46
Feasibility Report of MTS Solar power generation plant (pvt) Ltd. SUBMITTED TO: Mr. JAVEED IQBAL SUBMITTED BY: Sidra nor 11 Aysha sahar 25 Lubna malik 48 M.COM 4TH ( FINANCE) SESSION (2008-10)

Solar Power Generation Plant

  • Upload
    shani27

  • View
    1.048

  • Download
    9

Embed Size (px)

DESCRIPTION

Project feasibility report of Solar Energy Plant.The Islamia University of Bahawalpur, Pakistan.

Citation preview

Page 1: Solar Power Generation Plant

Feasibility Report ofMTS Solar power generation

plant (pvt) Ltd.

SUBMITTED TO: Mr. JAVEED IQBAL

SUBMITTED BY: Sidra nor 11

Aysha sahar 25 Lubna malik 48

M.COM 4TH ( FINANCE)

SESSION (2008-10)

DEPARTMENT OF COMMERCE

Page 2: Solar Power Generation Plant

THE ISLAMIA UNIVERSITY OF BAHAWALPUR

Page 3: Solar Power Generation Plant

We Dedicate our Project

To our

“BELOVED PARENTS

To our Honorable Teacher

“Mr.JAVEED IQBAL”

Page 4: Solar Power Generation Plant

TABLE OF CONTENTS

Serial No. ItemsPage No.

1 Executive Summary 5

2 Main Body 8

2.1 Project Idea & Background of project 8

2.2 Opportunity Rationale 9

2.3 Project Parameters 9

2.4 Plant Capacity 10

2.5 Implementation 10

2.6 Geographical Level 10

2.7 Project Promoters 11

2.8 Corporate Setup 11

2.9 Project Capacity and Rationale 11

2.10 Key Success Factors 11

2.11 Strategic Recommendations 11

2.12 Industry Analysis 12

2.13 Production Process 14

2.14 Machinery Requirement 17

2.15 Human Resource Requirement 18

2.16 Project Parameters 19

3 Annexure 19

4 Site layout 37

Page 5: Solar Power Generation Plant

Executive Summary

1.1The Project. ‘MTS’ Solar Power Generation Plant (Pvt) Ltd.

1.2Location Bahawalpur District.

1.3 SponsorsThis project has been financed with the financial assistance of BOP. The equity contribution is made by MTS and Son’s.

1.4 Distance from District Headquarter 8 k-m

1.5 Access

By Road Bahawalpur – Hasilpur Road.

By Rail Baghdad Railway station.

By Air Bahawalpur Airport.

1.6 Telecommunication Telecommunication facility is available.

Page 6: Solar Power Generation Plant

1.7 Land It is proposed to install 5MW on the land admeasuring about 20 Acre.

1.8 Land Characteristics Barren Land - Non Agricultural Land.

1.9 Type of Module Mounting Structure Fixed Structures, Earth Mounted Grid Connected.

1.10 Type of PV Modules Considered for the offer ‘Crystalline’

1.11 Proposed Capacity 5 MWp

1.12 Material Requirement Sun light is the basic material for our project. And the ideal range of temperature is from 25’C to 30

1.13 Project Engineering All the machineries are purchased from China, Like Solar panels and invertors and all the

remaining things are easily available at locally.

1.14 Manpower For this project there is the requirement of plant and administration staff which is easily available at local.

1.15 Implementation Stage The project will be completed in Six month. Its start date is 1-7-2010 and would be completed on 31-12-2010.And the commercial production is started in January 2011.

Page 7: Solar Power Generation Plant

1.16 Project Parameters

Cost of the project Fixed cost Rs. 766,197,000

Net Working Capital 9 25,000Total Cost 767, 122,000

Financial Plan Bank loan 70% Rs: 536,985,400

Equity 30% 230,136,600Total 767,122,000

Operating Results

2011 (in ,000) 2012(in ,000) 2013(in ,000)

Sales219000 232688 246375

G. Profit191159 204265 217283

Op. Profit186355 198740 210927

PBT109702 123661 137661

Net Profit67100 75588 84101

Financial Position of the Company

2011 2012 2013

Current Assets119727 196668 280425

Current Liabilities55960 63287 70871

Fixed assets757472 749847 742222

Long term debt 524735 510770 494850

Page 8: Solar Power Generation Plant

1.9 Terms and Conditions.

Sponsor contribution will be 30%. Land will be transferred to company name. BOP will pledge land as security. Final contract with material, machinery

supplier and civil work need to show to BOP Loan is to be repaid in 10 Years.

