Transportation Region/Bureau :
Bureau of Structures Solicitation ID : BOS-01
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Open
Anticipated Construction Cost :
N/A NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
31 Oct 2019
Project Purpose and Need :
Perform the annual Routine inspection and the Fracture Critical inspection of the Blatnik bridge, B-16-5, in accordance with the National Bridge Inspection Standards (NBIS), the Minnesota Department of Transportation Bridge and Structure Inspection Program Manual (BSIPM), the Wisconsin Department of Transportation (WisDOT) Structure Inspection Manual and the WisDOT Structure Inspection Field Manual.
Project Description : All inspections will be conducted in accordance with applicable standards and governing documents. All inspectors must be approved by the department prior to performing inspections; inspectors may be evaluated during the performance of inspections. It is anticipated that the consultant will need 10-12 inspectors. Department staff may accompany consultant inspection teams. All field work, including drone inspection, must be performed during July 2019.
Project ID Project Name Route County
0656-48-05 Blatnik Bridge IH 535 State Wide
Project ID(s)
Special Skills Certification License
Certified bridge inspector, or ability to gain WI certification.
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Staff performing inspection must meet requirements of National Bridge Inspection Standards.
A Certified Bridge Inspection Team Leader must be present at the bridge site at all times.
Staff using rope and rigging must have SPRAT or IRATA Level I, II or III certification.
SPRAT/IRATA Level I/II technicians must be under direct supervision of Level III technician.
Ability to perform non destructive testing.
Consultant Requirements ( Listed in approximate order of importance) :
Items
Underbridge inspection unit and operator.
Department Provides
Schedule Item Due Date
Submit an Inspection Work Plan for approval.
Approved work plans must be available on site.
Enter inspection reports in MN SIMS and WI HSI
Fracture Critical Inspection Report
Routine Inspection Report – Complex (Bridge B-16-5)
Schedule for Deliverables
Report Generated on 02/20/2019 3:47 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 2
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : For each proposed staff, please list specific role and current bridge inspection certifications. Equipment needed: 4 snoopers, lift. Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 3:47 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 2
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Bureau of Structures Solicitation ID : BOS-02
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Open
Anticipated Construction Cost :
N/A NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
01 Jul 2019 Anticipated Project Completion Date :
30 Jun 2021
Project Purpose and Need :
Perform bridge ratings and perform special projects to analyze existing structures for load carrying capacity. Analysis projects consist of highly complex analysis situations and partial structural system evaluations. Maintain manuals, in-house structural engineering applications, asset management systems and program management. Collect bridge field data with Unmanned Aerial System (UAS).
Project Description : Analysis may use finite element models of complex structures and may include structure monitoring or model building from in-field data. May assist maintaining manual; applications including structures software independent validation, producing structures program algorithms and MathCAD sheets; and asset management systems. May require the collection of bridge field data using Unmanned Aerial Systems (UAS) to support asset management and structures analysis and evaluation.
Master Group Id : March 2019 Complex Structural Analysis Master Group Type : Complex Structural Analysis, Evaluation, Rating, and Bridge Management
Consultants Requirements
Experience in bridge rating and structural analysis
Experience in finite element modeling
Experience with complex structural design and rating
Trouble shooting construction issues
Knowledge of the Department’s Structures (Bridge) Manual
Ability to design and rate structures in LRFD and LRFR
Consultant Requirements ( Listed in approximate order of importance) :
Items
Internal computer software may be provided if needed
Department Provides
Schedule Item Due Date
Complex structure analysis computations
Structure analysis of loads to partial systems
Review to produce finite element models of infield systems
Structure Rating for HL 93, HS-20 and oversize vehicles
Special Project analysis and analyzing in field data
LRFR, LFR, ASR Ratings and supporting documentation
Bridge Asset Management policy research and development
Computer spreadsheet/MathCAD creation and algorithms
Computer programs / edits to existing programs
Field data collected by Unmanned Aerial System (UAS)
Schedule for Deliverables
Report Generated on 02/20/2019 3:51 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Notification pertaining to DBE goals :
N/A
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Experience with structural design and rating of complex structures including curved bridges
Previous complex structural analysis
Three Dimensional Finite element analysis of bridge systems
Experience with bridge girder erection sequencing and procedures
Experience with bridge design and rating with AASHTO LRFD and LRFR
Experience with FHWA National Bridge Inventory System as related to In-service Bridge Inspections.
Experience with computer languages used in structural engineering software applications (C#, FORTRAN, and Java).
Experience with the use of Unmanned Aerial System (UAS) including agency coordination, operations, and UAS data post processing and management.
Special Skills/Certification License ( Listed in approximate order of importance) :
Experience with complex structural design and structure types, such as curved structural steel tub girders
Experience in structural software lifecycle development, production, testing, verification, and maintenance.
Experience with Bridge Inspection and Bridge Management information.
Experience with the use of Unmanned Aerial System (UAS)
Instrumentation and monitoring of structures
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 3:51 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Special Instructions : A consultant does not need to be able to provide all services listed above to be selected but should clearly indicate in the Notice of Interest Questionnaire which services it is able to provide for in-service structure or structures in process of development. Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 3:51 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Bureau of Planning and Economic Development
Solicitation ID : BPED-01
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Open
Anticipated Construction Cost :
N/A NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
01 Jul 2019 Anticipated Project Completion Date :
30 Jun 2021
Project Purpose and Need :
WisDOT requires assistance in data analysis and traffic forecasting consistent with Wisconsin corridor management principles and the transportation planning process as identified in 23 U.S.C.. Data collection through research may be involved. Data that might be analyzed includes traffic count data, the National Household Travel Survey data, and other trend data. Provide project management services and Benefit Cost Analysis for grant applications during alpha analysis.
Project Description : Improve data-driven forecasting and modeling techniques. Use survey data in travel demand models, complete further validation efforts, and corridor analysis. Conduct traffic forecasts, roadway analysis, turning movement forecasts and supplement data-driven tools with improved information. Special studies include research, data analysis, and technical reports on a variety of technical data-driven processes or procedures (including socio-economic trend data).
Master Group Id : March 2019 Traffic Modeling Services Master Group Type : Traffic Modeling Services
Consultant Requirements ( Listed in approximate order of importance) :
Items
Traffic forecasting protocols
Access to travel demand models
Access to regression analysis tools
Access to related inventory
Access to related guidance documents
Access to economic analysis tools
Department Provides
Schedule Item Due Date
Utilizing travel demand models
Utilizing microsimulation models
Utilizing regressions
Utilizing spreadsheet models
Analyzing travel behavior
Special corridor or asset/performance related studies
Evaluating data and methodological approaches
Update socio-economic, development and traffic count data
Developing performance measures to manage assets
Coordinating efforts with WisDOT region offices and MPOs
Documenting and compiling assumptions in reports
Conducting data analysis for long-range plan and program
Analyzing travel demand model and economic model data
Schedule for Deliverables
Report Generated on 02/20/2019 3:53 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
N/A
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Traffic data processing, analysis and data refinement/improvement
Traffic forecasting, traffic engineering and traffic analysis tools (regional to micro level analysis)
All phases of travel demand modeling and WisDOT’s traffic forecasting procedures
Citilabs® Cube® travel demand software, SAS, Microsoft® Excel®, Microsoft® Access®, and ESRI® ArcGIS® to manipulate and analyze data
Frequent communication (sometimes daily)
Ability to run meetings and the skills to collaborate (on-site) with others on short notice
Transportation data collection, processing, analysis and refinement/improvement
Innovative, inventive, clear, direct and logical analysis skills
Strong presentation, writing and consensus building skills
Ability to meet deadlines
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 3:53 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 3:53 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Northwest Region Solicitation ID : NW-01
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$4,000,000-$4,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
02 Aug 2021
Project Purpose and Need :
STH 46 is a minor arterial. The existing overlay has reached the end of its useful life and is showing signs of deterioration with alligator, longitudinal and transverse cracking and rutting. The existing paved shoulders are 3' wide, and have qualified for HSIP funds due to ROR crashes.
Project Description : The proposed improvement consists of 4-inch CIR with a 2-inch overlay. Pre-mill roadway 2-inches. Includes culvert rehabilitation, and guardrail, upgrades. Box culvert C-48-2333 will be rehabilitated. There will be minimal spot repair of curb and gutter in Deer Park, the pedestrian curb ramps will be updated and brought to current ADA standards. Widen shoulders to 5' paved and install rumble strips. This is 11.326 centerline miles STH 64 to Snow Street.
Project ID Project Name Route County
8072-00-00 CYLON - AMERY (8072-00-00) STH 046 POLK COUNTY, ST CROIX COUNTY
Project ID(s)
Items
Concept Definition Report
Base mapping
Utility contacts and task list
Traffic data, counts, projections
Crash rate data
Pavement design
Existing Right of Way Plats
As built plans
Access to project related documents/plans
Department Provides
Schedule Item Due Date
30% plans 01/01/2020 12:00 AM
Design Study Report 06/01/2020 12:00 AM
90% Plans 04/01/2021 12:00 AM
Draft PS&E 06/01/2021 12:00 AM
PS&E package 08/02/2021 12:00 AM
Field Survey, as needed
Pavement cores
Intersection lighting and lighting design
No records to display
Schedule for Deliverables
Report Generated on 02/20/2019 3:54 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification LicenseNo records to display
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge and experience with the environmental documentation and agency coordination required
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Electrical Engineering of Outdoor Electrical Distribution Systems
Consultant Requirements ( Listed in approximate order of importance) :
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 3:54 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 3:54 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Northwest Region Solicitation ID : NW-02
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$5,000,000-$5,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
31 Dec 2021
Project Purpose and Need :
STH 65 is a minor arterial. The existing pavement has reached the end of its useful life and is in need of rehabilitation.
Project Description : The proposed improvement is a 1.5-inch mill with a 2.5-inch HMA overlay. Spot lane repair, culvert work, guardrail, and other items necessary to complete the work are part of the project. Complete a concrete overlay on bridges B-48-10 and B-48-20. Structure B-48-10 will also include soffit repair and repainting. This is 14.98 centerline miles North Junction Jewell Street to USH 8.
Project ID Project Name Route County
8865-00-04 NEW RICHMOND - USH 8 (8865-00-04)
STH 065 POLK COUNTY, ST CROIX COUNTY
Project ID(s)
Consultant Requirements ( Listed in approximate order of importance) :
Items
Concept Definition Report
Base mapping
Utility contacts and task list
Traffic data, counts, projections
Crash rate data
Pavement design
As built plans
Access to project related documents/plans
Department Provides
Schedule Item Due Date
Utility and topographic surveys, as needed
Trans 220 coordination
Structure Survey Reports
30% plans 01/01/2020 12:00 AM
Design Study Report 06/01/2020 12:00 AM
90% Plans 04/01/2021 12:00 AM
Draft PS&E 06/01/2021 12:00 AM
PS&E package 08/02/2021 12:00 AM
No records to display
Schedule for Deliverables
Report Generated on 02/20/2019 3:56 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification LicenseNo records to display
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge and experience with the environmental documentation and agency coordination required
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 3:56 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 3:56 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southeast Region Solicitation ID : SE-01
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$25,000,000-$29,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
09 Sep 2019 Anticipated Project Completion Date :
15 Nov 2020
Project Purpose and Need :
Construction engineering for a freeway maintenance project with base patching, asphalt milling and paving, cable barrier, and bridge reconstruction.
Project Description : USH 41 from USH 41/45 split to Dodge County Line - work consists of removals, cable barrier, beam guard grading and shaping, HMA pavement, cable barrier type 1, cable barrier end terminal type 1, beam guard, storm sewer, pavement marking, permanent signing, traffic control, erosion control, restoration, bridge reconstruction, and all incidental items necessary to complete the work.
