building
services
plant
-
References
inception
stage
design.
1992.
•
HVCA. Standard Maintenance
Specification
forMechanical Services in
Buildings.
Vol II
-
ventilating
and
air
conditioning
systems.
1991.
•
CIBSE.
Commissioning
code series: R.
Refrigerating systems.
•
ASHRAE.
ANSJJASHRAE 15-1989.
Safety
code
for
mechanical
refrigeration.
Legislation
and
•
Health
and
Safety Regulations:
Regulations References
-
Ri,
R2, R3, R4, R6, R7, R8,
see
Section 2.2.
British Standards
•
BS 8313.Code
of
practice
for the
accommodation
of
building
services
in
ducts.
•
BS
4434.
Specification
for
safety
aspects
in the
design,
construction
and
installationof
refrigerating ppliances
and
systems.
•
BS5970. Code
of
Practice for the
thermal insulationof
pipework
and
equipment
(in
the
temperaturerange
-100°C
to
+870°C).
JULY1996
59
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 67/148
Space Requirements
Section
5
Component Requirements
M2.1
Liquid
Chillers
-
Summary
of
space requirements
torair cooled and watercooled chillers
(N
E
-o
C)
a
C)
C
400
600
800
1000
Cooling
output (kW)
Space requirements
or
aircooled chillers
C-')
E
a
C
CC
C)
CC
CC
a
0
500
1000
1500 2000 2500
Total
cooling capacitykW)
Space
requirements
orwater cooled chillers
(for
wo
equal
sized
machines)
Commentary
The
summary
above indicates
ypical space
requirements
orchiller
plant
and
does notallowfor
ancillary
equipment
(dealt
with
separately
n this
document).
The loadexpressed
n the
graphsis the total installed
cooling
capacityof the
installation.
Space requirements
or
aircooled
chillersare
dependent
on
manufacturer's
ecommendations where
hereare
considerable thiferences inthe
clearances
required
for
air
intakes on the sides
of
he machines.
60
JULY1996
0 200
0
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 68/148
Dimensions
S
Separation
between
adjacent
machines
(see
manufacturer s
recommendation). Space
required
or
emoval
ot
evaporator
tubes
ncorporated
in
clearance
to avoid airtlow
nterference
between
adjacent machines,
when S is
greater
than
W.
T
Separation
between
machine nd
enclosure
(see
manutacturer
s
recommendation).
W Widthofchiller
L
Length
ot
the machine
(All
dimensions
n
mm)
Commentary
Access
space
is
required
or
routine
inspection,
cleaning
and
adjustment
of he
plant;
leak detection on
refrigerant
pipework,
access
to
control
panels,pressure
and
emperaturegauges, safety
and
control
valves,
sightglasses,
etc. This will be
ona
frequent
basis and
thus
require permanent
clear access.
Replacement
of
major
plantcomponents
such
as
compressors
or
motors
will
require
heuseofmechanical
liftingequipment,
hus
space
shouldbeallowed
to
accommodate
the
handling
of he
plant
temand he
lifting
device; e.g.
electric
hoist onmobile
gantry.Lifting eyes
should
be
specified
for individual
plant
components
to
facilitate
mechanical
handling.
Space
will be
required
for
replacement
of
evaporator
ubes.
Sufficient
space
must
be
allowed
for the
withdrawal
of he
tube, equivalent
o the
full
length
of the heat
exchanger
plus
clearance.
Separation
between ndividual units is
needed to avoid interactionand short-
circuiting'
of
air
flow.The
air
cooledchillersshown are assumed tobe draw-
through'
discharging through
the
top
of he unit.
JULY1996
61
Space Requirements Section
5
Component Requirements
M2.2
Packaged
AirCooled
Liquid
Chillers
Space
Details
Access
Requirement
Frequent
I
W
S
W
I
1100
I I
L
600
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 69/148
M2.3
Water
Cooled
Liquid
Chillers
-
Space
Details
Dimensions
W Widthofchiller
L
Space
required
or
emoval
of
condenser
or
evaporator
tubes.
(All
dimensions
n
mm)
Commentary
See notes on datasheet
M2.3.
Space
will
be
required
for
replacement
of
evaporator
andcondenser
tubes.
Sufficient
space
must be
allowed
for
thewithdrawal
of
he
tube
equivalent
o
the
frill
length
of he heat
exchanger plus
clearance.
For
large
screwand
centrifugal
machines
(in
excess
of
1MW
coolingcapacity)
a
permanent ifting
beam
may
be
necessary ;
this
will
require
a loortobeam
clearance of heorder of
4.Om.
62 JULY1996
Space Requirements
Section
5
Component Requirements
L L
ccess
Requirement 600
Frequent
690
W
1100
W
1100
600
Control
panel
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 70/148
Space Requirements
Section5
Component Requirements
M2.4 Hermetic
Absorption
Chillers
-
Summary
of
Space Requirements
and
Space
Details
c'J
a
0
0
0
Ct
Ct
0
L)
Space
Details
Dimensions L
Length
ofchiller W Widthofchiller
Control
panel
door
Commentary
Space
requirements
or
absorption
chillers
are
similar to
those for
vapour
compression
machines. Sufficient clearance
must be
provided
on
all
sides of he
machine
for
access
for
maintenance.
Particular attention
should be
paid
to the
control
panel
doorclearance and
space
for the removal and
replacement
of heat
exchanger
tubes.
Space
requirements hown
n the
graph
are
for the
chillers
only. Ancillary equipment
suchassteamorhot waterboilers
servicing
the
machines'
generator,
or heat
rejection
devicesare not shownorallowed for in the
space provision.
JULY1996
63
Ion
160-
140-
120
—
Inn
-
0
—
60
—
40
—
20
I I I
I
I I I I
I
I
1000
Space
2000
requirements
3000
br
hermetic
4000 5000 6000 7000
absorption
chillers
8000 9000 10000 11000
Total
cooling capacity (kW)
L
Ill
00]
ontrol
anel
door
1100
W
1100
W
1100
1
Cu
1
.
'I
Ilir]
L
L
'1
1100
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 71/148
Space Requirements
Section
5
Component Requirements
5.1.3
Pumps
Three
categories
are
considered:
Circulating Pumps
-
Serving
'closed-circuit'
pipework systems; e.g.
heating,
chilled
water,
condenser
water
(although
in
some cases
may
be
open circuit). Pumps
with
small/medium
duties (less han
4kW
motor
size)
can be fitted
in-line
(pipeline
mounted)
toreduce
space requirements. Largerpumps
flow
rates
in
excess of15
Ifs)
are
generally
floormounted.
Space
provision
may
be
influenced
by
other factors other
than
accessfor
maintenance,
e.g.
connection
o
header
pipework.
Space
requirements
of
pumps
are dictated
by
the need for
frequent
maintenance
of
bearings
and heir
seals,
checking
and
cleaning
of
strainers, adjustment
ofbelt
drives,
etc.
Motorscan
be
fitted
to
pump
volutes
in
horizontal or
vertical
planes.
Motors which
are
horizontally
mounted
usually require
more floor
space
but
allow
ready
access
to seals
and
bearings.
•
Booster sets:
Fire
Protection
Serving
sprinkler,
hosereel and wet riser
systems.
Two common
types
of
fireservice booster set:
i)
Duplicate
electric
pumps
: Contains
two
electric-driven
pumps
+
possible
ockey
pump
and
control
panel.
ii)
Diesel
back
up
set:
Containsone
electric driven
pump
and
ockey
with
diesel
driven
support
pump
and
control
panel.
General
space requirements
are based ontheneed for
frequent
inspections
withtest runs and he
possibility
of
occasional
replacement
of
motors.
•
Booster
sets:
Drinking
and
Domestic
HotWater
-
Serving
cold
potable
water
systems
and other
domestic
uses within
a
building.
Two
common
ypes
of
package
booster
set
are:
i)
Single
duty
duplicate
pump
set
comprising
twoelectric
pumps
with
pressure
vessel and
control
panel.
ii)
Multiple
variable
duty
set
with several
pumps,
pressure
vessel and
control
panel.
General
space requirements
are based on
the
need for
frequent
inspections
and
he
possibility
of
occasional
replacement
of
pump
motors.
Risk assessment
main
hazards which
nfluence
the
provision
of
space:
•
Manual
handling
Sufficient
space
must
be
provided
to
lift and
handle
he
removal
of
motors
and
pump
bodies.
Space
must
not
only
be
provided
inthe
vicinity
of he
pump
but
also
on the entire
egress
route
from
the
building
which
must be
capable
of
safely bearing
he
weight
of hat
component
and ts
lifting
mechanism.
The
removal
of
a
pump
motor on
the
majority
of
sprinkler
andwetriser
sets
will
require
the useofa
mechanical
lifting
device.
Also,
the
removal
of
the diesel
engine
where
appropriate,
will
require
a
mobile
engine
hoist.
64
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 72/148
Space Requirements
Section
5
Component Requirements
Tripping
Pipework
discharge
onnections
re
generally
taken
to
high
level. However
in the
case
of
boostersets a smallamountof low level
pipework may
be
connected to an
adjacent
suction ank. See Section 3.1.2 onbasic hazards.
•
HotJCold urfaces
SeeSection 3.1on basichazards.
Good
Practice
•
BSRIATN 9/92.
Space
nd
weight
allowances for
building
services
plant
References
inception
stage
design.
1992.
•
HVCA. Standard
Maintenance
Specification
forMechanical Servicesin
Buildings.
Vol
1
-
Heating
and
pipework systems.
1990.
Vol II
-
Ventilating
and air
conditioning systems.
1991.
Legislation
and •
Health
and
Safety Regulations:
Regulations
References
-
Ri, R2, R3, R4, R6,
see Section 2.2.
British Standards
•
BS 8313.Code
of
practice
for the accommodationof
building
services
inducts.
•
BS6880. Low
temperature
hotwater
heating
systems
of
output greater
than
45kW.
Part
1: Fundamental
design
considerations. 1988.
Part
2:
Selection
of
equipment.
1987.
Part
3:
Installationmaintenanceand
commissioning.
1988.
JULY1996
65
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 73/148
Space Requirements
Section
5
Component Requirements
M3.1
CirculatingPumps
-
Space
Details
600
Preferable
max
mounting
height
1200
Dimensions
W
Width ot
pump
V
The clearance
on
the
pump
side ot he set
may
be
ntluenced
by
other
tactors
esides
access,
e.g.
connections
o headers.
S
Will be
nfluenced
by
aclorsother han
access,
e.g.
suction
pipework
connections.
(All
dimensions
n
mm)
Commentary
Access
space
is
required
for
frequent
inspection,
cleaning
and
adjustment
of
he
pump
and
motor.
In-line
pumps
mounted nvertical
pipework
shouldnotbefitted
higher
than
1200mm from
the
finished floor level
to
permit
safe
handling.
Atthis
height
a
maintenance
engineer
should not
manually
ift and
ower loads
greater
than
20kg;
ifa
twisting
action s
nvolved
in
this
process
the
maximum load
will be
lower,
see Manual
Handling Operations Regulations.
Loads
greater
than
this
should
behandledwith
mobile mechanical
lifting
devices
or with
ceiling
mounted
liftingeyes
or
lifting
beams.
If n-line
pumps
are
located above
preferredmountingheight,
space
must
be
provided
for the
erection
andsafeuseof
staging
for maintenance
purposes.
Where
pump
component
loads
require
mechanical
handing,
sufficient
space
must
be
allowed for
the
lifting
device
to
allow
it
to
bebrought adjacent
o the
pumpto
permit
safe
handling
of he loadand
hen
manoeuvred
to the
location
where he
repair/overhaul
will be carriedout.
Access
Requirement
Frequent
In-line
pumps
mounted in vertical
pipework
600
Elevation
lan
690
1+
50
Finished
loor
level
Close
coupledpumps
Elevation
Plan
690
150
W
150
690
S
L
1.SxL
700mm
S
A
single
common
ump
base
may
be
used
tor
everalsmall
pumps, working
clearances
still
apply
66 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 74/148
Space Requirements
Section
5
Component Requirements
M3.2 Booster
Sets:
Fire
Protection,
Drinking
and Domestic
Water
-
Space
Details
Suction
ank
Boosterset: Fire
Protection
x
W
1100
600
L
600
Booster et:
Drinking
Water
and Domestic Water
Dimensions
L
Length
of
package
unit
W Width of
package
unit
(All
dimensions
n
mm)
X
Typically
theseunits will be
placed
against plant
roomwall.Refer o
mant. recommendations
Commentary
See notes ondatasheet M31.
Space
requirements
or
diesel
enginestandbypumps
will be
considerably
greater.
