22
Sonderen Road Extension Revised 4/19/2021 Sponsor O'Fallon Project No. 21-000015 Project Type New Road TOTAL FUNDING Total County Sponsor Federal Other $2,695,041.22 $1,290,872.67 $234,704.12 $0.00 $1,169,464.43 Project Description This application consists of the proposed construction of a new portion of Sonderen Road in O'Fallon, MO. The limits of the project are from the intersection of Sonderen Road and Eggering Drive (where Sonderen currently terminates) and the intersection of Main Street and Third Street. This new roadway will extend approximately 1900 feet north and west from the existing terminus. A development for the existing property currently controlled by St. Mary's has been proposed to the City. In conjunction with this development, an extension of the existing Sonderen Road has been proposed such that it would make a direct connection between Main St. and Sonderen Road. Sonderen would serve as a complimentary pathway through the area for motorists traveling through this portion of the City. The proposed roadway is not considered part of, but will complement the proposed development. The proposed improvements will provide for an efficient and alternate route for vehicles traveling along Main St. to access the I70 interstate system. The scope of this project will include the following: (1) construct a new portion of Sonderen Road, beginning at Eggering Drive and connection with Main St. and the Third Street signalized intersection; (2) construct new pedestrian facilities, which will connect into existing facilities where possible, along the Sonderen Road extension for the existing and proposed residential and commercial properties and provide a pedestrian connection along Main St to a major City Park destination; (3) address drainage/stormwater concerns by replacing some existing infrastructure and installing new infrastructure to alleviate those issues.

Sonderen Road Extension - sccmo.org

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Sonderen Road Extension Revised 4/19/2021

Sponsor O'Fallon Project No. 21-000015

Project Type New Road

TOTAL FUNDING

Total County Sponsor Federal Other

$2,695,041.22 $1,290,872.67 $234,704.12 $0.00 $1,169,464.43

Project Description This application consists of the proposed construction of a new portion of Sonderen Road in O'Fallon, MO. The

limits of the project are from the intersection of Sonderen Road and Eggering Drive (where Sonderen currently

terminates) and the intersection of Main Street and Third Street. This new roadway will extend approximately 1900

feet north and west from the existing terminus.

A development for the existing property currently controlled by St. Mary's has been proposed to the City. In

conjunction with this development, an extension of the existing Sonderen Road has been proposed such that it would

make a direct connection between Main St. and Sonderen Road.

Sonderen would serve as a complimentary pathway through the area for motorists traveling through this portion of the

City. The proposed roadway is not considered part of, but will complement the proposed development. The proposed

improvements will provide for an efficient and alternate route for vehicles traveling along Main St. to access the I70

interstate system.

The scope of this project will include the following: (1) construct a new portion of Sonderen Road, beginning at

Eggering Drive and connection with Main St. and the Third Street signalized intersection; (2) construct new

pedestrian facilities, which will connect into existing facilities where possible, along the Sonderen Road extension for

the existing and proposed residential and commercial properties and provide a pedestrian connection along Main St to

a major City Park destination; (3) address drainage/stormwater concerns by replacing some existing infrastructure and

installing new infrastructure to alleviate those issues.

4/1/2021 Permit Detail

https://www2.citizenserve.com/Admin/PermitController 1/1

Road Board Application PROJECT INFORMATIONPermit #: RB21-000015 Project Type: New RoadName: Sonderen Road ExtensionLimits: Intersection of Main St. / Third Street and the intersection of Sonderen / Eggering DriveLane Miles: 1Federal Functional Classification: 3 - Major CollectorAnticipated useful life of the proposed improvements (years): 35 Estimated date of completion: 12/31/2024

New Road InformationTraffic Volume ADT: Construction Year: 2500 Future

PROJECT DESCRIPTIONThis application consists of the proposed construction of a new portion of Sonderen Road in O'Fallon, MO. The limits of the project are from the intersection of Sonderen Road and Eggering Drive (whereSonderen currently terminates) and the intersection of Main Street and Third Street. This new roadway will extend approximately 1900 feet north and west from the existing terminus.

A development for the existing property currently controlled by St. Mary's has been proposed to the City. In conjunction with this development, an extension of the existing Sonderen Road has been proposedsuch that it would make a direct connection between Main St. and Sonderen Road.

Sonderen would serve as a complimentary pathway through the area for motorists traveling through this portion of the City. The proposed roadway is not considered part of, but will complement the proposeddevelopment. The proposed improvements will provide for an efficient and alternate route for vehicles traveling along Main St. to access the I70 interstate system.

The scope of this project will include the following: (1) construct a new portion of Sonderen Road, beginning at Eggering Drive and connection with Main St. and the Third Street signalized intersection; (2)construct new pedestrian facilities, which will connect into existing facilities where possible, along the Sonderen Road extension for the existing and proposed residential and commercial properties and providea pedestrian connection along Main St to a major City Park destination; (3) address drainage/stormwater concerns by replacing some existing infrastructure and installing new infrastructure to alleviate thoseissues.