2.1 Project Idea:

BACKGROUND OF THE PROJECT

The Government of Pakistan’s (GOP) Renewable Energy Policy 2006 emphasizes the

development of renewable and clean energy in the country. In fiscal year 2005-06,

Pakistan’s consumption of energy generated through renewable energy (RE) sources

stood at only 180-MW. Development of the power generation potential of existing RE

sources, solar, biogas, biomass, micro-hydel, and windmills, offers significant business

opportunities for American manufacturers and exporters. Due to in-country depletion of

conventional energy resources and an expanding gap between power demand and

supply, the development of RE sources in the country has gained force over the past 3-4

years. The GOP has decided to encourage and invest in the development of the

infrastructure necessary for power generation through RE sources through its Alternate

Energy Development Board (AEDB).

The goal is to have power generation from RE sources contribute approximately 10

percent of the country’s overall energy requirements by 2015. American companies

already dominate the foreign-owned portion of the local RE power generation market

with almost 25 percent of market share, followed by European and Chinese companies,

which have 10 percent and 5 percent of market share respectively. The remaining 60

percent of current RE power generation is in the hands of domestic companies. AEDB

and the Pakistan Council of Renewable Energy Technologies (PCRET) are playing a

major role in promoting the development of infrastructure for RE power generation in

Pakistan.

Large multi-megawatt PV plants, approximately to 50 MW, are now in operation in the

world. Solar Photovoltaic (PV) is known to be an important energy source for developing

Page 9: Solar Power Generation Plant

countries like Pakistan. Its importance is now being realized even by developed

countries in view of its renewable and environment friendly character. In our country

also, optimum utilization of solar energy could not only lead to savings in conventional

energy but also result in many indirect benefits. But till now solar technology is

expensive compared to other technology and significant financial assistance from

government is needed to the developers and operators of new plants.

In view of this, the Ministry of New & Renewable Energy Sources has been promoting

electricity generation from Solar PV in Mega-Watt level. These projects are covered

under the Grid Interactive Solar PV Power Generation Projects of Ministry of New &

Renewable Energy Sources. The Ministry initiated the programme to establish as a

viable and environment friendly electricity generation option.

2.2 Opportunity Rationale:

Power generation from solar has many benefits which are as follows:

Power from the sun is clean, silent, limitless and free.

Photovoltaic process releases no CO2, SO2 or NO2 gases which are normally

associated with burning finite fossil fuel reserves and don’t contribute to global

warming.

Photovoltaic are now a proven technology which is inherently safe as opposed to

other fossil fuel based electricity generating technologies.

No fuel is required for generation, so fuel cost of power generation is zero.

Increase the grid reliability i.e., voltage and frequency.

Solar Powered Grid Connect Plants can act as tail end energizers, which in turn

reduces the transmission and distribution losses.

Provides a potential revenue source in a diverse energy range.

Assists in meeting renewable portfolio standards goal.

Generation of electricity from Solar PV is totally free of Green House Gas

emission.

Market Entry Timing

This is the best time to enter in the market because there is a short fall of electricity in the country, so presently it has a high demand.

Page 10: Solar Power Generation Plant

2.3 Project Parameters

Initial Capacity 80%Human Resource 28Machinery Foreign (China) & Local (Advance electronics)Location Bahawalpur.

2.4 Plant Capacity:

The proposed 5MWp solar power plant project will generate electricity from non-

conventional sources. The project will use “polycrystalline” technology for the first time

in the state for producing power by solar energy. This project will generate safe, reliable

electricity in an environmentally friendly way.

2.5 Implementation:

The project will be implemented as under:

Loan sanctioned in July 2010.

All formalities will be completed in July.

Civil work would be made in 5 months.

Machinery would be available and installed in 1 month.

Trail Production would be started in December 2010.

Commercial production would be started in January 2011.

2.6 Geographical Level:

We are operating in Southern Punjab distt. Bahawalpur. This is the perfect choice for our

project because here the weather conditions are good and ideal temperature for this

project is 25’c which is available whole the year. And this city is situated near the

Cholistan Desert.

Project Coverage:

Page 11: Solar Power Generation Plant

The project will impact positively to our economy while contributing in production in

electricity industry which would increase our GDP. And it is beneficial for our city as well

as our country because due to this plant we meet the demand and short fall of electricity

in our city. It would provide employment opportunity to the people which ultimately

increase their living standard.

2.7 Project Promoters:

Muhammad Tufail Sukhera and Son’s are well known businessman of this city and also

they have a good knowledge of solar energy. And they are working on solar system for

last 5 years. They initially promoted this project.

2.8 Corporate Setup:

MTS solar power generation Pvt. Ltd will be a Private limited company. 30% of the cost

will be provided by sponsors. MTS solar power generation Pvt. Ltd have best rational

and technically equipped corporate managers which have the ability to run effectively

and efficiently.

2.9 Project Capacity

This plant is installed at 5MW. This solar power plant produces 18250000 Kwh

electricity in a year at its full capacity. It can be computed as follows:

(5000 Kw*10 hrs*365 days).

2.10 Key Success Factors

There is a high demand of this project in this city.

The use of solar energy is environment friendly.

It gives long term benefit.

Using solar energy is more beneficial for producing electricity as compare to

produce electricity from hydel resources, because it takes less time to produce

electricity

2.11 Strategic Recommendations

Page 12: Solar Power Generation Plant

Initially, the electricity is supply to the near by areas. The company will later expand into

other cities through an agreement with WAPDA that we use their supply system or we

sell our electricity directly to the house holds.

2.12 INDUSTRY ANALYSIS:

As we analyze the industry, we see there is a huge demand of these kinds of projects at

present and in future to fulfill the demand and supply gap of electricity in the country.

2.12.1 World Scenario

It was estimated that in 2005, 86% of primary energy production in the world came from

burning fossil fuels, with the remaining non-fossil sources being hydroelectric 6.3%,

nuclear 6.0%, and renewable energy sources, i.e. geothermal, solar, wind, biomass and

wastes contributed only 0.9%.

Some Leading Countries which are working on solar energy:

France

China

Greece

America

Italy

European countries

India

2.12.2 Scenario in Pakistan

For about a year now, Pakistan is facing the worst energy crisis of his history. If on one

hand, the increase in the oil prices at the world level is severely affecting the common

masses, on the other hand, the shortage of electricity is creating disorder in the country.

Beside others, one important reason that is advocated for this shortage is the rise in

electricity demand due to increase in production as well as rise in household income.

Pakistan covers 796,095 square kilometers of land between latitudes 24° and 36° north

and longitudes 61° and 76° east. At present, it faces serious energy problems:

Page 13: Solar Power Generation Plant

95 per cent of its electricity generation comes from hydropower , which becomes less

productive during the driest, hottest months of the year and cannot keep pace with the

sharp rise in energy demand. Also, about 70 per cent of the populations live in some

50,000 villages dispersed around the country. Many of these villages are far from the

main transmission lines of the national grid and, because of their relatively small

populations; it is usually not economically viable to connect these villages to the grid.

Solar energy , on the other hand, has excellent potential in areas of Pakistan that

receive high levels of solar radiation throughout the year. Every day, for example, the

country receives an average of about 19 mega joules per square meter of solar

energy. Solar energy systems have already been developed and tested, and they

should now be adopted extensively as a way of supporting the economy of the country

and improving the living standards of its people. Not only can solar systems meet basic

needs of rural areas, but they can also reduce the pressure on conventional energy

sources in urban areas, leaving more of these valuable resources for other domestic and

industrial needs.

2.12.3 Current Industry Structure at Bahawalpur

In Bahawalpur division, a lot of work is being done on solar projects and at present,

there are two large projects are in pipe line that are,

Page 14: Solar Power Generation Plant

1. Solar power generation plant in Islamia University BWP.

2. A solar light set up is going to be installed in the Garrison park cantt

BWP.

And now MTS & son’s are going to be started a 5MW solar power generation plant in

BWP city to meet the demand of electricity in this city. Due to this people are

encouraged to set up industries in this city and also government of Pakistan will do

something in this regards, because government support is needed in this kind of

projects.

2.13 PRODUCTION PROCESS

Page 15: Solar Power Generation Plant

Production Process Flow

Page 16: Solar Power Generation Plant

How a PV System Works

A PV array produces power when exposed to sunlight, a number of other components

are required to properly conduct, control, convert, distribute, and store the energy

Page 17: Solar Power Generation Plant

produced by the array. Depending on the functional and operational requirements of the

system, the specific components required, and may include major components such as

a DC-AC power inverter, battery bank, system and battery controller, auxiliary energy

sources and sometimes the specified electrical load (appliances).

2.14 MACHINERY REQUIREMENT

Machinery Details,

Page 18: Solar Power Generation Plant

2500 Solar panel (Poly crystalline) PV module of 200w each. 5000 Invertors (1 KVA) Cables and fixing structure and miscellaneous.

Solar system is purchased from China because we need it in bulk and China manufactured high quality solar panels and all relevant material. And the other remaining things are easily available at locally.

Reference: www.alibaba.com www.google.com Advance electronics ( Mr. Afzal )

Cleaning and maintenance of Solar Panels

In developed countries, Solar PV module Panels dust cleaning system is widely used in

solar photovoltaic power station. Trees leaves, bird poop and airborne particles (from dirt

and pollen) make solar panels dirty, dirty panels causes power loss. Dirt and waste

reduce the ability of the solar array to perform at full capacity. The potential energy loss

depends on the level of fifth accumulated on solar panels. Energy loss could reach 25

percent of generating power. Cleaning system for solar panels will improve the

photovoltaic conversion rate, keep the generation capacity steady all over the year

capacity. Panels can ve cleaned either manually or mechanically.

In Mechanical cleaning system mainly, water sprinkler system is used, but it needs lot of

power to spray water in wide module area, Manual system need manpower for cleaning.

Though mechanical dust cleaning system are efficient than manual system. This solar

PV plant manual cleaning is proposed because manual labor cost is less compared to

total supplementary power cost.

So, the maintenance and cleaning cost of solar panel is 1% of the cost of solar panels that is Rs: 2500000

2.15 HUMAN RESOURCE REQUIREMENT

Page 19: Solar Power Generation Plant

2.16 Estimated Cost of Project

ADMIN. STAFF(3 NOS.)

PLANT MANAGER2 NO

OPERATION MANAGER (5 NO.)

MAINTENANCE & ADMINISTRATION MANAGER (5 NO.)

ADMIN. STAFF(3 NOS.)

ELECTRICAL TECHNICIAN

(4 NOS.)

TECHNICIAN(3 NOS.)

CONTROL ROOM TECHNICIAN

(3 NOS. )

TOTAL O&M STAFF = 28 NOS.

Page 20: Solar Power Generation Plant

Financial Plan Bank loan 70% Rs: 536,985,400

Equity 30% 230,136,600Total 767,122,000

All relevant Annexure of MTS solar power generation plant

(pvt) Ltd

Annexure-1

MTS SOLAR POWER PLANTEstimated cost of the Land

Sr.No. DescriptionArea in Acres

Unit cost (000)

Rs:("000") Total cost

1 Land 20 2500 50000

2 Registration & Legal Requirements 1% of cost of land 20 25 500

3 Stamp Duty 2% of cost of land 20 50 1000

4 District council fee 1% of cost of land 20 25 500

5 Capital Value tax is 4% of cost of land 20 100 2000

  Total cost of land   2700 54000

Annexure- 2

Page 21: Solar Power Generation Plant

MTS SOLAR POWER PLANTEstimated Cost of Civil Works

Sr.No: DescriptionPlinth Area B.P E.I P.H Total Amount (Rs:)