JULY1996 67
Access
Requirement
Frequent
600 L 690 500 600
x
W
1100
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 75/148
Space Requirements
Section5
Component Requirements
5.1.4 Pressurisation Units
Membrane
pressure
vessels
require
access tothe vessel o
adjust
the
pressure
as
necessary,
internal
access to
the tank and
space
toservice the level controller.
Precharged
vessels with
spill
tanks
require
accesstothe
pressure
vessel or
topping-up,
to the
pumps
for
inspection/lubrication,
internal
access
to the
spill
tank and
space
to
service the level controller.
Both
systems require
all-roundaccess for
general
attendanceandremoval of
equipment
items.
Riskassessment
-
main
hazardswhich influence the
provision
of
space:
•
Manual
handling
Space provision
mustbesufficientforthe installationand
possible
replacement
of
he entire
package.
On
larger
units
allowance should
be
made for the mechanical
lifting
and
handling
of
majorcomponents
such as
pressure
vessels
and
pumps.
•
Tripping
Therewill be low level
pipework
associated with
the
pressurisation
unit
that
may
constitutea
ripping
hazard.Low level
pipework
should not
intrude into
access
space
-
see Section3.2.
•
Pressurised
Gas
Sufficientclear
space
shouldbe
provided
for the safe
handling
and
storage
of
pressurisedgas
bottles.
Good Practice
•
BSRIA.
Space
and
weight
allowancesfor
building
services
plant
-
References
inception
stage
design.
1992.
•
HVCA.
Standard Maintenance
Specification
forMechanical Services
in
Buildings.
VolI
-
Heating
and
Pipework Systems.
1990.
Legislation
and
•
Health
and
SafetyRegulations:
Regulations References
-
Ri,
R2, R3, R4,
R6
&
R7,
see
Section 2.2.
•
The Pressure
Systems
and
Transportable
GasContainers
Regulations.
1989.
British Standards
•
BS 8313.Code
of
practice
for
he
accommodationof
building
services
in ducts.
•
BS6880. Low
temperature
hotwater
heatingsystems
of
output
greater
than
45kW.
Part
1:
Fundamental
design
considerations.
1988.
Part
2: Selectionof
equipment.
1987.
Part
3: Installation
maintenance and
commissioning.
1988.
•
BS7074.Part2:
Application,
selection and nstallationof
expansion
vessels and
ancillary
equipment
for sealedwater
systems.
CodeofPractice
for
low
and
medium
temperature
hot
water
heating systems.
BSI.
1989.
68
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 76/148
Space Requirements
Section
5
Component
Requirements
M4.1
PressurisationUnits
-
Summary
of
Space
Requirements
22
E
-o
20
a)
18
0.
'I,
C
Co
C-
Commentary
Thesummary
above indicates
the
typical space
requirements or
membrane
pressure
vessels and
precharged
vessels
with
spill
tank.
Space requirements
are
expressed
inrelationto thewater contentof he
system
and
emperature
change
which occurs
under
normal
operational
conditions.
JULY1996
69
V
Jca1ran9>
T'
100
200
14
12
10
8
6
4
2
0
2000
4000
6000
8000
10,000
12,000
U,
a)
14,000
a)
C
0
0
I:
500 600
700
800 900
Expansion
volume
(litres)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 77/148
Elevation
690
L
690
Plan
Pressurisation
unit
-
hydronicsystems
Pre-charged
vesselswith
spill
anks
1.lxH
over
H
690
w
1100
Commentary
Accessand
space requirements
are
governedby
the installation and
possible
subsequent eplacement
of he entire
package.
On
large
unitsconsideration
should
however
be
given
to
access
to
and
handling
of
major
components
suchas
pumps,
vesselsandbottled
nitrogengas.
Thevessels on
large pressurisation
unitswould
require
mechanical
lifting
devices for safe
handling
which
necessitates
appropriate
pace provision
andclearheadroom.
70 JULY1996
Space Requirements
Section
5
Component Requirements
M&2
Pressurisation Units
-
Space
Details
Access
Requirement
Frequent
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 78/148
Space Requirements
Section 5
Component
Requirements
5.1.5 Water
Treatment and Water
Softening
Equipment
will
consist
of:
Water
softening
plant.
Chemical
container and
dosing pump.
Softened
water
storage.
Salt
storage.
The
systems
considered are:
•
Base
exchange
water
softening
sets.
•
Chemical
treatment
froma
container
and
dosingpump
nto
piping
systems
via an
njection fitting.
Bothof hese
systems
require
space
for front
and
side
access
to
equipment
items
andfor
handling
saltcontainers
currentlyplastic
sacks)
to
replenish
he
brine
tank
of
hesoftener.
Space
to
remove,
manoeuvre and
replace
the chemical
drums
forthe
water treatment
systems
s
also
required.
Both
systems
require
front and side accessfor
general
attendanceandremoval
of
equipment
items.A
majorspace requirement
elated to water treatmentis he
storage
of
salt/
chemicals.The trafficroute betweenstore and
plant
needs
consideration also.
Dosing pots
are used for the manual
input
ofwater treatment chemicals tolow
temperature,
ow
pressure
closed
systems.
Although
it isa
simple
deviceitwill
require
direct
and
clear
access for valve
operation
and
dispensing
hemicals
into
the
container.
The water treatment
plant
discussed above
represents
common
but
basic
systems.
More
sophisticated
forms ofwater
treatment,
e.g.
reverse
osmosis,
will
have
greater
access
requirements;
eference
should
be
made to manufacturers
recommendations.
Risk
assessment
-
mainhazards
which influence
the
provision
of
space:
•
Manual
handling
The
provision
of
space
willbe
governed
by
the
handling
of
vessels which
may
necessitate the useofmechanical
lifting
and
handling
devices
on
larger plant.
Also consideration should
be
given
to
facilitating
he
lifting,
carrying
and
decanting
of
salt and
chemical containers.
•
Spillage
of
chemicals
Space
needs
o
be
sufficient
for the
safe
handling
of
salts
and
chemical
drums ominimise the riskof
spillage.
Provisions
need to
be in
place
in
the event of
spillage
ofwater treatment
chemicals;e.g.
eye wash,
hand
washing,
etc.
Good Practice
•
HVCA.
Standard Maintenance
Specification
forMechanical Services in
References
Buildings.
Vol IV
-
Ancillaries,plumbing
and
sewerage.
1992.
Legislation
and
•
Health
and
Safety
Regulations:
Regulations
References
-
Ri,R2, R3, R4, R6,
see
Section
2.2.
•
Controlof
SubstancesHazardous oHealth
Regulations.
1988.
British Standards
•
BS 8313.Code
of
practice
for
the
accommodationof
building
services
in ducts.
JULY1996
71
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 79/148
Space Requirements
Section 5
Component Requirements
M5.1 WaterTreatmentand Water
Softening Space
Details
14
a,
g
12
0
(1)
0
-o
a,
=
a
,
Ca
a,
C
10
8
Access
Requirement
Frequent
6
4
2
0
20
40
E
C,
Ca
0
0)
100
-o
a,
g
120
Ca
a,
<140
60
80
w
1100
Commentary
The
summary above
indicates he
typical space
requirements orwater
treatment.
All-round clearance will be
required
o
equipment
and
anks for
general
attendance
and
removal of
components
when
necessary,
and
for
replenishment
f
brine
regenerator.
Softened water
storage
ank
will
require
nternal
access, space
to
servicewater
level
controller,
and
a
water-proofed
"safe"
in
case of
ank
failure where anks are
installedabove
accommodationareas.
Drain-out
provisions
will also
be
necessary.
Space should
be
allocated
for
the
storageof
salt
-
3
months
supply
for
a
hard
water
supply
for
a
system
witha
high throughputmay require
of heorder of
10m2
of
storage
area.
72 JULY1996
600
L
600
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 80/148
Space Requirements Section5
Component Requirements
5.1.6 Water
Storage
This section onsiders
he
storage
ofhot and coldwater fora
variety
of
applications e.g.
domestic coldwater
supply,
sprinklers,
domestichot water
supply
etc.
Cold
waterstorage
Storage
cisterns
covered
by
thissectionare
assumed
o
be
sectional GRP
or
galvanised
mildsteel.General
space
requirements
are
based on the need
for
regular
inspections
and occasional maintenance ofvalves. On
less
frequent
occasionsinternal
cleaning
of he tank
may
be
required.
The
type
of
sectional tankwill affectthe
space
required
for erection.
Internally
flanged
as
opposed
to
externally
langed
sectionswill
allow thesideof he tankto
be
placed against
awall. With his
arrangementspace
must stillbeallowed for
pipework
and
valves ateither end of the tank.
This seemsamore efficientuse of
space
but the
opportunity
of
nspection
and
cleaning
of
he tank
face
against
the
wall
is
ost.
HWS calorifiers
(with
storage)
-
General
space requirements
are
based ontheneed for
regular
inspection
and
periodic
internal
cleaning
of he calorifiers.
RiskAssessment
mainhazards:
•
Manual
handling
Innormal
use there shouldbe
no
majorhandlingproblems
with
sectional
coldwater tanks. In the rare eventofa tank
panel
failure the
panels
can
be manhandled
by
2
people.
Most
removable
components
on
calorifiers
are
unlikely
to be oo
heavy
for
handlingby
2
people.
Removalof heheat
exchangers
in
large
calorifiers
may require lifting
equipment.
Replacement
of
arge
calorifiers will
requireheavy liftingequipment
such
asabeam and
pulley
block.
•
Tripping
Tankconnectionsat ow level will
nevitably
beonaccess routesand
step
over
ramps
should be
provided.
Overflow
and
floatvalveconnections
at
medium or
high
level should be
routeddown
the
side of the
tank to avoid
crossing
access routes.
Connections will
be
made
to
calorifiers
at
various levelsnormally from
high
level
pipework.
Careful
planning
should avoid connections
crossing
access
routes with
vertical
pipework
from
connections
kept
as
closeas
possible
to thecalorifier.
•
Tankaccess
Fixedexternalandcorrosion-resistantinternal
ladders shouldbe
provided
to maintain hefloatvalve
and
gain
access to the insideof he tank.
•
Hazardous substances
To reduce
the risk
of
egionellosis,stagnation
ofstored water
should be
preventedby
avoiding
oversizing
and with
good
water
distribution
n
the
vessel;
input
one end
output
theother.In
general,
the
cold
water
storage
tank
should
be
sized
for no
more thanthe
daily
wateruse.
JULY1996
73
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 81/148
Space Requirements
Section 5
Component
Requirements
GoodPractice
•
BSRIA
TN 9/92.
Space
nd
weight
allowancesfor
building
services
plant
References
inception
stage
design.
1992.
•
HVCA. StandardMaintenance
Specification
forMechanical Servicesin
Buildings.
VolW
-
Ancillaries,
Plumbing
and
Sewerage.
1992.
•
NHSEstates. Health
Technical Memorandum 2023. Access and
accommodation
for
engineering services.
1995.
•
CIBSE. Technical Memorandum. TM13:
Minimising
the risk
of
legionnaires
disease.
1991.
•
HSE.
Health
and
Safety
booklet HS(G)70.
he
control
of
egionellosis
(including legionnaires
disease.
1992.
Legislation
and
•
Healthand
Safety Regulations:
Regulations
References
-
Ri,R2, R3, R4, R6,
seeSection
2.2.
British Standards
•
BS 8313.Codeof
practice
for
the
accommodation
of
building
services
in
ducts.
• BS
6700. Design,
installation, esting
and
maintenance
of
services
supplying
water for domesticuse within
buildings
and heir
curtilages.
74 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 82/148
Space Requirements
Section5
Component Requirements
M6.1 Water
Storage
-
Summary
of
pace requirements
for
old water
storage
tanksand HWS
storage
calorifiers
160
—
E
-c
ci)
a
140
—
g
Cci
ci)
120
—
-
—
-
Typical
range
-
0
10
20
30
Commentary
The
summary
above indicates the
typical
space requirements
orsectional cold
water
storage
anks
and hot
watercalorifiers
and
does
not
nclude
anyancillary
equipment.
Afreeboard
of
500mm
has been
assumed
for each ank.
ForHWS
Storage
calorifiers
the
lower
boundary
limit
representsspace
for
vertical
vessels,
the
upperboundary
limit for
horizontal vessels.
