Upload
localenergy
View
215
Download
0
Embed Size (px)
Citation preview
8/6/2019 Solar Briefing Note for Local Authorities on Procurement
1/6
8/6/2019 Solar Briefing Note for Local Authorities on Procurement
2/6
Q&A for Local Authorities
Questions/Comments Answer
For clarity, schools need landlord permission to
install this type of kit and as the buildings are not
owned by schools but managed.
The premises used by a particular school may or
may not belong to the council and the school
may or may not have been given rights to allow
use of the building by third parties. This will
depend on a case-by-case basis.
It could in the worse case scenario result in
enforcement action to remove the equipment.
Understood, and it is why we have insisted that
all permissions are in place before an installation
can go ahead.
In terms of the equipment, this is not materially
different to the situation that exists with, for
example, existing electricity meters which are
owned by the electricity company and which the
electricity company has access rights under the
terms of its contracts, something landlords are
comfortable with.
Who is the Designer, Principle Contractor? Avonside Renewables which is a subsidiary of
Avonside Group Services (one of the biggest
roofing and renewables groups in the country
who have carried out a considerable amount of
school-related work in the past).
Is it notifiable under Construction Design and
Management regs 2007, the CDMC?
The contract size brings these installations
below the threshold where the CDMC
regulations apply but having said this, Avonside
intend to proceed as if they did apply from the
point of view of best practice including
preparation of a school-specific Health & Safety
Plan, to be shared in advance with each school.
Will the Head teacher be the Client in this case
and not the County Council?
The CDMC regs do not apply for the purposes of
defining who is the Client. This said, the client of
the contractor is the owner of the equipment,
being the investment fund paying for it. Forpractical liaison purposes the school head will,
however, be treated as the main contact.
Who assesses the risk assessments and method
statements for the principle contractor?
Although the CDMC regs do not apply,
nevertheless Avonside will be preparing a risk
assessment during site visits and which will be
provided to the school prior to installation.
Note also that the investors and banking group
funding the installations are very cautious and
require an independent Technical Adviser to vet
all aspects of the work being performed by the
installer including this aspect (the requirement
for which is included as a contractualrequirement in the terms of their appointment)
8/6/2019 Solar Briefing Note for Local Authorities on Procurement
3/6
Questions/Comments Answer
What procurement regime has been undertakenfor the appointment of the principle contractor?
Proposals were invited from six contractors andthe selection made on the advice of the
sponsors engineering adviser.
Schools are subject to public procurement rules
and must abide by them as any public
organisation should. If not then they could be
open to challenge from competitors in this
competitive market. Is it necessary to comply with
OJEU?
No because neither the school nor the local
authority is procuring anything: no payment is
being made or financial liability incurred by
either. However, were this to be the case, the
contract size would in any case come below the
de minimis threshold. This has been confirmed
by the sponsors legal advisers.
What competency checks have been undertaken
for the principle contractor and designer?
Avonside Group Services is one of the biggest
groups of its kind in the country. Avonside
Renewables is MCS registered for the purposesof the installation of microgeneration including
solar PV
What liability does the Head have with regard to
management of installation works?
None provided he/she allows access for
installation in accordance with the Terms and
Conditions.
Are risk assessments undertaken for the residual
risks associated with maintenance and servicing
of plant and equipment for the future workforce, ie
working at height edge protection etc?
Yes: O&M is also to be carried out by Avonside
Renewables under a long-term contract (25
years) - the investor group is particularly
concerned to ensure this is the case.
Note that O&M will differ from installation in that
during installation edge barriers will be in placewhereas for maintenance man-anchors will be
used.
What risks (if any) are associated with the
equipment on roofs?
All risks are assumed by the owner, although the
school must not permit unauthorised persons to
access to the PV panels. The owner, the school
and indeed the local authority will be included as
additional insured parties under the global
insurance policies being put in place by the
lenders and investors in support of the financing
of the installations. These include loss through
damage to the equipment, property, third party
cover, and personal liability to name a fewfeatures.
Please provide details of all trades associated
with the installation and if accredited to any trade
body, ie Electricians to NICEIC/ECA etc
Avonside has sub-contracted WT Parker, a
leading national electrical company, to proceed
with provision of electrical services.
Is it possible to negotiate changes to the Terms &
Conditions?
Unfortunately not: this is a portfolio financing
and this requires the contract terms for each
school to be identical or the school cannot be
included. This is in part why the Terms &
Conditions effectively impose most of the
responsibilities and all of the liabilities on the
funders where possible.
8/6/2019 Solar Briefing Note for Local Authorities on Procurement
4/6
Questions/Comments Answer
What safeguards are in place to ensure thecompany offering the scheme and their
subcontractors are suitably qualified and
accredited to undertake the work in terms of their
technical capabilities, health and safety, CRB
checks, asbestos awareness training,
assessment of structural integrity of roofs, roof
condition and replacement intervals expected
etc?