1 Officer Residence

1650 Sft 891 44 44 979/- 16,15,350/-

2B/Wall

- - - -    

 1650x10/100 = 165

165 Rft - - - 883/- 1,45,695/-

35x990 = 4950

4950 932 44 44 1020/- 50,49,000/

4B/Wall

- - - -    

 4950x10/100 = 495

495 - - - 883/- 4,37,085/-

5Solar Plant Room

- - - -    

 36x24 = 864 Sft

864 Sft 827 44 44 915 7,90,560/-

6

Control Buildings = 1800 Sft

1800 Sft 827 44 44 915 16,47,000/

7

Administration Buildings = 900 Sft

900 Sft 827 44 44 915 8,23,500/-

8Boundary Wall

- - - -    

 2054 Sft

2054 Sft 883 - - 883 18,13,682/

9Gate and Gate Pillars 1No 54000/- - - - - 54,000/-

  -

- - - - - 12,375,872/-

10 Add 15% External Development road Sewerage etc 99,25,413/- 14,88,812/-

11 Add Wapda Connection Transformer and Straw etc = 10,00,000/-

12 Contingency (5%)           743,234/-

  Total cost of civil works 15,607,918/-

               

Annexure- 3MTS SOLAR POWER PLANT

Page 22: Solar Power Generation Plant

Estimated Cost of Plant and Machinery

     Rs: ("000")

Rs: ("000")

Sr.No. Description Qty Unit CostTotal Cost

1 Solar panel (poly Crystaline-200w) 2500 100 250000

2 Invertors (1 KVA) 5000 60 300000

3 Cables/ Fixing structure 2500 40 100000

4 Contingency (1%) - - 6500

  Installation & erection cost is included in it. - - -

  Total Cost of Machinery     656500

Annexure- 4MTS SOLAR POWER PLANTPre-Production expenses

Sr. No. Description   Rs. ("000")

1 Registration Charges 500

2 Sales Tax Registration Charges 300

3 Consultancy & Report Preparation Charges 200

4 Printing & Stationary 30

5 Conveyance Charges 40

6 Telephone & Postage 30

  Total Pre-prodction Expenses 1100

Annexure- 5MTS SOLAR POWER PLANT

Page 23: Solar Power Generation Plant

Estimated Cost of Project

        Rs:("000")

Sr.No. DescriptionLCY (000) FCY Total cost

1 Land 54,000 - 54,000

2 Building 15,608 - 15,608

3 Machinery 656,500 - 656,500

4 Furniture and Fixture 230 - 230

5 Office Equipment 170 - 170

6 Pre-operating expenses 1,100 - 1,100

7 Vehicle 1,000 - 1,000

8 Interest during construction @ 7% - - 37,589

  Estimated fixed cost - - 766,197

Add: Net Initial Net Working Capital - - 925

  Total Estimated Cost of Project - - 767,122

Annexure- 5 (a)MTS SOLAR POWER PLANT

Estimated cost of Furniture & Fixture

      Rs: ("000") Rs: ("000")

Sr.No. Description Qty Unit Cost Total Cost

1 Almirah 5 20 100

2 Tables 10 10 100

3 Chairs 30 1 30

  Total - - 230

Annexure- 5 (b)MTS SOLAR POWER PLANT

Page 24: Solar Power Generation Plant

Estimated cost of Vehicle

      Rs: ("000") Rs: ("000")

Sr.No. Description Qty Unit Cost Total Cost

1 Sheroz Pick up 1 1000 1000

  Total - - 1000

Annexure- 5 (c)MTS SOLAR POWER PLANT

Estimated cost of office equipment

      Rs: ("000") Rs: ("000")

Sr.No. Description Qty Unit Cost Total Cost

1 Computer 5 20 100

2 Printer 2 10 20

3 Type writer 2 10 20

4 Charger controller 2 15 30

         

  Total - - 170

Annexure- 6MTS SOLAR POWER PLANT

Initial Net Working Capital Requirement

Page 25: Solar Power Generation Plant

Descriptions Rs. "000"

     

A. Current Assets:  

   

1 Advances, & Prepayments 350

2 Stores & Spares 300

3 Cash and bank balance 500

     

  Total Current Assets 1150

     

B. Current liabilities:  

   

1 Less: Bank borrowing 75% of stores & spares 225

     

  Initial Net Working Capital 925

     

Annexure- 7MTS SOLAR POWER PLANT

Depreciation Schedule of Fixed Assets

      Rs. ("000")  

Sr. No. Description T.Cost Rs. Dep.

1 Plant & Machinery @1% 656,500 6565

2 Building @ 5% 15,608 780

3 Furniture & Fixture @ 20% 230 46

4 Office Equipment @ 20% 170 34

5 Vehicles @ 20% 1,000 200

Total 673,508 7,625

Note: - Depreciation will be constant over the life of assets.