JULY 1996
75
100
80
60
40
20
0
-
Typical
range
-
20
Cold Water
Storage
(assumes
500mm ree
board)
40 60
100
-o
a)
-
80
a)
Co
<
60
40
20
0
80 100
Storage Capacity (ni3)
40
50
Total
Storage Capacity (m3)
Hot Water
Storage
Calorifiers
Two
equally
sized Calorifiers
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 83/148
Space Requirements
Section
5
Component Requirements
M6.2 Cold Water
Storage
-
Space
Details
Where external base
tianges
used
Dimensions
L
Length
of
ank
W Widthof
ank
H
Height
of ank
S
Space
to
Accomodate
intlow/outtlow
pipework
typically
1500mm
(All
dimensions
n
mm)
Commentary Space
requirementshave been basedupon
he use
of
a
sectional GRP
tank
or
galvanized
mild steel.Afreeboard of500mmhas been assumed oreach tank. An
addition of500mm shouldbe madetoclearance
heights
where externalbase
flanges
are
used
76 JULY1996
Access
Requirement
Occasional
S
L S
N N N
NMN
500
W
500
350
(790
orman
access)
H
500
N N N
N
N
N
[I [1
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 84/148
Space Requirements
Section 5
Component Requirements
M6.3 Hot Water
Storage
-
Space
Details
Access
Requirement
Occasional
Space
forTube Bundle Removal
600
x
x
1100 D 1100
Elevation
Dimensions
L+600
1100
Horizontal Calorifiers
I I
I
D
Diameter
ofvertical
calorifier
X
Length
of ube
bundle
H Dimensiono acilitate
cleaning
of he
loorof he vesselofscaleand
other
debris
(approx 500)
(All
dimensions
n
mm)
Commentary Spacerequirements
are
governed by
the need to removeheater tube bundlesand
to
gain
access
to the
calorifier
manhole
for internal
inspection.
JULY1996
77
___________
D
1.2D
Isolating
alvesclearof
withdrawal
space
for ube
bundle
D 1100 D 1100
600
L
Space
for ubebundle emoval
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 85/148
Space Requirements
Section
5
Component Requirements
5.1.1
Air
Handling
Units
Generally
air
handling
units
(AHUs)
have
the
largest space requirements
of
he
mechanical services
plant
tems.The
space requirements
for access
are
also
large.
Where
space
allowances
are
reduced
inorder to
improve
the net to
gross
floorarea
ratio,
the clientshouldbe aware of
he
implications
on maintenance
and
repair.
Two
categories
of
air
handling
units are
considered:
•
Mechanical Ventilation.
•
Air
Conditioning.
Specialist
containment
systems
such
as
microbiological afety
cabinets,
systems
handling
nuclear or
chemical
warfare
agents
and
fume
cupboards
areexcluded.
Specialist
advice should
be
sought
on these
systems.
The
space
requirements
ndicated
allow for construction and
assembly
as well
as
access
for maintenance
.g.
the
removal
of
coils,
filters
and
fans.
The useofdemountable
partitions may
be
specified;
if
a coilneeds
replacement
the
partition
willberemoved tofacilitatecoil withdrawal. The removal ofa
masonry
wall
isdeemed
unacceptable
asa
means
of
providing
access
to
plant.
Demountable
partitions
willbe
accepted
if
hey
canberemoved in 3 hours and
re-erected in4
hours,
butworkshallnot
nterrupt
the normal
operation
of he
establishment.
This
approach
will increase the
repair
time
but
will save on
space.
The
graphs
which summarise air
handling
pace
requirements
M7.1)
have been
separated
into
space
for mechanical ventilationand
space
forair
conditioning
plant.
Mechanical ventilation
plant
will
typically
have fewer
components
thanair
conditioning
plant
and
herefore
require ess
space.
Both
graphs
give
a
generalrange
defined
by
an
upper
and ower
boundary.
The
upper
boundary
will
be
typically
or
single
decked
plant
and he lower
boundary
for
double decked
plant.Although
double decked
plant
will
require
ess
plant
room
area,
the floorto
ceilingheight
will
naturally
need
to
be
greater.
Floor-by-floor
air
handling
plant
is
ndividually compact
intermsof
space
requirements,
however thecollective
space
requirement
will
normally
be in
excessof hat
provided
froma
single
central
plant.
Risk assessment mainhazards which nfluence the
provision
of
space:
• Manual
handling
Plant
space
must be sufficientfor the removal of
arge bulky
tems suchas
heating/cooling
coils.
The
coil
length
will dictate
he
withdrawal
pace
allocated. Coils
with
large
cross-sections
may
be
split
into
modules
to
facilitate
easy
removal and
handling.
Where
heavy plant
items are
involved
e.g. large
fans,
a mechanical hoist
will be
required,
or
provision
of
a
permanent ifting
beam.
Sufficient
space
must be
provided
not
only
in the
vicinity
of he item
of
plant
for the
component
andits
ifting
and
carryingequipment,
but
also
along
the
entire
egress
route.
78 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 86/148
Space Requirements
Section 5
Component Requirements
•
Falls rom
height
Some
larger
air
handlingplant may
be
'double decked'
which
may require
maintenance
ccess above2m
height.
In this
case, frequent
maintenance
checks and
adjustments
ontheA}{Umust be facilitated
by permanent
catwalks
protected
with
guard-rails.
For the
removal
of
coils
orfans,whichmaybe
expected
to
be
infrequent,
temporaryhigh
level access
may
be
provided
with
appropriate caffolding.
Space
is still
required
fortheerection of hemaintenance
platform
and
safe
working
and
handling
of
equipment
at
high
level.
•
Tripping
For
example
low level
pipework serving
coils,
condensate
drains,etc;
see
Section 3.1.2 onbasichazards.
Good Practice
•
BSRIA TN9/92.
Space
and
weight
allowances for
building
services
plant
-
References
inception stage desigu.
1992.
•
I{VCA.StandardMaintenance
Specification
for Mechanical Services in
Buildings.
Vol
II
-
ventilating
and air
conditioning systems.
1991.
•
NHSEstates. Health
Technical Memorandum 2023. Access
and
accommodationfor
engineering
services. 1995.
Legislation
and
•
Health
and
Safety Regulations:
Regulations
References
-
Ri, R2, R3, R4, R5, R8,
see Section 2.2.
•
Building Regulations: Approved
DocumentK
-
Stairways,
ramps
and
guards.
British Standards
•
BS 8313.Code
of
practice
fortheaccommodationof
building
services
in ducts.
• BS
6180. Code
of
Practice or
protective
barriers
in
and about
buildings.
•
BS
5395:Part3.
Stairs,
ladders
and
walkways.
Codeof
Practice or the
design
of
ndustrial
type stairs, permanent
adders and
walkways.
JULY1996
79
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 87/148
Space Requirements
Section 5
Component Requirements
M7.1 Air
Handling
Units
-
Summary
of
Space Requirements
200
E
180
1
60
.
40
120
100
80
60
40
20
0
TcaImnge
—---
Space
requirements
orAir
Conditioning
Commentary
The
summary
above
indicates
ypical space requirements
or
air
handling
units
for
mechanical
ventilation
andair
conditioning
AHUs.
It
represents
the
space
for
the
supply
and extract
AHUanddoes
not
allow for
ancillaryequipment dealt
with
separately
n this
document).
80
JULY1996
Space requirements
orMechanical
Ventilation
Air
volume
m3/s)
240
E
220
200
180
C
Co
140
120
100
80
60
40
20
0
0 4
8
12 16
20 24
28
Air olume
m3/s)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 88/148
Space
Requirements
Section
5
Component Requirements
ir00
Filterbank removal
(All dimensions
n
mm)
ii:
w
W/2 600
Sectionalisedcoils
to
reduce
space required
and
improve handling
ot
argecoils)
Commentary Space
requirement
or
air
handling
plant
is
governedby
the
removal
of
major
plantcomponents
such
as
coils,
fans
and filter
pods.
Isolating
valves must be locatedclearof he coil withdrawal
space
to
prevent
obstruction.
Large
coilscan be sectionalised to
reduce
the
space
needed for
coil
withdrawal. Accessto
the
both
sides
of
hecoil section
will
be
necessary
to
facilitate
emoval
and
handling
of
hecoil.
Units
which
operate
under
high humidity
must have
sufficient
space
for
regular
and
adequate
cleaning
anddisinfectionofcoilsand
drip
rays,
etc. Also corrosion
can be
a
significant problem
on structure
and as a
consequence
thereis
aneed to
gain
access
to all
sides of he
unit,
i.e. not locatedhard
against
thewall.
JULY1996
81
M7.2 Air
Handling
Units
-
General Points
Air
Handling
Plant
77(ithdrawal
—
space
Space
orcoil emoval
andclearance
Pipework
broken
here tor
coil
removal
Avoid his
Isolating
valves
obstructcoil
removal
Section
onnectors
W/2
1
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 89/148
Space Requirements
Section 5
Component Requirements
M7.3 Air
Handling
Units
-
Space
Details
Access
Requirement
Frequent
KEY
seedatasheetM7.3
Dimensions W
Width of
AHU
L
Length
ofAHIJ
(This
will
be
significantly
onger
for ir
conditioning ystems
which
normally
have
a
greater
number
of
components
han
mechanical
ventilation
HUs)
A
Attenuator
length
For
cooling
coils
h
Height
allowance bove
inished
floor
level
to
accomodate
condensate
trap.Trap
mustbe
deep enough
to esist
suction
pressure
of an and
provide
sufficient all to
discharge
to
adjacent
drain.
(All
dimensionsn
mm)
Commentary
Accessis
required
o
inspect
theconthtion of
ilters,
dampers,
fans,
heirdrives
and
guards
on a
frequent
basis
;
these tasks
requirepermanent
safeaccess.
The
changing
offilterswill
normally
be
ata moderate
frequency.
If he AHU s
double decked this
may require
maintenance
platforms
protected by
a
safety
rail.
Cleaning
of
coils,
fan motor
checks
and
adjustmentswill
take
place
on
an
occasional
basis,
access
provision
for adouble decked
system
may
be
temporary.
If
staging
susedit should be
designed
forthesafe
handling
of
plant
n termsof
space
and
be
capable
of
safelybearing
he
loads
of
plant components.
82 JULY1996
Withdrawal
space
tor ilter
pods
Withdrawal
space
forcoil
\".
it:
L
W
H
Plan
**ThiSdimension
may
be educed to200mm fAHU
installation
oes
not
require op
access
W+600
71w
600*
*
Thiscan be
reduced
if
provision
s
made
to avoid dirt
and
debris
buildingup
behind he AHU
A
C
LU
H_
Trap
'l
Elevation
Gulley
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 90/148
Space Requirements
Section 5
Component Requirements
M7.4
Floor-by-floor
Air
Handling
Units
-
Space
Details
Access
Requirement
Freshair shaft
Frequent
___________________________________
W1+600
600
690 L
Exhaustairshaft
Dimensions
Wi Widthof
supply
sectionof
AHIJ
W2
Widthofexhaust section
L
Length
ofAHU
(All
dimensionsn
mm)
Commentary
See notes
on
M7.3andM7.4
regarding
maintenance
asks
on
coils, filters, fans,
etc.
Floor
by
floor air
handing
plants
will
give
greater
flexibility
formulti-tenanted
buildings
but
will
generally require
more
space
for
plant
(in
otal)
than
a
conventionalcentral station
arrangement.
n smaller
buildings
low
profile
air
handling
plant up
to 1
m3Is)
can
be
locatedin
the
false
ceiling
void much
the
sameas fan
coils;
the
provision
formaintenancewillbe
similar,
see section 4.0.
JULY1996 83
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 91/148
Space Requirements
Section
5
Component Requirements
5.1.8
Fans
Two
fan
types
areconsidered:
•
Centrifugal
ans
(Single inlet/single
width
and
double inlet/double
width)
•
Axial fans
Fansdiscussed here are individual
plant
temswhich are used
in
ventilation
systems
which
may
be
simple supply
or
extract
arrangements
as
distinct
rom
the
packaged
air
handlingplant
discussed
in5.1.7.
Space
should
be
provided
for the
frequent
checks on
drives,
cleaning
and
lubrication
of
bearings,
etc.
Space
is also
required
for
the
possible
removal
of
majorplantcomponents
such
as
motors,
or
the
fan
impeller
and
casing.
Axial fans
may
be mounted n-line at
high
level
as
a
means of
reducing pace
requirements
n
the
plant
room. In-line
mountingmay
be in thehorizontal
or
vertical
plane. High
evel axial flowfans whichhave
support
frames with anti-
vibrationmountsfitted
below
thefans can intrude into bend
space below
by
more
than
expected. Larger
axial
fans will tend
to
be
floor mounted.
The
space requirements
ndicated n the data sheets summarise
he
space
required
for individual
centrifugal
andaxial flowfans. The
upper
boundary
is
typically
for
double
inlet,
double
width
centrifugal
fans
and
a
ower
boundary
is
defined for
single
inlet,
single
width
centrifugal
fans.Axial fans tend tobe more
compact
whichis
ndicated
by
the lowest
boundary
line.
If
high
level
in-line
axial
fans are used the
space requirement
will
be
reduced still
further,
but
space
provision
for the erection of
temporary
ccess formaintenance
purposes
must
be
considered.
Risk
assessment
main
hazards which nfluence the
provision
of
space:
•
Manual
handling
Plant
space
must be sufficient for the removal of
arge bulky
tems such as
motorsor
fans.
