Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Sol Invictus 6 PV Facility South West of Aggeneys, Northern Cape Province
Environmental Impact Assessment Process
Split Environmental Impact Report 2
DEA Ref No.: 14/12/16/3/3/2/871
August 2018
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Project Details Page i
PROJECT DETAILS
DEA Reference No. : 14/12/16/3/3/2/871
Title : Environmental Impact Assessment Process
Split Report 2: EIA Report for the Sol Invictus 6 PV
Facility, Northern Cape
Authors : Savannah Environmental (Pty) Ltd
Shaun Taylor
Jo-Anne Thomas
Specialists : Savannah Environmental
Jayson Orton of ASHA Consulting (Pty) Ltd
Dr John E. Almond of Natura Viva cc
Candice Hunter of Savannah Environmental
Jon Marshall of Afzelia Environmental Consultants
Simon Todd of Simon Todd Consulting
Client : Sol Invictus 6 (Pty) Ltd
Report Status
: Split Environmental Impact Assessment Report in
support of an Application for Amendment (Splitting) of
the Environmental Authorisation for public review
Review Period : 29 August 2018 to 1 October 2018
Report Date : August 2018
When used as a reference this report should be cited as: Savannah Environmental (2018) Environmental
Impact Assessment Report: Proposed Sol Invictus 6 PV Facility, Northern Cape
COPYRIGHT RESERVED
This technical report has been produced for Sol Invictus 6 (Pty) Ltd. The intellectual property contained in this report remains vested in Savannah Environmental. No part of the report may be reproduced in any manner without written permission from Savannah
Environmental (Pty) Ltd or Sol Invictus 6 (Pty) Ltd.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page ii
PURPOSE OF THE ENVIRONMENTAL IMPACT ASSESSMENT REPORT
Sol Invictus 6 (Pty) Ltd (formerly known as, Cyralex (Pty) Ltd) is proposing the development of the Sol
Invictus 6 PV facility and associated infrastructure on Portion 5 of the Farm Ou Taaisbosmond 66 which is
earmarked as the project area for the proposed development. The project area is situated approximately
30 km south-west of Aggeneys in the Northern Cape Province and is located within the Nama Khoi Local
Municipality and borders the Khai-Ma Local Municipality. Both municipalities fall under the jurisdiction of
the Namakwa District Municipality.
Savannah Environmental (Pty) Ltd undertook an Environmental Impact Assessment (EIA) process on behalf
of the project applicant, in terms of the EIA Regulations of 2014 GN R. 993 of the National Environmental
Management Act (No. 107 of 1998). The Final Environmental and Social Impact Assessment Report was
submitted to the National Department of Environmental Affairs (DEA), as the competent authority, in June
2016. On the basis of the outcomes of the EIA process, Environmental Authorisation (EA) for the project
was issued by the Department of Environmental Affairs (DEA) in September 2016.
The PV facility has been authorised for a contracted capacity of up to 150 MW, and will be connected to
the national grid via the Aggeneis-Nama 220 kV overhead line that connects to the Eskom’s Aggeneis
Substation, located 17 km east of the project area. On the basis of the outcomes of the EIA process, the
following project components have been authorised:
» Arrays of PV panels with a contracted capacity of up to 150 MW;
» Mounting structures to support the PV panels;
» Cabling between the project components;
» On-site inverters to convert the power from direct current to an alternating current;
» On-site substation;
» Battery storage mechanism with a storage capacity of 300 MWh;
» 33/220kV transformer;
» 220kV double circuit powerline;
» Temporary laydown areas;
» Batching plant;
» Internal access roads and fencing around the development site;
» Site offices; and
» Workshop areas for maintenance and storage.
The proposed project development site is considered suitable and favourable by the developer for the
construction of a solar PV facility from a technical perspective due to the following site characteristics:
» Climatic conditions: Climatic conditions determine the economic viability of a solar energy facility as
it is directly dependent on the annual direct solar irradiation values for a particular area.
» Topographic conditions: The local site conditions are optimum for a development of this nature. A
level surface area (i.e. with a minimal gradient in the region of 1%) is preferred for the installation of
PV panels. The site slope and aspect of the proposed development area is predominantly flat.
» Extent of the site: Significant land area is required for the proposed development. The site is larger
than the area required for development which allows for the avoidance of any identified
environmental and/or technical constraints.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page iii
» Proximity: This site is located in close proximity to an existing Eskom substation, which minimises the
need for a long power line connection. This is preferred from an environmental and technical
perspective.
1. Application to Split the Environmental Authorisation
The project is intended to be bid into future rounds of the Department of Energy’s (DoE) Renewable
Energy Independent Power Producers Procurement (REIPPP) Programme which is expected to be in
November 2018. in terms of the Department of Energy’s (DoE) competitive bidding process for procuring
renewable energy from Independent Power Producers in South Africa, a threshold has been set for the
maximum amount of megawatts per project entered into the bid. The threshold for a single solar energy
project for submission into the bid has been set at 75 MW. In terms of the DoE’s requirements, a separate
authorisation is required for each 75 MW facility. Therefore, the applicant is requesting that the authorised
facility of 150 MW in capacity be split into two (2) separate projects of no more than 75 MW each. These
projects are to be known as Sol Invictus 4 PV Solar Facility and Sol Invictus 6 PV Solar Facility. Each of these
EAs should include authorisation for the relevant associated infrastructure. The requested amendment for
the split of the EA into two (2) separate EAs (i.e. each of 75 MW total output capacity) will fall within the
originally authorised footprint of the facility and does not trigger any new listed activities.
Information in the report which has been updated has been underlined for ease of reference. Otherwise
the information presented here is identical to that presented in the original EIA report. No substantive
changes to the EIA Report submitted in support of the original application for authorisation have been
made, although changes have been made where corrections or updates to factual information is
required. The EMPr has also been amended to separately consider each aspect.
This is Split Report 2 for the Sol Invictus 6 PV Facility.
Apart from the splitting of the Environmental Authorisation, the following amendments to the Authorisation
are also requested:
Project title: Sol Invictus 6 PV Facility and associated infrastructure, South West of Aggeneys, Northern Cape
Co-Ordinates of corner points of the site and associated infrastructure:
Infrastructure Dimensions/ Details
Corner points for the Sol Invictus 6
development site
NW Corner
NE Corner
SW Corner
SE Corner
29° 17' 57.39" S 18° 36' 53.92" E
29° 17' 58.63" S 18° 38' 05.47" E
29° 18' 32.21" S 18° 36' 53.16" E
29° 18' 33.57" S 18° 38' 04.65" E
Corner points for the Sol Invictus 6
Infrastructure
NW Corner
NE Corner
SW Corner
SE Corner
29° 18' 23.79" S 18° 36' 53.47" E
29° 18' 24.37" S 18° 37' 28.97" E
29° 18' 32.06" S 18° 36' 53.33" E
29° 18' 32.79" S 18° 37' 28.78" E
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page iv
Project details: The following project components comprise the Sol Invictus 6 PV Facility:
» Arrays of PV panels with a contracted capacity of up to 75 MW;
» Mounting structures to support the PV panels;
» Cabling between the project components;
» On-site inverters to convert the power from direct current to an alternating current;
» On-site substation;
» Battery storage mechanism with a storage capacity of 300 MWh;
» 33/220kV transformer;
» 220kV double circuit power line;
» Temporary laydown areas;
» Batching plant;
» Internal access roads and fencing around the development site;
» Site offices; and
» Workshop areas for maintenance and storage.
