Upload
shakthi-thiyageswaran
View
225
Download
1
Embed Size (px)
Citation preview
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
1/63
M IN RO DS
Western Australia
Revision Register
EXAMPLE SCHEDULES OF RATES/BILLS OF QUANTITIES
template for SOR/BQ p reparat ion.)
REVISION REGISTER
Date Item Number Description of Revision Authorised By
10-Jul-12 Whole document Complete Review SCO
3-May-11 302.1 Amended duplicate numbering for 302.10 A/MPCMP
12-Aug-09 503.08 Geotextile Reinforced Seal added PSM
502 Stone Mastic Asphalt has been added A/SCO
504 Reference to Polymer Modified Binder added
30-Jan-08 References to 'Particular Preambles' amendedto 'Contract Specific Preambles'
MPCMP
02-Feb-07 204.07 Unit corrected from 'Item' to 'No.' SO
28-Sep-06 General Items -Series 100 Section numbers added and Item numberingamended SO
07-Sep-06 General "Revision Register" created SOGeneral Some section/specification titles updatedFurther
ExamplesNote added
Author's Notes Reference to "Particular Preambles" added
(For Information o nly - Delete this sheet & table from Spreadsheet if i t is to be used as a
24-Apr-09
]
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
2/63
MAIN ROADSWestern Australia
Contents
EXAMPLE OF FORMAT AND LAYOUT
SAMPLE SCHEDULES OF RATES/BILLS OF QUANTITIES
CONTRACT No. ??/??
SCHEDULES OF RATES/BILLS OF QUANTITIES
CONTENTS
THIS PAGE - CONTENTS 1
SCHEDULE No. 1 - GENERAL ITEMS 2
SCHEDULE No. 2 - ROADWORKS 6
SERIES 300 - EARTHWORKS 7
SERIES 400 - DRAINAGE 10
SERIES 500 - PAVEMENT & SURFACING 14
SERIES 600 - TRAFFIC FACILITIES 17
SERIES 700 - ELECTRICAL & LIGHTING 20
SERIES 900 - MISCELLANEOUS 22
SCHEDULE No. 3 - PROVISIONAL SUMS 24
SCHEDULE No. 4 - DAYWORK 26
BILL No. 1 - BRIDGE No. ? OVER ? 28
SERIES 800 - BRIDGES & MAJOR STRUCTURES 29
SUMMARY 39
FURTHER EXAMPLES 41
AUTHOR'S NOTES 43
REVISION REGISTER 45
Contract No. ??/?? Page 2
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
3/63
MAIN ROADS
Western Australia
Summary
SUMMARY
Contract No. ??/?? Page 3
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
4/63
MAIN ROADSWestern Australia
Summary
EXAMPLE OF FORMAT AND LAYOUT
SAMPLE SCHEDULES OF RATES/BILLS OF QUANTITIES
CONTRACT No. ??/??
SUMMARY
SCHEDULE No. 1 - GENERAL ITEMS $0.00
SCHEDULE No. 2 - ROADWORKS
SERIES 300 - EARTHWORKS $0.00
SERIES 400 - DRAINAGE $0.00
SERIES 500 - PAVEMENT & SURFACING $0.00
SERIES 600 - TRAFFIC FACILITIES $0.00
SERIES 700 - ELECTRICAL & LIGHTING $0.00
SERIES 900 - MISCELLANEOUS $0.00 $0.00
SCHEDULE No. 3 - PROVISIONAL SUMS $0.00
SCHEDULE No. 4 - DAYWORK $0.00
BILL No. 1 - BRIDGE No. ? OVER ? $0.00
SERIES 800 BRIDGES & MAJOR STRUCTURES $0.00
GST EXCLUSIVE AMOUNT $0.00
ESTIMATED GST PAYABLE $0.00
TOTAL OF TENDER $0.00
Contract No. ??/?? Page 4
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
5/63
MAIN ROADSWestern Australia
General Items
SCHEDULE No. 1 - GENERAL ITEMS
Contract No. ??/?? Page 5
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
6/63
MAIN ROADSWestern Australia
General Items
Item Description Unit Qty Rate Amount
CONDITIONS OF CONTRACT
GCC GENERAL CONDITIONS OF CONTRACT
GCC.01 Insurances in accordance with the General
Conditions of ContractItem 1
GCC.02 Contractor's superintendence during the execution ofthe Works
Item 1
GCC.03 All charges, costs and obligations relating to theGeneral Conditions of Contract not provided forelsewhere
Item 1
SPECIAL CONDITIONS OF CONTRACT
SCC.01 All charges, costs and obligations relating to theSpecial Conditions of Contract not provided for
