15
Solar Shield project - lessons learned and advances made Pulkkinen, A., M. Hesse, S. Habib, F. Policelli, B. Damsky, L. Van der Zel, D. Fugate, W. Jacobs, E. Creamer Space Weather Workshop, April 27-30, 2010, Boulder, CO. 1

Solar Shield project - lessons learned and advances made

Embed Size (px)

DESCRIPTION

Solar Shield project - lessons learned and advances made. Pulkkinen, A., M. Hesse, S. Habib, F. Policelli, B. Damsky, L. Van der Zel, D. Fugate, W. Jacobs, E. Creamer. Contents. Solar Shield overview. Solar Shield forecasting system. - PowerPoint PPT Presentation

Citation preview

Page 1: Solar Shield project - lessons learned and advances made

Solar Shield project - lessons learned and advances made

Solar Shield project - lessons learned and advances made

Pulkkinen, A., M. Hesse, S. Habib, F. Policelli, B. Damsky, L.

Van der Zel, D. Fugate, W. Jacobs, E. Creamer

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

11

Page 2: Solar Shield project - lessons learned and advances made

ContentsContents• Solar Shield overview.• Solar Shield forecasting system.

– Level 1+ approach. The first tailored first-principles-based 2-3 day lead-time forecasts.

– Level 2+ approach. The first first-principles-based 30-60 min lead-time GIC forecasts.

• Coupling of the system to the SUNBURST research support tool.

• List of additional activities.• Team recommendations.

22Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 3: Solar Shield project - lessons learned and advances made

Solar Shield overviewSolar Shield overview

• In Solar Shield, we developed an experimental system to forecast space weather effects on the North American power grid; three-year project funded by NASA’s Applied Sciences Program.

• Focus on first-principles-based space weather modeling.

• NASA/GSFC/CCMC and Electric Power Research Institute (EPRI) the key players.

• Final report was delivered to NASA Applied Sciences Program on April 1, 2010.

33Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 4: Solar Shield project - lessons learned and advances made

System requirements (summary)

System requirements (summary)

• Two-level GIC forecasts:– Level 1 providing 1-2 day lead-time.– Level 2 providing 30-60 min. lead-

time.

• Coupling to EPRI’s SUNBURST research support tool.

44

Used by the SUNBURST member utilities to monitor GIC.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 5: Solar Shield project - lessons learned and advances made

Level 1 forecastsLevel 1 forecasts

55Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 6: Solar Shield project - lessons learned and advances made

Level 1 forecastsLevel 1 forecasts

April 3, 2008April 3, 2008 66

Solar observations of eruptive events are used to compute “cone model” parameters. NASA/ESA SOHO/LASCO data used.

Solar observations of eruptive events are used to compute “cone model” parameters. NASA/ESA SOHO/LASCO data used.

Plasma “cone” introduced to the inner boundary of a heliospheric MHD model. Model propagates the disturbance to the Earth. Computations carried out at the Community Coordinated Modeling Center.

Plasma “cone” introduced to the inner boundary of a heliospheric MHD model. Model propagates the disturbance to the Earth. Computations carried out at the Community Coordinated Modeling Center.

MHD output at the Earth used in a statistical model providing probabilistic estimate for GIC at individual nodes of the power grid. GIC forecast file is generated.

MHD output at the Earth used in a statistical model providing probabilistic estimate for GIC at individual nodes of the power grid. GIC forecast file is generated.

Page 7: Solar Shield project - lessons learned and advances made

Level 1 improvement: automatic determination

of the cone model parameters

Level 1 improvement: automatic determination

of the cone model parameters

77

Sequence of binary images

generated from LASCO C3

min{v,x0 ,ω ,θ }

(y i − ˆ y i)2 + (zi − ˆ z i)

2( ) + μ ω −ω0i

∑[ ]

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 8: Solar Shield project - lessons learned and advances made

Level 2 forecastsLevel 2 forecasts

88Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 9: Solar Shield project - lessons learned and advances made

April 3, 2008April 3, 2008 99

Lagrange 1 observations used as boundary conditions for magnetospheric MHD. NASA’s ACE data used.

