Maine Department of Transportation Work Plan for Calendar Years 2014-2015-2016
Work Plan Town Report 1 January 8, 2014
South Portland
This report shows the 2014-2016 Work Plan entries for South Portland. The costs listed are the total cost of
these projects – some of which may extend into neighboring towns. It also shows a listing of maintenance
work specifically recorded to South Portland in 2013, as well as any 2013 Local Road Assistance payments.
Activities that are managed on a larger scale, such as snow & ice control, and maintenance work done by
contract are not listed. The maintenance accomplishments may also extend into neighboring towns, but are
listed in the first town where the work was reported. Finally, any capital projects that were completed in 2013
are also listed.
Planned Capital and Maintenance Work 2014-2016Work Plan Year: 2014Municipalities(s): South PortlandAsset(s): Bill Vachon Drive
Description: Beginning at Carver Boulevard and extending 0.05 of a mile to Main Street, and 378' of Ramp towards I-295 -PACTS sponsored.
ID020242.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority2
Estimated Funding$40,000
Work Plan Year: 2014Municipalities(s): South PortlandAsset(s): Market Street
Description: Beginning at Waterman Drive and extending north 0.19 of a mile to Ocean Street - PACTS sponsored.
ID020299.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority5
Estimated Funding$113,600
Work Plan Year: 2014Municipalities(s): South PortlandAsset(s): Cottage Road
Description: Beginning at Broadway and extending 0.26 of a mile to Ocean Street - PACTS sponsored.
ID020257.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority5
Estimated Funding$192,500
Work Plan Year: 2014Municipalities(s): South Portland, PortlandAsset(s): Route 9
Description: Beginning 0.68 of a mile north of Long Creek Drive extending northerly 0.78 of a mile to Route 22.
ID020287.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority2
Estimated Funding$257,900
Work Plan Year: 2014Municipalities(s): South PortlandAsset(s): Stanford Street
Description: Beginning at Henley Street and extending 0.06 of a mile to Broadway Street - PACTS sponsored.
ID020310.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority5
Estimated Funding$43,900
Work Plan Year: 2014Municipalities(s): South PortlandAsset(s): Broadway
Description: Install second traffic control cabinet at Waterman Drive - PACTS sponsored.
ID020560.00
Scope of WorkHighway Safety and Spot Improvements
Highway Corridor Priority3
Estimated Funding$50,000
Work Plan Year: 2014Municipalities(s): South Portland, PortlandAsset(s): Casco Bay Bridge
Maine Department of Transportation Work Plan for Calendar Years 2014-2015-2016
Work Plan Town Report 2 January 8, 2014
Description: Seal sidewalk on Casco Bay Bridge (No.5900) that crosses Fore River.
ID021127.00
Scope of WorkMaintenance - Bridge/Structures
Highway Corridor Priority3
Estimated Funding$78,000
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): Eastern Trail
Description: Bicycle and Pedestrian Improvements along Old Bog Road. Beginning at Gary L. Maietta Way in SouthPortland and extending to Pond View Drive in Scarborough - PACTS sponsored.
ID019426.00
Scope of WorkBicycle/Pedestrian
Highway Corridor PriorityN/A
Estimated Funding$189,300
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): Route 1
Description: New multi-use path from Broadway Street and extending 0.7 of a mile to Veterans Memorial Bridge (No. 3945)over Fore River - PACTS sponsored.
ID020548.00
Scope of WorkBicycle/Pedestrian
Highway Corridor Priority1
Estimated Funding$301,100
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): I-295 Ramp 5/Red Brook Br
Description: Restore Aquatic Organism passage in Red Brook at Interstate-295 Ramp 5/Red Brook Bridge (No. 6284).
ID020535.00
Scope of WorkBridges Other
Highway Corridor Priority1
Estimated Funding$86,000
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): Route 1
Description: Beginning 0.04 of a mile south of Maine Turnpike On Ramp and extending northerly 0.08 of a mile.
ID022542.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority1
Estimated Funding$250,000
Work Plan Year: 2015-16Municipalities(s): South Portland, ScarboroughAsset(s): Cummings Road
Description: Beginning at Payne Road and extending northerly 0.5 of a mile.
ID022530.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority3
Estimated Funding$300,000
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): Route 1
Description: Beginning at Broadway and extending northerly 0.06 of a mile.
ID022547.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority1
Estimated Funding$145,000
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): Route 1
Description: Beginning 0.03 of a mile south of Memory Lane and extending northerly 1.02 miles.
ID022534.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority1
Estimated Funding$664,000
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): Maine Turnpike Approach
Description: Beginning at Payne Road and extending easterly 3.68 miles, includes both eastbound and westbound lanes.
Maine Department of Transportation Work Plan for Calendar Years 2014-2015-2016
Work Plan Town Report 3 January 8, 2014
ID020273.00
Scope of WorkHighway Preservation Paving
Highway Corridor Priority1
Estimated Funding$2,494,000
Work Plan Year: 2015-16Municipalities(s): South PortlandAsset(s): Maine Turnpike Approach
Description: Beginning at Western Avenue and extending westerly 1.90 miles.
ID022520.00
Scope of WorkHighway Safety and Spot Improvements
Highway Corridor Priority1
Estimated Funding$600,000
Local Road Assistance – Fiscal Year 2013 $356,222
Maintenance Accomplishments – 20131.00 Drainage Structures Repaired
541.00 Linear Feet of Shoulder Rebuilt
32.78 Shoulder Miles of Mowing
33.71 Miles of Striping Applied
16.00 Minor Sign(s) Installed or Maintained
5.20 Ton(s) of Cold Patch Applied
13.90 Shoulder Miles of Sweeping
300.00 Linear Feet of Brush Removed
3.00 Emergency Event Responses
66.17 Shoulder Miles of Litter and Debris Removal16.00 Linear Feet of Bridge Joints Repaired or Replaced
3.00 Bridge(s) Washed
100.00 Linear Feet of Guardrail or Fence Maintained
6.00 Trees Removed
Completed Capital Projects – 2013 019091.00 SO. PORTLAND, CUMMINGS ROAD Highway Reconstruction: Beginning at Running Hill Road and
extending northerly 0.73 of a mile to the Westbrook town line. 019098.00 SO. PORTLAND, BROADWAY Highway Resurfacing: Beginning at Cottage Road and extending
northeasterly 1.14 miles to Pickett Street. 016788.00 SCARBOROUGH-FALMOUTH, I-295 NB Highway Resurfacing: Beginning approximately 400 feet
northerly of the MTA toll booth and extending northerly 7.82 miles to the Portland - Falmouth town line. 019084.00 SO. PORTLAND, RUMERY ST. Highway Resurfacing: Beginning at Route 1 and extending northerly
0.57 of a mile to Dartmouth Street. 019097.00 SO. PORTLAND, DARTMOUTH ST. Highway Resurfacing: Beginning at Rumery Street and extending
easterly 0.23 of a mile.019117.00 PORTLAND, INTERNAT'L PKY Highway Resurfacing: Beginning at Congress St. and continuing for 0.42
of a mile to .06 miles southerly of Jetport Blvd. Jetport Blvd: Extending 0.05 of a mile to the intersection ofInternational Parkway, for a total of 0.47 of a mile.
017929.10 PORTLAND 295 BR DECK SEC 2 Continuation of Bridge deck paving, joint work and guardrailattachments in Portland and South Portland on 12 bridges.