Upload
bennett-mathews
View
213
Download
1
Embed Size (px)
Citation preview
Software Project Management Task Sequencing
Activity Sequencing Concepts
PERT charts
Critical Path Analysis
Project Time Management Processes
Project time management involves the processes required to ensure timely completion of a project. Processes include:
Activity definition (your WBS) Activity sequencing (this topic) Activity duration estimating (next week)
Activity Definition•This comes from your WBS
Recall it encompasses the total scope of the project It is organized by a perspective, or organizing principle
•What it doesn’t do: Help you plan temporally You need to know X needs to be done before Y because X may
produce a deliverable (or knowledge) required for Y You may need to ensure you can provide all of the resources
(people, technology, etc.) at a given time to ensure success
Time
Quality
Scope
CostExpectations
Activity SequencingInvolves developing a more detailed WBS and supporting
explanations to understand all the work to be done An outgrowth of your WBS’ work packages Initial dependencies should arise
• What needs to be done before to make data available (flow)• What tasks are a “part of” other tasks (decomposition)• This is the resulting sequencing of activities to achieve goals
Review activities and determine dependencies Mandatory: inherent in the nature of the work; hard logic
• Example: Coding must happen before testing
Discretionary: defined by the team; soft logic applied within a process• Example: Order in which components are implemented
External: involve relationships between project & non-project activities• Example: 3rd party / open source software release
Resource: Multiple projects depend on same resource• Example: You have only 1 Oracle-certified DBA but 2 projects
Activity Sequencing
Tools for Activity Sequencing Task networks, PERT charts, Critical Path Analysis
Task networks A graphical representation of tasks Visualizes tasks, flows, and relationships Two formats:
• Activity-on-Arrow (AOA)– Nodes represent Events, Lines represent Tasks
• Activity-on-Node (AON)– Nodes represent Tasks, Lines dependencies between Tasks
AON:
STARTCode
Module
WriteUnit Test
PerformCode Review
FixDefects
Check-inCode
AOA Example
*Taken from Scach 4th ed. P. 289
Activity Sequencing
Temporal Dependencies between Tasks• Finish-to-Start (FS)
B cannot start till A finishes A: Construct fence; B: Paint Fence
• Start-to-Start (SS) B cannot start till A starts A: Pour foundation; B: Level concrete
• Finish-to-Finish (FF) B cannot finish till A finishes A: Add wiring; B: Inspect electrical
• Start-to-Finish (SF) B cannot finish till A starts (rare)
Critical Path Method (CPM)
CPM is a project network analysis technique used to predict total project duration A critical path is the series of activities that determines the earliest
time by which the project can be completed The critical path is the longest path through the network diagram
and has the least amount of slack or float Typically used in conjunction with PERT charts (or also with Activity-
Task Analysis, Task Networks, etc.)
Finding the Critical Path First develop a good project network diagram Add the durations for all activities on each path through the project
network diagram The longest path is the critical path
Course Technology, 1999
Determining the Critical Path
Consider the following project network (AOA) diagram. Assume all times are in days.
2 3
4
5
A=2 B=5C=2
D=7
1 6
F=2
E=1
start finish
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to complete this project?
Course Technology, 1999
Determining the Critical Path
Course Technology, 1999
Example (AOA):
More on the Critical PathMisconceptions:
The critical path is not the one with all the critical activities; it only accounts for time
There can be more than one critical path if the lengths of two or more paths are the same
The critical path can change as the project progresses
If one of more activities on the critical path takes longer than planned, the whole project schedule will slip unless corrective action is taken We will discuss what “corrective actions” are possible
with scheduling next week.
Course Technology, 1999
PERT ChartsProgram Evaluation and Review Technique
Network analysis technique used to estimate project duration if there is a high degree of uncertainty about individual activity duration estimates
PERT uses probabilistic time estimates based on using optimistic, most likely, and pessimistic estimates of activity durations
Course Technology, 1999
Prepare Material forBusiness Management
98/29/95 9/4/95
Conduct the BusinessManagement Review
109/5/95 9/11/95
RD Approved by IS Dir,DMA Dir, Cust Sponsor
119/11/95 9/11/95
Approval to Proceed toNext Stage
129/11/95 9/11/95
RequirementsDefinition (Analysis)
18/1/95 9/11/95
Prepare for Analysis
28/1/95 8/7/95
Analyze the CurrentSystem
48/8/95 8/14/95
Develop and EvaluateAlternative Solutions
68/15/95 8/21/95
Plan the Next Stage
88/22/95 8/28/95
Reaccess ApplicationArchitecture
58/8/95 8/14/95
Outline Transaction,Security and Training
78/15/95 8/21/95
Define SystemRequirements (Business)
38/8/95 8/14/95
ITDE(0.3),ITI
ITDBA(0.3) ITDBA(0.3)
EXAMPLE: