CE POWER SOLUTIONS FAMILY OF COMPANIES
CE Power - Kentucky
CE Power - Florida
CE Power - Tennessee
Hope Engineering - Michigan
3rd Party NETA Independent Testing Companies
CE Power - Ohio
CE Power - Minnesota
www.cepower.net
800.434.0415
Client Type: Electric Utility
Challenge/Issue: Provide client with modern technology and interrupting capability replacing existing, within the confines of existing conditions
Equipment Involved: 15kV, 1200A and 2000A vacuum circuit breakers
Solutions: Design, build and install new units
Scope/Deliverables: Provide design engineering for retrofill circuit breakers to match existing switchgear with limited modification to bus work and breaker cradles
Timeframe: Approximately 6 weeks, including 2 week outage for installation
Solution ProfileSwitchgear Upgrade