SNAGGING REPORT
On completion of the snagged works, a final inspection should be conducted and checked either ‘Yes or No’ that the works has been satisfactory completed.
Location Description Yes No
INTERNAL Master Bedroom suite
general cleaning and removal of fine debris around window sills
missing sash windows insect screens laches to be installed complete
paint marks at door edges to be removed and make good finish
bathtub support at side wall was considered inadequate and needs to be reinforced
grout residue left at the ceiling level to be removed and make good finish
complete installation of hanging rods to walking closet
Common Bathroom moulding strip should be installed at ceiling to conceal irregular grout finish.
complete painting finish at door edges
Remove stain on floor tiles
Bedroom 1 check and repair stiffness of vertical movement to single hung sash window.
complete painting at edge of door
Bedroom 2 remove painting stains on architrave trimming and make good finish
door to receive one coat of paint
remove paint marks on door knob and make good finish
sash windows insect screens laches to be installed complete
Corridor alignment of architrave trimming and door frame requires improvement
PROJECT: CONSTRUCTION OF RESIDENCE
Location : Zicack Portsmouth Inspection: Date: February 17 2014
Contractor: Martin Inspected By: Engineer
Living Room /Dining repair required to cracks develop between joints of drywall at ceiling
plug finish to screw heads at skirting board to be
completed.
make good wall surface at lamp holder and paint finish
remove paint mark on lamp holder at ceiling level
sash windows insect screens laches to be
installed complete
Install complete lower strike plate for dead bolt lock
remove stain on floor tiles in dining room
general cleaning to remove fine debris at windows
Kitchen at fridge location the side cladding installed requires some bracing to improve stability
complete and make good grout finish at window jamb
make good finish to broken wall tile at switch.
EXTERNAL Rainwater Downpipes
rainwater pipe terminated at building foundation wall should be extended with bends away from the building into side drains
downpipe connection at the northeast corner of
the building should be made good for water discharge into pvc pipe
Access ramp the access ramp slope of 1:2 is to seep; the accepted gradient is 1:10 or maximum 1:8
the ramp should be finished at grade level and not
with a riser
Plumbing pipe grey water pipes exposed at grade to be buried at least 12” below grade, or ground level be raised 12” with selected backfilled material
grey water pipes should have a minimum 2% fall
Make good to broken tile edge and complete joint with grout
Clean and remove all stain on wall tiles surface
Improve wall surface preparation at lamp and make good paint finish
Remove paint marks on lamp holder
The slope to this ramp exceeds the minimum slope of 1:10
The exposed grey water pipes are required to be buried