Annexure- 8MTS SOLAR POWER PLANT

Manufacturing Overhead Cost

Page 26: Solar Power Generation Plant

  Rs ("000")

Fixed Cost:  

 

Depreciation 7,625

Insurance @ 2% of the solar system and spare parts 13006

650300*2%=13006  

Maintenance :  

 

Maintenance of solar pv module @ 1% of cost of solar panel 2500

Maintenance of Building @ 5% of Cost of Building 780

Maintenance of Vehicles @ 5% of Cost of Vehicles 50

         

Total Fixed Cost 23,961

Year ending Manufacturing Overheads as per Different Capacities:

Description

Years

2011 2012 2013

Rupees ("000")

  80% 85% 90%

Fixed Cost 23,961 23,961 23,961

   Total Cost of Manufacturing Overheads 23,961 23,961 23,961

Annexure- 9MTS SOLAR POWER PLANT

Sales Revenue

Page 27: Solar Power Generation Plant

 

DescriptionUnit price per

Kwh

Rupees (000)

  80% 85% 90%

      2011 2012 2013

(A)5 MW solar power plant produce 18250000

Kwh RS: 15 219000 232688 246375

  electricity in a year at its full capacity. - - - -

 That is computed as (5000 Kw*10 hrs*365 days) - - - -

    - - - -

  Total Sales - 219000 232688 246375

  Assumptions:

  1. Tariff rate is fixed for 20 years.

Annexure- 10MTS SOLAR POWER PLANT

Estimated income Statement

  Rupees (000)

Year ending December 31: 80% 85% 90%

  2011 2012 2012

sales 219000 232688 246375

Less: cost of sales:-  

Raw material -

-

-

Labor 3880 4462 5131

Manufacturing Overhead 23,961 23,961 23,961

Cost of sales 27,841 28,423 29,092

Gross profit 191159 204265 217283

Page 28: Solar Power Generation Plant

Operating expenses:      

Administrative expenses 3209 3690 4245

General expenses 1595 1835 2111

Total operating expenses 4804 5525 6356

Operating profit 186355 198740 210927

Other expenses:

 Financial charges on:

Long term loan @ 14% 75178 73463 71508

Bank borrowing -

-

-

Amortization of pre-production expenses 367 367 367

Total other expenses 75545 73830 71875

Profit Before Tax and Worker's Fund 110810 124910 139052

Worker's fund @ 1% 1108 1249 1391

Profit/(Loss) Before Tax 109702 123661 137661

Tax provision @ 40% 42602 48073 53560

Net Profit 67100 75588 84101

Annexure- 11MTS SOLAR POWER PLANT

Balance Sheet

  End of Operating Years

Page 29: Solar Power Generation Plant

Const.Year ending Dec 31 2,010 2,011 2,012 2,013Assets:   RS: (000)  Current Assets:        Cash and Bank Balance 275 71556 96729 126568Short term investment - 47,521 99289 153207

Stores & Spares 300 300 300 300

Advances and Prepayments 350 350 350 350

         Total current assets 925 119,727 196,668 280,425         Fixed Assets:        Fixed Assets at cost 765,097 765,097 765,097 765,097Less: accumulated Depriciation

- 7625 15,250 22,875

Fixed Assets Net 765,097 757,472 749,847 742,222

Intangibles 1100 733 367 -

Total Assets 767,122 877,932 946,882 1,022,647 Current Liabilities:        

Taxes payables - 42602 48073 53560

Worker's Fund payable - 1108 1249 1391

Current Maturity of Long term debt

- 12,250 13,965 15920

Total Current Liabilities - 55,960 63,287 70,871

Long Term Debts:        BOP Loan 536,985 524,735 510,770 494,850Total Long Term Debt 536,985 524,735 510,770 494,850Equity:        Capital 230,137 230,137 230,137 230,137

Retained Earnings - 67100 142688 226789

Total Equity 230,137 297,237 372,825 456,926         Total Debt and Equity 767,122 877,932 946,882 1,022,647