Where the fansare
large,
a mechanical hoistwillbe
required,
or
provision
of
a
permanent ifting
beam.
Sufficient
space
must
be
provided
for the
component
being
removedandthe
lifting/carrying
devicenot
only
in the
plant
oom but
on the entire
egress
route.
•
Falls
from
height
Some
axial fans are mounted
n-line
at
high
level which
will
require
maintenance ccess above 2m
height.
On smallfans this
may
be
temporary
safe access
for
inspection, adjustment
and
ubrication. On
larger
fans
located
at
high
level
frequent
maintenance asks must be
facilitated
by permanent
platforms protected
with
guard-rails.
For theremoval ofaxial fans at
high
level,
temporaryhigh
level access
may
be
provided
with
appropriate caffolding.
Space
is
required
for
erectionof hemaintenance
platform
withsufficient
space provided
on
the
platform
for safe
working,
handling,
and
owering
of
equipment
rom
high
level.
•
Rotatingmachinery
Fixed
guards
are
required
o enclose
dangerousparts
of
rotating
machinery, pulley wheels,
fan
belts, etc,
with
finger
proof
meshes.
84
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 92/148
Space Requirements
Section 5
Component
Requirements
GoodPractice
•
BSRIA
TN9/92.
Space
and
weight
allowances for
building
services
plant
-
References
inception
stagedesign.
1992.
•
HVCA.
Standard Maintenance
Specification
for
Mechanical Services in
Buildings.
VolII
-
ventilating
andair
conditioning systems.
1991.
•
NHS Estates.
HealthTechnical Memorandum 2023. Accessand
accommodationfor
engineering
ervices.
1995.
Legislation
and
•
Healthand
Safety Regulations:
Regulations
References
-
Ri, R2, R3, R4, R6,
see Section
2.2.
British Standards
•
BS 8313.
Codeof
practice
for
the
accommodationof
building
services
in ducts.
JULY1996
85
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 93/148
Space Requirements
Section
5
Component Requirements
M8.1 Fans
Summary
of
Space Requirements
E
-o
a
,
C,
'C
0.
Commentary
The
summary
above indicates
typical space
requirements
or
centrifugal
and
axialflowfans.
It
represents
he
space
for
the
fan,
motor
and,
where
ndicated,
attenuators
anddoesnotallow for
ancillary
equipment
(dealt with
separately
in
thisdocument).
86
JULY1996
45
40
35
30
25
20
15
10
5
0
-
—
Typical
range ..—
z>-
I I I I I
0 4 8
12 16
20 24 28 32 36 40
44
Volume low rate
(m3/s)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 94/148
Space Requirements
Section 5
Component Requirements
M8.2
Centrifugal
and Axial
Fans
-
Space
Details
Access
Requirement
Occasional
Centrifugal
Fans
floor
mounted)
1100
x
1100
1000mm
H
I I I
W
600
Dimensions
W Width
of
an
X
Depth
of an
D Diameter 01axial110w fan
A Attenuator
(All
dimensionsn
mm)
Attenuators
length
approximately equal
to
one andiameter
690
D
1100
600
Flexible connection
Commentary
Access
is
required
o
inspect
the
condition
ofdrivesand
adjust,
lubricate
bearings,
on a
occasional
basis. For smallaxial fans mounted n-lineat
high
level
with
sealed-for-life
bearings,
temporary
ccess
may
be
sufficient.
Space
must
be
provided
also for
the
removal
of
major
plant
components
suchas
motors
orfan
casings
together
with the
mechanical
lifting
device
which
may
be
used to handleand
manoeuvre
largerplant
tems.
JULY1996
87
600
Axial fans
(floor mounted)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 95/148
Space Requirements
Section
5
Component Requirements
5.1.9 Heat
Rejection
This section onsidershe
following
heat
rejection
devices:
•
Cooling
Towers
-
open
and
closed-circuit
owers,
using
nduced
or
forced
draught.
•
Air
cooledcondensers
Space
requirements
or
cooling
owers
must be
sufficient
to
allow
for the
effective
cleaning
of
he
tower,
its
packing (open
tower)
or
tubebundle
(closed
-
circuit
tower)
and
pond. Space
mustbe
sufficient
for
regular stripping
down
of he unit
and
provision
must be madefor
handling arge bulkycomponents
such
as
the
packing
section.
During
his
process
consideration
shouldbe
given
as to
where
the
large
plant
components
will be stored.
The maintenance
of
cooling
owersis
governedby
the
need
to
minimise the risk
of
egionnaires
disease;
detailed
guidance
is
given
inHSE and
CIBSE
documents,
see
data
sheetM9.1.The need
to
ensure
the
cleanliness of
he
tower,
its
packing
(open tower)
or tube
bundle
(closed
tower)
and
ponds
is
essential.
Cleaning
will
becarried out at least
twice
a
year
-
in
polluted
environments
it
may
be more
frequent.
Itwill necessitate he
stripping
down
of he
tower
to
clean
individual
components
such
as
packing, louvres,
eliminators
and the
pond.
Generally
located
outsideonthe
roof-top
or
ground
level
pen, space
should be
allowed for the
use
ofacrane for
nstallation orremoval
of
majorcomponents.
If
located
internally
with ductedair
supply,
sufficient headroom should
be
provided
for the
dismantling
of he tower
and
removal
of
arge bulkycomponents
and
he
associated
liftingequipment.
For
forced
draught
cooling owers
using
centrifugal
fans,
space
must
be
provided
for the removal of he fan shaft which
may
run the
entire
length
of he
unit,
driving
anumber of
mpellers.
The use of
axial
flow fans
will reduce
the
space
requirement.
Aircooledcondensers
require
a
greater
area than
cooling
owers for the same
heat
rejection
load.
Both
cooling
owers
and air
cooled condensers
need free
access
for the
entering
air.
Buildings,
enclosures
and
other
heat
rejecting
devicescan
disrupt
that
airflow orcause
'short-circuiting'
whichwill affect he
equipment performance.
Itis
essentialthatunits are
separated
n
accordance
with
manufacturer's
recommendations
to
minimise
the
interaction.
Risk assessment mainhazards which nfluence
space provision:
•
Manual
handling
The
packing
or tube
bundle section
ofa
cooling ower,
axial fans locatedat
high
level on induced
draught
towers
and air
cooledcondensers will
require
mechanical
lifting
equipment
for
removal. Sufficient
space
must
be
allowed for the removal
of
hese
components
in
the
vicinity
of he
plant
and
along
the entire
egress
route
from
the
building
whichmust also
be
capable
of
safely bearing
the
weight
of hat
component
and
its
lifting
mechanism.
88 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 96/148
Space Requirements Section 5
Component Requirements
•
Hazardous substances
Thecontrol of
egionellosis depends upon
cleanliness of
he
towerand
condenser water.
Space
andaccessaround the towerwill be
governed by
the need to
carry
out
regular
inspection
and
cleaning,
seebelow for CIBSE
and HSE
guidance.
•
Tripping
For
example,
low level
pipework
connectionsto
cooling
ower
ponds
and
aircooled
condensers,
see Section 3.1.2onbasic hazards.
•
Falling
rom
height
Frequent
nspection
and
cleaning
will be
necessary
for
components
located
at
high
level,
such as
eliminators andinduced
draught
fans. For
large
cooling
owersand aircooledcondensers the
working
height
will
almost
certainly
be
above
2m,
and
permanent
safe access
may
be
necessary
in
the
form
of
a
maintenance
platform protected
with
guard
rails.
Good Practice
•
BSRIA
TN
9/92. Space
and
weight allowances for building services
plant
-
References
inception stage desigu.
1992.
•
HVCA. Standard
Maintenance
Specification
forMechanical Services in
Buildings.
VolII
-
ventilating
and air
conditioning systems.
1991.
•
NHS Estates. Health
Technical Memorandum 2023. Accessand
accommodationfor
engineering
ervices.
1995.
•
CIBSE. Technical
Memorandum TM13.
Minimising
the riskof
legionnaires
disease.1991.
•
HSE.Healthand
Safety
booklet
HS(G)70.
The
control
of
egionellosis
(including legionnaires disease).
1992.
Legislation
and
•
Health
and
Safety Regulations:
Regulations
References
-
Ri,
R2,
RB,
R4, R6,
see
Section
2.2.
•
BuildingRegulations: Approved
DocumentK
-
Stairways, amps
and
guards.
•
HSC.
Approved
Code
of
Practice.
The
prevention
of
egionellosis
(including
legionnaires
disease). 1991.
British Standards
•
BS 8313.Codeof
practice
for the
accommodationof
building
services
in ducts.
•
BS6180.
Codeof Practice or
protective
barriersinandabout
buildings.
•
BS
5395:
Part
3.
Stairs,
ladders
and
walkways.
Code
of
Practice or the
designof ndustrialtype stairs, permanent adders
and
walkways.
JULY1996
89
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 97/148
Space Requirements
Section
5
Component Requirements
M9.1
Cooling
Towers and
Air
CooledCondensers
-
Summary
of
Space Requirements byCooling
Towers and
Air
Cooled Condensers
Cooling
Towers
E
-n
a)
a
a)
Ca
Ca
Ca
0
Air-cooledCondensers
c
250
-c
a
)
Ca
Ca
0
225
200
175
150
125
100
75
50
25
0
Commentary
The
summary
above
indicates
ypical space requirements
or
cooling
owers
(forced
draught
and nduced
draught)
and aircooledcondensers.
It
represents
the
space
for two
units of
equalrating;
the
total
heat
rejection
of
he
setis
expressed
inthe
graphs.
The
space provisions
do
not
allow
for associated
quipment
(dealt
with
separately
n this
document).
For
cooling
owers he
upper
limit is
typified
by
forced
draught owers,
the lower
by
induced
draught types.
The
space requirement
foraircooled condensers
(ACCs)
is
significantly
greater
than
for
cooling owers;
theupperlimit
typified by
low
profile
ACCs,
the lower limit
by
machines with vertical
coils.
90 JULY1996
0 500
1000 1500
2000 2500
Heat
ejection (kW)
0 500
1000
1500
2000 2500
Heat
rejection
kW)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 98/148
Space Requirements
Section
5
Component Requirements
M9.2
Cooling
Towers
-
Space
Details
1
I
I
I
I I
___I
___
L
L
Forced
Draught
with
Centrifugal
Fans
HSH HSH
I
I
Induced
Draught
with Axial Fans
Dimensions
L
Length
of machines
S
Separation
between
adjacent
machines
(see
manufacturers
ecommendations)
I
Separation
fromenclosure
(see
manufacturer
s
recommendations)
W Width
of
machine
Commentary
Space
is
required
for the
permanent
safeaccess
provisions
for the
frequent
inspection
and
cleaning
of all
the
towers'
wetted
surfaces. The
towerneeds
tobe
stripped
down
to
gain
accessto
the
packing (open towers),
tube bundle
(closed
-
circuit
towers)
and
the
ponds
foreffective
cleaning
andwater level control
adjustment.Space
shouldbe
provided
tofacilitate he
dismantling
procedure
and
accommodatethe mechanical
liftingequipment
generally
needed.
The
spacing
of
cooling
owers
on
installations,
where
several
are
used,
should
be
such to
avoid
interaction
of
he air
flow
with
the enclosure
and
from other
machines to
prevent short-circuiting'.
On
larger
towers consideration needs
o
be
madefor
working
at
height;
thiswill
require
the
provision
ofmaintenance
platforms protected
by guardrails to
allow
frequent
nspection
and
cleaning of
components
suchas induced
draught
fans
andeliminators.
On
forced
draught
cooling
towers
using
centrifugal
fans,
sufficient clearance
needs to
be
provided
for theremoval
of
he fanshaft.
JULY1996 91
Access
Requirement
Frequent
I
L
S L I
T
W
I
I
W
T
T
L S
L
I
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 99/148
Space
Requirements
Section 5
Component Requirements
M9.3 Air Cooled Condensers
-
Space
Details
Access
Requirement
Frequent
T
boMoM
I
I L
T
T
OOOO
IOOMOOL
T
I
X S
L I
Space Requirements
orAir
Cooled Condensers
Dimensions
L
Length
ofmachine
S
Separation
between
adjacent
machines
(see
manufacturers
recommendations)
T
Separation
trom
enclosure
(see
manufacturers
recommendations)
W
Width otmachine
Commentary Space
is
required
for the
frequent nspection
and
cleaning
of
he
condenser
coils,
fans
etc. which
requires permanent
safe
access.
Space
shouldbe
provided
to facilitate
heremoval
of
principal
elementssuch as
axialflow
fans
which
are
generally
located at
high
levelandaccommodate the
mechanical
liftingequipment
needed.
The
separation
of
air
cooled condensers (ACCs)from the enclosure
and
from
other
heat
rejection equipment
is
critical to avoid
interactionof the air
flow
and
'short-circuiting'.