Avonside is a major national roofing companywith MCS qualified experts and CRB qualified
team leaders. They have done extensive work in
schools in the past and this has been a pre-
condition to their selection. Screening of
schools suitability for inclusion in the
programme is being carried out based on an
assessment of roof condition by experienced
roof installation experts together with qualified
structural engineers. The quality of their work
will be reviewed and assessed by a leading
international engineering consultancy on behalf
of the funding entities as a condition of
proceeding.
Do the investors plan to combine the Feed in
Tariffs (FITs) with any other form of public funding
support (eg councils loans/guarantees, grants
etc)?
Advice from Ofgem (the industry regulator)
indicates that programmes receiving other public
funding support in whatever form will not be
eligible for FITs since the EU prohibits
combination of different sources of state aid and
council loans/finance/guarantees are considered
to be state aid.
The sales pitch appears to be designed to rush
schools into making a major decision in a month.
In addition once the school has signed they
appear to be locked in for 25 years.
We are not looking to rush schools and the
programme timetable has been extended to the
end of the summer term. However, places
available in the programme are limited to acertain number of kW and only those schools
that have been accepted onto the programme at
the time the funding is drawn will therefore be
able to take advantage of the proposal so it is
time sensitive.
It should also be noted that from 30 April 2012 it
is highly likely that the FITs will be reduced. This
means that any private sector offering to schools
will be on inferior terms. Therefore time is of the
essence.
There is no clear process concerning emergency
works.
The process is explained in the Terms &
Conditions. The School will contact theOperations Manager who will coordinate actions
with the school. Details of the Operations
Manager will be provided if a school is accepted
onto the programme
8/6/2019 Solar Briefing Note for Local Authorities on Procurement
5/6
Questions/Comments Answer
What warranties and guaranties are in place toensure quality of the equipment and
installation? Is it clear where liabilities rest as a
result of any failures?
Because the programme is being funded byleading international financial institutions, this is
being managed carefully for financing purposes.
The PV plant and equipment is owned by the
special purpose vehicle that is being financed
and there will have been a sign off by the
independent technical adviser as to the quality
of the equipment to be installed as a condition of
financing. The Terms and Conditions make it
clear that maintenance and replacement is the
responsibility of the Owner, not the school.
The maintenance arrangements are short on
detail.
Since the school is not the purchaser or owner,
it merely needs to know where responsibility lies(and on this the Terms & Conditions are
explicit). The Owner and the O&M Contractor
have a detailed contract prepared to
international project finance standards (>60
pages), as required by the financing institutions.
The Schools can take comfort that the lead
institution is funded by major pension funds who
are every bit as concerned as they are.
There are lots of clauses affecting the school, for
instance the requirement for access between
0800-2000 hours. This would mean the school
would have to provide out of hours staff.
The installation process is around one week and
the school will of course be advised about the
precise installation timing in advance. Avonside
as the roof installation group have done aconsiderable amount of school work in the past
and have recommended the hours on the basis
that certain aspects of the work will be best
carried out outside of normal school hours eg
loading and unloading in the interests of health
and safety. Once the installation is complete
access would be by arrangement with the school
only.
8/6/2019 Solar Briefing Note for Local Authorities on Procurement
6/6
Questions/Comments Answer
The document contains open ended terms like 'asquickly as possible'. These clearly need to be
defined to reduce the opportunities for
misunderstandings. In fact the whole agreement,
whilst written in the spirit of co-operation is
vague. This leaves the document open to
interpretation.
The contract has been carefully prepared inconjunction with a major law firm to be on a
basis that (1) the schools can and should
actually understand what they are agreeing to
and (2) at a level of detail which is appropriate to
the scope and extent of what they are being
asked to do, namely hosting PV panels at no
cost to themselves in return for which they are
given the power for free. There is plenty of case
law as the meaning of terms such as as quickly
as possible although it is considered that
people will understand what this means in
practice. Please also bear in mind that since
continuous performance is also demanded by
the financing institutions and that part of the
operations managers remuneration is based on
maintaining performance in the usual way, there
is, in fact alignment of interests to ensure
downtime is minimised. This is also the reason
for having real-time remote monitoring of each
PV facility to ensure outages can be minimised
Please do accept this correspondence in the spirit
in which it is meant; that is to get the best
possible deal for public money and our schools
whilst helping reduce carbon emissions. The
County Council and the Energy Team are strong
supporters of the Eco-Schools programme and
want to see the existing good quality maintained
so feel bound to make our comments and
concerns known to you.
It is key to appreciate that public money is not
being spent on this programme. It is funded by
the private sector at a scale where best practice
associated with international financings (rather
than cowboy installers) can be employed. At the
end of the day, however, it will not be possible to
include a school if it is located in an area where
the local authority is unsupportive: the investors
will not accept this and Eco-Schools is therefore
seeking to avoid this.