Project ID Project Name Route County
1107-00-71 USH 41 (1107-00-71) USH 041 WASHINGTON COUNTY
1100-27-70 USH 41 LOC STR MILWAUKEE COUNTY, WASHINGTON COUNTY, WAUKESHA COUNTY
1100-41-70 MILWAUKEE - FOND DU LAC (1100-41-70)
USH 041 WASHINGTON COUNTY
Project ID(s)
Consultant Requirements ( Listed in approximate order of importance) :
Items
Overall project management
Construction project leader
Staff engineer/inspector
Department Provides
Schedule Item Due Date
Finals documentation
Construction materials testing
Construction documentation
Construction inspection
Construction contract administration
Materials Technician
Construction inspectors
Construction assistant project leader
Survey and necessary equipment
Structural leader
Staff engineer/inspector
Office engineer/materials coordinator
Schedule for Deliverables
Report Generated on 02/20/2019 3:46 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Selected consultants will be required to apply field rate accounting consistent with FDM 8-10-20. If the selected consultant does not currently have field office accounting in place, the consultant will have the option of negotiating a field office rate that will act as an indirect cost ceiling for the contract in lieu of implementing field office accounting.
Basis of Payment Notification
Advertised Fixed Fee % : 6.75
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
HTCP - Transportation materials sampling technician (TMS)
HTCP - Portland cement concrete technician 1 (PCCTEC-I)
HTCP - Nuclear density technician 1 (NUCDENSITY-I)
HTCP - Aggregate testing for transportation systems (ATTS)
Materials Coordinators' Training - Department (MCT-D)
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Experience in Public Relations coordination in rural areas
Experience in coordinating with other staged Freeway Construction projects occurring along the corridor
Knowledge of WisDOT construction oversight procedures
Experience in staged freeway construction
Familiarity with specialized construction methods in regards to roadway projects
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 3:46 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
Debra Evers [email protected]
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will be conducted
Interview Information : Questions are provided below. At least eight (8) business days before the interview, short-listed firms will be provided specific interview time and location.
Interview Date : 22 Mar 2019
Interview Place : 141 NW Barstow Street, Waukesha, WI
Other Information : 2019 – Asst. PL, 0-1 Staff 2020- Asst. PL, Roadway Lead, Structures Lead, 1-2 Staff In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit. Please be prepared to answer the following questions during your interview: 1. Construction Inspection for Rural Freeway Maintenance Projects - What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 2. Interface with Project Manager, Project Controls, and Program Staff – What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 3. Construction Traffic Control and Traffic Coordination – What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 4. Construction Traffic Mitigation and Public Involvement – What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 5. Blended WisDOT/Consultant Construction Teams - What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 6. Innovation – What has your team applied in the past decade and what potential innovations could your team apply to improve efficiency, effectiveness, and/or quality for this project? Please provide details (scope; Department savings of cost and/or time) as well as noting those ideas not implemented.
Report Generated on 02/20/2019 3:46 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-01
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$8,000,000-$8,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
30 Nov 2022
Project Purpose and Need :
The roadway surface is aged and deteriorated with heavy cracking and rutting in the wheel tracks. The 4.5-inch asphaltic pavement was constructed in 1995. B-29-73 is 4 steel culvert pipes with concrete apron endwalls. The pipes are deteriorating with section loss.
Project Description : Replace the pavement. Begin the project 300' N of STH 21 at the existing pavement joint. Replace curb ramps as needed to meet ADA requirements. Replace B-29-73 with pipe. Remove US Fish and Wildlife parking area and bypass lane. Project includes railroad coordination. Project length is 15.9 miles. This is a perpetuation project.
Project ID Project Name Route County
1620-02-08 NECEDAH - BABCOCK STH 80 JUNEAU COUNTY
Project ID(s)
Consultant Requirements ( Listed in approximate order of importance) :
Items
Concept Definition Report
Crash rate data
Meta Manager information
Pavement design
Traffic data, counts, projections
Bridge as-built plans
Aerial Mapping and survey
As built plans
Existing Right of Way Plats
Department Provides
Schedule Item Due Date
Final Environmental Document 09/01/2020 12:00 AM
30% plans 09/01/2020 12:00 AM
Design Study Report 11/01/2020 12:00 AM
60% plans 11/01/2020 12:00 AM
DT1078 utility submittal 11/01/2020 12:00 AM
90% Plans 02/01/2022 12:00 AM
PS&E package 04/01/2022 12:00 AM
No records to display
Schedule for Deliverables
Report Generated on 02/20/2019 4:00 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Cost Per Unit
Actual Cost Plus Fixed Fee
Specific Rate
Special Skills Certification LicenseNo records to display
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Knowledge and experience with the environmental documentation and agency coordination required
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Experience in hydrologic analysis, hydraulic analysis and hydraulic modeling, including structure sizing.
Extensive experience with geometric layout of stream and grade separation structures
Experience with traffic control staging, design coordination and Traffic Management Plan development.
Experience with public involvement process, local official coordination and agencies coordination process
Ability to work with public and local officials
Good organizational and communication skills.
Experience with FDM design standards, WisDOT bridge Manual and the PSE process
Experience with agency coordination, including railroads
Knowledge of WisDOT FDM and PS&E process
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:00 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:00 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-02
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$4,000,000-$4,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
01 Aug 2022
Project Purpose and Need :
The purpose of this project is to improve the existing pavement of STH 60. The project is needed because the existing pavement is aged and deteriorated with cracking. The pavement has also been overlaid several times to extend the pavement’s usage. The proposed improvement is to mill and overlay the pavement, update curb ramps as needed, and replace guardrail end treatments as needed. The project length is approximately 11 miles. This is a perpetuation project.
Project Description : The project is in Crawford County and begins at Old Hwy 60 and continues easterly through the Village of Wauzeka to the west abutment of B-12-35, which is located just west of STH 131. In the rural sections, 2 inches of the pavement will be removed by milling and overlayed with 2.5 inches of HMA. In the urban section, 4 inches of the pavement will be removed by milling and overlayed wth 4 inches of HMA. Beam guard terminals will be upgraded to current standards.
Project ID Project Name Route County
5180-00-00 BRIDGEPORT - BOSCOBEL STH 60 CRAWFORD COUNTY
Project ID(s)
Consultants Requirements
Traffic Counts & Crash Data
Knowledge of WisDOT FDM and PS&E process
Demonstrated curb ramp design knowledge
Familiarity with design criteria – both with WisDOT’s Facilities Development Manual and the AASHTO Roadside Design Guide – for rural and urban roadways.
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience with utility coordination
Consultant Requirements ( Listed in approximate order of importance) :
Items
Traffic Counts & Crash Data
High Resolution Orthography
Bare Earth Lidar Data
Title Searches
Department Provides
Schedule Item Due Date
Environmental Document (PCE) 08/01/2020 12:00 AM
DSR, Plat, 1078s 09/01/2020 12:00 AM
PSE 09/01/2022 12:00 AM
Pre-PSE Review 07/01/2022 12:00 AM
No records to display
Schedule for Deliverables
Report Generated on 02/20/2019 4:02 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification LicenseNo records to display
Special Skills/Certification License ( Listed in approximate order of importance) :
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:02 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:02 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-03
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$4,000,000-$4,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
01 Aug 2022
Project Purpose and Need :
Project Description :
The purpose of this project is to improve the pavement of STH 80 and complete repairs to structures B-62-0030 and B-62-0031. The project is needed because the pavement surface is aged and deteriorated with extensive cracking. Structure B-62-0030 and B-62-0031 have spalls and cracks in the concrete slabs along with the railing that also have cracks and spalls with exposed rebar. B-26-0030 SE and NE wing walls have spalls with exposed rebar. Perpetuation project to replace the existing pavement.
The project begins at CTH C in Vernon County and continues northerly to the south abutment of South Fork Baraboo River Bridge located just outside of Hillsboro. The pavement treatment will consist of milling off 2 inches of the existing asphalt and overlaying with 3.5 inches of HMA. Beam guard ends through out the project will be upgraded to current standards. Four structures (B-62-31 & 30, B-52-103 & 102) will receive concrete overlays. The consultant will perform the structure designs.
Project ID Project Name Route County
5040-03-00 RICHLAND CENTER - HILLSBORO STH 80 VERNON COUNTY
Project ID(s)
Consultants Requirements
Ability to meet project milestones and engineerin goals
Experience with FDM and PSE process
Experience with Roadside Design Standards
Experience with Utility Coordination
Consultant Requirements ( Listed in approximate order of importance) :
Items
Structure Designs
Traffic Counts & Crash Data
High Resolution Orthography
Bare Earth Lidar Data
Department Provides
Schedule Item Due Date
Structure Survey Report 09/02/2019 12:00 AM
Environmental Document (PCE) 10/01/2020 12:00 AM
PrePSE Review 06/01/2022 12:00 AM
PSE 08/01/2022 12:00 AM
DSR & 1078s 11/01/2020 12:00 AM
No records to display
Schedule for Deliverables
Report Generated on 02/20/2019 4:03 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification LicenseNo records to display
Special Skills/Certification License ( Listed in approximate order of importance) :
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:03 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:03 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-04
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$5,000,000-$5,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
01 May 2021
Project Purpose and Need :
Roadway surface is aged and deteriorated with cracking and deep ruts. The project is needed to improve the pavement performance. The proposed improvement is to mill and remove the existing pavement and overlay with new asphalt pavement along with replacing guard rail end terminals as needed. This is a perpetuation project.
Project Description : The project is located in Grant County near the State line, begins 0.3 miles east of STH 35 and continues easterly to the Village of Hazel Green. The existing 5 inch asphalt pavement will be removed by milling operations and repaved with the same depth of HMA. Beam guard terminals will be upgraded to current standards. Four approach slabs will be mud jacked to correct settling, and two additional structures will have misc repairs. Two retaining walls will be replaced.
Project ID Project Name Route County
1706-00-00 DUBUQUE - SHULLSBURG STH 11 GRANT COUNTY
Project ID(s)
Special Skills Certification LicenseNo records to display
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Ability to meet project timelines and aggressive engineering goals
Experience with FDM and PSE process
Experience with Work Zone TMP
Experience with Utility Coordination
Consultant Requirements ( Listed in approximate order of importance) :
ItemsNo records to display
Department Provides
Schedule Item Due Date
Environmental Document (PCE) 01/01/2020 12:00 AM
Pre PSE Review 03/01/2021 12:00 AM
PSE 05/01/2021 12:00 AM
DSR & 1078s 02/01/2020 12:00 AM
No records to display
Schedule for Deliverables
Basis of Payment Notification
Report Generated on 02/20/2019 4:04 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 2
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Fixed Fee Notification
Report Generated on 02/20/2019 4:04 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 2
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-05
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$2,000,000-$2,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
30 Jul 2021
Project Purpose and Need :
The project is needed because the existing roadway surface is aged and deteriorated with extensive cracking and rutting. The pavement has been patched and overlaid several times. Treatment is needed to extend the service life. The proposed treatment is a 3-lane TWLTL. This proposed rehabilitation will help the update the existing facility and utilities, increase the longevity of the roadway and the safety for the roadway users. The project length is 0.91 miles.
Project Description : This project within the City of La Crosse begins at Oakland Street and continues easterly to Losey Blvd. The University of Wisconsin-La Crosse abuts the highway to the south. Myrick Park and Oak Grove Cemetary abuts the highway to the north. Rear end crashes from left turning vehicles are the predominant crash pattern that will be addressed with the project. To mitigate these crashes, La Crosse St will be reconstructed with a Two Way Left Turn Lane and bike lanes.
