3/26/2018 SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4 (TR-4) | Department of Public Works and Highways http://www.dpwh.gov.ph/dpwh/PPP/projs/TR4 1/2 (/dpwh/) SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4 (TR-4) Project Description: A new four (4)-lane toll road from Sto. Tomas, Batangas to Tayabas/Lucena City in Quezon, 56.87 kms. long The revised alignment is divided into five (5) packages as follows: SECTIONS LENGTH (km) Package A: Calamba to Makban, Laguna 11.32 Package B: Makban to San Pablo, Laguna 12.12 Package C: San Pablo to Tiaong, Quezon 7.50 Package D: Tiaong to Candelaria, Quezon 15 Package E: Candelaria to Tayabas, Quezon 10.93 Project Objectives: This project aims to: improve the transport of goods and services from Southern Provinces to Manila and vice versa. shorten travel time, decongest, and reduce the volume of traffic plying the Pan Philippine Highway. enhance the economic efficiency of the existing South Luzon Expressway (SLEX), allowing to meet the increasing demand of traffic volumes due to the rapid growth of population, urbanization, and economic development of Quezon Province and adjoining provinces. Project Benefits: At the end of construction, the project is expected to: efficiently move people, products/goods and services to and from Laguna, Batangas, Quezon, and Bicol Region. reduce travel time along the 58-kilometer stretch between Sto. Tomas and Lucena from 4 hours to 1 hour. provide the motorists with safer and more convenient travel on modern tollway facilities like well-lit toll plazas, fiber optics, and CCTV cameras, among others. Project Concessionaire: South Luzon Tollways Corporation (SLTC) DPWH

SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4 …...enhance the economic efficiency of the exist ing South Luzon Expressway (SLEX), allowing to meet the increasing demand of traffic volumes

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4 …...enhance the economic efficiency of the exist ing South Luzon Expressway (SLEX), allowing to meet the increasing demand of traffic volumes

3/26/2018 SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4 (TR-4) | Department of Public Works and Highways

http://www.dpwh.gov.ph/dpwh/PPP/projs/TR4 1/2

(/dpwh/)

SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4(TR-4)

Project Description:

A new four (4)-lane toll road from Sto. Tomas, Batangas to Tayabas/Lucena City in Quezon, 56.87 kms. long The revised alignment is divided into five (5) packages as follows:

SECTIONS LENGTH (km)Package A: Calamba to Makban, Laguna 11.32Package B: Makban to San Pablo, Laguna 12.12Package C: San Pablo to Tiaong, Quezon 7.50Package D: Tiaong to Candelaria, Quezon 15Package E: Candelaria to Tayabas, Quezon 10.93

Project Objectives:

This project aims to:

improve the transport of goods and services from Southern Provinces to Manila and vice versa.

shorten travel time, decongest, and reduce the volume of traffic plying the Pan Philippine Highway.enhance the economic efficiency of the existing South Luzon Expressway (SLEX), allowing to meet the increasing demand of traffic volumes due to the rapid growth of population, urbanization,

and economic development of Quezon Province and adjoining provinces.

Project Benefits:

At the end of construction, the project is expected to:

efficiently move people, products/goods and services to and from Laguna, Batangas, Quezon, and Bicol Region.reduce travel time along the 58-kilometer stretch between Sto. Tomas and Lucena from 4 hours to 1 hour.provide the motorists with safer and more convenient travel on modern tollway facilities like well-lit toll plazas, fiber optics, and CCTV cameras, among others.

Project Concessionaire:

South Luzon Tollways Corporation (SLTC)

DPWH

Page 2: SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4 …...enhance the economic efficiency of the exist ing South Luzon Expressway (SLEX), allowing to meet the increasing demand of traffic volumes

3/26/2018 SOUTH LUZON EXPRESSWAY (SLEX) TOLL ROAD 4 (TR-4) | Department of Public Works and Highways

http://www.dpwh.gov.ph/dpwh/PPP/projs/TR4 2/2

Project Cost: P 13.10 Billion

Project Status:

DPWH ROW Team in placeOngoing alignment reconnaisance, ground survey and staking works for Packages A and B.

Ongoing

Project Alignment:

Project Timeline:

ACTIVITIES DATEIssuance of ECC by DENR 14 July 2014Construction Schedule June 2017 – August 2021

Package A: Calamba to Makban, Laguna 01 June 2017 – 25 August 2018Package B: Makban to San Pablo, Laguna 26 February 2018 – 20 August 2019Package C: San Pablo to Tiaong, Quezon 23 November 2018 – 18 November 2019Package D: Tiaong to Candelaria, Quezon 20 August 2019 to 10 February 2021Package E: Candelaria to Tayabas, Quezon 16 May 2019 to 09 August 2021