In terms of Condition 6 of the Environmental Authorisation and Chapter 5 of the EIA Regulations of
December 2014 (as amended on 07 April 2017), it is possible for an applicant to apply, in writing, to the
competent authority for a change or deviation from the project description to be approved. Savannah
Environmental has therefore prepared this split EIA report in support of the amendment application
submitted on behalf of Sol Invictus 6 (Pty) Ltd. An amendment application for the split has been submitted
to the DEA. The DEA has advised that this application is considered to be a Part 2 amendment as
contemplated in terms of Regulation 31 of the EIA Regulations (2014), as amended.
Regulation 32 of the EIA Regulations (2014), as amended, deals with the process and consideration of Part
2 amendment applications as follows:
32(1) The applicant must within 90 days of receipt by
the competent authority of the application made in
terms of regulation 31, submit to the competent
authority -
(a) a report, reflecting –
(i) an assessment of all impacts related to the
proposed change;
(i) No environmental impacts will result. The report is
effectively a “repackage” of the original final EIA
report dated June 2016, submitted to DEA, and
which was authorised 22 September 2016. This
report considers the Sol Invictus 6 PV facility and
associated infrastructure and provides an
assessment of the impacts in this regard, as
originally presented in the original final EIA report
(dated June 2016). No new information has been
provided for the requested amendment of the split
of the EA.
(ii) advantages and disadvantages associated
with the proposed change; and
(ii) The need for the split is presented above, in the
“PURPOSE OF THE SPLIT OF THE ENVIRONMENTAL
IMPACT ASSESSMENT REPORT” section. There are no
environmental advantages or disadvantages per se
associated with the requested split amendment.
However, should the amendment not be granted,
the applicant will not be able to meet the
requirements of the DoE or the lenders. The project
may then not proceed which would result in a lost
opportunity in terms of the provision of renewable
energy to the grid and local socio-economic
benefits.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page v
(iii) measures to ensure avoidance,
management and mitigation of impacts
associated with such proposed change;
and
(iii) No additional mitigation measures are proposed as
a result of the requested split amendment since no
additional environmental impacts are associated
with this requested amendment.
(iv) any changes to the EMPr; (iv) The EMPr has been amended to only include those
measures applicable to the relevant project under
consideration and is included in Appendix I. The
mitigation measures presented in this split EIA report
are relevant to the Sol Invictus 6 PV Facility and
associated infrastructure only as presented in the
original EIA report (dated June 2016). No additional
mitigation measures are proposed since no new
impacts will occur as a result of the split
amendment.
2. Other Amendments being Applied for
Apart from the splitting of the EA, the following amendments are also requested for each EA:
1. Increase in height of the authorised PV panels from 3m to 5m:
Following developments in technology after the issuing of the original EA and due to economic efficiency
considerations, Sol Invictus 6 (Pty) Ltd (applicant) is proposing to install a PV technology on the site which is
best suited to the conditions on the site (and will increase the efficiency of the facility). The applicant is
therefore requesting to amend the height of authorised PV panels from 3m to 5m. This amendment is
being proposed in order to increase the efficiency of the facility and consequently, the economic
competitiveness thereof.
2. Change in company name and postal address details, as well as addition of the cell phone number
details of the holder of the Environmental Authorisation:
The company name and postal address details for Cyralex (Pty) Ltd (now called Sol Invictus 6 (Pty) Ltd)
have changed. In addition, the cell phone details of the relevant contact person are available and are to
be added to the EA. Therefore, the relevant details of the holder of the environmental authorisation need
to be amended.
A separate amendment motivation report has been prepared by Savannah Environmental for the above
two amendments.
3. Layout of the Split EIA Report
The nature and extent of the Solar Facility, as well as the potential environmental impacts associated with
the construction, operation and decommissioning phases are explored in more detail in this Split EIA
Report. The Split EIA Report consists of nine chapters, which include:
» Chapter 1 provides background to the project and the environmental impact assessment, and an
introduction to the rationale behind the selected development site and technology proposed.
» Chapter 2 provides the project description, need and desirability, rationale of the development site
selection and identified project alternatives.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page vi
» Chapter 3 outlines the strategic legal context for the energy planning in South Africa, and specifically
for the project.
» Chapter 4 outlines the approach to undertaking the environmental impact assessment process.
» Chapter 5 describes the existing biophysical and socio-economic environment within and surrounding
the project area.
» Chapter 6 provides an assessment of the potential issues and impacts associated with the project and
presents recommendations for mitigation of significant impacts.
» Chapter 7 provides an assessment of the potential for cumulative impacts.
» Chapter 8 presents the conclusions and recommendations based on the findings of the EIA.
» Chapter 9 provides a list of reference material used to compile the EIA Report.
The Scoping Phase of the EIA process identified potential issues associated with the proposed project, and
defined the extent of the studies required within the EIA Phase. The EIA Phase addresses those identified
potential environmental impacts and benefits associated with all phases of the project including design,
construction and operation, and recommends appropriate mitigation measures for potentially significant
environmental impacts. The Split EIA report aims to provide the environmental authorities with sufficient
information to make an informed decision regarding the proposed project.
The release of a Split EIA Report provided stakeholders with an opportunity to verify that the issues they
have raised to date have been captured and adequately considered within the study. The Split EIA
Report will incorporate all issues and responses prior to submission to the National Department of
Environmental Affairs (DEA), the decision-making authority for the project. The Split EIA report
demonstrates that the conditions of the Acceptance of the Scoping Report, and the comments received
during the review period of the EIA report (including those received from the Competent Authority) have
been considered and addressed as required.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page vii
DEA REQUIREMENT FOR THE SPLIT ENVIRONMENTAL IMPACT ASSESSMENT
REPORT
Savannah Environmental has compiled a table (refer to Table 1 below) which outlines the DEA
requirements as outlined in the acceptance of the scoping report dated 17 February 2016, and where in
the Split EIA report the requirements have been addressed within this report for ease of reference.
TABLE 1: Information Requested By DEA
No. Information Requirements Cross Reference in this
Split EIA Report
i This Department advises that the applied listed activities and their relevant issues
be addressed and assessed in the EIAr.
Chapter 4
ii Please ensure that all relevant listing notice activities applied for, are specific
and that it can be linked to the development activity or infrastructure described
in the project description.
Chapter 4
Chapter 6-7
iii Should there be a need to amend the application form, please note that the
Departments application form template has been amended and can be
downloaded from the following link
https://www.environment.gov.za/documents/forms.
Appendix L
iv It is imperative that the relevant authorities are continuously involved throughout
the EIAr process.
Appendix B
Appendix C
v The EIAr must provide an assessment of the impacts and mitigation measures for
each of the listed activities applied for.
Chapter 6-7
vi All specialist studies submitted with the Scoping Report must form part of the EIAr
and must be current, consider cumulative impacts, be relevant to the
development and comply with Appendix 6 of the EIA Regulation 2014.
Appendix D-H
Chapter 5-7
vii An avifaunal impact assessment must be conducted and submitted to the
Department with the EIAr.
Appendix E
viii You are further reminded to provide a description of any identified alternatives
for the proposed activity that are feasible and reasonable, including the
advantages and disadvantages that the proposed activity or alternatives will
have on the environment and on the community that may be affected by the
activity. Alternatively, submit written proof of an investigation and motivation if
no reasonable or feasible alternatives exist.
Chapter 2
ix The EIAr must provide the technical details for the proposed facility in a table
format as well as their description and/or dimensions. A sample of the minimum
information required is listed under point 2 of the EIA information required for SEF
below.