Project ID Project Name Route County
7575-07-03 C LA CROSSE, LA CROSSE STREET (7575-07-03)
STH 016 LA CROSSE COUNTY
Project ID(s)
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Experience in Public Involvement and SDIC
Ability to meet project timeline and aggressive engineering goals
Urban design experience in constrained environments
Experience in facilitating the Section 106 process
Consultant Requirements ( Listed in approximate order of importance) :
Items
Crash Data
High Resolution Orthography
Title Searches
As-builts
Department Provides
Schedule Item Due Date
Environmental Document (PCE) 05/01/2020 12:00 AM
DSR, Plat, 1078s 06/01/2020 12:00 AM
PSE 09/01/2021 12:00 AM
Pre PSE 07/01/2021 12:00 AM
No records to display
Schedule for Deliverables
Report Generated on 02/20/2019 4:05 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 2
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Special Skills Certification LicenseNo records to display
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:05 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 2
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-06
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$2,000,000-$2,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
15 Aug 2020
Project Purpose and Need :
Perpetuation/Short term 2" mill and overlay. Existing pavement is deteriorated with extensive cracking and rutting. Treatment is needed to extend the pavement service life.
Project Description : The project includes resurfacing STH 78 with a 2-inch mill and overlay and replacing guardrail. No structure work.
Project ID Project Name Route County
5601-00-30 BLACK EARTH - SAUK CITY LOC STR DANE COUNTY
Project ID(s)
Consultants Requirements
Knowledge and skills required to complete topographic surveys, cross sections, DTMs, utility surveys, and control surveys.
Consultant Requirements ( Listed in approximate order of importance) :
Items
Existing traffic data
Traffic data, counts, projections
Pavement design
Wetland Delineation
Concept Definition Report
Asbuilt Plans
Department Provides
Schedule Item Due Date
Field Survey, as needed 07/01/2019 12:00 AM
Initial Agency Coordination 06/01/2019 12:00 AM
Send out 1077s 06/01/2019 12:00 AM
Local Offical/Public Inv. Meeting 09/01/2019 12:00 AM
Environmental Document 09/15/2019 12:00 AM
60% TMP 09/15/2019 12:00 AM
DSR 10/01/2019 12:00 AM
60% Plan 10/01/2019 12:00 AM
DT1078 Utility Submittal 10/01/2019 12:00 AM
90% TMP Submittal 03/01/2020 12:00 AM
Draft PS&E Submittal 03/01/2020 12:00 AM
PS&E Submittal 05/01/2020 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:06 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Land Surveyor
Professional Engineer
Special Skills/Certification License ( Listed in approximate order of importance) :
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Knowledge and experience with the environmental documentation and agency coordination required
Experience completing the PS&E process as described in WisDOT FDM
Experience in preparing the SSR/TMP/DSR/Environmental documents and other required docs
Knowledge of Departments current engineering platform (Civil 3D)
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:06 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Interview Information :
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:06 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-07
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$8,000,000-$8,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
08 Aug 2023
Project Purpose and Need :
Perpetuation/Pavement Replacement Project.The purpose and need is to replace the existing pavement and to improve the safety and operations of this principal arterial highway.
Project Description : Recondition work on STH 33, includes pavement, storm sewer, curb and gutter, driveways, sidewalk, curb ramps, base aggregate, erosion control items, signing, pavement marking. Include municipal plans for sanitary sewer and water main improvements. Complete environmental document, historical properties are within the project limits. Hazardous materials are anticipated within the project limits. Utility coordination, survey and development of a right of way plat are anticipated.
Project ID Project Name Route County
5090-05-01 C BARABOO, EIGHTH STREET STH 33 SAUK COUNTY
5090-05-30 REEDSBURG - BARABOO LOC STR SAUK COUNTY
Project ID(s)
Items
Existing traffic data
Geotechnical Report
Traffic data, counts, projections
Pavement design
Concept Definition Report
Department Provides
Schedule Item Due Date
Survey
Section 106 Coordination 02/01/2020 12:00 AM
Environmental Document 06/01/2020 12:00 AM
30% Plan 05/01/2020 12:00 AM
Preliminary TPP 12/01/2020 12:00 AM
TMP 12/01/2020 12:00 AM
DSR 01/15/2021 12:00 AM
60% Plan 11/01/2020 12:00 AM
Final TPP 02/01/2021 12:00 AM
DT 1078 Utility Submittal 03/01/2021 12:00 AM
90% Plan 03/01/2023 12:00 AM
Draft PS&E Package 03/01/2023 12:00 AM
PS&E Submittal 05/01/2023 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:08 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project :
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Engineer
Professional Traffic Operations Engineer
Professional Land Surveyor
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Experience completing the PS&E process as described in WisDOT FDM.
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Knowledge and experience with the environmental documentation and agency coordination required
Knowledge of department’s current engineering platform and the appropriate file formats used by department staff (Civil 3D, CAiCE, SDMS, etc.)
Staking R/W and providing CSMs or Plat of Surveys.
Consultant Requirements ( Listed in approximate order of importance) :
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:08 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
Special Instructions :
Interview :
Interview Information :
Interview Date :
Interview Place :
Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interviews will be conducted
Questions are provided below. At least eight (8) business days before the interview, short-listed firms will be provided specific interview time and location.19 Mar 2019
SW Region Truax Antigo Room
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit. Please be prepared to answer the following questions (in the order presented) during your interview: 1. Project Management and Design Delivery – What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 2. Urban pavement projects (2-lane and 4-lane) – What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 3. Construction staging, scheduling, estimating - What are your team’s qualifications from the past decade, capacity to deliver over the next two years, and strategies for success on this project? 4. Innovation – What has your team applied in the past decade and what potential innovations could your team apply to improve efficiency, effectiveness, and/or quality for this project?