92
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 100/148
Space Requirements
Section 5
Component Requirements
5.1.10 Lifts
There are
two common
groups
of lift drive
systems.
•
Electric
Traction
Lifts
•
Hydraulic
Lifts
General
space requirements
or lifts are based
upon nspection, cleaning
and
adjustment
at
frequent
ntervals.
Space
should alsobe
provided, however,
against
the
requirement
to
replace
a drive
unit,
traction
sheave, motor, hoisting
ropes
or controller.
Provisions
for safe
working
in
machine/pulley
rooms
-
It
sessentialthata safemeans ofaccess be
provided
and hat
permanent
safety
signs
are
displayed
on
the
outside
of
he machine
and
pulley
room doors.
Electric lighting should
be
provided
on
the
basis of
at
least
200
lux
at
floor level
and
at
the
equipment.
In
addition,
an
adequateemergency lighting
source should
be
available
for use
in the
event offailure of
he
normal
ightingsupply.
All
dangerous
parts
are
required
obe
effectively
guarded,
unless
they
are so
placed
or
constructed
as
to
be as
safe
as
if
they
were
so
guarded.
The
following
items,
for
example,
are
consideredas
dangerous parts:
•
gear
and
pulley
drives
•
protruding
shaft ends
•
overspeed governors
Where practicable, consideration
shouldbe
given
to
the
provision
of
certificated
lifting
acilitiesforthe
handling
of
heavy equipment.
Electric shock
treatment
notices should
be
prominently displayed
in
the
machine room.
To
protectagainst
electric
shock,
a
rubber
mat
complying
with BS
921 and
of
suitabledimensions should be
placed
on the floor infront of
each
controller,
and
also,
where
necessary,
at he
rear.
Thefloorshouldbeof
non-slip
materials
without
ripping
hazards. When the
floor
comprises
a number
of
evels,
differing by
more
than
0.5m,
stairways
or
steps
and
guard
rails shouldbe
provided.
Ifaccess tothe mains switch fora iftis
difficult,
or remote from the liftmachine
and/or
controller,
the
following
precautions
hould be
adopted.
•
asuitable
stop
switch should be fitted
on,
or
adjacent o,
the
lift
machine;
•
a
meansof
nterrupting
hemain
supply
shouldbe
provided on,
or
adjacent
o,
the
controller.
On
multiple
installations,
eachmachine roomorall the machine and
pulley
room
equipment
associated
with
each ift
should
be
clearly
identified.
JULY1996
93
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 101/148
Space Requirements
Section
5
Component Requirements
Proceduresfor
safe
working
n
machine/pulley
rooms
-
Doorsto therooms
shouldbe
kept
locked
to
prevent
unauthorised
ccess.
Works should
not:
•
be
undertakenon
machinery
whileit is
in
motion,
or
which s
capable
of
intermittent
motion.
•
be
carried out on
orso
near
tolive electrical
equipment
thatelectrical
danger foreseeablyarises,
unless
working
in this
way
is
unavoidable. In
such
situations,
adequateprecautions
should be taken
to
avoid electrical
shock or
burn
njuries, e.g.by making
use
of
nsulatingmats, temporary
shrouding
and nsulated
tools,
and heworkshould
only
be carriedout
by
a skilled
person,
underthe
DEO(W)
Safety
RulesProcedures
-
Electricity.
Riskassessment
-
mainhazards
which influence
the
provision
of
space:
•
Manual
handling
Theremoval ofa
motor,
drive
unit,
traction
sheave,hoisting opes
or
controller,
will
require
he
use
of
a
mechanical
lifting
device
and
he
permanent
provision
for the removal of
heavy plant
ifting
components
will be
necessary
e.g. lifting
beam.
Sufficient
space
must be
provided,
not
only
in
the
plant oom,
to
lift and
handle
he
removal ofdrive
units, motors, etc,
but
also on the entire
egress
route from the
building
whichneeds
o be
capable
of
safely bearing
the
weight
of hat
component
and ts
lifting
mechanism.
•
Working
on
top
of ift
cars
The
tops
of iftcars are
extremely
hazardous
areas,
and
only
authorised
and
properly
trained
personnel
shouldbe
permitted
on
the
top
of he
lift car.
•
Lift motor
rooms
The
lift
motor room
may
contain
rotatingmachinery
and
electrical control
devices.
Only
authorised
and
properly
trained
personnel
shouldbe
permitted
n
the lift motor ooms.
•
Lift wells
Theliftwells
may
contain
rotating
and
moving machinery. Only
authorised rained
personnel
shouldbe
permitted
n the liftwells.
Space requirements
or lifts
-
Reference
should
be
made
o
BS5655.
Part
5:
Specification
for thedimensions of
standard lift
arrangements.
1989.This Standard
gives
a
comprehensive guide
to
the
provision
of
space
for traction
and
hydraulic
lifts and motor rooms for
a
arge
number of ift
arrangements.
Good
Practice
•
CIBSE. Guide D
Transportation
n
Buildings.
1993.
References
•
NALM.
Principles
of
Planning
and
Programming
aLift Installation.
1994.
•
NALMICIBSE
Guidance
on
the
Management
and
Maintenance ofLifts
and
Escalators.
•
JAMES
G.
ProvisionsandProcedures
-
a
safe
combination.
Proceedings
of
ELEVCON,
pages
222-229.
1995.
Legislation
and
•
Healthand
SafetyRegulations:
Regulations References
-
Ri,
R2, R3, R4, R5, R6,
see
Section
2.2.
British
Standards
•
B55655.Lifts
and
service lifts:
Parts
1
to
12. 1983/1990.
•
BS7255. CodeofPractice for theSafe
Working
onLifts.
1989.
94
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 102/148
Space Requirements
Section 5
Component Requirements
5.2CENTRALSTATION
PLANT
-
ELECTRICAL
5.2.1 HV
Equipment
Several
common
types
of
HighVoltage
(HY)
equipment
areconsidered:
•
HV
Switchgear
-
Indoor
•
Cast Resin
and
Dry
Type
Transformers
•
Indoor Substations with Cast Resinand
Dry
Type
Transformers
•
Oil FilledTransformers
and
Transformer
Compounds
•
Substationswith
Oil Filled Transformers
•
Ring
Main Units
•
Packaged
Substations
Where
a
substationor
switchgear
includes he
regional electricity company's
(REC's)
metering
he
REC
may
insist on
permanent
access.
This
can
often serve
an
additional unction
as an
emergency escape
route from the HV room.
Most indoor
switchgear
includesa ruck for withdrawal of he circuit breakeror
switch;
sufficient
space
must be
allowed
for this.
Transformers and
some
packaged
substationsare
provided
with
wheelsor
rollers and
switchgear
cubicles
require
suitable
trolleys
or
acks.
It
is
notcommon
practice
to install
lifting
beams in switchrooms.
Plant
removal from
external installationscan
be
carried out
using
a
streetcrane
providing
there are no overhead obstructions. Particular care must be takenif
there are
overhead lines.
With ndoor
switchrooms,
plant installation
and
removal
may
require
use
of
ork
lift trucks or manual
trolleys.
Access doorswith demountable lintels and
removable
panels
over thedoors
may
be
necessary.
Where cables
are installed
in
trenches suitable rench
covers
must
be
provided.
These must
be
smooth
enough
o allow
the
switchgear
truck
to be
wheeled across
if
necessary,
andbe
strong
enough
tocater for
any
plant
emoval
operations.
Allow
a
minimum
of
800mm access
space
for
fitting
cable
glands
or
greater
if
requiredby
the
manufacturer.
Anyspace
for
expansion
must be
designed
infrom the start andmust include for
allupstreamand
downstream equipment, for example
an
additional
transformer
would
requireprovision
for
an
HV
switchgear
cubicle,
an
LV switchboard and
routesfor theLVdistribution ablesorbusbars.
Additional
space
must
beallowed
for
auxiliary
tems such
as
tripping
batteries
and
storage
of
tools
or
switchgear
removal
trucks.
These
must not reduce he
clear
gangway
areas.
Separate storage pace
for transformeror
switchgear
oil
must
be
provided;
it is
notrecommendedto
keep
these
in the switchroom.
Indoor
transformersand
largeswitchgear
installations
will
require permanent
ventilation. The
heat
output
should be checkedwith
the
manufacturer.Sufficient
space
must be allowed for ductwork andfans.Ducts
may
needtobe constructed
from
fire rated materials or fitted with fire
dampers.
Some locations
may
require
a
ixedfire
fighting system.
(For
example
whereoutdoor
switchgear
is
nstalled
in
an
occupied building.)
JULY1996 95
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 103/148
Space Requirements
Section5
Component Requirements
Indoor
substations
onstructed
using
external
switchgear (ring
main
units)
may
require
to beconverted tointernalcubicle
type
switchgear
ata ater date.
It
s
essentialthat sufficient
space
forthis is
designed
inatthestart.
Legislation
and
•
Electricity
atWork
Regulations: R1,R2,R3,R4,R5,R6,
ee Section 2.2.
Regulations
British Standards •
BS 8313.Codeof
practice
for the
accommodationof
building
services
in
ducts.
•
BS6626 Code of
practice
formaintenance ofelectrical
switchgear
and
control
gear
for
voltages
above
1
kV and
up
to and
including
36
kV.
96
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 104/148
Space Requirements
Section5
Component Requirements
E1.1
HV
Switchgear
-
ndoor
-
Space
Detailsand
Summary
of
Space Requirements
Access
Requirement
Occasional
690
A
B
1000
690
W
W
W W
690
Access
50
-o
-
40
30
20
10
A
Typical
range
.-
—
I
—
I I I
0
1
2
3
4
5 6
7
8
9 10
Number
of
cubicles
Headroom
Allow 3500
headroom.
Some
voltage
ransformers
require
to be
emoved
vertically
rom he
op
of the
cubicle
Clearance
Dimensions
,
B and W must be obtainedrom
manufacturers ata.
Dimension
Amust nclude
any
allowanceorcable ermination
boxes.
Allow 1000additional
pace
for
working
on withdrawn
reakers
(All
dimensions
n
mm)
Commentary Space requirements
are
typical
of
modern11kV
oil,gas
orvacuum
breakers,
switches
or
contactors. Some older
or
air-insulated
witchgear may
be
considerably larger.
JULY1996
97
I I I I I I
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 105/148
Space Requirements
Section
5
Component Requirements
El 2 CastResin and
DryType
Transformers
-
Space
Details
(In
basic sheet steel
enclosures)
Access
Requirement
Occasional 690
Transformer 1 enclosure
W
Draw
out
space
Till
___________
W+1000
Draw
out
space
TR2
Translormer2enclosure W
690
690
690
690
Transformer enclosure W
Drawoutspace
W
%000
Escape
door
690
690
Headroom
Allow
at
east1000
clearance above
the enclosure. his
will
require
pprox.
3000
headroom
for
ransformers
p
to l000kVAand 3500
tor
arger
izes.
These
dimensions
may
need
to
be increased it
op enfry
connections re
used.
(All
dimensionsn
mm)
Commentary
In
multiple
transformer nstallations he
space
between
adjacent
units
should
be
atleast 1000more thanthe transformerwidth o
permit
accessfor
pullinggear
and
rotating
therollers
through
900.
See
dimensionX.
The
doors should
be
wide enough
to
permittransformer
emoval.
Installations
of
more
than
wo transformers
n
line will
require
doors for eachdraw
out
space.
(Continued)
98 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 106/148
Space Requirements
Section 5
Component Requirements
[1.2
Cast Resin and
DryType
Transformers
(Continued)
-
Summary
of
Space Requirements
40
-c
C,
=
a
<
30
-
2
TransformerS
20
_-
nsfor-
10
—
0
HI
__________
Transformer
rating
kVA)
Space Requirements
for
Transformer nstallation
Commentary
The
rating
n
the
graphs
is
the
rating
of
each
individual transformer.
JULY 1996
99
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 107/148
Space Requirements
Section 5
Component Requirements
El
3
Indoor
Substations
with Cast
Resin
or
DryType
Transformers
-
Space
Details
(Transformers
in
enclosures)
690
C
A
W
W+1000(X)
W B
fl'\
scape
door
C,
*
o
0
F.m
a
Headroom
Allow at
east
1000
learance
above he allestenclosure. hiswill
require
approx.
3000headroom for ranstormers
up
o1000kVA and 3500 or
arger
sizes. These
dimensions
may
need
to be
ncreased it
op
entry
onnections
are used.
Clearances
Dimensions
A
and B should be 900 minimumbut B mustallow
tor
ny
Ring
Main Unit
operating
handles.
DimensionsCandD will
vary
t
rear
accesss
required.