Annexure- 12MTS SOLAR POWER PLANT

Cash Flow Statement

 End of Construction Operating Years

Page 30: Solar Power Generation Plant

Years Ending Dec 31 2,010 2,011 2,012 2,013Sources of Funds   Rs 000 Rs 000 Rs 000

Operating profit - 186,355 198,740 210,927

Add: Depreciation - 7625 7625 7625

Total funds from operation - 193,980 206,365 218,552

Other sources:        

BOP Loan 536,985 -

-

-

Paid-Up Capital 230,137 -

-

-

Total sources of funds 767,122 193,980 206,365 218,552Application of funds        

Investment in Fixed Assets 727,508 -

-

-

Preproduction expenses 1100 -

-

-

Interest During Const. 37,589 -

-

-

Repayment of :        

BOP Loan -

- 12,250 13,965

Financial Charges on:        

Long Term loans - 75178 73463 71508

Payment of :        

Taxes -

- 42602 48073

Worker's Fund -

- 1108 1249

Increase in current asset (other than cash)

650

-

-

-

Short term investments -

47,521

51,769

53,918

Total Applications 766,847 122,699 181,192 188,713Cash Surplus 275 71,281 25,173 29,839

Cash at Beginning of Year - 275 71556 96729

Cash at end of Year 275 71,556 96,729 126,568

Annexure- 13MTS SOLAR POWER PLANTAdministrative expenses

  Rs: (000)  

Sr.No Designation No. of Salary/Month Annual

Page 31: Solar Power Generation Plant

Employees Salary

    Rupees(''000'')

1 Managing Director 2 50 1200

2 Accountant 3 15 540

3 Clerk 2 12 288

4 Chowkider 2 6 144

5 Peon/sweeper 2 5 120

    - - -

  Total 11 88 2292

Add: Fringe Benefits @ 40% - - 917

  Total Cost of Administrative Staff   3209

Year Wise Administrative Salaries:

       

      Rupees(''000'')

Sr.No DescriptionNo. of Employees 2011 2012 2013

1 Managing Director 2 1200 1380 1587

2 Accountant 3 540 621 714

3 Clerk 2 288 331 381

4 Chowkider 2 144 166 191

5 Peon/Sweeper 2 120 138 159

    - - - -

Total   11 2292 2636 3032

Add: Fringe Benefits @ 40% - 917 1054 1213

Total Administrative Salaries per Year 3209 3690 4245

Assumptions:Administrative salaries will increase 15% every year.

General Expenses

Sr.No Description Year Exp.(''000'')

1 Travelling Expenses 200

Page 32: Solar Power Generation Plant

2 Printing &stationary 70

3 Telephone,Telex,Postage 500

4 Rent, Rates and Taxes 400

5 Entertainment 50

6 Legal & Audit 175

7 Miscellaneous 200

  Total 1595

General Expenses:

Sr.No Description   Rupees(''000'')

1 Travelling Expenses 200 230 265

2 Printing &stationary 70 81 93

3 Telephone,Telex,Postage 500 575 661

4 Rent, Rates and Taxes 400 460 529

5 Entertainment 50 58 67

6 Legal & Audit 175 201 231

7 Miscellaneous 200 230 265

Total   1595 1835 2111

Annexure- 14MTS SOLAR POWER PLANT

Estimated labor cost

Labor cost Rs: (000)

Page 33: Solar Power Generation Plant

Sr.No DescriptionNo. of

Employees Salary/Month/Worker

Total Annual Salary

1 Plant Manager 2 20 4802 Operation Manager 5 18 10803 Control room Technician 3 10 3604 Electric Technicians 7 9 756

  Total 17 57 2676Add: Fringe Benefit (45% of basic salary)       1204

 Total Cost of Plant

Labor     3880

Assumptions:1. Direct labor will increase every year @ 15%

Year wise wages of Labor:

    Years

Sr.No Description 2011 2012 2013

    Rs(''000'')

1 Plant labor 3880 4462 5131

Total cost of labor 3880 4462 5131

Annexure- 15MTS SOLAR POWER PLANT

BREAK-EVEN ANALYSIS

Page 34: Solar Power Generation Plant

Commercial Break-even in the first Operating Year:

( At 80% Capacity )

( Rs. In '000' )

Items       Variable Cost  Fixed Cost   Total Cost

 