Report Generated on 02/20/2019 4:08 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-08
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$500,000-$749,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
01 Aug 2022
Project Purpose and Need :
Perpetuation/ Resurfacing 4inch overlay.The roadway surface is aged and deteriorated with cracking and rutting. A mill and overlay was completed in 2000, there is a need to extend the service life of this pavement. This is a rural 6.16 mile resurfacing/perpetuation project.
Project Description : Treat the pavement with a mill and overlay. Replace the guardrail end terminals. No structure work.
Project ID Project Name Route County
6630-00-00 PARDEEVILLE - MANCHESTER LOC STR COLUMBIA COUNTY
Project ID(s)
Consultants Requirements
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge and experience with the environmental documentation and agency coordination required
Knowledge of department’s current engineering platform and the appropriate file formats used by department staff (Civil 3D, CAiCE, SDMS, etc.)
Knowledge and skills to complete topo
Consultant Requirements ( Listed in approximate order of importance) :
Items
Meta manager information
Concept Definition Report
Department Provides
Schedule Item Due Date
Environmental Document 06/01/2020 12:00 AM
TMP 07/01/2020 12:00 AM
DSR 08/01/2020 12:00 AM
60% Plan 07/01/2020 12:00 AM
DT 1078 Utility Submittal 11/01/2020 12:00 AM
90% Plan 05/01/2022 12:00 AM
Draft PS&E Package 05/01/2022 12:00 AM
PS&E Submittal 08/01/2022 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:09 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Land Surveyor
Professional Engineer
Professional Soil Scientist
Engineer in Training
Special Skills/Certification License ( Listed in approximate order of importance) :
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:09 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
No records to display
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:09 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-09
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$2,000,000-$2,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
30 Dec 2022
Project Purpose and Need :
This is a Perpetuation Project/Resurfacing mill and overlay.The roadway surface is aged and deteriorated with extensive cracking. A 4.5 inch mill and overlay was constructed in 1992. Treatment is needed to extend the pavement service life.
Project Description : Treat the pavement with a 3-1/2 Inch mill and overlay. Update curb ramps as needed to meet ADA requirements. No structure work included in project.
Project ID Project Name Route County
5939-00-00 COBB - AVOCA LOC STR IOWA COUNTY
Project ID(s)
Consultants Requirements
Experience with Trans 220 utility coordination process
Consultant Requirements ( Listed in approximate order of importance) :
Items
Existing traffic data
Aerial Mapping and survey
Photo log of project limits
Pavement design
Wetland Delineation
Department Provides
Schedule Item Due Date
Survey 08/01/2019 12:00 AM
Environmental Document 10/01/2019 12:00 AM
30% Plan 10/01/2019 12:00 AM
TMP 11/01/2019 12:00 AM
DSR 06/01/2020 12:00 AM
60% Plan 06/01/2020 12:00 AM
Final TPP 08/03/2020 12:00 AM
DT 1078 Utility Submittal 10/01/2020 12:00 AM
90% Plan 05/03/2021 12:00 AM
Draft PS&E package 06/01/2021 12:00 AM
PS&E Submittal 08/02/2021 12:00 AM
TLE Acquisition exhibit 06/01/2020 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:10 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Land Surveyor
Professional Engineer
Professional Traffic Operations Engineer
Professional Soil Scientist
Engineer in Training
Special Skills/Certification License ( Listed in approximate order of importance) :
Experience with the public involvement process
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge and experience with the environmental documentation and agency coordination required
Knowledge and skills required to complete topographic surveys, cross sections, DTMs, utility surveys, and control surveys.
Knowledge of department’s current engineering platform and the appropriate file formats used by department staff (Civil 3D, CAiCE, SDMS, etc.)
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:10 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:10 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-10
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$5,000,000-$5,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
29 Dec 2023
Project Purpose and Need :
This is a Perpetuation/Preservation Project This section of USH 51 begins at Tomlinson Road in the Village of Poynette, and goes north for almost 11 miles to Ontario Street in the City of Portage. The roadway surface is aged and deteriorated with extensive cracking. Treatment is needed to extend the pavement service life. The bridge over Duck Creek has longitudinal cracking.
Project Description : Treat the pavement with a mill and overlay. Update curb ramps as needed to meet ADA requirements. Replace guardrail end terminals as needed. Place an HMA overlay with membrane on the deck of B-11-94 over Duck Creek. Exception to net project length at the bridge over Rocky Run Creek, project 6020-04-80.
Project ID Project Name Route County
6020-04-02 Deforest-Portage USH 051 COLUMBIA COUNTY
Project ID(s)
Items
Aerial Mapping and survey
Existing traffic data
Photo log of project limits
Pavement design
Utility contacts and task list
Department Provides
Schedule Item Due Date
Section 106 Coordination 09/02/2019 12:00 AM
Environmental Document 01/01/2020 12:00 AM
30% Plan 01/01/2020 12:00 AM
Preliminary TLE Acquisition Exhibit 07/01/2020 12:00 AM
TMP 07/01/2020 12:00 AM
DSR 07/01/2020 12:00 AM
60% Plan 07/01/2020 12:00 AM
Preliminary Structure Plan 10/01/2020 12:00 AM
Final TLE Acquisition Exhibit 08/03/2020 12:00 AM
DT 1078 Utility Submittal 10/01/2020 12:00 AM
Final Structure Plan 05/02/2022 12:00 AM
90% Plan 05/02/2022 12:00 AM
Draft PS&E package 07/01/2022 12:00 AM
PS&E Submittal 08/01/2022 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:11 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Engineer
Engineer in Training
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge and experience with the environmental documentation and agency coordination required
Knowledge and skills required to complete topographic surveys, cross sections, DTMs, utility surveys, and control surveys.
Knowledge of department’s current engineering platform and the appropriate file formats used by department staff (Civil 3D, CAiCE, SDMS, etc.)