(All
dimensionsn
mm)
*
Space requirements
forHV
Switchgear
shouldbe determined fromData sheetEl 1
Commentary
Where the HVandLV
switchgear
and ransformerare installed n
separate
rooms the
space
requirements
hould bedetermined rom the datafor the
individual
equipment
items.
In
multiple
transformer nstallations he
space
between
adjacent
units
should be
at
least
1000
more
thanthe transformerwidth to
permit
accessfor
pullinggear
androtating
the
rollersthrough
900.
See
dimension X.
The
doors
shouldbe
wide
enough
to
permit
transformer emoval.
(Continued)
100 JULY1996
Access
Requirement
Occasional
Escape
door
690
690
Ct
a
w
a
,-
aem
00
mi5
E
I
E
—
I-
82t
aa
0
oo
cj
em
00
g
I I I I
D
*
690
I
I
I
I I
C A W W B
D
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 108/148
Space Requirements
Section
5
Component Requirements
El
3
IndoorSubstationswith CastResinor
Dry
Type
Transformers
(Continued)
-
Summary
of
space requirements
E
-o
=
g
60
Ct
a,
2 Transfonners
—
Transformer
-
—-
-
Iii
I I I I
Space
Requirements
orSubstations
Cast resin or
dry
ype
transformers
IndividualTransformer
rating kVA)
Commentary
The
rating
n the
graphs
is
the
rating
of
each
ndividual transformer.
JULY1996
101
50
40
30
20
10
0
CC) U)
-
CC)
U-C
U)
(0
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 109/148
Space Requirements
Section
5
Component Requirements
El 4
Oil Filled TransformersandTransformer
Compounds
-
Space
Details
Access
Requirement
Occasional
Escape
door
690
L
690
690 W 690 W
Headrooni Allow3000headroom
for
ransformers
up
to 1000kVA
and3500
or
larger
sizes
Allowextra
height
oroilconservators if itted.
(All
dimensions
in
mm)
690
L
690
Commentary
Thedimensions L and
W
nclude he
requirements
or
an
oil
catchpit
of
ypical
depth.
In someinstallations
it
may
be
possible
tohave
a
deeper
catchpit
ocated
directly
belowthe transformer.
The
clearance
around
he
transformer
should
take
this
nto
account.
For
indoor
installations he
doors should
be
wide enough
to
permittransformer
removal.
In
outdoor
installations ransformerswill
normally
be
lifted
by
crane.
(Continued)
102 JULY1996
Oil catch
pit
Transformer
690
690
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 110/148
Space Requirements
Section 5
Component Requirements
E1.4
Oil Filled TransformersandTransformer
Compounds (Continued)-Summary
of
pace requirements
60
-c
0
a
j
0
40
30
20
10
0
________________________________________
_________________________________________
Individual
ransformer
rating
kVA)
Space Requirements
or
Transformer nstallation
Oil filledTransformer &Transformer
Compounds
Commentary
The
rating
n the
graphs
is
the
rating
ofeach
individual transformer.
JULY1996
103
2
Transformers
----
Transformer
—
—
I I
—
0
—
c,
(0 C'J (0
'
(C)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 111/148
Space Requirements
Section
5
Component Requirements
E1.5
Substationswith Oil Filled
Transformers
-
Space
Details
Access
Requirement
Escape
door
Frequent
I
__________________________
690
Oil catch
pit
_______
*
coc
Transformer
L
690
'C' A W
B'
-
Escape
door
690
Oil catch
pit
Oil catch
pit
*
0&)
Transformer Transformer
L
________ ________
>
690
C A
'
W 690 W
'
B
Headroom
Allow 3000headroom
for
ransformers
up
o
1000kVA and 3500
for
arger
izes.
Clearances
Dimensions
A
and B should be 900 minimumbut B mustallow
or
any
Ring
Main Unit
operating
handles.
Dimensions
C
and
D will
vary
f earaccess
is
required.
(All
dimensions
n
mm)
*
Space requirements
or -tV
Switchgear
should be
determined
fromDatasheet
E1.1
Commentary
The
dimensions
L and W
include
the
requirements
or
anoil
catchpit
of
ypical
depth.
In someinstallations
it
may
be
possible
tohave
a
deeper
catchpit
ocated
directly
belowthe transformer.
The
clearance
around
the
transformershould ake
this
nto
account.
For
ndoor
installations
he
doors
shouldbe
wide enough
to
permittransformeror
switchgear
removal.
In
outdoor installations
equipment
will
normally
belifted
by
crane.
(Continued)
104
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 112/148
Space Requirements
Section 5
Component Requirements
El
5 Substations
withOilFilled Transformers
(Continued) Summary
of
Space Requirements
Space Requirements
forSubstations withOil FilledTransformers
Transformer
rating
kVA)
Commentary
The
rating
n the
graphs
isthe
rating
ofeach ndividual
transformer.
JULY1996
105
60
a)
=
a)
Ct
a)
40
30
20
10
0
2
Transformers
—
Transformer
—
—
I
I
I
I
U•)c,
c
'
)
-
CD
c)
(cC
—
—
C4)
C
(cC
c'J
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 113/148
Space Requirements
Section
5
Component Requirements
El .6
Ring
Main Units
-
Space
Details
Access
Requirement
Occasional
Ring
Main Unit
Operating
Area
Typically
-10
m2.
Rating
doesnot atiect
size
Headroom
Allow 3000
headroom
for ndoor
nstallations.
Dimensions A-
Ring
main unitwidth
B
-
Ring
main unit
length
(All
dimensionsn
mm)
Allow additional
pace
tor
uture
conversion to
indoor
type
switchgear
tor
ndoor
nstallations
Commentary
The
operating
areamust allow for
any
removablehandles or doorsonoutdoor
units. For indoorinstallations he doors should be wide
enough
to
permit
equipment
emoval.Inoutdoor
installations
equipment
will
normally
be
lifted
by
crane.
106
JULY1996
690 B
690
H
690
A
Mm 1000
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 114/148
Space Requirements
Section
5
Component Requirements
El 7
Packaged
Substations
-
Space
Details
-
With
dry ype
ransformers
in
basic sheetsteelenclosures
Headroom Allow
at
east1000clearanceabove he enclosure. This
will
require
approx.
000
headroom for ransformers
up
o 1000kVA
and 3500 or
larger
sizes.These dimensions
may
need
to
be ncreased
it
opentry
connections reused.
(All
dimensionsn
mm)
Access
Requirement
Frequent
Commentary
The
overall space requirements do
notvary
significantly
with the
different
transformer
orientations.The
doors should
be
wide
enough
to
permit
transformer
removal.
(Continued)
JULY1996
107
Spaceavailable
or
ancillaries
or
building
structure
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 115/148
Space Requirements
Section 5
Component Requirements
El7
Packaged
Substations
(Continued)
-
Summary
of
Space Requirements
6O
-o
0
0)
40
35
30
25
20
10
0
Space Requirements
or
Packaged
Substations
Commentary
The
summary
above indicates
ypical space
requirements
or substationswitha
typical
mix of
outgoing
LV circuits.
108 JULY1996
0
250 500 750
1000 1250
1500
1750
2000
Rating
kVA)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 116/148
Space Requirements
Section 5
Component Requirements
5.2.2 LV
Switchgear
and
Components
Three common
groups
ofLow
Voltage
(LV)
equipment
areconsidered:
•
Main LV Switchboards
-
both
front andrearaccess
•
LV switchboards andMotor Control
Centres
(MCCs)
in
Plantrooms
•
Control/Alarm/Supervisory
Systems
Sufficient
space
must be allowed for MCCsand
any control,
alarm or
supervisory
systempanels
installedin
plantrooms.
Auto ransformersand
arge
contactors
may requirespace
for
liftinggear
for removal.
Legislation
and
•
Electricity
at
Work
Regulations:
reference
-
R1,R2,R3,R4,R5
&
R6,
see
Regulations
section 2.2.
•
Electricity
at
Work: safe
working practices.
HS(G)85.
HSE. 1992.
British Standards
•
BS
8313. Code
of
practice
fortheaccommodation
of
building
services
in ducts.
•
BS6423. Codeof
practice
formaintenance
of
electrical
switchgear
and
controlgear
for
voltagesup
to and
ncluding
1
kV.
JULY1996
109
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 117/148
Space Requirements
Section
5
Component Requirements
E2.1 Main LV Switchboards
(Front
Access)
-
Space
Details
Access
Requirement
690
Frequent
H
Headroom
For
ypical witchgear height
of
2250 allow3000
headroom forbottom
entry
units and 3500 or
op
entry.
(All
dimensions
n
mm)
2xW
(mm 2000)
Commentary
An
emergencyescape
exitshould
be
provided
but isnot
a
egal requirement.
(Continued)
110 JULY1996
690
LV
witchgear,
front
access
Circuit
Breaker Withdrawal
Space
w
w
690
w
V
witchgear,
frontaccess
Circuit
Breaker
Withdrawal
Space
1
Circuit Breaker Withdrawal
Space
LV
switchgear,
frontaccess
w
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 118/148
Space Requirements
Section 5
Component Requirements
E2.1
Main LV
Switchboards
(Front
Access) (Continued)
-
Summary
ot
Space
Requirements
40
Ca
a,
Space
Requirements
or
Single
Switchboards
'40
C
Space Requirements
orTwo Switchboards face to ace
Commentary
For
single
units the
space
requirements
or
front
and rear
access
boardsare
similar. The
saving
n
depth
withafront accessboard
s
negatedby
the extra
length
of he
cabling compartments.
The load
expressed
in the
graphs
is the total installed
capacity.
JULY 996
111
30
20
10
wi
enerator
and bus
stion
breakers and PFC ubicle
0 300 1000 2000kVA
30
20
10
with
generator
andbus
stion
breakers and
PFC cubicle
\
/7Z<
Basic
0 300
1000 2000kVA
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 119/148
Space Requirements
Section 5
Component Requirements
E2.2 MainLV Switchboards
(RearAccess)
-
Space
Details
Access
Requirement
Frequent
Circuit
'Front
Headroom
For
typical
switchgear height
of2250 allow3000
headroom
forbottom
entry
unitsand 3500for
op
entry.
(All
dimensions
n
mm)
Commentary
An
emergency escape
exit
shouldbe
provided
butisnota
egalrequirement.
For
single
units the
space requirements
or frontand rearaccess boards are
similar.Thesaving
n
depthwith
a
front
access
board
s
negated
by
the extra
length
of
he
cabling compartments.
(Continued)
112 JULY1996
690 690
LV
witchgear,
rear access
900
w
w
690
900
w
2xW
(mm
200
w
900
Front
Circuit Breaker Withdrawal
Space
Breaker Withdrawal
Space
LV
witchgear,
rear
access
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 120/148
Space Requirements
Section 5
Component Requirements
E2.2 Main LV Switchboards
(RearAccess)Continued)
-
Summary
of
Space Requirements
40
30
20
2000
kVA
Commentary
The load
expressed
n the
graphs
is the total installed
capacity.
JULY1996 113
10
0 300
1000
SpaceRequirements
or
Single
Switchboards
40
33
with
generator
and bus
section
breakers
and PFC
cubicle
—
T
asic
—--
0
300
1000
Space Requirements
forTwo Switchboards face o ace
2000
kVA
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 121/148
Space Requirements
Section 5
Component
Requirements
E2.3
LV Switchboards
and Motor Conirol
Centres
-
Space
Details
-
General
requirements
for
nstallation
in
plant
ooms
or
electrical rooms.
Facing
Front rom wall
Front
romdoor
Backto back
Back trom wall
If rontaccessX
=
If earaccessX
=
90 A
Back romdoor
0
U-
End
from
door
Clearances
Dimensions
arked
A
may
need
to be
ncreased
toallow or
large
door
panels
ordraw-out ircuit
breakers.
Dimensions
arked
B
may
need
to be
ncreased
if
learance
for
moving arge
equipment
is
required.
(All
dimensions
n
mm)
Commentary
For situationswhere
space
cannot
befound
fora
single
larger
nclosure a
numberofsmallerenclosures
may
be
necessary.
114
JULY1996
0
U-
If ront
access
X
=
0
If ear
access
X
=
690
End on
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 122/148
Space Requirements
Section
5
Component Requirements
5.2.3
Lininterruptible
Power
Supplies
Uninterruptible powersupplies
UPSs)
re considered undertwo main
categories.
Battery
rooms are similarfor both
types.
•
Static UPS
-
Space
requirements or the static UPS are similar
o
MCCs.
Units are in
floor-standing enclosures,
all
requiring
access from
the front with
some
manufacturer's
quipment requiring
rear
or side access
in
addition.
Larger
units
are
supplied
in
sections for
assembly
onsite.
Small
desk-side
UPSs for
individual
computer
stations
are notcovered
here.
•
Rotary
UPS-
Space
and
access
requirements
or
rotary
UPSs
vary according
to
the
locationof
he
motor-generator.