elsewhere
Item 1
SERIES 100 - GENERAL REQUIREMENTS
101.00 DESCRIPTION OF WORKS
101.01 Provision of access for others to undertake work Item 1
101.02 Contractors programs Item 1
101.03 Project works sign No.
102 SURVEY INFORMATION
102.01 Survey information, control and setting out of theworks
Item 1
103 SITE FACILITIES
Contractors Site Facilities
103.01 Provision of Contractor's site facilities Item 1
103.02 Maintenance of Contractor's site facilities Item 1
103.03 Removal of Contractor's site facilities Item 1
Superintendent's Site Facilities
103.04 Provision of the Superintendent site facilities Item 1
103.05 Maintenance of the Superintendent site facilities Item 1
103.06 Removal of the Superintendent site facilities Item 1
Superintendent's Living Facilities
103.07 Provision of the Superintendent living facilities Item 1
103.08 Maintenance of the Superintendent living facilities Item 1
Contract No. ??/?? Page 6
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
7/63
MAIN ROADSWestern Australia
General Items
Item Description Unit Qty Rate Amount
103.09 Removal of the Superintendent living facilities Item 1
103.10 Superintendent's meals M/day
104 ENTRY TO LAND
104.01 Entry to land Item 1
105 WATER SUPPLIES
105.01 Supply of water Item 1
106 UTILITIES AND SERVICES
106.01 Liaison, programming, location and protection ofutilities and services
Item 1
106.02 Relocation of ? mains Item 1
106.03 Relocation of existing street lighting Item 1
SERIES 200 - MANAGEMENT REQUIREMENTS
202 - TRAFFIC
202.01 Traffic management Item 1
202.02 Traffic control devices Item 1
202.03Traffic controllers
Item 1
202.04 Construction, maintenance and removal ofsidetracks, temporary driving surfaces and temporarypedestrian access
Item 1
202.05 Maintenance of existing roads Item 1
203 - OCCUPATIONAL SAFETY AND HEALTH
203.01 Occupational safety and health including safety plansand safety audits
Item 1
204 - ENVIRONMENT
204.01 Protection, preservation and monitoring of Aboriginalsites
Item 1
204.02 Protection of flora and fauna Item 1
204.03 Fire prevention Item 1
204.04 Waste disposal Item 1
204.05 Dieback control Item 1
Contract No. ??/?? Page 7
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
8/63
MAIN ROADSWestern Australia
General Items
Item Description Unit Qty Rate Amount
204.06 Protection of public and property Item 1
204.07 Pre-construction property inspections No. 1
204.08 Dust control Item 1
To Summary
Contract No. ??/?? Page 8
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
9/63
MAIN ROADSWestern Australia
Roadworks
SCHEDULE No. 2 - ROADWORKS
Contract No. ??/?? Page 9
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
10/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
SERIES 300 - EARTHWORKS
301 - CLEARING
301.01 Site clearing ha,m
302 - EARTHWORKS
TOPSOILINGTopsoil Removal
302.01 Topsoil removal, ? deep ha,m
302.02 Topsoil removal, ? deep, and disposal of to Contractor'sspoil area off-site
ha,m
Topsoil Spreading
302.03 Respread topsoil, ? thick ha,m
Topsoil Stockpiles
302.04 Batter protection to stockpiles using hydro-mulch ha,m
REMOVAL OF REDUNDANT ITEMS302.05 Removal of redundant pavement including seal m
302.06 Removal of redundant seal from existing pavement m
302.07 Ripping and rehabilitating redundant pavement m
302.08 Preparation of retained pavement to receive overlay m
302.09 Removal of redundant kerbs m
302.10 Marking out and cutting edge along junction between newpavement and existing pavement including trimmingexisting pavement layers as required to bond to newpavement
m
UNSUITABLE MATERIAL
302.11 Excavation and removal of unsuitable material m
302.12 Backfilling unsuitable material excavations with site
excavated material or imported materialm
EXCAVATION IN ROCK
302.13 Excavation and removal of rock m
EMBANKMENT CONSTRUCTION
302.14 Embankment foundation compaction m
302.15 Embankment foundation compaction in widenings m
302.16 Embankment construction using site excavated materialand imported material
m
Contract No. ??/?? Page 10
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
11/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
302.17 Embankment construction in widenings using siteexcavated material and borrow material
m
302.18 Embankment construction for noise bunds using siteexcavated material
m
SUBGRADE
302.19 Subgrade improvement ? thick using select borrowmaterial
m
302.20 Subgrade m
302.21 Subgrade in road widenings m
302.22 Subgrade to principal shared path m
303 - PITS AND QUARRIES
EMBANKMENT MATERIAL BORROW PITS303.01 Establishment of embankment material borrow pits Item 1
303.02 Reinstatement of embankment material borrow pits Item 1
EXISTING PAVEMENT MATERIAL BORROW PITS
303.03 Reinstatement of existing pavement material borrow pits Item 1
304 - REVEGETATION AND LANDSCAPING
304.01 Seed collection hr
304.02 Transplanting ? Plants No.
304.03 Herbicide treatment ha,m
304.04 Ground preparation ha,m
304.05 Erosion control netting type? ha,m
304.06 Imported topsoil, ? thick ha,m
304.07 Seed mixture type ? ha,m
304.08 Seed mixture type ? by hydro-seeding ha,m
304.09 Grass turf ha,m
304.10 Grass stolons planted at the rate of ?m of turf to cover?m of ground
ha,m
304.11 Grass seeding planted at the rate of ?m of seed to ?mof ground
ha,m
304.12 Plants type? No.
304.13 Mulch, ? thick, in plant beds ha,m
Contract No. ??/?? Page 11
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
12/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
304.14 Hydro-mulch, ? thick ha,m
304.15 Tree grates No.
304.16 Reinstate existing verges including landscaped areas,
irrigation, etc.
Item 1
304.17 Irrigation system installed complete including connectionto scheme water supply
Item 1
304.18 Establishment of vegetation wk
To Summary
Contract No. ??/?? Page 12
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
13/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
SERIES 400 - DRAINAGE
401- NOT USED
402 - SURFACE DRAINS AND LEVEES
SURFACE DRAINS AND LEVEES
402.01 Drain type ? m
402.02 Drain type ? and parallel levee m
402.03 Culvert outlet drain type ?, not exceeding ?m wide atbase
m
402.04 Levee, not exceeding ? high m
402.05 Extra over surface drains for excavation in rock m
402.06 Table drain block No.
402.07 Reinforced concrete check structure type ? No.
SPOON DRAINS
402.08 Spoon drain type ?, size ? x ? m
DRAINAGE BASINS
402.09 Drainage basin at Cha. ? (Approx. cut volume ? m) No.
403 - SUBSOIL DRAINS
403.01 ? Diameter slotted PVC pipe subsoil drain including filteraggregate, geotextile lining and drainage layer
m
403.02 Cleanout/flushout point to ? diameter pipe subsoil drainincluding concrete cover and removable cap
No.
404 - CULVERTS
CULVERTSReinforced Concrete Pipes Class ?
404.01 ? Diameter pipe culvert m
Corrugated Steel Pipes
404.02? Diameter pipe culvert
m
Reinforced Concrete Box Sections
404.03 ? x ? Box culvert m
All Culverts
404.04 Selected bedding material m
404.05 Extra over culverts for cement stabilised backfill m
404.06 Reinforced concrete base slab and shear keys m
Contract No. ??/?? Page 13
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
14/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
404.07 Reinforced concrete insitu end treatment m
404.08 Extra over culverts for excavation in rock m
404.09 Precast concrete end treatment to suit ? diameter pipe No.
Redundant Culverts
404.10 Removal of existing ? diameter pipe culvert andbackfilling excavations
m
404.11 Removal of existing ? diameter pipe culvert (Nobackfilling - culvert replaced)
m
404.12 Removal of existing ? x ? box culvert and backfillingexcavations
m
404.13 Removal of existing ? x ? box culvert (No backfilling -culvert replaced)
m
404.14 Extra over removal of existing ? diameter pipe culvert fordelivering salvageable pipes to Main Roads depot at ?
m
404.15 Removal of existing culvert end treatment (All sizes) No.
STORMWATER DRAINSReinforced Concrete Pipes Class ?
