Solar Briefing Note for Local Authorities on Procurement

Embed Size (px)

Citation preview

  • 8/6/2019 Solar Briefing Note for Local Authorities on Procurement

    1/6

  • 8/6/2019 Solar Briefing Note for Local Authorities on Procurement

    2/6

    Q&A for Local Authorities

    Questions/Comments Answer

    For clarity, schools need landlord permission to

    install this type of kit and as the buildings are not

    owned by schools but managed.

    The premises used by a particular school may or

    may not belong to the council and the school

    may or may not have been given rights to allow

    use of the building by third parties. This will

    depend on a case-by-case basis.

    It could in the worse case scenario result in

    enforcement action to remove the equipment.

    Understood, and it is why we have insisted that

    all permissions are in place before an installation

    can go ahead.

    In terms of the equipment, this is not materially

    different to the situation that exists with, for

    example, existing electricity meters which are

    owned by the electricity company and which the

    electricity company has access rights under the

    terms of its contracts, something landlords are

    comfortable with.

    Who is the Designer, Principle Contractor? Avonside Renewables which is a subsidiary of

    Avonside Group Services (one of the biggest

    roofing and renewables groups in the country

    who have carried out a considerable amount of

    school-related work in the past).

    Is it notifiable under Construction Design and

    Management regs 2007, the CDMC?

    The contract size brings these installations

    below the threshold where the CDMC

    regulations apply but having said this, Avonside

    intend to proceed as if they did apply from the

    point of view of best practice including

    preparation of a school-specific Health & Safety

    Plan, to be shared in advance with each school.

    Will the Head teacher be the Client in this case

    and not the County Council?

    The CDMC regs do not apply for the purposes of

    defining who is the Client. This said, the client of

    the contractor is the owner of the equipment,

    being the investment fund paying for it. Forpractical liaison purposes the school head will,

    however, be treated as the main contact.

    Who assesses the risk assessments and method

    statements for the principle contractor?

    Although the CDMC regs do not apply,

    nevertheless Avonside will be preparing a risk

    assessment during site visits and which will be

    provided to the school prior to installation.

    Note also that the investors and banking group

    funding the installations are very cautious and

    require an independent Technical Adviser to vet

    all aspects of the work being performed by the

    installer including this aspect (the requirement

    for which is included as a contractualrequirement in the terms of their appointment)

  • 8/6/2019 Solar Briefing Note for Local Authorities on Procurement

    3/6

    Questions/Comments Answer

    What procurement regime has been undertakenfor the appointment of the principle contractor?

    Proposals were invited from six contractors andthe selection made on the advice of the

    sponsors engineering adviser.

    Schools are subject to public procurement rules

    and must abide by them as any public

    organisation should. If not then they could be

    open to challenge from competitors in this

    competitive market. Is it necessary to comply with

    OJEU?

    No because neither the school nor the local

    authority is procuring anything: no payment is

    being made or financial liability incurred by

    either. However, were this to be the case, the

    contract size would in any case come below the

    de minimis threshold. This has been confirmed

    by the sponsors legal advisers.

    What competency checks have been undertaken

    for the principle contractor and designer?

    Avonside Group Services is one of the biggest

    groups of its kind in the country. Avonside

    Renewables is MCS registered for the purposesof the installation of microgeneration including

    solar PV

    What liability does the Head have with regard to

    management of installation works?

    None provided he/she allows access for

    installation in accordance with the Terms and

    Conditions.

    Are risk assessments undertaken for the residual

    risks associated with maintenance and servicing

    of plant and equipment for the future workforce, ie

    working at height edge protection etc?

    Yes: O&M is also to be carried out by Avonside

    Renewables under a long-term contract (25

    years) - the investor group is particularly

    concerned to ensure this is the case.

    Note that O&M will differ from installation in that

    during installation edge barriers will be in placewhereas for maintenance man-anchors will be

    used.

    What risks (if any) are associated with the

    equipment on roofs?

    All risks are assumed by the owner, although the

    school must not permit unauthorised persons to

    access to the PV panels. The owner, the school

    and indeed the local authority will be included as

    additional insured parties under the global

    insurance policies being put in place by the

    lenders and investors in support of the financing

    of the installations. These include loss through

    damage to the equipment, property, third party

    cover, and personal liability to name a fewfeatures.

    Please provide details of all trades associated

    with the installation and if accredited to any trade

    body, ie Electricians to NICEIC/ECA etc

    Avonside has sub-contracted WT Parker, a

    leading national electrical company, to proceed

    with provision of electrical services.

    Is it possible to negotiate changes to the Terms &

    Conditions?

    Unfortunately not: this is a portfolio financing

    and this requires the contract terms for each

    school to be identical or the school cannot be

    included. This is in part why the Terms &

    Conditions effectively impose most of the

    responsibilities and all of the liabilities on the

    funders where possible.

  • 8/6/2019 Solar Briefing Note for Local Authorities on Procurement

    4/6

    Questions/Comments Answer

    What safeguards are in place to ensure thecompany offering the scheme and their

    subcontractors are suitably qualified and

    accredited to undertake the work in terms of their

    technical capabilities, health and safety, CRB

    checks, asbestos awareness training,

    assessment of structural integrity of roofs, roof

    condition and replacement intervals expected

    etc?

    Avonside is a major national roofing companywith MCS qualified experts and CRB qualified

    team leaders. They have done extensive work in

    schools in the past and this has been a pre-

    condition to their selection. Screening of

    schools suitability for inclusion in the

    programme is being carried out based on an

    assessment of roof condition by experienced

    roof installation experts together with qualified

    structural engineers. The quality of their work

    will be reviewed and assessed by a leading

    international engineering consultancy on behalf

    of the funding entities as a condition of

    proceeding.

    Do the investors plan to combine the Feed in

    Tariffs (FITs) with any other form of public funding

    support (eg councils loans/guarantees, grants

    etc)?

    Advice from Ofgem (the industry regulator)

    indicates that programmes receiving other public

    funding support in whatever form will not be

    eligible for FITs since the EU prohibits

    combination of different sources of state aid and

    council loans/finance/guarantees are considered

    to be state aid.

    The sales pitch appears to be designed to rush

    schools into making a major decision in a month.

    In addition once the school has signed they

    appear to be locked in for 25 years.

    We are not looking to rush schools and the

    programme timetable has been extended to the

    end of the summer term. However, places

    available in the programme are limited to acertain number of kW and only those schools

    that have been accepted onto the programme at

    the time the funding is drawn will therefore be

    able to take advantage of the proposal so it is

    time sensitive.

    It should also be noted that from 30 April 2012 it

    is highly likely that the FITs will be reduced. This

    means that any private sector offering to schools

    will be on inferior terms. Therefore time is of the

    essence.

    There is no clear process concerning emergency

    works.

    The process is explained in the Terms &

    Conditions. The School will contact theOperations Manager who will coordinate actions

    with the school. Details of the Operations

    Manager will be provided if a school is accepted

    onto the programme

  • 8/6/2019 Solar Briefing Note for Local Authorities on Procurement

    5/6

    Questions/Comments Answer

    What warranties and guaranties are in place toensure quality of the equipment and

    installation? Is it clear where liabilities rest as a

    result of any failures?

    Because the programme is being funded byleading international financial institutions, this is

    being managed carefully for financing purposes.

    The PV plant and equipment is owned by the

    special purpose vehicle that is being financed

    and there will have been a sign off by the

    independent technical adviser as to the quality

    of the equipment to be installed as a condition of

    financing. The Terms and Conditions make it

    clear that maintenance and replacement is the

    responsibility of the Owner, not the school.

    The maintenance arrangements are short on

    detail.

    Since the school is not the purchaser or owner,

    it merely needs to know where responsibility lies(and on this the Terms & Conditions are

    explicit). The Owner and the O&M Contractor

    have a detailed contract prepared to

    international project finance standards (>60

    pages), as required by the financing institutions.

    The Schools can take comfort that the lead

    institution is funded by major pension funds who

    are every bit as concerned as they are.

    There are lots of clauses affecting the school, for

    instance the requirement for access between

    0800-2000 hours. This would mean the school

    would have to provide out of hours staff.

    The installation process is around one week and

    the school will of course be advised about the

    precise installation timing in advance. Avonside

    as the roof installation group have done aconsiderable amount of school work in the past

    and have recommended the hours on the basis

    that certain aspects of the work will be best

    carried out outside of normal school hours eg

    loading and unloading in the interests of health

    and safety. Once the installation is complete

    access would be by arrangement with the school

    only.

  • 8/6/2019 Solar Briefing Note for Local Authorities on Procurement

    6/6

    Questions/Comments Answer

    The document contains open ended terms like 'asquickly as possible'. These clearly need to be

    defined to reduce the opportunities for

    misunderstandings. In fact the whole agreement,

    whilst written in the spirit of co-operation is

    vague. This leaves the document open to

    interpretation.

    The contract has been carefully prepared inconjunction with a major law firm to be on a

    basis that (1) the schools can and should

    actually understand what they are agreeing to

    and (2) at a level of detail which is appropriate to

    the scope and extent of what they are being

    asked to do, namely hosting PV panels at no

    cost to themselves in return for which they are

    given the power for free. There is plenty of case

    law as the meaning of terms such as as quickly

    as possible although it is considered that

    people will understand what this means in

    practice. Please also bear in mind that since

    continuous performance is also demanded by

    the financing institutions and that part of the

    operations managers remuneration is based on

    maintaining performance in the usual way, there

    is, in fact alignment of interests to ensure

    downtime is minimised. This is also the reason

    for having real-time remote monitoring of each

    PV facility to ensure outages can be minimised

    Please do accept this correspondence in the spirit

    in which it is meant; that is to get the best

    possible deal for public money and our schools

    whilst helping reduce carbon emissions. The

    County Council and the Energy Team are strong

    supporters of the Eco-Schools programme and

    want to see the existing good quality maintained

    so feel bound to make our comments and

    concerns known to you.

    It is key to appreciate that public money is not

    being spent on this programme. It is funded by

    the private sector at a scale where best practice

    associated with international financings (rather

    than cowboy installers) can be employed. At the

    end of the day, however, it will not be possible to

    include a school if it is located in an area where

    the local authority is unsupportive: the investors

    will not accept this and Eco-Schools is therefore

    seeking to avoid this.