Table 2.1 and 2.2 in
Chapter 2
x The EIAr must provide the four corners coordinates for the proposed
development site (note that if the site have numerous bend points, each and
every bend point coordinates must be provided) as well as the start, middle and
end point of all linear activities.
Table 2.3 in Chapter 2
xi The EIAr must provide the following:
• Clear indication of the envisioned area for the proposed solar facility;
i.e. placing of photovoltaic (PV) arrays and all associated infrastructure
should be mapped at an appropriate scale.
• Clear description of all associated infrastructure. This description must
include, but not limited to the following:
I. Power lines;
Appendix K: Maps
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page viii
No. Information Requirements Cross Reference in this
Split EIA Report
II. Internal roads infrastructure; and;
III. All supporting onsite infrastructure such as laydown area, guard
house and control room etc.
xii The EIAr must provide an indication of the solar facility in respect to the location
of other energy facilities and its associated infrastructure.
Chapter 7
xiii The EIAr must provide detailed need and desirability as to why there is a need
for the development and why the specific location is desirable.
Chapter 1-2
xiv The Department of Water and Sanitation (DWS) must be consulted during the
course of the process. Proof of consultation must be provided for in the EIAr.
Appendix C
xv The EIAr must provide an indication of the internal access roads and the impact
associated with them must be adequately assessed in the EIAr and the EMPr.
Chapter 6
xvi The inclusion of all received comments and response thereto in the comments
and response report.
Appendix C
xvii Information on services required on the site, e.g. sewage, refuse removal, water
and electricity. Who will supply these services and has an agreement and
confirmation of capacity been obtained? Proof of these agreements must be
provided.
Chapter 2
xviii The EIAr must provide a layout which depicts the entire facility, i.e. the solar and
grid connection infrastructure.
Appendix K
Chapter 8 (Figure 8.2)
xix The assessment of impacts and the Environmental Impact Assessment process;
and, the requirements of the Public Participation Process (PPP) must be in
accordance with the Regulation 39 to 44 of the GN R982 of EIA Regulations
2014.
Appendix C
xx A copy of the final site layout map. All available biodiversity information must be
used in the finalisation of the layout map. Existing infrastructure must be used as
far as possible e.g. roads. The layout map must indicate the following:
• Positions of PV arrays and its associated infrastructure;
• Permanent laydown area footprint;
• Internal roads indicating width (construction period width and
operation period width) and with numbered sections between the
other site elements which they serve (to make commenting on sections
possible);
• Wetlands, drainage lines, rivers, stream and water crossing of roads and
cables indicating the type of bridging infrastructures that will be used.
• The location of sensitive environmental features on site e.g. CBAs,
heritage sites, wetlands, drainage lines etc. that will be affected by the
facility and its associated infrastructure;
• Substation(s) and/or transformer(s) sites including their entire footprint;
• Connection routes (including pylon positions) to the distribution/
transmission network;
• All existing infrastructure on the site, especially roads;
• Buffer areas;
• Buildings, including accommodation; and,
• All “no-go” areas.
Appendix K
Chapter 8 (Figure 8.2)
xxi An environmental sensitivity map indicating environmental sensitive areas and
features identified during the EIA process.
Appendix K
Chapter 8 (Figure 8.1)
xxii A map combining the final layout map superimposed (overlain) on the
environmental sensitivity map.
Appendix K
Chapter 8 (Figure 8.1)
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page ix
No. Information Requirements Cross Reference in this
Split EIA Report
xxiii A Shapefile of the preferred development layout/ footprint must be submitted
to this Department. The Shapefile must be created using the Hartebeesthoek 94
Datum and the data should be in Decimal Degree Format using the WGS 84
Spheroid. The Shapefile must include at a minimum the following extensions i.e.
.shp; .shx; .dbf; .prj; and, .xml (Metadata file). If specific symbology was assigned
to the file, then the .avl and/or the .lyr file must be included. Data must be
mapped at a scale of 1: 10 000 (please specify if an alternative scale was used).
The metadata must include a description of the base data used for digitising.
Submitted with the final
EIAr as a separate CD.
Environmental Management Programme
i All recommendations and mitigation measures recorded in the EIAr and the
specialist studies conducted.
Appendix I
ii The final site layout map Appendix I
Figure 1.1
iii Measures as dictated by the final site layout map and micro-siting. Appendix I
Figure 1.1
iv An environmental sensitivity map indicating environmental sensitive areas and
features identified during the EIA process.
Appendix I
Figure 1.2
v A map combining the final layout map superimposed (overlain) on the
environmental sensitivity map.
Appendix I
Figure 1.2
vi An alien invasive management plan to be implemented during construction
and operation of the facility. The plan must include mitigation measures to
reduce the invasion of alien species and ensure that the continuous monitoring
and removal of alien species is undertaken.
Appendix E of the EMPr
(Appendix I)
vii A plant rescue and protection plan which allows for the maximum transplant of
conservation important species from areas to be transformed. This plan must be
compiled by a vegetation specialist familiar with the site and be implemented
prior to commencement of the construction phase.
Appendix G of the EMPr
(Appendix I)
viii A re-vegetation and habitat rehabilitation plan to be implemented during the
construction and operation of the facility. Restoration must be undertaken as
soon as possible after completion of construction activities to reduce the
amount of habitat converted at any one time and to speed up the recovery to
natural habitats.
Appendix F of the EMPr
(Appendix I)
ix An open space management plan to be implemented during the construction
and operation facility.
Appendix E of the EMPr
(Appendix I)
x A traffic management plan for the site access roads to ensure that no hazards
would results from the increased truck traffic and that traffic flow would not be
adversely impacted. This plan must include measures to minimise impacts on
local commuters e.g. limiting construction vehicles travelling on public roadways
during the morning and late afternoon commute time and avoid using roads
through densely populated built-up areas so as not to disturb existing retail and
commercial operations.
Appendix H of the EMPr
(Appendix I)
xi A transportation plan for the transport of components and other large pieces of
equipment.
Appendix H of the EMPr
(Appendix I)
xii A storm water management plan to be implemented during the construction
and operation of the facility. The plan must ensure compliance with applicable
regulations and prevent off-site migration of contaminated storm water or
increased soil erosion. The plan must include the construction of appropriate
Appendix I of the EMPr
(Appendix I)
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page x
No. Information Requirements Cross Reference in this
Split EIA Report
design measures that allow surface and subsurface movement of water along
drainage lines so as not to impede natural surface and subsurface flows.
Drainage measures must promote the dissipation of storm water run-off.
xiii A fire management plan to be implemented during the construction and
operation of the facility.
Appendix K of the EMPr
(Appendix I)
xiv An erosion management plan for monitoring and rehabilitating erosion events
associated with the facility. Appropriate erosion mitigation must form part of this
plan to prevent and reduce the risk of any potential erosion.
Appendix J of the EMPr
(Appendix I)
xv An effective monitoring system to detect any leakage or spillage of all
hazardous substances during their transportation, handling, use and storage. This
must include precautionary measures to limit the possibility of oil and other toxic
liquids from entering the soil or storm water systems.
Section 6.5 of the EMPr
(Appendix I)
xvi Measures to protect hydrological features such as streams, rivers, pans,
wetlands, dams and their catchments, and other environmental sensitive areas
from construction impacts including the direct or indirect spillage of pollutants.
Appendix I of the EMPr
(Appendix I)
Savannah Environmental has compiled a table (refer to Table 2 below) which addresses the comments
raised by the DEA in the letter dated 3 June 2016 based on the on the EIAr dated May 2016, and clearly
indicates where in the Final EIR the requirements have been addressed within this report for ease of
reference.