Labor 3,880

- 3,880

Manufacturing Overheads - 23,961 23,961

Administrative & General Expenses - 4,804 4,804

Interest / Mark-Up Expenses - 75,178 75,178

Amortization of pre-production expenses 367 367

Total: 3,880 104,310 108,190

Sales from Operations: 219,000

Break-Even Point:

104,310  

X 80%219,000 - 3,880

Break-Even Point: 39%

Page 35: Solar Power Generation Plant

Commercial Break-even in the third Operating Year:

( At 90% Capacity )

(Rs. In '000' )

Items      Variable

Cost  Fixed Cost   Total Cost

 

Labor 5,131 - 5,131

Manufacturing Overheads - 23,961 23,961

Administrative & General Expenses - 6,356 6,356

Interest / Mark-Up Expenses - 71,508 71,508

Worker's Participation Fund 1,391 - 1,391

Debt Payment -

13,965 13,965

Tax - 53,560 53,560

Total: 6,522 169,350 175,872

Sales from Operations: 246,375

Break-Even Point:

169,350  

X 90%246,375 - 6,522

Annexure-16

Break-Even Point: 63.54%

Page 36: Solar Power Generation Plant

MTS Solar Power plant (Pvt) Ltd.Calculation of Internal Financial Rate of Return

Years

CapitalOperatin

g Depreciation

Worker'sTaxes

Net Cash

Net Cash Inflow

Outlay Profit Fund Return (Outflow)

- 766,847 - - - - -

(766,847)

1 - 186,355 7,625 - - 193,980 193,9802 - 198,740 7,625 1,108 42,602 162,655 162,6553 - 210,927 7,625 1,249 48,073 169,230 169,2304 - 210,927 7,625 1,391 53,560 163,601 163,6015 - 210,927 7,625 1,391 53,560 163,601 163,6016 1,400 210,927 7,625 1,391 53,560 163,601 162,2017 - 210,927 7,625 1,391 53,560 163,601 163,6018 - 210,927 7,625 1,391 53,560 163,601 163,6019 - 210,927 7,625 1,391 53,560 163,601 163,601

10 - 210,927 7,625 1,391 53,560 163,601 163,60111 1,400 210,927 7,625 1,391 53,560 163,601 162,20112 - 210,927 7,625 1,391 53,560 163,601 163,60113 - 210,927 7,625 1,391 53,560 163,601 163,60114 - 210,927 7,625 1,391 53,560 163,601 163,60115 - 210,927 7,625 1,391 53,560 163,601 163,60116 1400 210,927 7,625 1,391 53,560 163,601 16220117 - 210,927 7,625 1,391 53,560 163,601 16360118 - 210,927 7,625 1,391 53,560 163,601 16360119 - 210,927 7,625 1,391 53,560 163,601 16360120 210,927 7,625 2,782 107,120

Assumptions:-

Calculation of IFRR for the project has been carried out under the following

assumptions:-

1. The economic life of the project would be 20 years.

IFRR

Page 37: Solar Power Generation Plant

2. The entire capital outlay would be incurred one year prior to the Commencement of

commercial operations.

3. Motor Vehicles and operating equipment would be replaced after every five years.

4. Salvage value at the end of the life of the project represents recovery of working

capital, book value of buildings, office furniture and fixtures and original value of land.

Annexure - 17MTS solar power plant

Loan Repayment Schedule

Years

Opening

Interest@14% Principle Payment

(000) Closing

Balance Balance

1 536,985 75,178 12,250 87,428 524,735

2 524,735 73,463 13,965 87,428 510,770

3 510,770 71,508 15,920 87,428 494,850

4 494,850 69,279 18,149 87,428 476,701

5 476,701 66,738 20,690 87,428 456,011

6 456,011 63,842 23,586 87,428 432,425

7 432,425 60,540 26,888 87,428 405,537

8 405,537 56775 30,653 87,428 374,884

9 374,884 52484 34,944 87,428 339,940

10 339,940 47592 39,836 87,428 300,104

11 300,104 42015 45,413 87,428 254,691

12 254691 35657 51,771 87,428 202,920

13 202920 28409 59,019 87,428 143,901

14 143901 20146 67,282 87,428 76,619

15 76619 10727 76701 87,428 -