Where the
motor-generator
is mounted
n the
base of
hecontrol
cabinet
sufficient
space
must be
available
to withdraw
t
horizontally
before it
can
be
lifted.
•
Battery
Rooms
-
Access must be
provided
for
regularinspection
of
battery electrolyte
levels
and he
layout
should enable all cells tobe
nspected
or
topped upeasily.
Individualcellsare small
enough
to bemoved
through
personnel
access
doors
although
the
weight
of
arge
cells or
multiple
blocks will
require
a
trolley
of
some
type.
In
this
event
consideration should be
given
to
the
ingress
and
egress
route with
respect
o the
handling
ofa
loaded
trolley.
The removal ofa ransformeror
motor-generator
will
require
heuse ofa
mechanical
lifting
device.
On
largerrotary
UPSs the
motor-generator
may
weigh
4000
o
5000
kgand
permanent
provision
of
a
iftingbeam
should
be
considered.
Control cabinets of
arge
UPSs can
normally
be
split
intomodules or sections.
However,
some can stillbe
large
enough
tocause
handling
difficulties and
determine hesizeof he access route.
Space
must be
provided
for the
safe
storage
of
battery electrolyte
and
protective
clothing.
A
first-aid cabinet
and
eye-wash facility
are
required.
UPS installations
equire
ventilationboth for
the
equipment
room and
for the
battery
room.
Portable ire
extinguishers
hould
be
provided.
Legislation
and
•
Electricity
at
Work
Regulations:
reference
-
R1,R2,R3,R4,R5&R6,
Regulations
see
Section 2.2.
British
Standards
•
BS8313. Codeof
practice
fortheaccommodationof
building
services
in
ducts.
•
BS6132. Codeof
practice
for safe
operation
ofalkaline
secondary
cells
andbatteries.
•
BS6133. Codeof
practice
for safe
operation
of
ead-acid
secondary
cells
and
batteries.
JULY1996
115
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 123/148
a
-c
a)
=
0
)
Co
a
0
0
Headroom
MostUPSsot ess hanabout
75kVA
will
be
less han 1800
high
and
headroom
will
not
present
a
problem.
Units over100kVA
may
be
up
o
2200
high
and will
require
3000 minimum
headroom for
bottom
entry
units and3500for
op
entry.
(All
dimensionsn
mm)
Commentary
If
data
on
the
component
withdrawal
pace
is not
known,
a
space equal
to
the
depth
of
he cabinets
should
be
allowed.
DimensionsmarkedX
depend
onthe
requirement
or side orrear access. Where
side orrear accessis
necessary
allow 690 minimum.
116
JULY1996
Space Requirements
Section
5
Component Requirements
E3.1 Static
Uninterruptible
Power
Supplies
-
Space
Details and
Summary
of
Space Requirements
Access
Requirement
x
Frequent
x
-x
w
w
900
Multiple
units or
rallel
operation
0 100 200 300 400 500 600
700
Total
installedUPS
capacitykVA)
30
25
20
15
10
5
0
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 124/148
Space Requirements
Section 5
Component Requirements
E3.2
Rotary Uninterruptible
Power
Supplies
-
Space
Details
x
x
Rotary
UPS
(with
internal motor-
generator)
Withdrawal
space
for
transformer
ormotor-
generator
w
900
Headroom
Most
UPS S01
less han
about 75kVA
willbe ess han 1800
high
and
headroom
willnot
present
problem.
Unitsover 100kVA
may
be
up
to2200
high
and will
require
3000 minimum
headroom
for
bottom
entry
units and 3500for
top entry.
(All
dimensionsn
mm)
Commentary
If
dataonthe
component
withdrawal
pace
is
notknown a
space equal
o
the
depth
of
he
cabinets
shouldbe
allowed. Some
manufacturers
provide
detachable
rails forremoval of he internal
motor-generator
andsufficient
space
must be
allowed for these.
DimensionsmarkedX
depend
on
the
requirement
or side orrearaccess. Where
side orrearaccess is
necessary
allow 690 minimum.
External
motor-generators
should be treatedas
rotating
equipment
and a
minimum
space
of900 should be
provided
on all sides.
Whereunits have
separatemotor-generators
thecables should
be
run
in
floor
trenchesor ducts.
Trench covers
shouldbe strong
enough
to
support
he
weight
of
any liftinggear
or
trolleys.
(Continued)
JULY1996 117
Access
equirements
Frequent
-x
w
900
-x
W
W
900
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 125/148
Space
Requirements
Section 5
Component Requirements
E3.2
Rotary
Uninterruptible
Power
Supplies
Continued)
-
Summary
of
Space requirements
400 500 600 700
Total
installed
UPS
capacitykVA)
400 500 600 700
Total installedUPS
capacitykVA)
Commentary
The
rating
n the
graphs
is the
rating
of each ndividual UPS.
Battery
rooms
are
considered
separately.
118
JULY1996
a
-o
a
a
0
0
30
Multiple
units for
parallel
operation
25
—
20
—
—
15
10
—
5—
0
I I I
Single
unit with
bypass
0 100 200 300
Space
requirement
or
UPS
withintegral
motor-generator
C
—
Multiple
units or
paralleloperation
30
-
15
—
10
—
5—
0
I I
0 100 200
300
Space
requirement
or
UPS
with
separate
motor-generator
Single
unit with
bypass
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 126/148
Space Requirements
Section 5
Component Requirements
E3.3
Ballery
Rooms
-
Space
Details
x
Headroom
Battery
racksshould be low
enough
o
enable
the
highest
ellso be
opped
up by
person
standing
n
the looiThe room
height
hould allowsufficient
headroom
under
any
ventilation
ucts.
(All
dimensionsn
mm)
x
x
900
x
Commentary
A
working
area of900
minimum
depth
should
be
allowedin
front of
battery
racks.The
clearance between
the batteries
and
he
walls,
dimension
X,
should be
sufficient to
permit
viewing
of he backs
of hecells ocheck for
leakage.
(Continued)
JULY 1996
119
Battery
Racks
Eye
Wash
Battery
Racks
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 127/148
Space Requirements
Section
5
Component Requirements
E3.3
Battery
Rooms
Continued)
-
Summary
of
Space Requirements
a
150
45
30
25
20
15
10
5
0
The
graphs
are based on
a
single
level
battery
roomwith cells nstalled
in
tiered
racks.
The
kVA
ratings
are based on a
3-phase
400/230
VUPSwith
15
minute
autonomy.
120 JULY1996
Commentary
0 100 200 300 400 500
600 700
Total installedUPS
capacitykVA)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 128/148
Space
Requirements
Section5
Component Requirements
5.2.4
Rotating Machinery
Two
ypes
of
equipment
are
considered:
•
Diesel Generators
-
water
cooled,
high speedengines
•
Frequency
Convertors
Space
requirements
are
given
for watercooled
high speedengines
operating
at
1500or 1800revmm-1.
The
space
requirements
orductwork on air
cooled
engines
vary
according
to the
layout
of
he
engine.
Low
speed
engines
used in
base load or CHP
installationsare
generally
more
specialised
in
nature.
Inboth
cases the
manufacturer
hould beconsulted.
For
generator
installations
space
must be
provided
for
cooling
airductwork and
ancillaries uch as
day
tanks
or heat
exchangers.
The
room
must have
sufficient
headroom for
removing components vertically
abovethe
set.
Lifting
beams
should
be
provided
for
liftingengine components duringmajor
overhauls.
Allowance
must be made
for cooling
air
ductwork
and
fuel
and
exhaust
pipe
routes to the
generator
oom. Bulk
fuel
storage
anks shouldbe
outside
the
building
if
possible.
Complete
removal of he setfor
rebuilding
at the
manufacturer'sworks
may
involveremoval ofdemountable
partitions
orductwork. Demountable
partitions
are
acceptable
if
hey
can be removedor re-erected inaround
three
to
four
hours.
The
removal
of
a
masonry
wall is
deemed
unacceptable
as a
means of
providing
accessto
plant.
The removal of he
motor-generator
ofa
requency
convertor will
require
he
use ofa
mechanical
lifting
device.On
larger
units the
motor-generator
may
weigh
4000
to
5000
kg andpermanent
provision
of
a
iftingbeam
should be
considered.
Where the
motor-generator
is
mounted in
the base of the
control
cabinet sufficient
space
must
beavailable
towithdraw
it
horizontally
before it
can be
lifted.
Legislation
and
•
Electricity
at Work
Regulations:
reference
-
R1,R2,R3,R4,R5
&
R6,
Regulations
see Section 2.1.
JULY1996
121
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 129/148
Space Requirements
Section 5
Component Requirements
E4.1
Diesel
Generating
Sets: Basic
Generator
Room
-
Space
Details
-
Water cooled,
high
speed engines (1500/1
800 rev
mm-i)
Access
Requirement
Frequent
P1
4
Airflow
4
Airflow
4
Airflow
Space
available
or
ancillaries
or
building
structure
Removable louvresor
doubledoorswith inlet
louvres
Removable louvres r
doubledoorswith inlet
louvres
BasicGenerator
Room
Headroom
Allow 3000
headroom for
he smallestsetsand 3500
above
about15OkVA.
Requirements varyaccording
o
engine onfiguration
and silencer ocation. Manufacturers atashould beconsulted.
Allow
space
for
ifting
beam
over
ength
of
generator
setand
clear
area behind.
(All
dimensionsn
mm)
Commentary Space requirements
or
installations
using
remoteradiators withoutheat
exchangers
are similar o thebasic
layout.
Heat
exchangers
require
a similar
area to the
outlet attenuator shownon the roomwith acoustic louvres.
The
double doors
for
nstallation/removal
of he
set
may
be
at
either end but
should
be
in
line with
theset.
(Continued)
122 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 130/148
Space Requirements
Section
5
Component Requirements
E4.1 Diesel
Generating
Sets
-
BasicGenerator
Room
(Continued)
-
Summary
of
Space Requirements
100
90
80
70
60
50
40
30
20
10
0
100
90
80
70
60
50
40
30
20
10
0
-
Two Sets
cal
ange
I.
I I I
0
100 200
300 400 500 600 700 800 900 1000
Generator
Rating
kVA)
Space Requirements
for
Diesel
Generating
Sets
Commentary
The load
expressed
in the
graphs
is he
capacity
ofeach
generating
set.
JULY1996
123
-
Single
Set
E
-o
=
a
)
E
-a
a)
=
a
)
-
Typical range
1-
100 200 300 400 5( 0 600 700
800 900 1000
Generator
Rating (kVA)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 131/148
Space
Requirements
Section5
Component Requirements
E4.2 Diesel
Generating
Sets: GeneratorRoom with AcousticLouvres
-
Space
Details
-
Water cooled
high speed engines
(1500/1800
ev
mm-i)
Access
Requirements
Frequent
Space available
for
ancillaries
_______
or
building
structure
Headroom
Allow 3000
headroom
for he smallestsetsand 3500 aboveabout
15OkVA.
Requirements
vary
according
to
engine configuration
and
silencer location. Manufacturer
sdata
hould be consulted.
Allow
space
tor
ifting
beam
over
ength
of
generator
etand clear
area
behind
et.
Headroom
should allow or
any
acoustic
reatment
on the
ceiling.
(All
dimensionsn
mm)
Commentary
Space
requirements
or installations
using
remoteradiators without heat
exchangers
aresimilar tothebasic
ayout.
Heat
exchangers require
asimilar
area
to the
outlet attenuator.
Either
the
inlet or outlet
louvre
must be
removable for
set
installationand
removal. Accessis
required
for
cleaning
debris drawn nto the inlet attenuator.
(Continued)
124 JULY1996
Generator Room
with Acoustic
Attenuators
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 132/148
Space Requirements
Section5
Component
Requirements
E42 Diesel
Generating
Sets:
Generator
Room
with
Acoustic
Louvres
Continued)
-
Summary
of
Space Requirements
E
100
=
90
<
80
70
60
50
40
30
20
10
0
0
Generator
RatingkVA)
Two Sets
ge
Space Requirements
for
Diesel
Generating
Sets
Generator
Rating (kVA)
Commentary
The load
expressed
n the
graphs
isthe
capacity
ofeach
generating
set.
JULY1996
125
Single
Set
i---
I
I I I I I
100 200 300 400
500 600 700 800 900 1000
E
100
a,
90
80
70
60
50
40
30
20
10
0
0
100 200
300 400 500 600 700 800 900 1000
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 133/148
Space Requirements
Section 5
Component Requirements
E4.3 Diesel
Generating
Sets
-
Generator Room with AcousticEnclosure
-
Space
Details
-
Water cooled
high speed engines (1
500/1800 ev
mm-i)
Access
Requirement
Frequent
Generator room
coustc
—
I
Diesel
I
generator
I
E
-II
-
Enclosure access
doors
(typical)
H
1500
1500
Commentary
The
upper
and ower imits
represent
the
space
requirements
or
typical
enclosures with
3OdB(A)
and
l5dB(A)
reduction
respectively.
126 JULY1996
H
4
Airflow
Removable
duct oair
outlet
Removable
duct from
airoutlet
4
Airflow
Space
availableorancillaries
_______ or
building
structure
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 134/148
Space Requirements
Section
5
Component Requirements
[4.3 Diesel
Generating
Sets
-
Generator Room
with
Acoustic
Enclosure
(Continued)
-
Summary
ot
Space Requirements
-
Water cooled
high speed engines (1
500/1
800 rev
mm-i)
Generator
Rating kVA)
Headroom Allow at least1000 learance above he acousticenclosure. This
will
requireapprox.
3000
headroom for he smallestsetsand 4000 aboveabout150kVA. Silencers re
normally
nstalled
above heenclosure. Headroom should allow
or
any
acousticreatment on the
ceiling.
Allow
space
fora
ifting
beam over he
length
of
he
generator
enclosure
(All
dimensions
n
mm)
Access
Requirement
Frequent
Commentary
Most enclosures have sufficient internal
space only
forroutine
maintenanceand
minor
servicing. Space
requirementsmust
allow
fordismantling
he
enclosure
to
performmajor
workon the set.
JULY1996
127
*100
j90
80
<
70
60
50
40
30
20
10
0
caI
ange
0 100 200 300 400 500 600
700 800 900
1000
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 135/148
E4.4
Rotary Frequency
Convertors
-
Space
Details and
Summary
of
Space
Requirements
Access
Requirements
x
Frequent
F
=
a
C"
F
0
0
Headroom
Units over
100kVA
may
have
controlpanelsup
p
2200highand will
require
3000 minimum
headroom for
bottom
ntry
units and 3500
for
op
entry.
(All
dimensions
n
mm)
x
Commentary
Dimensions
marked
X
depend
on the
requirement
or side
or
rearaccess. Where
side orrearaccessis
necessary
allow 690 minimum.
A
minimum
space
of900 should be
provided
onallsides of
motor-generators
and
between
he
motor
generator
and he
open
cabinetdoors.
Cables
to the
motor-generator
should
be run
infloortrenches
or
ducts.Trench
covers should
be
strongenough
to
support
he
weight
of
any
iftinggear
or
trolleys.
128 JULY1996
Space Requirements
Section 5
Component Requirements
x
900
900
900
900
35
30
25
20
15
10
5
00
-
—
-
-
ypical
Range
-
100 200 300 400 500
600
700
Rotary
convertor
apacity
kVA)
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 136/148
Space Requirements
6
Design
Certificates
The
Design
Certificates described in thisSection
provide
a
systematic approach
to establish
compliance
of
a
design
or installationwith
a
minimum
provision
of
access
and
space
for
services.
The
Design
Certificate is a
quality
assurance
ool
whichwill ensurechecks have been carried out on access
and
space
allowances.
Compliance
willbeestablishedwiththe
completion
of he checklists'
at
outline
and
detail
design
stagesof he
project,
with
a
final
check
at
handover.
Thechecklists and their use are described
below.
The
Design
Certificates should
certify
that thechecklist items are accounted for.
Any
deviations should
be
explained
and
be
fully
riskassessed.
6.1
CHECKLISTS
Theselistsare to
ensure
that the
principles
embodied
in
the FunctionalGuide
are
fully recognised
and aken intoaccount to
provide
a
simple
method of
recording compliance. Specimenchecklists
are
shown
in
Annexe
A.
6.1.1 Outline
Design Stage
At theOutline
Design Stage
it is
ntended
hat
consideration
is
given
to overall
adequatespace
forserviceswithinthe
ranges
indicatedwithinthisdocument
and/or other
published
documents.
Thus the checklist records that
acknowledgement
has been made
of
he
space
requirements
of
he
particular
nstallation.
Itisthe
responsibility
of
he
Project Manager
o
complete
the
Design
Certificate
with
reference
to this
Guide
to
verify
a
minimum
standard of
access
and
space
hasbeen built into the outline
design.
6.1.2
Detail
Design
Stage
At
the
Detail
Design
Stage
the
particular
checklist
provides
certification
that
sufficient
space
has
been
allocated
to enable
plant
to
be
placed
n
position
and
connected
safely;
that
sufficient
space
has
been
designed-in
tofacilitatesafe and
progressivetesting
and
commissioning,
andthat the
spaces
around all itemsof
equipment forming
the installationsaresafe foraccessandsufficient for all
maintenance
ctivities
necessary
for the installations.
JULY1996
129
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 137/148
Space Requirements
Section 6
Design
Certificates
It s he
responsibility
of he
Project Manager
o
complete
the
Design
Certificate
withreference to thisGuideto
verify
aminimum standardofaccess and
space
has been built into the detail
design.
6.1.3
Handover
Stage
The
Handover
StageSpace
Allowance checklist
comprises
anitemised
coverage
of
required
access
and
maintenance
spaces
and
isto be
used
toconfirmthat
the
provisions
made are
acceptable
in
every
instance and detailto the
person
responsible
for
takeover of
he
installations
on behalfof he
client.
Thischecklist alsoforms acertificate of
conformity
with all
space
allowance
requirements
and
should
be
counter-signed
by
the
Project Manager.
6.1.4
Records
Copies
of
all
checklists should
be
incorporated
into
the
Health
and
Safety
File
(CDM
Regulations R4,
see
Section
2.2)
and located
as directed
by
the
Project
Manager.
130
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 138/148
Space
Requirements
Annexe
A
-
Installation Checklists
This .Annexe
presents
specimen
checklists referred to in Section
6
of his
report.
JULY1996
131
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 139/148
Space Requiremenis
Annexe A Installation Checklists
OUTLINE DESIGN
STAGE
SPACE REQUIREMENTCHECKLIST
Item
Checked
Comments
Plant/switch
rooms
disposition
access
egress/escape
space
allowance
External services
underground
drainage
services trench
routes
accessibility
meter
room/sub-station locations
Distribution
ceiling space
verticalriser
allocation
riser
disposition
duct
entries
Signature
Role/Authority
132
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 140/148
Space Requirements
Annexe A Installation Checklist
DETAIL DESIGN STAGESPACE REQUIREMENTCHECKLIST
Function Checked Comment
Plantlswitchrooms
disposition
access
egress/escape
space
allowance
maintenance
pace
requirements
manufacturer's
pace requirement
plant
emoval and
replacement
routes
multi-service co-ordination
provisions
Distribution
riser
disposition
riser access
ceiling
void
space
ceiling
void access
maintenance
ccess
into
ceiling
void
plant
and
equipment
removal
multi-service
co-ordination
provisions
Signature Role/Authority
JULY1996 133
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 141/148
Space Requirements
Annexe
A
Installation Checklist
HANDOVERSTA6E SPACE ALLOWANCECHECKLIST
Function Checked Comment
Boiler
room
access allowance
egress/escape
manufacturer's maintenance llowances
burner
access
tube
cleaning
allowance
flue
cleaning space
plant removallreplacement
drainageprovisions
Control
panels
panel
clearance
noobstructions over
Pipework
nstallation
pipe
replacement
instrument/sensor
withdrawal
space
valveactuator withdrawal
pace
strainer basket
removal
space
Ductwork nstallation
instrument/sensorwithdrawal
space
damper
actuator
withdrawal
space
duct
heater/cooler
battery
access
manual
damper
access
fire
damper
access
Air
handling
plant
installation
damper
access
filter
access andremoval
space
heater/cooler
cleaning
access
space
heater/cooler removal
space
fan
access
Fuel
storage
installation
oil resistant
tankingall-round access
outflow
heater
withdrawal
pace
filter basketremoval
space
Water
storage
and
treatment
installation
waterproof
containment
all-round access
immersion heater removal
space
water
level controller's access
drainageprovisions
all-round
access
to
water
softener
salt
storageprovisions
salt
handling
equipment
134 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 142/148
Space Requirements
Annexe A Installation Checklist
HANDOVERSTAGE SPACEALLOWANCECHECKLIST
continued)
Function Check Comment
Pumps
accesstomotor
motorremoval
space
impeller
emoval
space
complete
removal
space
Pressurisation
equipment
accessallround
accessto
spill
tank
level controls
pump
emoval
space
nitrogen
cylinder storage
Fan
coil
units/VAV
erminal units
accommodation n
ceiling space
maintenance ccess
provisions
for
removallreplacement
location
marking
-
position/type
Ancifiary
equipment requirements
removal
space
allowancefor:
pipeline
hermometers
pipelinepressure
gauges
pipeline
controls sensors
motorised
valve
actuators
motorised
damper
actuators
pipeline
strainer
baskets
duct
-
mounted
instruments
duct
-
mounted sensors
space
for
draining
-
down
provision
for
drainage
near
to
drain
points,storage
tanks and other containers
HIT
switchgear
-
ndoor
access allowance
egress/escape
withdrawal
space
for circuit breakers
clearance
with
circuit
breakers
withdrawn
floor finish suitablefor
switchgear
truck
accesstoVTs
and
cable
termination
boxes
removal
space
forVTs
coverson loor trenches
no intrusion
by
other
services
(especially
wet)
JULY1996 135
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 143/148
Space Requirements
AnnexeA Installation Checklist
HANDOVERSTAGE SPACEALLOWANCECHECKLIST
(continued)
Function
Check Comment
Cast
resin and
dry
ype
transformers
access allowance
egress/escape
draw out
space
for transformers
floor
finish suitable
for transformer
wheels
or
rollers
access tocable
termination
boxes
coversonfloor trenches
no intrusion
by
other
services
(especially
wet)
Indoor substations
witheast
resin
or
dry
ype
transformers
(inc
packaged
substations)
as above
plus
space
for
ring
main unit
operating
handles
clearances aroundHV and LV
switchgear
Compounds
oroil filled transformer
access allowance
access tocable
termination
boxes
clearance around
any
drain
pipes,
conservators,
Buchholz
relays,
etc
size ofoilcatch
pit
Substations
with
oil
ifiled
transformers
as
above
plus
space
for
ring
main unit
operating
handles
clearances aroundHVand LV
switchgear
Ring
mainunits
access allowance
access
tocable terminationboxes
space
for
ring
main unit
operating
handles
LV
switchboards
access allowance
access tocable
termination
boxes
clearance with doors
open
orcircuit
breakers
withdrawn
(if
applicable)
no intrusion
by
other services
(especiallywet)
136
JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 144/148
Space Requirements
Annexe A
Installation Checklist
HANDOVERSTAGESPACE ALLOWANCECHECKLIST
(continued)
Function Check
Comment
UPS
-
staticand
rotary
/
frequency
convertors
as
LV
switchboards
plus
drawout
space
for
transformersor
integral
motor
generator
floor finishsuitablefor
transformer
wheels
or
rollers
coversonfloor trenches
no intrusion
by
other services
(especially
wet)
Battery
rooms
access
allowance
cells
at
suitable
height
for
checking
electrolyte
level/toppingup
rear ofcells visible
protective clothing
and
safetyequipment
Rotating machinery
-
generating
sets
access
allowance
egress/escape
clearance
with circuitbreakers
withdrawnor
panel
doors
open
covers
on
floor
trenches
guards
in
place
access to
routinemaintenance tems
(filtersetc)
access
to batteries
access to inlet
air
louvres
access
aboveset for
disassembly
or
overhaul
Control
panels
asLV
swithboards
plus
controlsand
nstruments
atcorrect
height
Signature
Role/Authority
JULY1996
137
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 145/148
Space Requirements
Annexe
B
-
Change Suggestion
Form
If
you
have
any
comments onthisdocument
please
fillin
a
photocopy
of heform
opposite
and send
it
o
DEO(W).
Please donotuse the shadedsectionsof he
form.
138 JULY1996
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 146/148
Space Requirements
Annexe B
Change Suggestion
Form
CHANGE
SUGGESTIONFORM
DEFENCE
ESTATE
ORGANISATION
(WORKS)
St
George's
Barracks
Blakemore Drive
Sutton
Coldfleld
B75
7RL
Change Sug,
SpaceRequirements
for Plant
Access,
Operation
&
Monitoring
stion
Form
Originator: Date:
Ref:
Change
Suggestion:
Section:
Page:
Change
Detail:
Continuation
Sheet
ncluded ? Y/N
Reason:
Continuation
Sheet
ncluded ? Y/N
DEO(W)
Review
Action:
Ref:
Action Date:
Approved:
Actioned:
JULY1996
139
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 147/148
Printed
n
he United
Kingdom
for IMSO
Dd301374 9/96C19G559 10170
\UO
7/23/2019 Space Requirement
http://slidepdf.com/reader/full/space-requirement 148/148