Solar PV On-Site Installer’s Guide. On arrival at the site, check and confirm the following Scaffolding is in place and safe to use Materials and equipment are on site System design documents are available. - PowerPoint PPT Presentation

Citation preview

Page 1: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Solar PV On-Site Installer’s Guide

Page 2: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

On arrival at the site, check and confirm the following

Scaffolding is in place and safe to use

Materials and equipment are on site

System design documents are available

Page 3: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Familiarise yourself with the site and confirm the expected location of the panels and the electrical fittings

Page 4: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Fix the inverter securely into the selected position

Allow correct air spaces as per manufacturers instructions

Page 5: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Fix the DC isolator switch(es) into position

Page 6: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Fix the AC isolator switch in position

Page 7: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Attach the cabling between the inverter and the switches

Page 8: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Complete the installation of the DC switch(es) and label them

Page 9: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Position and install the generation meter and main AC isolator switch

Usually this is to be located adjacent to the distribution board

Page 10: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Use an experienced roofer to install a proprietary roof entry for the DC cables to pass through the roof

Page 11: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External / Internal works

Feed the DC cables through the fitting and into the internal roof space.

Page 12: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Record the voltage (VOC) and current (ISC) values for each panel.

Page 13: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Use an experienced roofer to fit the brackets in place

Page 14: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Measure and square up the rails when fitting.

Page 15: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Position the required length of DC cable and secure with zip ties.

Page 16: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Bring the panels safely up to the installation level.

Take extra care if it is windy.

Page 17: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Align the first panel and fix in place.

Page 18: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Fix the panels in place ensuring they are straight and square. Pay special attention to positioning the first panel in a string.

Page 19: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Add further panels, keeping the alignment.

Connect the panel cables as each one is fixed in place.

Page 20: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

Secure each panel in place.

Page 21: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

External works

With the panel array(s) in place and connected, return to the inverter for testing and commissioning.

Page 22: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Complete all AC tests in accordance with BS7671 Inspection & Test

Page 23: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal worksComplete tests on DC circuitry including:IR testsVOC testsISC testsIrradiance level tests

Page 24: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Ensure all electrical components are fully labelled.

Page 25: Solar PV On-Site Installer’s Guide

Solar PV On-Site Guide

Internal works

Place a system schematic at the inverter location, and at the main consumer unit for the property