Table 2: Response to comments raised by the DEA in the letter dated 3 June 2016 based on the on the EIAr
dated May 2016
DEA Ref Comments from DEA on the draft EIAr Report Reference and Response
from EAP
i It is noted that the exact thresholds related to the applied listed
activities are not specified in the application form. For instance,
the Environmental Assessment Practitioner (EAP) mentioned that
“the facility will require the construction of new internal access
roads within which will be wider than 8 metres”. Please ensure that
all required thresholds have been correctly specified in both the
application form and the final EIAr.
The activities applied for in the
application form are the same as
those mentioned in the Split EIAr.
All relevant listed activities applied
for, are specific and can be linked
to the development activity or
infrastructure as described in the
project description. Please refer to
Table 4.1 and Chapter 4 of the Split
EIA report.
ii Should there be a need to amend the application form, please
note that the Department’s application form template has been
amended and can be downloaded from the following link
https://www.environment.gov.za/documents/forms.
An amended application has been
submitted to update the
applicant’s details (refer to
Appendix L).
iii Coordinates for the proposed site as well as substation and power
line must be provided with the final EIAr. Coordinates must be
provided in the format DDMMSS.
Coordinates for the proposed site
as well as substation and power
line are provided in Table 2.3
Chapter 2 of the Split EIAr.
Coordinates are provided in the
format DDMMSS.
iv In terms of Appendix 3 of the EIA Regulations, 2014, the report must
include an undertaking under oath or affirmation from the EAP in
relation to:
An EAP affirmation is provided in
Appendix J
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page xi
DEA Ref Comments from DEA on the draft EIAr Report Reference and Response
from EAP
• The correctness of the information provided in the reports;
• The inclusion of comments and inputs from stakeholders and
interested and affected parties (I&APs);
• The inclusion of inputs and recommendations from the
specialist reports where relevant;
• Any information provided by the EAP to interested and
affected parties; and
• Responses by the EAP to comments or inputs made by
interested or affected parties.
v In terms of Appendix 4 of the EIA Regulations, 2014, the
environmental management programme (EMPr) must include an
environmental awareness plan describing the manner in which-
• The applicant intends to inform his or her employees of any
environmental risk;
• Which may result from their work; and
• Risks must be dealt with in order to avoid pollution or the
degradation of the environment.
An environmental awareness plan
is provided in section 6.4 of the
EMPr (refer to Appendix I)
vi Please ensure that all issues raised and comments received during
the circulation of the EIAr from registered I&APs and organs of state
which have jurisdiction (including this Department’s Biodiversity
Section) in respect of the proposed activity are adequately
addressed and included in the final EIAr.
All issues raised and comments
received during the circulation of
the Split EIAr from registered I&APs
and organs of state which have
jurisdiction in respect of the
proposed activity have been
adequately addressed and
included in the Split EIAr.
vii Proof of correspondence with the various stakeholders must be
included in the final EIAr. Should you be unable to obtain
comments, proof should be submitted to the Department of
attempts that were made to obtain comments.
Proof of correspondence with the
various stakeholders has been
included in Appendix C of this
report.
viii The Public Participation Process must be conducted in terms of
Regulation 39, 40, 41, 42, 43 and 44 of the EIA Regulations 2014.
The Public Participation Process
was conducted in terms of
Regulation 39, 40, 41, 42, 43 &44 of
the EIA Regulations 2014.
ix Proof that the notice of Environmental Impact Assessment process
was advertised in print media must be included in the final EIAr.
Alternatively, motivation as to why this was not done must be
provided.
Proof that the notice of
Environmental Impact Assessment
process was advertised in print
media and is included in the Split
EIAr Appendix C of this report.
x Recommendations provided by specialist reports must be
considered and used to inform the layout plan and EMPr.
Recommendations provided by all
specialists have been considered
and in response to the identified
need to adequately manage
impacts within sensitive areas
identified on the site development
footprint.
xi All specialist reports that were done in-house must be externally
peer reviewed before submission of the final EIA report.
The SIA is the only study that was
undertaken internally. This study
was externally reviewed by Dr.
Bews. A letter of proof is attached
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Purpose of the EIA report Page xii
DEA Ref Comments from DEA on the draft EIAr Report Reference and Response
from EAP
to the SIA report (refer to Appendix
H).
xii The EIAr must provide the technical details for the proposed facility
in a table format as well as their description and/or dimensions. A
sample of the minimum information required is listed under point 2
of the EIA information required for solar energy facility as requested
in the acceptance of the final Scoping Report (SR).
The technical details for the
proposed facility have been
provided in a table format together
with descriptions and/ or
dimensions have been included in
this EIAr (refer to Chapter 2, of the
report).
xiii The final EIAr must provide the final EMPr and final layout plan with
the information as requested in the acceptance of the final SR.
A final EMPr is provided in Appendix
I of the Split EIAr. A map combining
the final layout map superimposed
(overlain) on the environmental
sensitivity map has been included
in the Split EIAr – (refer to Chapter 8
and Appendix of the Split EIAr).
xiv You are further reminded that the final EIAr to be submitted to this
Department must comply with all the requirements in terms of the
scope of assessment and content of the EIAr in accordance with
Appendix 3 of the EIA Regulations, 2014.
This Split EIAr complies with all the
requirements in terms of the scope
of assessment and content of the
EIAr in accordance with Appendix
3 of the EIA Regulations, 2014.
xv Further note that in terms of Regulation 45 of the EIA Regulations
2014, this application will lapse if the applicant fails to meet any of
the timeframes prescribed in terms of these Regulations, unless an
extension has been granted in terms of Regulation 3(7).
The application meets the
timeframes prescribed in terms of
Regulation 45 of the EIA
Regulations 2014.
You are hereby reminded of Section 24F of the National
Environmental Management Act, Act No 107 of 1998, as
amended, that no activity may commence prior to an
environmental authorisation being granted by the Department.
The EAP acknowledges this
condition.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Invitation to Comment on Split EIA Report Page xiii
PUBLIC REVIEW OF THE SPLIT EIA REPORT
Savannah Environmental (Pty) Ltd has prepared a “split” Final Environmental Impact Assessment Report
(FEIR) as a motivation in support of the application for amendment to the EA, on behalf of Sol Invictus 6
(Pty) Ltd. This is split Report 1, which assesses the impacts of the Sol Invictus 6 PV Solar facility and
associated infrastructure. This split report is therefore effectively a “repackage” of the final EIA report
submitted to DEA in June 2016 in order to provide relevant and applicable information (i.e. the relevant
activities, properties, impact assessment, and mitigation for the facility). No new information to that
provided within the final EIA report is presented in this split report.
This draft Split Environmental Impact Assessment Report has been made available for review and
comment by Interested and Affected Parties (I&APs) and stakeholders at www.savannahSA.com from 29
August 2018 – 1 October 2018. CD copies were available on request.
Comments must be submitted by the latest on 1 October 2018, in writing to the contact details below:
PO Box 148, Sunninghill, 2157
Phone: 011 656 3237
Fax: 086 680 0547
E-mail: [email protected]
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Executive summary Page xiv
EXECUTIVE SUMMARY
Sol Invictus 6 (Pty) Ltd is proposing the
development of the Sol Invictus 6 PV facility and
associated infrastructure on Portion 5 of the Farm
Ou Taaisbosmond 66 which is earmarked as the
project area for the proposed development. The
project area is situated approximately 30 km
south-west of Aggeneys in the Northern Cape
Province and is located within the Nama Khoi
Local Municipality and borders the Khai-Ma Local
Municipality. (refer to Figure 1).