CONTACT INFORMATIONSponsoring Agency: City of O'FallonContact Person Name: Anthony FriedmanTitle:Telephone Number: (636) 379-5492E-mail Address: [email protected]

SIGNATURE

____________________________________ ____________________ signature date

04/15/21

Planning & DevelopmentGeographic Information SystemsO'Fallon, Missouri µ

9,000 0 9,0004,500 Feet

Thoroughfare Plan MapExisting Road Classifications (April 2019)

M:\Maps\Data For Planning\Comprehensive Plan Maps\2019 Updates\Map 12 - Thoroughfare Plan Map - Existing Road Classifications.mxd

Printed: 4/17/2019

LegendRail Road

Road_Classifications_Arterial

Road_Classifications_Minor_Arterial

Road_Classifications_Collector

Road_Classifications_Freeway

Residential Streets

O'Fallon City Limits

PROJECT LOCATION MAP

Project Location

ST. CHARLES COUNTY ROAD BOARD

2022 - 2024 TIP FINANCIAL WORKSHEET

County Sponsor Federal Other Total

Design $0.00 $0.00 $0.00 $132,000.00 $132,000.00

Utility Relocations $0.00 $0.00 $0.00 $0.00 $0.00

Right-of-Way $0.00 $0.00 $0.00 $216,000.00 $216,000.00

Construction $1,290,872.67 $234,704.12 $0.00 $821,464.43 $2,347,041.22

TOTAL $1,290,872.67 $234,704.12 $0.00 $1,169,464.43 $2,695,041.22

PERCENT (%) 47.90% 8.71% 0.00% 43.39% 100.00%

Design County Sponsor Federal Other Total

2022 $132,000.00 $132,000.00

2023 $0.00

2024 $0.00

Utility Relocations County Sponsor Federal Other Total

2022 $0.00

2023 $0.00

2024 $0.00

Right-of-Way County Sponsor Federal Other Total

2022 $216,000.00 $216,000.00

2023 $0.00

2024 $0.00

Construction County Sponsor Federal Other Total

2022 $0.00

2023 $1,290,872.67 $234,704.12 $821,464.43 $2,347,041.22

2024 $0.00

(55% construction) (10% construction) (35% construction)

FUNDING FOR IMPROVEMENTS

FINANCIAL PLAN

Revised 4/19/2021

CITY'S ESTIMATE - CITY OF O'FALLON, MISSOURI4/15/2021

NO. TOTAL CONSTRUCTION COST-SONDEREN UNIT QUANTITY UNIT COST TOTALREMOVAL OF IMPROVEMENTS LS 1 $150,000.00 $150,000.00CLEARING AND GRUBBING LS 1 $15,000.00 $15,000.00SAWCUT (ANY DEPTH/MATERIAL) LF 350 $3.00 $1,050.00LINEAR GRADING, CLASS 1 STA 18.2 $100.00 $1,820.007" CONCRETE PAVEMENT SY 7,575 $80.00 $606,000.006" VERTICAL CURB LF 6,701 $18.00 $120,618.004" CONCRETE TRAIL SY 1,934 $50.00 $96,700.004" CONCRETE SIDEWALK (WITH AGGREGATE BASE) SY 1,162 $50.00 $58,100.00CURB RAMP (7" THICK) SY 12 $150.00 $1,800.00TRUNCATED DOMES SF 345 $35.00 $12,075.004" TYPE 5 AGGREGATE BASE SY 11,130 $7.00 $77,910.00STAMPED CONCRETE (MEDIANS) SY 277 $55.00 $15,235.00STANDARD STREETLIGHTS EA 17 $3,500.00 $59,500.0012" CLASS III RCP LF 100 $75.00 $7,500.0024" CLASS III RCP LF 1,958 $90.00 $176,220.0024" CLASS III RCP (DETENTION BASIN OUTFALL) LF 20 $120.00 $2,400.00DOUBLE CURB INLET EA 2 $4,000.00 $8,000.00SINGLE CURB INLET EA 9 $2,500.00 $22,500.00AREA INLET EA 1 $2,500.00 $2,500.0012" FLARED END SECTION EA 1 $1,500.00 $1,500.0024" FLARED END SECTION EA 1 $3,500.00 $3,500.00STORM MANHOLE EA 9 $2,500.00 $22,500.00MISC STORM SEWER INLET REPAIR LS 1 $2,000.00 $2,000.00DETENTION BASIN OUTFALL EA 1 $2,500.00 $2,500.00DETENTION BASIN/LANDSCAPING LS 1 $75,000.00 $75,000.00RETAINING WALL/DETENTION BASIN SF 1,400 $35.00 $49,000.00CONNECT EXISTING PIPES TO NEW STRUCTURE LS 1 $5,000.00 $5,000.00SANITARY MANHOLE EA 11 $2,000.00 $22,000.008" SANITARY SEWER PIPE LF 1,750 $65.00 $113,750.006" SANITARY SEWER PIPE (LATERAL) LF 215 $58.00 $12,470.00CONNECT SANITARY SEWER TO EX. SEWER EA 1 $650.00 $650.00PVC CLEANOUT EA 2 $600.00 $1,200.008" WATER MAIN LF 2,163 $45.00 $97,335.00BLOW OFF VALVE EA 5 $1,000.00 $5,000.00CONNECT TO EXISTING WATERMAIN EA 2 $1,500.00 $3,000.00FIRE HYDRANT ASSEMBLY EA 6 $3,500.00 $21,000.008" X 8" X 6" TEE EA 5 $2,500.00 $12,500.00COMBO LIGHTING CONTROLLER AND POWER SUPPLY EA 1 $7,500.00 $7,500.00PULL BOX, PREFORMED CLASS 1 (LIGHTING) EA 8 $850.00 $6,800.00CABLE, 6 AWG. 2 CONDUCTOR, 1 BARE NEUTRAL (LIGHT CIRCUITS & 110v RECEPTACLE) LF 3,636 $1.25 $4,545.00CABLE, 10 AWG 1 CONDUCTOR, POLE AND BRACKET LF 1,700 $0.75 $1,275.002 INCH CONDUIT (TRENCH) (LIGHTING) LF 1,450 $5.75 $8,337.502 INCH CONDUIT (PUSHED) (LIGHTING) LF 300 $7.00 $2,100.00PERMANENT YELLOW PAVEMENT STRIPING (4" PAINT) LF 360 $1.50 $540.00PERMANENT WHITE PAVEMENT STRIPING (4" PAINT) LF 250 $1.50 $375.00PERMANENT WHITE PAVEMENT STRIPING (4" PAINT) (SKIP WHITE) LF 75 $1.50 $112.50PERMANENT WHITE PAVEMENT STRIPING (24" PAINT) (STOP BAR) LF 60 $4.50 $270.00PERMANENT PAVEMENT MARKING ARROWS (PAINT) EA 4 $750.00 $3,000.00PERMANENT SIGNS (STOP SIGNS WITH STREET NAME) SF 16 $100.00 $1,600.00CHANNELIZERS (TRIM LINE) EACH 42 $20.00 $840.00CHANGEABLE MESSAGE SIGN, (NOISELESS), RENTAL EA 1 $4,500.00 $4,500.00STANDARD TRAFFIC CONTROL DEVICES LS 1 $10,000.00 $10,000.00SOLAR POWERED PEDESTRIAN SIGNAL EA 4 $3,500.00 $14,000.00SODDING SY 12,180 $5.00 $60,900.00CONSTRUCTION INSPECTION AND TESTING LS 1 $25,000.00 $25,000.00CONSTRUCTION SURVEYING LS 1 $25,000.00 $25,000.00AS BUILT PLANS LS 1 $5,000.00 $5,000.00SILTATION CONTROL LS 1 $5,000.00 $5,000.00MOBILIZATION (3%) LS 1 $62,145.84 $62,145.84

TOTAL CONSTRUCTION COST-SONDEREN TOTAL $2,133,673.8410% CONTINGENCY $213,367.38

TOTAL CONSTRUCTION COST $2,347,041.22RIGHT OF WAY ACRE 2.16 $100,000.00 $216,000.00

DESIGN/SURVEY COST LS 1 $132,000.00 $132,000.00TOTAL COST $2,695,041.22

SONDEREN ROAD (MAIN STREET TO EGGERING DRIVE)

Revised 4/19/2021

Activity DescriptionStart Date

(MM/YYYY)

Finish Date

(MM/YYYY)

Time Frame

(Months)

Receive notification letter Oct-21 Oct-21 0

Execute agreement (project sponsor and DOT] Nov-21 Jan-22 3

Engineering services contract submitted and approved* May-21 Jun-21 1

Obtain environmentaI clearances (106, CE2, 7&E, etc.) Jul-21 Aug-21 2

Public meeting/hearing Sep-21 Oct-21 1

Develop and submit preliminary plans Jul-21 Sep-21 3

Preliminary plans approved Oct-21 Nov-21 2

Develop and submit right-of-way plans Nov-21 Dec-21 2

Review and approval of right-of-way plans Dec-21 Jan-22 1

Submit and receive approval for notice to proceed for

right-of-way acquisition (A-Date) *Jan-22 Feb-22 2

Right-of-way acquisition Feb-22 Feb-22 1

Utility coordination Mar-22 Apr-22 2

Develop and submit PS&E Apr-22 May-22 2

District approval of PS&E/advertise for bids* May-22 Jun-22 1

Submit and receive bids for review and approval Jul-22 Aug-22 1

Project implementation/construction Aug-22 Jan-23 6

PROJECT DEVELOPMENT SCHEDULE