9
SNAGGING REPORT On completion of the snagged works, a final inspection should be conducted and checked either ‘Yes or No’ that the works has been satisfactory completed. Location Description Yes No INTERNAL Master Bedroom suite general cleaning and removal of fine debris around window sills missing sash windows insect screens laches to be installed complete paint marks at door edges to be removed and make good finish bathtub support at side wall was considered inadequate and needs to be reinforced grout residue left at the ceiling level to be removed and make good finish complete installation of hanging rods to walking closet Common Bathroom moulding strip should be installed at ceiling to conceal irregular grout finish. complete painting finish at door edges Remove stain on floor tiles Bedroom 1 check and repair stiffness of vertical movement to single hung sash window. complete painting at edge of door Bedroom 2 remove painting stains on architrave trimming and make good finish door to receive one coat of paint remove paint marks on door knob and make good finish sash windows insect screens laches to be installed complete Corridor alignment of architrave trimming and door frame requires improvement PROJECT: CONSTRUCTION OF RESIDENCE Location : Zicack Portsmouth Inspection: Date: February 17 2014 Contractor: Martin Inspected By: Engineer

Snagging Report_ Residential Building2

Embed Size (px)

Citation preview

SNAGGING REPORT

On completion of the snagged works, a final inspection should be conducted and checked either ‘Yes or No’ that the works has been satisfactory completed.

Location Description Yes No

INTERNAL Master Bedroom suite

general cleaning and removal of fine debris around window sills

missing sash windows insect screens laches to be installed complete

paint marks at door edges to be removed and make good finish

bathtub support at side wall was considered inadequate and needs to be reinforced

grout residue left at the ceiling level to be removed and make good finish

complete installation of hanging rods to walking closet

Common Bathroom moulding strip should be installed at ceiling to conceal irregular grout finish.

complete painting finish at door edges

Remove stain on floor tiles

Bedroom 1 check and repair stiffness of vertical movement to single hung sash window.

complete painting at edge of door

Bedroom 2 remove painting stains on architrave trimming and make good finish

door to receive one coat of paint

remove paint marks on door knob and make good finish

sash windows insect screens laches to be installed complete

Corridor alignment of architrave trimming and door frame requires improvement

PROJECT: CONSTRUCTION OF RESIDENCE

Location : Zicack Portsmouth Inspection: Date: February 17 2014

Contractor: Martin Inspected By: Engineer

Living Room /Dining repair required to cracks develop between joints of drywall at ceiling

plug finish to screw heads at skirting board to be

completed.

make good wall surface at lamp holder and paint finish

remove paint mark on lamp holder at ceiling level

sash windows insect screens laches to be

installed complete

Install complete lower strike plate for dead bolt lock

remove stain on floor tiles in dining room

general cleaning to remove fine debris at windows

Kitchen at fridge location the side cladding installed requires some bracing to improve stability

complete and make good grout finish at window jamb

make good finish to broken wall tile at switch.

EXTERNAL Rainwater Downpipes

rainwater pipe terminated at building foundation wall should be extended with bends away from the building into side drains

downpipe connection at the northeast corner of

the building should be made good for water discharge into pvc pipe

Access ramp the access ramp slope of 1:2 is to seep; the accepted gradient is 1:10 or maximum 1:8

the ramp should be finished at grade level and not

with a riser

Plumbing pipe grey water pipes exposed at grade to be buried at least 12” below grade, or ground level be raised 12” with selected backfilled material

grey water pipes should have a minimum 2% fall

Make good to broken tile edge and complete joint with grout

Clean and remove all stain on wall tiles surface

remove paint marks; varnish and make good finish

Improve wall surface preparation at lamp and make good paint finish

Remove paint marks on lamp holder

Remove paint from upper strike plate

Install lower strike plate for dead bolt lock

Make good to ceramic tile surface at light switch

Make good finish to grout at window jamb

The slope to this ramp exceeds the minimum slope of 1:10

The exposed grey water pipes are required to be buried

Remove downpipe and make good connection to discharge water

Provide for rainwater downpipes to run away from buildings foundation to drain