The project area is approximately 5000 ha in
extent comprising of privately owned land. The
proposed the PV Facility will have a facility
development footprint of ~210ha (within which
the solar field and other associated infrastructure
is included) within a designated development
site of approximately 700ha. The PV facility is
proposed to have a contracted capacity of up
to 75 MW.
The full extent of the 5 000 ha project area was
considered in the Scoping Study. However,
based on the specialist findings and sensitivities
identified during the scoping phase, it was
recommended at the end of the scoping phase
that the development site for the PV facility
(~700ha in extent) should appropriately located
in the north east corner of the project area.
The Sol Invictus 6 PV facility project will comprise
the following infrastructure typical of a PV
installation, and required associated
infrastructure, which is included in the scope of
this EIA:
» Arrays of PV panels with a contracted
capacity of up to 75 MW;
» Mounting structures to support the PV panels;
» Cabling between the project components,
to be laid underground where practical;
» On-site inverters to convert the power from a
direct current (DC) to an alternating current
(AC) and a on-site substation to facilitate the
connection between the solar energy facility
and the Eskom electricity grid;
» Battery storage mechanism with a storage
capacity of 300 MWh;
» Grid connection infrastructure including
33/220kV transformer and a new 220kV
double circuit power line from the PV facility
substation to loop in and loop out of the
Aggeneis-Nama 220kV power line, which runs
along the southern boundary of the project
area to the Aggeneis Substation;
» Temporary laydown areas;
» Batching plant;
» Internal access roads and fencing around
the development site and; and
» Site offices and workshop areas for
maintenance and storage.
In terms of sections 24 and 24D of NEMA, as read
with Government Notices R982, R983, R984, R985,
a Scoping and EIA process is required for the
proposed Sol Invictus 6 PV facility project.
EVALUATION OF THE PROPOSED PROJECT
The chapters contained of this report together
with the specialist studies contained within
Appendices D – H provide a detailed assessment
of the environmental impacts on the social and
biophysical environment as a result of the Sol
Invictus 6 PV facility. The assessment of potential
environmental impacts presented in this report is
based on a layout of the PV facility and
associated infrastructure provided by Sol Invictus
6 (Pty) Ltd. The nature and extent of this facility,
as well as potential environmental impacts
associated with the construction and operation
of a facility of this nature are explored in more
detail in this Environmental Impact Assessment
(EIA) Report. In summary, the following
conclusions have been drawn from the specialist
studies undertaken (refer to Appendix D-H and
Figure 2 for the sensitivity map).
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Executive summary Page xv
OVERALL CONCLUSION (IMPACT STATEMENT)
The technical viability of establishing a PV facility
with a capacity of up to 75 MW on a site located
on Portion 5 of the Farm Ou Taaisbosmond 66 has
been established by Sol Invictus 6 (Pty) Ltd. The
positive implications of establishing the Solar
Facility on the identified site include the following:
» The potential to harness and utilise solar
energy resources within the Northern
Province
» The project will assist the South African
government in reaching their set targets for
renewable energy.
» The project will assist the South African
government in the implementation of its
green growth strategy and job creation
targets.
» The project will assist the district and local
municipalities in reducing level of
unemployment through the creation of jobs
and supporting local business
» The National electricity grid in the Northern
Cape Province will benefit from the
additional generated power.
» Promotion of clean, renewable energy in
South Africa
» Creation of local employment, business
opportunities and skills development for the
area.
The findings of the specialist studies undertaken
within this EIA to assess both the benefits and
potential negative impacts anticipated as a
result of the proposed project conclude that
there are no environmental fatal flaws that should
prevent the proposed project from proceeding,
provided that the recommended mitigation and
management measures are implemented. The
significance levels of the majority of identified
negative impacts have been reduced by
implementing the mitigation measures
recommended by the specialist team during the
EIA process, and this specifically included the
consideration of the facility layout in relation to
sensitivities identified. The avoidance of areas of
sensitivity is illustrated by the facility layout
drawing included as Figure 8.1. The project has
considered constraints, and is considered to
meet the requirements of sustainable
development. Environmental specifications for
the management of potential impacts are
detailed within the Environmental Management
Programme (EMPr) for the PV facility included
within Appendix I.
With reference to the information available at this
planning approval stage in the project cycle, the
confidence in the environmental assessment
undertaken is regarded as acceptable provided
all measures are taken to protect and preserve
surrounding environment.
OVERALL RECOMMENDATION
Global climate change is widely recognised as
being one of the greatest environmental
challenges facing the world today. How a
country sources its energy plays a big part in
tackling climate change. As a net off-setter of
carbon, renewable energy technologies can
assist in reducing carbon emissions, and can play
a big part in ensuring security of energy supply, as
other sources of energy are depleted or become
less accessible. South Africa currently relies on
coal-powered energy to meet more than 90% of
its energy needs. As a result, South Africa is one
of the highest per capita producers of carbon
emissions in the world and Eskom, as an energy
utility, has been identified as the world’s second
largest producer of carbon emissions. With the
aim of reducing South Africa’s dependency on
coal generated energy, and to address climate
change concerns, the South African Government
has set a target, through the Integrated Resource
Plan (IRP) for electricity to develop 17.8 GW of
renewables (including 8,4GW solar) within the
period 2010 – 2030.
Based on the nature and extent of the proposed
project, the local level of disturbance predicted
as a result of the construction and operation of
the facility and associated infrastructure, the
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Executive summary Page xvi
findings of the EIA, and the understanding of the
significance level of potential environmental
impacts, it is the opinion of the EIA project team
that the impacts associated with the
development of the PV Facility project can be
mitigated to an acceptable level. In terms of this
conclusion, the EIA project team support the
decision for environmental authorisation.
The layout shown in Figure 8.2 is acceptable and
the following conditions would be required to be
included within an authorisation issued for the
project:
» All mitigation measures detailed within this
report and the specialist reports contained
within Appendices D to H must be
implemented.
» The Environmental Management Programme
(EMPr) as contained within Appendix I of this
report should form part of the contract with
the Contractors appointed to construct and
maintain the proposed PV facility, and will be
used to ensure compliance with
environmental specifications and
management measures. The
implementation of this EMPr for all life cycle
phases of the proposed project is considered
to be key in achieving the appropriate
environmental management standards as
detailed for this project.
» The final location of the PV facility and
associated infrastructure within identified
sensitive areas (if any) must be informed by
pre-construction surveys undertaken by
ecological, heritage and avifaunal
specialists. The findings of these surveys must
be included in the site-specific EMPr to be
compiled for the project.
» Following the final design of the facility, must
be submitted to DEA for review and
approval prior to commencing with
construction.
» Disturbed areas should be kept to a
minimum and rehabilitated as quickly as
possible and an on-going monitoring
programme should be established to detect
and quantify any alien species.
» A comprehensive search for threatened and
near-threatened plant and animal
populations must be undertaken within the
development site of the proposed
infrastructure prior to construction, once the
final position of infrastructure if known. For
plants, this must ideally take place during an
appropriate season to maximise the likelihood
of detecting plants of conservation concern.
A permit may be required to be obtained in
terms of Chapter 7 of the National
Environmental Management: Biodiversity Act
to carry out a restricted activity involving a
specimen of a listed threatened or protected
species.
» Implement an operation phase monitoring
programme to record the impact on bird
species using the site.
» Establish an on-going monitoring programme
to detect, quantify and remove any alien
plant species that may become established.
» Adequate stormwater management
measures to be put in place as the soils on
parts of the site may be prone to erosion.