Lagrange 1 observations used as boundary conditions for magnetospheric MHD. NASA’s ACE data used.

Magnetospheric MHD model used to model the magnetospheric-ionospheric dynamics. Computations carried out at the Community Coordinated Modeling Center.

Magnetospheric MHD model used to model the magnetospheric-ionospheric dynamics. Computations carried out at the Community Coordinated Modeling Center.

Magnetospheric MHD output used to drive geomagnetic induction and GIC code providing GIC at individual nodes of the power grid. GIC forecast file is generated.

Magnetospheric MHD output used to drive geomagnetic induction and GIC code providing GIC at individual nodes of the power grid. GIC forecast file is generated.

Page 10: Solar Shield project - lessons learned and advances made

Level 2 improvement: usage of inner

magnetospheric models

Level 2 improvement: usage of inner

magnetospheric models

1010Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 11: Solar Shield project - lessons learned and advances made

1111

KAMELEON

interpolation library

Linear interpolation:

MHD ionosphere grid- CRCM ionosphere

grid

KAMELEON

interpolation library

CRCM run

MHD BATSRUS run at the CCMC

MHD B-field

B-field at the whole CRCM

region

electric field potential in the ionosphere

CRCM potential in the ionosphereat the CRCM polar boundary

MHD T, n

Equatorial n,T at the CRCM

polar boundary

CRCM polar boundary

Region II Birkeland currents 3-D H+, e- fluxes Self-consistent E-field

N. Buzulukova

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 12: Solar Shield project - lessons learned and advances made

Level 2 improvement: usage of inner

magnetospheric models

Level 2 improvement: usage of inner

magnetospheric models

1212

Hours from the beginning of August 11, 2000.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 13: Solar Shield project - lessons learned and advances made

Coupling to the SUNBURST research support tool

Coupling to the SUNBURST research support tool

1313

% Level 1 GIC forecast produced by REALTIMEGIC_LEVEL1%% The format of the data is as follows: % 0 0 0 0 0 lat1 lon1 lat2 lon2 . . .% yy mm dd hh mi GIC1low GIC1high GIC2low GIC2high . . .% 0 0 0 0 53.16 -99.29 45.39 -68.532006 12 14 14 6 76 15 153

% Level 2 GIC forecast produced by REALTIMEGIC_LEVEL2% % The format of the data is as follows: % 0 0 0 0 0 0 lat1 lon1 lat2 lon2 . . .% 0 0 0 0 0 0 53.16 -99.29 45.39 -68.532008 03 19 11 02 31 -0.11 0.00 0.13 0.00 2008 03 19 11 04 31 0.02 0.00 0.03 0.00 2008 03 19 11 06 31 -0.02 0.00 0.04 0.00 2008 03 19 11 08 31 0.00 0.00 0.01 0.00 Space Weather Workshop,

April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 14: Solar Shield project - lessons learned and advances made

List of additional activitiesList of additional activities

• Detailed V&V using historical events.• Development of the real-time validation tool.• Analysis of transformer dissolved gas

measurements carried out during strong storms.

• Analysis of economic impacts of large GIC events. (coupled with V&V analyses)

• For details, see Benchmark Report (April 1, 2010).

1414

cost/benefit

Model forecast ratios

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Page 15: Solar Shield project - lessons learned and advances made

Team recommendationsTeam recommendations

• Level 2 part of the system is applicable only to high-latitude locations. Extension of the forecasting system to cover lower latitudes is needed for the application of the Level 2 approach to the US power grid.

• SUNBURST GIC dataset played a critical role in the establishment of the forecasting system. Installation of new GIC monitoring sites especially to the continental US would enable expansion and increased utility of the newly developed GIC forecasting system.

• Forecasting system (as many space weather applications) relies on aging ACE and SOHO spacecraft. Operational capacity providing robust streams of in situ solar wind and remote solar (coronagraph) data needs to be established.

1515Space Weather Workshop, April 27-30, 2010, Boulder, CO.

Space Weather Workshop, April 27-30, 2010, Boulder, CO.