Consultant Requirements ( Listed in approximate order of importance) :
Concept Definition Report
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:11 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:11 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-11
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Open
Anticipated Construction Cost :
N/A NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
01 Jul 2019 Anticipated Project Completion Date :
30 Jun 2020
Project Purpose and Need :
Surplus land management and disposal activities, property management, and assistance with asbestos inspections and abatement contracts, demolition contracts, and building winterizing. Consultant will also research and update SW Region READS surplus land inventory. Coordinate the sales of surplus lands. Consultant to be hired for one-year period with two optional annual renewals. Consultant to work in the SW Region Madison office approximately 4 days per week based on work load.
Project Description : Consultant will: Evaluate and update existing SW Region surplus land inventory for accuracy, which may include in-house regional research. Research prior WisDOT projects and identify potential surplus land, which may include in-house regional research. Work with the Region to develop annual marketing plans for existing and future surplus land parcels. Obtain needed regional section approvals for the sale of surplus lands. Map location of regional surplus lands as instructed by SW Region.
Project ID Project Name Route County
0632-01-00 Surplus Land N/A Southwest Region Wide
Project ID(s)
Consultants Requirements
Consultant shall provide professional, competent staff who have the necessary skill and experience to provide quality and timely services for the services listed above.
Knowlege and experience in surplus land marking and sales
Ability to analyze and interpret plats, title work, and legal descriptions
Familarity with Chapter 6 of the Real Estate Program Manual (REPM)
Effective written and oral communications skills
Effective computer skills and ability to quickly learn computer programs used by Department, including READS
Experience with procuring property management services
Consultant Requirements ( Listed in approximate order of importance) :
Items
READS access and READS training as needed.
Department Provides
Schedule Item Due Date
Performance monitoring and improvement
Property management, such as: lease management
Complete and submit the annual surplus land marketing plan
Meet goals set forth in the marketing plan
Consultant will need to comply with Wisconsin Act 392
Create asbestos inspection & abatement solicitation as neede
Schedule for Deliverables
Report Generated on 02/20/2019 4:13 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Notification pertaining to DBE goals :
N/A
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats. The Department will negotiate a one-year contract with an option of another two consecutive one-year renewals. Consultant will need to identify the level of experience held by staff member assigned to this contract. Consultant will coordinate with project engineers to develop demolition contracts as needed in order to meet PS&E timelines.
Interview : Interviews will not be conducted
Interview Information :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Mid Level Real Estate Specialist
Ability to interpret plans, title work and legal descriptions
Special Skills/Certification License ( Listed in approximate order of importance) :
Experience with preparing demolition contracts through bid letting
Experience in marketing and advertising surplus land and building improvements
Experience with the sale and removal of building improvements
Ability to interact with internal and external customers
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:13 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: "Can your firm offer any efficiencies to the delivery of this project"? If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf. document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:13 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-12
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$1,000,000-$1,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
31 Dec 2024
Project Purpose and Need :
Pavement Replacement/Rehabilitation. Gapping and joint degradation is occurring in the longitudinal joints along auxiliary lanes, ramps, and tapers. Areas of corner and mid panel cracking are occurring along mainline.
Project Description : Work includes panel replacement and corner repair along mainline, pavement replacement on ramps, auxiliary lanes and tapers. Mill and overlay at gore areas, and adjacent to any panel and pavement replacement. Beam guard upgrades in areas with deficient standards.
Project ID Project Name Route County
5490-00-33 C MADISON, STH 30 STH 30 DANE COUNTY
Project ID(s)
Consultants Requirements
Experience with the public involvement process
Knowledge and experience with the environmental documentation and agency coordination required
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge and skills required to complete topographic surveys, cross sections, DTMs, utility surveys, and control surveys.
Knowledge of department’s current engineering platform and the appropriate file formats used by department staff (Civil 3D, CAiCE, SDMS, etc.)
Consultant Requirements ( Listed in approximate order of importance) :
Items
Utility contracts and task list
Department Provides
Schedule Item Due Date
Surveying
Section 106 Coordination 04/01/2021 12:00 AM
Environmental Document(s) (including factor sheets) 06/01/2021 12:00 AM
Design Study Report 07/01/2021 12:00 AM
Traffic Management Plan 07/01/2021 12:00 AM
PS&E package 05/01/2022 12:00 AM
30% Plan 05/01/2021 12:00 AM
60% Plan 07/01/2021 12:00 AM
DT 1078 Utility Submittal 10/01/2021 12:00 AM
90% Plan 02/01/2022 12:00 AM
Draft PS&E Submittal 02/01/2022 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:15 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Engineer
Special Skills/Certification License ( Listed in approximate order of importance) :
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:15 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:15 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-13
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$750,000-$999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
29 Dec 2023
Project Purpose and Need :
Perpetuation/Bridge Rehabilitation 0.753 mile urban project. The bridges over Fair Oaks Avenue are a 2-span steel deck girder structure. Both decks have transverse leaching cracks. The girders have areas of corrosion. The east abutment backwall of B-13-206 is spalled with exposed rebar for the entire length. The west abutment backwall of B-13-206 has two areas of spalls.
Project Description : Concrete overlay and painting of both bridges. Replace abutment backwalls of B-13-206.
Project ID Project Name Route County
5490-00-32 C MADISON, STH 30 LOC STR DANE COUNTY
Project ID(s)
Consultants Requirements
Experience in structure load rating calculations
Experience with Trans 220 utility coordination process
Experience with public involvement.
Consultant Requirements ( Listed in approximate order of importance) :
Items
Bridge as-built plans
Department Provides
Schedule Item Due Date
Survey
Section 106 Coordination 02/01/2021 12:00 AM
Environmental Document 06/01/2021 12:00 AM
Exception to Standards Report 05/01/2021 12:00 AM
30% plans 05/01/2021 12:00 AM
60% plans 07/01/2022 12:00 AM
90% Plans 02/01/2023 12:00 AM
Traffic Management Plan (TMP) 07/01/2022 12:00 AM
Design Study Report 07/01/2022 12:00 AM
Preliminary Road and Structure Plans 07/01/2022 12:00 AM
Utility coordination including 1078 plan submittals 10/01/2022 12:00 AM
Final Structure Plans 02/01/2023 12:00 AM
Draft PS&E 02/01/2023 12:00 AM
PS&E package 05/01/2023 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:17 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
Notification pertaining to DBE goals :
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
DBE goal on project : No
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Land Surveyor
Professional Engineer
Structural Engineer
Special Skills/Certification License ( Listed in approximate order of importance) :
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge and skills required to complete topographic surveys, cross sections, DTMs, utility surveys, and control surveys.