404.16 ? Diameter drain in trench, depth not exceeding 1.5m m
404.17 ? Diameter drain in trench, depth exceeding 1.5m but notexceeding 2.5m
m
404.18 ? Diameter drain in trench, depth exceeding 2.5m but notexceeding 3.5m
m
404.19 ? Diameter drain in trench, depth exceeding 3.5m but notexceeding 4.5m
m
All Stormwater Drains
404.20 Extra over stormwater drains for cement stabilised backfill m
404.21 Extra over stormwater drains for excavation in rock m
Redundant Stormwater Drains
404.22 Removal of existing ? diameter pipe drain and backfilling
excavations
m
404.23 Extra over removal of existing ? diameter pipe drain fordelivering salvageable pipes to Main Roads depot at ?
m
405 - DRAINAGE STRUCTURES
MANHOLES
405.01 Manhole type ? No.
GULLIES
Contract No. ??/?? Page 14
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
15/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
405.02 Gully type ? No.
405.03 Gully type ? with silt trap No.
CATCHPITS
405.04 Catchpit type ? No.
ALTERATIONS TO EXISTING DRAINAGE STRUCTURES405.05 Breaking into existing drainage structure and building-in ?
diameter pipeNo.
405.06 Breaking into existing drainage structure, building-in ?diameter pipe and alteration of structure and cover to suitnew finished level
No.
405.07 Alteration of structure and cover to suit new finished level No.
405.08 Replacement of existing non-trafficable cover withtrafficable cover type ? No.
REDUNDANT DRAINAGE STRUCTURES
405.09 Removal of existing drainage structure No.
406 - ROCK PROTECTION
406.01 ? Rock protection to embankments m
406.02 ? Grouted rock protection to embankments m
406.03 ? Limestone spalls m
406.04 Rock Mattresses m
406.05 Gabions m
406.06 Geotextile Lining m
407 - KERBING
407.01 Kerb type ? m
407.02 Temporary kerb type ? m
407.03 Kerb opening type ? No.
407.04 Extra over kerbs for pedestrian ramp type ? No.
407.05 Extra over kerbs for driveway kerb m
408 - REVETMENT MATTRESS
408.01 ? Thick revetment mattress m
408.02 Extra over ? revetment mattress for footing includingexcavation
m
Contract No. ??/?? Page 15
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
16/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
409- NOT USED
410 - LOW STRENGTH INFILL
REDUNDANT STORMWATER DRAINS410.01 Filling of existing redundant ? diameter pipe, box or duct
drains with low strength infillm
REDUNDANT DRAINAGE STRUCTURES
410.02 Filling of existing redundant ? drainage structure with lowstrength infill
No.
To Summary
Contract No. ??/?? Page 16
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
17/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
SERIES 500 - PAVEMENT & SURFACING
501 - PAVEMENTS
DRAINAGE LAYER
501.01 ? Geotextile lining laid over subgrade m
501.02 ?mm Thick sand drainage layer m
SUBBASE
501.03 ?mm Thick subbase m
501.04 ?mm Thick subbase in widenings m
501.05 Varying thickness subbase overlay m
501.06 Final trimming of varying thickness subbase overlay m
Material Supplied By Principal Free Of Charge From Stockpiles501.07 ?mm Thick gravel subbase m
501.08 ?mm Thick gravel subbase in widenings m
501.09 Varying thickness gravel subbase overlay m
501.10 Final trimming of varying thickness gravel subbaseoverlay
m
BASECOURSE
501.12 ?mm Thick basecourse m
501.13 ?mm Thick basecourse inwidenings
m
501.14 Varying thickness basecourseoverlay
m
501.15 Final trimming of varying thickness basecourse overlay m
Material Supplied By Principal Free Of Charge From Stockpiles501.16 ?mm Thick gravel basecourse m
501.17 ?mm thick gravel basecourse in widenings m
501.18 Varying thickness gravel basecourse overlay m
501.19 Final trimming of varying thickness gravel basecourseoverlay
m
PAVEMENT STABILISATION
501.20 Extra over gravel pavement for cement stabilisation, ?deep
m
501.21 Extra over gravel pavement in widenings for cementstabilisation, ? deep
m
Contract No. ??/?? Page 17
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
18/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
501.22 Extra over gravel pavement for lime stabilisation, ? deep m
501.23 Extra over gravel pavement in widenings for limestabilisation, ? deep
m
PRINCIPAL SHARED PATH
501.24 ?mm Thick basecourse m
Material Supplied By Principal Free Of Charge From Stockpiles501.25 ?mm Thick gravel basecourse m
502 - STONE MASTIC ASPHALT
ROADWORKS
502.01 Tack coat m
502.02 ?mm Thick stone mastic asphalt m
502.03 ?mm Thick stone mastic asphalt with Polymer ModifiedBinder (PMB)
m
502.04 Varying thickness stone mastic asphalt t
502.05 Varying thickness stone mastic asphalt with PMB t
503 - BITUMINOUS SURFACING
ROADWORKSPrime
503.01 Prime coat with BAR of ? litres/m m
Primerseal
503.02 First coat primerseal with BAR of ? litres/m and ?mmaggregate
m
503.03 Second coat primerseal with BAR of ? litres/m and ?mmaggregate
m
503.04 Single coat primerseal with BAR of ? litres/m and ?mmaggregate
m
Seal
503.05 First coat seal with BAR of ? litres/m and ?mmaggregate
m
503.06 Second coat seal with BAR of ? litres/m and ?mmaggregate
m
503.07 Single coat seal with BAR of ? litres/m and ?mmaggregate
m
Geotextile Reinforced Seal (GRS)
503.08 Single coat GRS with BAR of ? litres/m and ?mmaggregate
m
Contract No. ??/?? Page 18
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
19/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
503.09 First coat GRS with BAR of ? litres/m and ?mmaggregate
m
503.10 Second coat GRS with BAR of ? litres/m and ?mmaggregate
m
BRIDGEWORKSPrime
503.11 Prime coat with BAR of ? litres/m m
Seal
503.12 Single coat rubberised seal with BAR of ? litres/m and?mm aggregate
m
PRINCIPAL SHARED PATH
503.13 Prime coat with BAR of ? litres/m m