» Implement site specific erosion and water
control measures to prevent excessive
surface runoff from the site.
» Plan the road and site layout in such a way as
to make maximum use of existing roads and
fence/border areas to minimise impacts and
to keep grazing and natural units as intact as
possible.
» Where feasible, training and skills
development programmes for locals should
be initiated at the initiation of the
construction phase.
» Use of fire prevention and fire management
strategies for the PV facility, to reduce risks to
landowners.
» Construction managers/foremen should be
informed before construction starts on the
possible types of heritage sites and cultural
material they may encounter and the
procedures to follow when they find sites (as
detailed in the EMPr).
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Executive summary Page xvii
» Applications for all other relevant and
required permits to be obtained by Sol
Invictus 6 (Pty) Ltd or the construction
contractor must be submitted to the relevant
regulating authorities. This includes permits for
the transporting of all components (abnormal
loads) to site.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Summary Page xviii
Figure 1: Environmental sensitivity map for the project study area illustrating sensitive areas in relation to the development footprint of the
Sol Invictus 6 PV Facility
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Table of Contents Page xix
TABLE OF CONTENTS PAGE
PURPOSE OF THE ENVIRONMENTAL IMPACT ASSESSMENT REPORT ....................................................................... II
DEA REQUIMENT FOR THE ENVIRONMENTAL IMPACT ASSESSMENT REPORT ...................................................... VII
INVITATION TO COMMENT ON THE EIA REPORT ................................................................................................. XIII
EXECUTIVE SUMMARY .......................................................................................................................................... XIV
APPENDICES ...................................................................................................................................................... XXIII
DEFINITIONS AND TERMINOLOGY .................................................................................................................... XXIV
ABBREVIATIONS AND ACRONYMS .................................................................................................................. XXVII
CHAPTER 1 INTRODUCTION ..................................................................................................................................... 1
1.1. BACKGROUND TO THE PROJECT ..................................................................................................................... 1
1.2. CONCLUSIONS FROM THE SCOPING PHASE ...................................................................................................... 4
1.3. REQUIREMENT FOR AN ENVIRONMENTAL IMPACT ASSESSMENT PROCESS................................................................ 7
1.4. DETAILS OF ENVIRONMENTAL ASSESSMENT PRACTITIONER AND EXPERTISE TO CONDUCT THE SCOPING AND EIA ........... 8
CHAPTER 2 OVERVIEW OF THE PROPOSED PROJECT ............................................................................................. 10
2.1. NEED AND DESIRABILITY OF THE DEVELOPMENT AT THE PREFERRED SITE LOCATION .................................................. 10
2.1.1 Site Selection and Pre-Feasibility Analysis.................................................................................... 11
2.1.2 Receptiveness of the site to development of the solar energy facility ..................................... 11
2.1.3 Renewable Energy Development Zones (REDZ) ......................................................................... 13
2.1.4 Benefits of Renewable Energy ..................................................................................................... 16
2.2. PROJECT AND SITE DESCRIPTION .................................................................................................................. 17
2.3. PROJECT ALTERNATIVES UNDER CONSIDERATION FOR THE PV FACILITY ................................................................ 18
2.3.1 Site-specific or Layout Design Alternatives ................................................................................. 18
2.3.2 Technology Alternatives ............................................................................................................... 23
2.3.4 Site Access Alternatives ............................................................................................................... 23
2.3.5 Grid connection and Substation Alternatives............................................................................. 23
2.3.6 The ‘do-nothing’ Alternative ........................................................................................................ 24
2.4. TECHNOLOGY CONSIDERED FOR THE SOLAR PHOTOVOLTAIC (PV) FACILITY AND THE GENERATION OF ELECTRICITY .... 25
2.4.1 Description of the Photovoltaic Technology .............................................................................. 25
2.4.2 Description of the Infrastructure associated with the Facility .................................................... 26
2.5. PROPOSED ACTIVITIES DURING THE PROJECT DEVELOPMENT STAGES .................................................................. 27
2.5.1. Design and Pre-Construction Phase ............................................................................................ 27
2.5.2. Construction Phase ...................................................................................................................... 28
2.6. PROJECT OPERATION PHASE ....................................................................................................................... 30
2.7. PROJECT DECOMMISSIONING PHASE ............................................................................................................ 31
CHAPTER 3 REGULATORY AND PLANNING CONTEXT ........................................................................................... 32
3.1. STRATEGIC ELECTRICITY PLANNING IN SOUTH AFRICA ...................................................................................... 32
3.2. NATIONAL POLICY ..................................................................................................................................... 33
3.2.1 The Kyoto Protocol, 1997 .............................................................................................................. 34
3.2.2. White Paper on the Energy Policy of the Republic of South Africa, 1998 ................................. 34
3.2.3. The National Energy Act (2008) ................................................................................................... 35
3.2.4. The Electricity Regulation Act, 2006 (Act No. 4 of 2006), as amended ..................................... 35
3.2.5. Renewable Energy Policy in South Africa ................................................................................... 35
3.2.6 National Development Plan ........................................................................................................ 36
3.2.7 Strategic Integrated Projects (SIPs) ............................................................................................. 37
3.2.8. Integrated Energy Plan (IEP) ........................................................................................................ 37
3.2.9. Final Integrated Resource Plan 2010 - 2030 ................................................................................ 38
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Table of Contents Page xx
3.2.10. Department of Energy process for Independent Power Producers (IPP).................................. 38
3.3. PROVINCIAL AND LOCAL LEVEL DEVELOPMENTAL POLICY ................................................................................ 39
3.3.1 Northern Cape Province Provincial Growth and Development Strategy ................................ 39
3.3.2. Northern Cape Province Spatial Development Framework (NCPSDF) ..................................... 40
3.4 LOCAL AUTHORITY LEVEL DEVELOPMENTAL POLICY ......................................................................................... 41
3.4.1 Namakwa District Municipality Integrated Development Plan ................................................. 41
3.4.2 Nama Khoi Local Municipality Integrated Development Plan (IDP) (2012-2017) .................... 42
3.5 LEGISLATION AND GUIDELINES ..................................................................................................................... 43
CHAPTER 4 APPROACH TO UNDERTAKING THE EIA PHASE ................................................................................... 57
4.1. RELEVANT LISTED ACTIVITIES ........................................................................................................................ 57
4.2. SCOPING PHASE ....................................................................................................................................... 59
4.3. ENVIRONMENTAL IMPACT ASSESSMENT PHASE ................................................................................................ 60
4.3.1. Tasks completed during the EIA Phase ....................................................................................... 60
4.3.2 Authority Consultation .................................................................................................................. 60
4.3.3. Public Involvement and Consultation ......................................................................................... 61
4.3.4. Identification and Recording of Issues and Concerns ............................................................... 65
4.3.5. Assessment of Issues Identified through the Scoping Process .................................................... 65
4.3.6 Assumptions and Limitations ........................................................................................................ 67
CHAPTER 5 DESCRIPTION OF THE RECEIVING ENVIRONMENT .............................................................................. 68
5.1. REGIONAL SETTING .................................................................................................................................... 68
5.2. LAND USE OF THE STUDY AREA..................................................................................................................... 70
5.3. TOPOGRAPHY, GEOLOGY, SOILS AND LAND CAPABILITY ................................................................................. 70
5.4 CLIMATIC CONDITIONS .............................................................................................................................. 71
5.5. AREAS OF CONSERVATION IMPORTANCE ...................................................................................................... 72
5.5.1 Critical Biodiversity Areas and Broader Scale Processes ............................................................ 72
5.4.2 National Freshwater Ecosystem Priority Areas............................................................................. 73
5.4.3 Nature Reserves ............................................................................................................................ 73
5.5.3 Riemvasmaak Community Conservancy ................................................................................... 74
5.5.4 Nature Reserves and Important Bird Areas (IBAs) ....................................................................... 75
5.6. ECOLOGICAL PROFILE OF THE STUDY AREA INCLUDING FLORA AND FAUNA ........................................................ 77
5.6.1. Vegetation .................................................................................................................................... 77
5.6.2 Alien Vegetation .......................................................................................................................... 77
5.6.3 Listed and Protected Plant Species............................................................................................. 79
5.6.4 Terrestrial Fauna ............................................................................................................................ 80
5.7 AVIFAUNA ............................................................................................................................................... 81
5.7.1 Red Data species ......................................................................................................................... 81
5.7.2 Resident Avifauna ........................................................................................................................ 82
5.7.3 Waterbirds ..................................................................................................................................... 82
5.8. ARCHAEOLOGICAL PROFILE AND PALAEONTOLOGICAL POTENTIAL ................................................................... 83
5.8.1 Palaeontological profile ............................................................................................................... 83
5.8.2 Archaeological profile ................................................................................................................. 83
5.8.3 GRAVES .................................................................................................................................................. 84
5.8.4 BUILT ENVIRONMENT ................................................................................................................................... 85
5.9 SOCIAL PROFILE ........................................................................................................................................ 85
5.10 VISUAL RECEPTORS .................................................................................................................................... 87
5.10.1 Possible visual receptors and sensitivities ........................................................................................... 88
CHAPTER 6 ASSESSMENT OF IMPACTS PV FACILITY AND ASSOCIATED INFRASTRUCTURE:................................... 89
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Table of Contents Page xxi
6.1 ALTERNATIVES ASSESSMENT ......................................................................................................................... 90
6.2. ASSESSMENT OF POTENTIAL IMPACTS ON FLORA AND FAUNA ............................................................................ 92
6.2.1. Results of the Ecological Study .................................................................................................... 92
6.2.2. Description of Ecological Impacts............................................................................................... 94
6.2.3. Impact table summarising the significance of impacts on ecology during the construction
phase (with and without mitigation) ............................................................................................................ 95
6.2.4. Impact table summarising the significance of impacts on ecology during the operation
phase (with and without mitigation) ............................................................................................................ 96
6.2.5. Impact table summarising the significance of impacts on ecology during the
decommissioning phase (with and without mitigation ............................................................................. 100
6.2.6. Implications for Project Implementation ................................................................................... 101
6.3. ASSESSMENT OF POTENTIAL IMPACTS ON AVIFAUNA ...................................................................................... 101
6.3.1. Results of the Avifaunal Study .................................................................................................... 101
6.3.2. Description of Impacts on Avifauna .......................................................................................... 104
6.3.3. Impact tables summarising the significance of impacts on avifauna (with and without
mitigation) .......................................................................................................................................................... 105
6.3.4. Implications for Project Implementation ........................................................................................... 107
6.4. ASSESSMENT OF POTENTIAL VISUAL IMPACTS ................................................................................................ 108
6.4.1. Results of the Visual Study .......................................................................................................... 108
6.4.2 Description of the Visual Impacts .............................................................................................. 111
6.4.3 Impact table summarising the significance of visual impacts (with and without mitigation)111
6.4.4 Implications for Project Implementation ............................................................................................ 116
6.5. ASSESSMENT OF POTENTIAL IMPACTS ON HERITAGE AND PALEONTOLOGICAL RESOURCES .................................... 117
6.5.1. Results of the Archaeological Heritage survey ......................................................................... 117
6.5.2. Description of the Heritage Impacts ......................................................................................... 118
6.5.3 Impact tables summarising the significance of impacts on heritage resources during construction
(with and without mitigation) ...................................................................................................................... 118
6.5.5 Implications for Project Implementation ............................................................................................ 120
6.6. ASSESSMENT OF POTENTIAL SOCIAL AND/ ECONOMIC IMPACTS ...................................................................... 121
6.6.1 Results of the Social Study................................................................................................................... 121
6.6.2. Description of the Socio-Economic Impacts ............................................................................ 122
6.6.3. Impact tables summarising the significance of social and economic impacts associated
with the construction phase (with and without mitigation measures) ..................................................... 124
6.6.4 Impact tables summarising the significance of social and economic impacts associated with the
operation phase (with and without mitigation measures) ........................................................................ 128
6.6.5 Impact tables summarising the significance of social and economic impacts associated with the
decommissioning phase (with and without mitigation measures) ........................................................... 130
6.6.6. Implications for Project Implementation ................................................................................... 130
6.7. THE ‘DO-NOTHING’ ALTERNATIVE ............................................................................................................... 130
CHAPTER 7 ASSESSMENT OF POTENTIAL CUMULATIVE IMPACTS ........................................................................ 134
7.1 APPROACH TAKEN TO ASSESS CUMULATIVE IMPACTS..................................................................................... 134
7.2 CUMULATIVE IMPACTS ON ECOLOGICAL PROCESSES .................................................................................... 139
7.3 CUMULATIVE IMPACTS ON AVIFAUNA ......................................................................................................... 140
7.4 CUMULATIVE VISUAL IMPACTS ................................................................................................................... 142
7.5 CUMULATIVE HERITAGE IMPACTS................................................................................................................ 146
7.6 CUMULATIVE SOCIO-ECONOMIC IMPACTS .................................................................................................. 147
7.7 CUMULATIVE IMPACTS OF UP TO FOUR PV PLANTS ON FARM PORTION 5 OF THE FARM OU TAAISBOSMOND 66 ....... 149
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Table of Contents Page xxii
7.8 CONTRIBUTION OF THE PROJECT TO CLIMATE CHANGE MITIGATION................................................................. 150
7.9. CONCLUSION REGARDING CUMULATIVE IMPACTS ........................................................................................ 151
CHAPTER 8 CONCLUSION AND RECOMMENDATIONS ....................................................................................... 153
8.1. EVALUATION OF THE PROPOSED PROJECT .................................................................................................... 155
8.1.1. Impacts on Ecology ................................................................................................................... 156
8.1.2 Impacts on Avifauna .................................................................................................................. 156
8.1.3 Impacts on Heritage and Palaeontological Resources ........................................................... 157
8.1.4 Impacts on visual quality of the area ........................................................................................ 157
8.1.5 Socio Economic Impacts ........................................................................................................... 157
8.1.6 Assessment of Potential Cumulative Impacts ........................................................................... 158
8.2 ENVIRONMENTAL SENSITIVITY MAPPING ....................................................................................................... 159
8.3. CONSIDERATION OF ALTERNATIVES ............................................................................................................. 161
8.4 ENVIRONMENTAL COSTS OF THE PROJECT VERSUS BENEFITS OF THE PROJECT ...................................................... 161
8.5 OVERALL CONCLUSION (IMPACT STATEMENT) .............................................................................................. 162
8.7. OVERALL RECOMMENDATION ................................................................................................................... 163
CHAPTER 9 REFERENCES ...................................................................................................................................... 166
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Table of Contents Page xxiii
APPENDICES
Appendix A: EIA Project Consulting Team and Specialist CVs
Appendix B: Correspondence with Authorities
Appendix C: Public Participation Process
Appendix C1: I&AP Database
Appendix C2: Site Notices and Newspaper Advertisements
Appendix C3: Background Information Document
Appendix C4: Organs of State Correspondence
Appendix C5: Stakeholder Correspondence
Appendix C6: Comments Received
Appendix C7: Minutes of Meeting
Appendix C8: Comments and Response Report
Appendix D: Ecology Study
Appendix E: Avifauna Study
Appendix F: Visual Study
Appendix G: Heritage Study
Appendix H: Social Study
Appendix I: EMPr
Appendix J: EAP Affirmation and Specialist Declarations
Appendix K: Maps
Appendix L: Updated Application forms
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Definitions and Terminology Page xxiv
DEFINITIONS AND TERMINOLOGY
Alternatives: Alternatives are different means of meeting the general purpose and need of a proposed
activity. Alternatives may include location or site alternatives, activity alternatives, process or technology
alternatives, temporal alternatives or the ‘do nothing’ alternative.
Archaeological material: Remains resulting from human activities which are in a state of disuse and are in
or on land and which are older than 100 years, including artefacts, human and hominid remains and
artificial features and structures.
Cumulative impacts: The impact of an activity that in itself may not be significant, but may become
significant when added to the existing and potential impacts eventuating from similar or diverse activities
or undertakings in the area.
Direct impacts: Impacts that are caused directly by the activity and generally occur at the same time and
at the place of the activity (e.g. noise generated by blasting operations on the site of the activity). These
impacts are usually associated with the construction, operation or maintenance of an activity and are
generally obvious and quantifiable
‘Do nothing’ alternative: The ‘do nothing’ alternative is the option of not undertaking the proposed activity
or any of its alternatives. The ‘do nothing’ alternative also provides the baseline against which the impacts
of other alternatives should be compared.
Drainage: A drainage line is a lower category or order of watercourse that does not have a clearly defined
bed or bank. It carries water only during or immediately after periods of heavy rainfall i.e. non-perennial,
and riparian vegetation may or may not be present
Endangered species: Taxa in danger of extinction and whose survival is unlikely if the causal factors
continue operating. Included here are taxa whose numbers of individuals have been reduced to a critical
level or whose habitats have been so drastically reduced that they are deemed to be in immediate
danger of extinction.
Endemic: An "endemic" is a species that grows in a particular area (is endemic to that region) and has a
restricted distribution. It is only found in a particular place. Whether something is endemic or not depends
on the geographical boundaries of the area in question and the area can be defined at different scales.
Environment: the surroundings within which humans exist and that are made up of:
i. The land, water and atmosphere of the earth;
ii. Micro-organisms, plant and animal life;
iii. Any part or combination of (i) and (ii) and the interrelationships among and between them;
and
iv. The physical, chemical, aesthetic and cultural properties and conditions of the foregoing that
influence human health and well-being.
Environmental impact: An action or series of actions that have an effect on the environment.
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Definitions and Terminology Page xxv
Environmental impact assessment: Environmental Impact Assessment (EIA), as defined in the NEMA EIA
Regulations and in relation to an application to which scoping must be applied, means the process of
collecting, organising, analysing, interpreting and communicating information that is relevant to the
consideration of that application.
Environmental management: Ensuring that environmental concerns are included in all stages of
development, so that development is sustainable and does not exceed the carrying capacity of the
environment.
Environmental management programme: An operational plan that organises and co-ordinates mitigation,
rehabilitation and monitoring measures in order to guide the implementation of a proposal and its on-
going maintenance after implementation.
Fossil: Mineralised bones of animals, shellfish, plants and marine animals. A trace fossil is the track or
footprint of a fossil animal that is preserved in stone or consolidated sediment.
Heritage: That which is inherited and forms part of the National Estate (Historical places, objects, fossils as
defined by the National Heritage Resources Act of 2000).
Indigenous: All biological organisms that occurred naturally within the study area prior to 1800
Indirect impacts: Indirect or induced changes that may occur as a result of the activity (e.g. the reduction
of water in a stream that supply water to a reservoir that supply water to the activity). These types of
impacts include all the potential impacts that do not manifest immediately when the activity is undertaken
or which occur at a different place as a result of the activity.
Interested and affected party: Individuals or groups concerned with or affected by an activity and its
consequences. These include the authorities, local communities, investors, work force, consumers,
environmental interest groups and the general public.
Perennial and non-perennial: Perennial systems contain flow or standing water for all or a large proportion
of any given year, while non-perennial systems are episodic or ephemeral and thus contains flows for short
periods, such as a few hours or days in the case of drainage lines.
Project development property: The project development areas considered through the EIA process in
defining the area for the PV facility project include, and are defined as follows:
» Project area: The project area refers to the total extent of Portion 5 of the Farm Ou Taaisbosmond 66
which is 5000 ha in extent. The entire 5000 ha of the project area was subjected to the scoping level
assessment in order to provide the option of identifying more suitable positions for development of the
PV facility, should any of the areas be found to be technically or environmentally constrained.
» Development site: The site of the proposed PV Project, is situated in the north east corner of Portion 5 of
Farm Ou Taaisbosmond 66 (project area), and is 700 ha in extent.
» Facility development footprint: The total development footprint on the development site for the PV
facility, including associated infrastructure is ~ 450 ha in extent.
Riparian: the area of land adjacent to a stream or river that is influenced by stream-induced or related
processes. Riparian areas which are saturated or flooded for prolonged periods would be considered
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Definitions and Terminology Page xxvi
wetlands and could be described as riparian wetlands. However, some riparian areas are not wetlands
(e.g. an area where alluvium is periodically deposited by a stream during floods but which is well drained).
Photovoltaic effect: Electricity can be generated using photovoltaic solar panels which are comprised of
individual photovoltaic cells that absorb solar energy to directly produce electricity. The absorbed solar
radiation excites the electrons inside the cells and produces what is referred to as the Photovoltaic Effect.
Rare species: Taxa with small world populations that are not at present Endangered or Vulnerable, but are
at risk as some unexpected threat could easily cause a critical decline. These taxa are usually localised
within restricted geographical areas or habitats or are thinly scattered over a more extensive range. This
category was termed Critically Rare by Hall and Veldhuis (1985) to distinguish it from the more generally
used word "rare".
Red data species: Species listed in terms of the International Union for Conservation of Nature and Natural
Resources (IUCN) Red List of Threatened Species, and/or in terms of the South African Red Data list. In
terms of the South African Red Data list, species are classified as being extinct, endangered, vulnerable,
rare, indeterminate, insufficiently known or not threatened (see other definitions within this glossary).
Significant impact: An impact that by its magnitude, duration, intensity, or probability of occurrence may
have a notable effect on one or more aspects of the environment.
Watercourse: as per the National Water Act means -
(a) a river or spring;
(b) a natural channel in which water flows regularly or intermittently;
(c) a wetland, lake or dam into which, or from which, water flows; and
(d) any collection of water which the Minister may, by notice in the Gazette, declare to be a watercourse,
and a reference to a watercourse includes, where relevant, its bed and banks
Wetlands: land which is transitional between terrestrial and aquatic systems where the water table is
usually at or near the surface, or the land is periodically covered with shallow water, and which under
normal circumstances supports or would support vegetation typically adapted to life in saturated soil
(Water Act 36 of 1998); land where an excess of water is the dominant factor determining the nature of
the soil development and the types of plants and animals living at the soil surface (Cowardin et al., 1979).
SOL INVICTUS 6 PV FACILITY, NORTHERN CAPE PROVINCE
Split Environmental Impact Assessment Report August 2018
Abbreviations and Acronyms Page xxvii
ABBREVIATIONS AND ACRONYMS
BID Background Information Document
CO2 Carbon dioxide
DEA National Department of Environmental Affairs
DEADP Department of Environment Affairs and Development Planning
DoE