Knowledge of department’s current engineering platform and the appropriate file formats used by department staff (Civil 3D, CAiCE, SDMS, etc.)
Working knowledge of the AASHTO LRFD Bridge Design Specifications and the ability to design structures using the LRFD specification.
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:17 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Interview Information :
Interview Date :
Interview Place :
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.
Report Generated on 02/20/2019 4:17 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 3 of 3
Solicitation Scope Of Service - DETAILS REPORT
Transportation Region/Bureau :
Southwest Region Solicitation ID : SW-14
Solicitation Month and Year :
March 2019 Solicitation Type(Roster/Open) :
Roster
Anticipated Construction Cost :
$3,000,000-$3,999,999 NOI Due Date : 06 Mar 2019
Anticipated Project Start Date :
20 May 2019 Anticipated Project Completion Date :
09 Nov 2021
Project Purpose and Need :
Rehabilitation. Replace existing structure which will be turned over to City of Jefferson after replacement. Bridge is currently an 84.10 structure. Existing deck is spalled and delaminated on both top of deck and underside. South abutment has crack running from top to bottom through center. Piers and abutments have been patched in the past and the patches are beginning to deteriorate.
Project Description : Work will consist of replacing the existing bridge. Minimal approach work will be completed north of the bridge. Reconstruction of the intersection of Main Street and Riverview Drive will be completed south of the bridge. Minor real estate acquisition or temporary easements are anticipated. South Main Street will be closed during construction.
Project ID Project Name Route County
3993-01-01 S MAIN STREET, C JEFFERSON (3993-01-01)
LOC STR JEFFERSON COUNTY
Project ID(s)
Items
Structure Survey Report
Geotechnical Report
Title searches
Aerial Mapping and survey
Soils/geotechnical investigation
Pre-60% roadway plans
Pavement design
Environmental Document
Base mapping
Asbestos reports
Department Provides
Schedule Item Due Date
Preliminary TPP submittal 06/14/2019 12:00 AM
Traffic Management Plan (TMP) 06/30/2019 12:00 AM
Design Study Report 10/30/2019 12:00 AM
60% plans 08/22/2019 12:00 AM
90% Plans 11/14/2020 12:00 AM
Utility coordination including 1078 plan submittals 01/29/2020 12:00 AM
Draft PS&E 12/22/2020 12:00 AM
Final TPP 10/14/2019 12:00 AM
PS&E package 04/15/2021 12:00 AM
Schedule for Deliverables
Report Generated on 02/20/2019 4:18 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 1 of 3
Solicitation Scope Of Service - DETAILS REPORT
DBE goal on project :
DBE goal : DBE goal in $ 0.00
Basis of Payment Notification
The contract price will be based on the selected consultant’s actual costs plus fixed fee. Actual costs will be defined as those costs allowable under the cost principles in Part 31 of Federal Acquisition Regulation (FAR).
Consultant costs including indirect cost rates and cost accounting system will be subject to audit. Consultant firms that are unable to account for costs consistent with requirements of the FAR are not eligible to contract. Consultants selected will be required to either submit or have on file with WisDOT a Consultant Financial Report prior to contract execution. Information on the report may be found at http://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rgistr/fncl-rpt.aspx.
Basis of Payment Notification
Advertised Fixed Fee % : 7.25
The Basis of Payment will be one or more of the following:
Lump Sum
Specific Rate
Cost Per Unit
Actual Cost Plus Fixed Fee
Special Skills Certification License
Professional Engineer
Engineer in Training
Professional Land Surveyor
Street Lighting Designer
Special Skills/Certification License ( Listed in approximate order of importance) :
Consultants Requirements
Experience with Trans 220 utility coordination process
Experience with the public involvement process
Experience in preparing the SSR / TMP / DSR / Environmental documents and other required design documents.
Experience completing the PS&E process as described in WisDOT FDM.
Knowledge of department’s current engineering platform and the appropriate file formats used by department staff (Civil 3D, CAiCE, SDMS, etc.)
Staking R/W and providing CSMs or Plat of Surveys.
Knowledge and experience with the environmental documentation and agency coordination required
Consultant Requirements ( Listed in approximate order of importance) :
Utility contacts and task list
Concept Definition Report
Fixed Fee Notification
The fixed fee for this contract will apply an indirect cost factor of 150% to the consultant’s estimated direct labor, regardless of the consultant’s actual indirect rate.
Basis of Payment Notification
Fixed Fee Notification
Report Generated on 02/20/2019 4:18 PM[Timezone: (UTC-06:00) Central Time (US & Canada)]
Page 2 of 3
Solicitation Scope Of Service - DETAILS REPORT
Name Email
No records to display
Notification pertaining to DBE goals :
Special Instructions : Do not include any information that meets the definition of “trade secret” as that term is defined in s. 134.90(1)(c), Wis. Stats.
Interview : Interviews will not be conducted
Interview Information :
Interview Date :
Interview Place :
Project Amount in $No records to display
Disadvantaged Business Enterprise ( DBE ) Subcontracting goal on this solicitation will be
Other Information : In addition to completing the Consultant Notice of Interest, you may attach an answer to the following question to your Bureau of Structures is completing bridge design. 30% design and documents are complete. NOI submission: “Can your firm offer any efficiencies to the delivery of this project?” If applicable, answer the above question in 500 words or less, and attach your answer as a word or pdf document to your submission. Your answer should be attached to NOI submission and may be different for each NOI you submit.