Primerseal
503.14 Single coat primerseal with BAR of ? litres/m and ?mmaggregate m
504 - ASPHALT SURFACING
ROADWORKS
504.01 Tack coat m
504.02 ?mm Thick dense graded asphalt m
504.03 ?mm Thick dense graded asphalt with PMB m
504.04 ?mm Thick dense graded coloured asphalt m
504.05 Varying thickness dense graded asphalt t
504.06 Varying thickness dense graded asphalt with PMB t
504.07 ?mm Thick open graded asphalt m
504.08 ?mm Thick open graded asphalt with PMB m
504.09 Varying thickness open graded asphalt t
504.10 Varying thickness open graded asphalt with PMB t
BRIDGEWORKS
504.11 Tack coat m
504.12 ?mm dense graded asphalt on bridge deck m
PRINCIPAL SHARED PATHS
504.13 Tack coat m
504.14 ?mm Thick dense graded coloured asphalt m
Contract No. ??/?? Page 19
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
20/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
505 - SEGMENTAL PAVING
PRINCIPAL SHARED PATHS
505.01 ?mm x ?mm Brick paving units on and including ?mmsand bedding
m
505.02 Tactile ground surface indicators m
MEDIANS AND TRAFFIC ISLANDS
505.03 ?mm x ?mm Brick paving units on and including ?mmsand bedding
m
505.04 Removal of existing concrete slab paving, storage andrelaying including ?mm sand bedding
m
508 - COLD PLANING
508.01 Cold planing of ?mm asphalt m
509 - POLYMER MODIFIED BITUMINOUS SURFACING
ROADWORKSSeal
509.01 Single coat PMB seal with BAR of ? litres/m and ?mmaggregate
m
To Summary
SERIES 600 - TRAFFIC FACILITIES
601 - SIGNS
SINGLE POST SIGNS
601.01 Traffic sign ? (Stop) No.601.02 Not used
DOUBLE POST SIGNS
601.03 Traffic sign ? (Hazard board) No.
MAJOR SIGNS
601.04 Major sign ?, size ?m x ?m No.
REMOVAL OF EXISTING SIGNS
601.05 Single post sign No.
601.06 Double post sign No.
601.07 Major sign No.
RELOCATION OF EXISTING SIGNS
601.08 Single post sign No.
601.09 Double post sign No.
Contract No. ??/?? Page 20
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
21/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
601.10 Major sign No.
REPLACEMENT OF EXISTING SIGN COMPONENTS
601.11 Post type ? No.
601.12 Sign panel type ? No.
602 - GUIDE POSTS
602.01 Guide post No.
602.02 Guide post with footing cast into concrete edge wall No.
602.03 Guide post (supplied by Principal free of charge fromMain Roads depot at ?)
No.
602.04 Removal of existing guide post No.
602.05 Relocation of existing guide post No.
603 - ROAD SAFETY BARRIER SYSTEMS
BARRIER
603.01 Galvanised W-Beam barrier m
603.02 Galvanised Thriebeam barrier m
603.03 Galvanised Thriebeam/W-Beam transition No.
603.04 Galvanised modified eccentric loader terminal (MELT) No.
WIRE ROPE ROAD SAFETY BARRIER SYSTEM
603.05 Wire rope road safety barrier system complete m
603.06 Anchor block to wire rope road safety barrier No.
REDUNDANT ROAD SAFETY BARRIER SYSTEM603.07 Removal of redundant W-Beam guardrail m
INSITU CONCRETE BARRIER
603.08 Cast insitu concrete barrier complete m
603.09 Transition treatment between instu concrete barrier and
W-Beam barrierNo.
603.10 Insitu concrete end treatment No.
604 - PAVEMENT MARKING
ROAD PAVEMENT MARKINGS
604.01 Line type ? m
604.02 Gore/Diagonal marking type ? m
604.03 ? Turn arrow No.
604.04 Removal of redundant road pavement markings m
Contract No. ??/?? Page 21
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
22/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
RAISED PAVEMENT MARKERS
604.05 Raised pavement marker type ? No.
604.06 Temporary raised pavement markers No.
604.07 Removal of redundant raised pavement marker No.
605 - GRAB RAILS AND BOLLARDS
GRAB RAILS
605.01 ? Wide x ? diameter pipe grab rail type ? No.
605.02 Removal of redundant grab rail No.
605.03 Relocation of existing grab rail No.
BOLLARDS
605.04 ? Diameter bollard type ? No.
605.05 Removal of redundant bollard No.
605.06 Relocation of existing bollard No.
To Summary
Contract No. ??/?? Page 22
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
23/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
SERIES 700 - ELECTRICAL & LIGHTING
701 - ROADWAY LIGHTING
LIGHTING POLES
701.01 Concrete base for single outreach arm pole No.
701.02 Galvanised steel light pole (Type ?) ?m high overallcomplete with ?m outreach arm
No.
701.03 Roadway lighting luminaire fixed to lighting pole outreacharm
No.
SWITCHBOARDS
701.04 Switchboard No. ? No.
CONDUITS AND CABLING
Conduits701.05 ? Diameter heavy duty PVC conduit in trench m
701.06 Extra over conduit in trench for excavation in rock m
701.07 Extra over conduit in trench for directional drilling underexisting roadway
m
701.08 Cable pit type ? No.
Cabling
701.09 ? Core ?mm diameter cabling between Switchboard No.? and lighting poles
m
701.10 ? Core ?mm diameter cabling between circuit cabling andluminaire
m
701.11 Connection to consumer mains Item 1
702 - EMERGENCY ROADSIDE TELEPHONES
702.01 Emergency roadside telephone No.
702.02 ? Thick concrete paving surround Item 1
704 - CABLE CONDUITS FOR INTELLIGENT TRANSPORT SYSTEMS
704.01 ?mm Diameter heavy duty PVC conduit in trench m
704.02 Extra over conduit in trench for excavation in rock m
704.03 Extra over conduit in trench for directional drilling underexisting roadway
m
704.04 Lockable cable pit type ? No.
712 - TRAFFIC SIGNALS
Contract No. ??/?? Page 23
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
24/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
? STREET INTERSECTION
712.01 Traffic signal controller No.
712.02 Traffic signal poles No.
712.03 Traffic signal aspects No.
712.04 Traffic signal detection loop No.
712.05 Pedestrian push button No.
712.06 Advanced flashing warning signal mounted on doublepoles
No.
712.07 Red light infringement camera and housing No.
712.08 Red light infringement camera pole No.
712.09 Traffic signal cable pit type ? No.
712.10 ? Diameter heavy duty PVC conduit in trench m
712.11 Extra over conduit in trench for directional drilling underexisting roadway
m
712.12 ? Core ?mm diameter cabling between traffic controllerand traffic signals, (pedestrian push buttons, red lightinfringement camera and advanced flashing warningsignal> as required
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
25/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
SERIES 900 - MISCELLANEOUS
901 - CONCRETE - GENERAL WORKS
901.01 ?mm Thick concrete footpath m
903 - FENCING
Chainlink Fencing
903.01 ? High chainlink non-railed tension wire fence (Type ?) m
903.02 ? Wide x ? high single chainlink gate No.
Agricultural Fencing
903.03 ? High agricultural fence (Type ?) m
Relocation Of Existing Fencing
903.04 Relocation of existing ? high chainlink fencing m
903.05 Relocation of existing ? wide x ? high chainlink gate No.
Removal Of Redundant Fencing
903.06 Removal of redundant ? high chainlink fencing includinggates
m
904 - NOISE WALLS
904.01 Reinforced concrete footings including excavation,formwork and reinforcement
m
904.02? Brickwork in noise wall type ?
m
904.03 Extra over brickwork in noise wall for ? x ? pier (In ? No.piers)
m
904.04 ? x ? capping to pier No.
906 - STOCK GRIDS
906.01 Stock grid type ?, size ?m x ?m No.
906.02 Removal of redundant stock grid type ?, size ?m x ?m No.
907 - LITTER BINS
907.01 Litter bin No.
907.02 Relocation of existing litter bin No.
907.03 Removal of redundant litter bin No.
908 - ANTI-GRAFFITI
908.01 Anti-graffiti coating to brick noise wall m
Contract No. ??/?? Page 25
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
26/63
MAIN ROADSWestern Australia
Roadworks
Item Description Unit Qty Rate
To Summary
Contract No. ??/?? Page 26
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
27/63
MAIN ROADSWestern Australia
Roadworks
Contract No. ??/?? Page 27
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
28/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 28
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
29/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 29
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
30/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 30
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
31/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 31
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
32/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 32
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
33/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 33
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
34/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 34
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
35/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 35
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
36/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 36
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
37/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 37
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
38/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 38
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
39/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 39
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
40/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 40
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
41/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 41
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
42/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 42
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
43/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 43
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
44/63
MAIN ROADSWestern Australia
Roadworks
Amount
Contract No. ??/?? Page 44
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
45/63
MAIN ROADSWestern Australia
Provisional Sums
SCHEDULE No. 3 - PROVISIONAL SUMS
Contract No. ??/?? Page 45
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
46/63
MAIN ROADSWestern Australia
Provisional Sums
Item Description Unit Qty Rate Amount
PROVISIONAL SUMS
SUPERINTENDENT'S TELEPHONE AND FACSIMILE CALLS
PS.01 Allow the Provisional Sum of $? (? Thousand
Dollars) for the cost of metered telephone andfacsimile calls of the Superintendent
P.S.
EARTHWORKS
PS.02 Allow the Provisional Sum of $? (? ThousandDollars) for the removal and replacement ofunsuitable material
P.S.
PS.03 Allow the Provisional Sum of $? (? ThousandDollars) for the excavation of rock
P.S.
PS.04 Allow the Provisional Sum of $? (? Thousand
Dollars) for landscaping
P.S.
DRAINAGE
PS.05 Allow the Provisional Sum of $? (? ThousandDollars) for the removal and replacement ofunsuitable insitu bedding material
P.S.
PAVEMENTS AND SURFACING
PS.06 Allow the Provisional Sum of $? (? ThousandDollars) for backrolling of sealed sections of
P.S.
MISCELLANEOUS
PS.07 Allow the Provisional Sum of $? (? ThousandDollars) for fencing
P.S.
BRIDGEWORKS
PS.08 Allow the Provisional Sum of $? (? ThousandDollars) for pile set-up tests
P.S.
PS.09 Allow the Provisional Sum of $? (? ThousandDollars) for load testing of falsework
P.S.
SERVICES
PS.10 Allow the Provisional Sum of $? (? ThousandDollars) for the relocation of existing ?? Mains
P.S.
To Summary
Contract No. ??/?? Page 46
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
47/63
MAIN ROADSWestern Australia
Daywork
SCHEDULE No. 4 - DAYWORK
Contract No. ??/?? Page 47
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
48/63
MAIN ROADSWestern Australia
Daywork
Item Description Unit Qty Rate Amount
DAYWORK
LABOUR
DW.01 Allow the Provisional Sum of $? (? Thousand
Dollars) for labour of the Contractor only expendedon persons employed on daywork
P.S.
DW.02 Labour on-costs %
MATERIALS
DW.03 Allow the Provisional Sum of $? (? ThousandDollars) for the net cost of delivered materials of the
Contractor only expended on daywork includingdelivery to site
P.S.
DW.04 Materials on-costs %
PLANT
DW.05 Allow the Provisional Sum of $? (? ThousandDollars) for the cost of plant of the Contractor onlyexpended on daywork
P.S.
DW.06 Subcontractors on-costs %
SUBCONTRACTORS
DW.07 Allow the Provisional Sum of $? (? ThousandDollars) for the cost of labour, materials and plant ofSubcontractors expended on daywork
P.S.
DW.08 Subcontractors on-costs %
To Summary
Contract No. ??/?? Page 48
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
49/63
MAIN ROADSWestern Australia
Bridge
BILL No. 1 - BRIDGE ? OVER ?
Contract No. ??/?? Page 49
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
50/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
SERIES 800 - BRIDGES AND MAJOR STRUCTURES
801 - EXCAVATION AND BACKFILL FOR STRUCTURES
STRUCTURAL EXCAVATION
Abutments And Approach Slabs
801.01 Abutment footing excavation not exceeding ? m deepcommencing at existing ground level
m3
801.02 Extra over abutment footing excavation forexcavation in rock
m3
Piers
801.03 Pier footing excavation not exceeding ? m deep
commencing at existing ground levelm3
801.04 Extra over pier footing excavation for excavation inrock
m3
Retaining Walls
801.05 Retaining wall footing excavation not exceeding ? mdeep commencing at existing ground level
m3
801.06 Extra over retaining wall footing excavation forexcavation in rock
m3
EMBANKMENT CONSTRUCTION
801.07 Embankment construction behind abutment usingselect material
m3
801.08 Extra over selected embankment fill for compactionin zone of special compaction
m3
801.09 Preparation, levelling and trimming embankmentconstruction to receive wingwall footing
m2
802 - MECHANICALLY STABILISED EARTH WALLS
802.01 Mechanically stabilised earth wall to abutment Item 1
803 - DISMANTLING AND DEMOLITION
803.01 Demolition of existing Bridge No. ? m2
803.02 Removal of redundant reinforced concrete deck
overlay
m2
803.03 Removal of redundant timber traffic barrier m
808 - INCREMENTAL LAUNCHING
808.01 Casting bay and temporary supports Item 1
808.02 Launching girder Item 1
808.03 Launching system Item 1
Contract No. ??/?? Page 50
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
51/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
808.04 Launching of deck segment No.
810 - DRIVEN STEEL PILES
810.01 Mobilisation and demobilisation of piling plant Item 1
810.02 ?UC? Steel pile (In ? No. piles) t
810.03 ?UC? Steel pile extension (Provisional Quantity) t
810.04 Extra over ?UC? steel piles and ?UC? steel pileextensions for galvanising (Provisional Quantity)
t
810.05 Preparation, handling and pitching of ?UC? steel pile No.
810.06 Driving of ?UC? steel pile (Provisional Quantity) m
810.07 Site welded splice to ?UC? steel pile (ProvisionalQuantity) No.
810.08 Re-driving of ?UC? steel pile (Provisional Quantity) m
810.09 Cutting off top of ?UC? steel pile and preparing headfor bonding into structure
No.
811 - DRIVEN CONCRETE PILES
811.01 Mobilisation and demobilisation of piling plant Item 1
811.02 ? x ? Concrete pile, ?m long No.
811.03 Preparation, handling and pitching of ? x ? concretepile
No.
811.04 Driving of ? x ? concrete pile m
811.05 ? x ? Concrete pile extension m
811.06 Re-driving of ? x ? concrete pile m
811.07 Cutting off top of ? x ? concrete pile and preparinghead for bonding into structure
No.
819 - FALSEWORK
819.01 Provision and erection of falsework Item 1
819.02 Maintenance of falsework Item 1
819.03 Removal of falsework Item 1
820 - CONCRETE FOR STRUCTURES
ABUTMENTS AND APPROACH SLABSPlain Insitu Concrete Class ?
820.01 ? Blinding layer under abutment footing (In ? m2) m3
Contract No. ??/?? Page 51
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
52/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
820.02 ? Blinding layer under abutment capbeam andwingwalls (In ? m2)
m3
820.03 ? Blinding layer under wingwall (In ? m2) m3
820.04 ? Blinding layer under approach slab (In ? m2) m3
820.05 ? Blinding layer under dual use path (In ? m2) m3
Reinforced Insitu Concrete Class ?
820.06 Abutment footing m3
820.07 Abutment wall and wingwalls m3
820.08 Abutment column m3
820.09 Abutment capbeam and wingwalls m3
820.10 Wingwall m3
820.11 Approach slab m3
820.12 Dual use path m3
PIERSPlain Insitu Concrete Class ?
820.13 ? Blinding layer under pier footing (In ? m2) m3
Reinforced Insitu Concrete Class ?
820.14 Pier footing m3
820.15 Pier m3
820.16 Pier column m3
820.17 Pier capbeam m3
RETAINING WALLSPlain Insitu Concrete Class ?
820.18 ? Blinding layer under retaining wall footing (In ? m2) m3
Reinforced Insitu Concrete Class ?
820.19 Retaining wall footing m3
820.20 Retaining wall m3
DECKReinforced Insitu Concrete Class ?
820.21 Deck slab, diaphragms and beams m3
820.22 Dual use path m3
Post-tensioned Prestressed Insitu Concrete Class ?820.23 Deck slab, diaphragms and beams m3
821 - FORMWORK
Contract No. ??/?? Page 52
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
53/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
ABUTMENTS AND APPROACH SLABSFormwork Class ?
821.01 Sides of abutment footing m2
821.02 Sides of abutment wall and wingwalls m2
821.03 Sides of abutment wall and wingwalls, curved on m2
821.04 Sides of abutment column, curved on plan m2
821.05 Sides of abutment capbeam and wingwalls m2
821.06 Sides of wingwall m2
821.07 Sides of wingwall, curved on plan m2
821.08 Sides of approach slab m2
821.09 Sides of dual use path m2
PIERSFormwork Class ?
821.10 Sides of pier footing m2
821.11 Sides of pier m2
821.12 Sides of pier, curved on plan m2
821.13 Sides of pier column, curved on plan m2
821.14 Sides and soffit of pier capbeam m2
RETAINING WALLSFormwork Class ?
821.15 Sides of retaining wall footing m2
821.16 Sides and ends of retaining wall m2
821.17 Sides of retaining wall, curved on plan m2
DECKFormwork Class ?
821.18 Sides of diaphragm m2
821.19 Soffit of deck slab m2
821.20 Sides of deck slab and upstand m2
821.21 Sides and soffit of diaphragm m2
821.22 Sides of kerb/edge beam m2
821.23 Sloping soffit of diaphragm m2
821.24 Sides of dual use path m2
Contract No. ??/?? Page 53
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
54/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
Permanent Steel Formwork
821.25 ? Bondek to soffit of deck slab m2
Permanent Void Formwork
821.26 ? Diameter x ? thick helical lock seam corrugated
galvanised steel pipe void former (In ? No.)
m
822 - STEEL REINFORCEMENT
ABUTMENTS AND APPROACH SLABSReinforcing Bars
822.01 Bars less than 16 diameter in abutment footing t
822.02 Bars less than 16 diameter in abutment wall andwingwalls
t
822.03 Bars less than 16 diameter in abutment column t
822.04 Bars less than 16 diameter in abutment capbeamand wingwalls t
822.05 Bars less than 16 diameter in wingwall t
822.06 Bars less than 16 diameter in approach slab t
822.07 Bars less than 16 diameter in dual use path t
822.08 Bars 16 - 36 diameter in abutment footing t
822.09 Bars 16 - 36 diameter in abutment wall and wingwalls t
822.10 Bars 16 - 36 diameter in abutment column t
822.11 Bars 16 - 36 diameter in abutment capbeam andwingwalls
t
822.12 Bars 16 - 36 diameter in wingwall t
822.13 Bars 16 - 36 diameter in approach slab t
822.14 Bars 16 - 36 diameter in dual use path t
Reinforcing Fabric
822.15 ? Fabric in approach slab m2
822.16 ? Fabric in dual use path m2
PIERSReinforcing Bars
822.17 Bars less than 16 diameter in pier footing t
822.18 Bars less than 16 diameter in pier t
822.19 Bars less than 16 diameter in pier column t
822.20 Bars less than 16 diameter in pier capbeam t
Contract No. ??/?? Page 54
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
55/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
822.21 Bars 16 - 36 diameter in pier footing t
822.22 Bars 16 - 36 diameter in pier t
822.23 Bars 16 - 36 diameter in pier column t
822.24 Bars 16 - 36 diameter in pier capbeam t
Reinforcing Wire
822.25 Wire less than 16 diameter in pier column t
Reinforcing Fabric
822.26 ? Fabric in pier capbeam m2
RETAINING WALLSReinforcing Bars
822.27 Bars less than 16 diameter in retaining wall footing t
822.28 Bars less than 16 diameter in retaining wall t
822.29 Bars 16 - 36 diameter in retaining wall footing t
822.30 Bars 16 - 36 diameter in retaining wall t
Reinforcing Fabric
822.31 ? Fabric in retaining wall m2
DECKReinforcing Bars
822.32 Bars less than 16 diameter in deck slab, diaphragmsand beams
t
822.33 Bars less than 16 diameter in dual use path t
822.34 Bars 16 - 36 diameter in deck slab, diaphragms andbeams
t
822.35 Bars 16 - 36 diameter in dual use path t
822.36 ?mm Diameter mechanical splice No.
Reinforcing Fabric
822.37 ? Fabric in deck slab, diaphragms and beams m2
822.38 ? Fabric in dual use path m2
824 - PRESTRESSING OF CONCRETE
DECK
824.01 Stressing anchorage type ? No.
824.02 Dead end anchorage type ? No.
824.03 Coupler type ? No.
Contract No. ??/?? Page 55
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
56/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
824.04 Prestressing tendon comprising ? No. ? diameterwires in ? diameter tendon sheathing duct (In ? No.tendons)
m
824.05 Stressing of ? No. x ? diameter wire tendon and
grouting of ? diameter tendon sheathing duct
No.
825 - SANDBLASTED CONCRETE FINISH
ABUTMENTS AND APPROACH SLABS
825.01 Sandblasted finish to exposed surfaces of abutmentwall and wingwalls
m2
PIERS
825.02 Sandblasted finish to exposed surfaces of pier m2
RETAINING WALLS
825.03 Sandblasted finish to exposed surfaces of retaining
wall
m2
828 - PRECAST CONCRETE MEMBERS
Precast Prestressed Concrete "I" Beams
828.01 ?m Long "I" beam No.
Precast Prestressed Concrete Plank Beams
828.02 ? x ? Plank beam, ?m long No.
829.01 Parapet panel type ?, ? long No.
830 - STRUCTURAL STEELWORK
830.01 ?WB? Deck beam (In ? No. beams) t
830.02 ?UC? Deck bracing (In ? No. braces) t
830.03 ? x ? x ? Beam base plate No.
831 - MINOR STEEL ITEMS
831.01 Galvanised ? x ? x ? plate fixed to abutment wall withchemical anchors
No.
831.02 Galvanised pier shear key No.
603 - SAFETY BARRIER SYSTEMS FORSTRUCTURES
BARRIER
603.01 3 rail RHS traffic barrier system for structure m
603.02 Galvanised Thriebeam barrier system m
603.03 Galvanised W-Beam barrier system m
603.04 Galvanised Thriebeam/W-Beam barrier systemtransition
No.
Contract No. ??/?? Page 56
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
57/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
603.05 Galvanised modified eccentric loader terminal No.
833 - BALUSTRADES AND HANDRAILS
BALUSTRADES833.01 Galvanised and painted balustrade (complete
system)m
833.02 Extra over balustrade for light pole base all asDrawing ? including conduit connection to junctionbox, and casting in edge plate and tie-inreinforcement to deck slab
No.
835 - PROTECTIVE TREATMENT OF STEELWORK
835.01 Extra over ?WB? deck beam for galvanising t
835.02 Extra over ?UB? bracing for galvanising t
835.03 ? Coat chlorinated rubber paint to deck beam m2
850 - TIMBER BRIDGES
850.01 Preparation of timber decking to receive concreteoverlay
m2
850.02 Routine maintenance of outside timber stringer (In ?No. stringers)
m
850.03 Replacement of timber stringer with ?UB? Stringer(In. ? No. stringers)
m
850.04 Stringer or corbel bolting No.
850.05 Anti-fungal groundline treatment of timber pile No.
850.06 Pile repair type ? to abutment pile No.
850.07 Pile band to variable diameter timber pile No.
850.08 Bolt tightening to ? No.
850.09 End grain sealing to ? Item 1
850.10 Vegetaion and debris clearance below bridge Item 1
860 - BRIDGE BEARINGS
BRIDGE BEARINGS
860.01 ? Diameter x ? elastomeric laminated rubber bearingincluding galvanised ? O.D. x ? CHS socket cast intoconcrete, ? diameter galvanised dowel ? long, drypack mortars, forming horizontal recess, etc.
No.
Contract No. ??/?? Page 57
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
58/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
860.02 ? x ? Rubber bearing pad including ? diametergalvanised dowel cast into concrete
No.
APPROACH SLAB BEARINGS
860.03 Approach slab bearing comprising ? x ? x ?
polyethylene sheet (HDPE), ? x ? x ? rubber bearingpad, galvanised dowel cap cast into approach slaband ? diameter galvanised dowel ? long cast intodeck slab all as Drawing ?
No.
870 - COMPRESSION JOINT SEAL
870.01 ? Compression seal including galvanised expansionjoint edging with anchor straps cast into concrete andgalvanised cover plates all as Drawing ? (In ? No.expansion joints)
m
875 - WATERPROOF MEMBRANE
ABUTMENTS AND APPROACH SLABS
875.01 Bituthene ? waterproof membrane (? wide) appliedbehind contraction joint in abutment wall
m2
DECK
875.02 Bituthene ? waterproof membrane laid on deck slabunder dual use path and median
m2
908 - ANTI-GRAFFITI - BRIDGES/MAJOR
STRUCTURES
ABUTMENTS AND APPROACH SLABS
908.01 Anti-graffiti coating to exposed surfaces of abutment
wall and wingwalls
m2
PIERS
908.02 Anti-graffiti coating to exposed surfaces of pier m2
RETAINING WALLS- BRIDGES
908.03 Anti-graffiti coating to exposed surfaces of retainingwall
m2
407 - KERBING
407.01 ? x ? Overall precast concrete kerb laid on deck slabincluding mortar bed and all necessary insitu infill
m
MISCELLANEOUS
ABUTMENTS AND APPROACH SLABSExpansion Joints
M.01 Expansion joint between ? approach slab andabutment wingwalls including treating wingwall facewith bond breaker, forming ? x ? groove at top andsealing with approved sealant as Drawing ?
m
Contract No. ??/?? Page 58
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
59/63
MAIN ROADSWestern Australia
Bridge
Item Description Unit Qty Rate Amount
M.02 ? x ? Polystyrene foam between approach slabblinding layer and abutment as Drawing ?
m
Contraction Joints
M.03 Contraction joint in ? approach slab comprising ?
plywood ? wide set vertically and ? deep groove attop surface sealed with approved sealant as Drawing
m
M.04 ? Diameter Class ? PVC pipe set vertically inabutment wall and tied to reinforcement behinddummy joint including end caps (In ? No.)
m
Waterstops
M.05 ? Waterstop cast into concrete m
RETAINING WALLSExpansion Joints
M.06 Expansion joint comprising ? bitumen impregnated
fibreboard joint filler ? wide with ? x ? sealant and ?centre type waterstop cast into concrete, ? diametergalvanised dowels ? long with PVC caps andbituminous paint cast into concrete at ? centres andforming groove in front face all as Drawing ?
m
To Summary
Contract No. ??/?? Page 59
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
60/63
MAIN ROADSWestern Australia
Further Examples
FURTHER EXAMPLES
Contract No. ??/?? Page 60
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
61/63
MAIN ROADSWestern Australia
Further Examples
Item Description Unit Qty Rate Amount
SERIES 300 - EARTHWORKS
304 - REVEGETATION AND LANDSCAPING
304.01 Notwithstanding Main Roads Standard Method of
Measurement for Construction Works Clause304.2.4, establishment of landscaping shall bemeasured as an Item.
Note
304.02 Ground preparation m2
304.03 Imported topsoil, ? thick m2
304.04 Mulch, ? thick, in plant beds m2
304.05 Grass stolons planted at the rate of ?m2 of turf tocover ?m2 of ground
m2
304.06 Establishment of landscaping Item 1
To Summary
Note Refer also to SMM Example Contract Speci f ic
Preamblesfor alternative method where items
not currently measured in SMM need to be
included
Example of a "Contract Specific
Preamble"inserted in the relevant
schedule/bill in accordance with the
"Principles For Preparing Schedules Of
Rates And Bills Of Quantities" Clause 1.5
Contract No. ??/?? Page 61
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
62/63
MAIN ROADSWestern Australia
Author's Notes
Where additional items are added to Schedule 2 - Roadworks, the Cont
should be checked, and when necessary manually corrected.
If the "Bridge" Bill(s) is/are not required, delete the sheet and the entri
and Summary pages. If extra Bridge Bills are required, copy the Bridge
edit/amend both the Contents and the Summary page to suit.
ALL items in the Schedule of Rates/Bill of Quantities that have, 'Item'
measurement shall have the quantity of '1'entered in the Quantity colu
encourage tenderers to provide an individual rate or price for each item
the requirements of the Preambles To The Schedule of Rates And Bills
Clause 9.12 of the Conditions Of Tendering.
Correct the Contract number shown in ALL the footers :
Press the CTRL & i keys together, and follow the prompts.
With correct use of this document, ALL totals should automatically be
Section Total and Summary. However, Authors should still check that
happened.
This document must be completed by a Qualified Quantity Surveyor ex
Roads WA Major Works Contracts. Main Roads' Quantity Surveyor ca
to ensure accuracy and completeness of these Schedules of Rates and/o
Quantities and compliance with Main RoadsStandard Method Of Me
Construction Works.
The Project Description lines only need to be entered on the Contents P
information entered there will automatically appear on the Summary Pa
AUTHOR's NOTES
Delete these notes fr om (or Do Not Prin t with) fi nal tende
This Document must be measured and compiled in accordance with M
Standard Method Of Measurement For Construction Worksand in
Preambles To The Schedule of Rates And Bills Of Quantities andwContract Specific Preambles.
Contract No. ??/?? Page 62
8/10/2019 SMM Example Schedule of Rates - Bill of Quantities 10July2012.u_3842828r_1n_D12^23210355
63/63
MAIN ROADSWestern Australia
Author's Notes