SMEDA CNG Filling Station

Embed Size (px)

Citation preview

  • 8/3/2019 SMEDA CNG Filling Station

    1/32

    Pre-Feasibility Study

    CNG FILLING STATION

    Small and Medium Enterprise Development AuthorityGovernment of Pakistan

    www.smeda.org.pk

    HEAD OFFICE

    6th Floor, LDA Plaza, Egerton Road, LahoreTel: (042) 111-111-456, Fax: (042) 6304926, 6304927

    [email protected]

    REGIONAL OFFICEPUNJAB

    REGIONAL OFFICESINDH

    REGIONAL OFFICE

    NWFP

    REGIONAL OFFICE

    BALOCHISTAN

    8th Floor, LDA Plaza, EgertonRoad, Lahore.

    Tel: (042) 111-111-456Fax: (042) 6370474

    [email protected]

    5TH Floor, BahriaComplex II, M.T. Khan Road,

    Karachi.Tel: (021) 111-111-456

    Fax: (021) [email protected]

    Ground FloorState Life Building

    The Mall, Peshawar.Tel: (091) 9213046-47

    Fax: (091) [email protected]

    Bungalow No. 15-AChaman Housing Scheme

    Airport Road, Quetta.Tel: (081) 831623, 831702

    Fax: (081) [email protected]

    May, 2005

  • 8/3/2019 SMEDA CNG Filling Station

    2/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    1

    1 INTRODUCTION TO SMEDA................................................................................. 22 Purpose of the document............................................................................................23 Crucial Factors & Steps in decision making for investment........................................3

    3.1 Key Success Factors........................................................................................... 33.2 Opportunities .....................................................................................................3

    3.3 Threats ...............................................................................................................34 Project Profile............................................................................................................34.1 Opportunity Rationale ........................................................................................34.2 Project Brief.......................................................................................................34.3 Introduction to CNG .......................................................................................... 44.4 Proposed Business Legal Status ......................................................................... 44.5 Project Cost........................................................................................................44.6 Viable Economic Size........................................................................................54.7 Proposed Capacity.............................................................................................. 54.8 Proposed Location.............................................................................................. 54.9 CNG Policy........................................................................................................5

    4.10 CNG Consultancy Services ................................................................................65 Market Analysis.........................................................................................................65.1 Target Customers............................................................................................... 65.2 Market Demand ................................................................................................. 65.3 Market Supply ...................................................................................................65.4 Industry Growth.................................................................................................6

    6 REGULATIONS, Licenses and incentives.................................................................76.1 License...............................................................................................................76.2 Certificate (by HDIP) .........................................................................................76.3 NOCs.................................................................................................................76.4 Incentives...........................................................................................................8

    6.4.1 Sales Tax....................................................................................................86.4.2 Custom Duty ..............................................................................................8

    6.5 Regulatory Requirements ...................................................................................86.5.1 Quality Certificate ......................................................................................86.5.2 List of Equipment....................................................................................... 86.5.3 Income Tax on the Import of CNG Equipment ...........................................8

    6.6 Income Tax........................................................................................................87 The Project CONCEPT.............................................................................................. 9

    7.1 Project Cost........................................................................................................97.2 Project Financing ...............................................................................................97.3 Project Details.................................................................................................... 9

    7.3.1 Location .....................................................................................................97.3.2 Land........................................................................................................... 97.3.3 Building ................................................................................................... 107.3.4 Material Inputs .........................................................................................117.3.5 CNG Equipment....................................................................................... 117.3.6 Suppliers ..................................................................................................127.3.7 Stores & Spares ........................................................................................ 137.3.8 Furniture and Fixtures .............................................................................. 13

  • 8/3/2019 SMEDA CNG Filling Station

    3/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    2

    7.3.9 Office Equipment ..................................................................................... 137.4 Manpower Requirement ...................................................................................13

    8 Basis for Financial Projections................................................................................. 148.1 Inflation Rate ................................................................................................... 148.2 Revenue Assumptions ...................................................................................... 14

    8.2.1 No. of Cars............................................................................................... 148.2.2 Gas per Vehicle........................................................................................ 148.3 Depreciation on Assets..................................................................................... 15

    8.3.1 Accounting Profit ..................................................................................... 158.3.2 Taxable Profit...........................................................................................15

    8.4 First Year Allowance ....................................................................................... 158.5 Multiple Shift Allowance ................................................................................. 158.6 Amortization of Preliminary Expenses ............................................................. 168.7 Working Capital...............................................................................................16

    8.7.1 Accounts Receivables............................................................................... 168.7.2 Advances to Employees............................................................................16

    8.7.3 Accrued Utilities and Power Expenses ..................................................168.7.4 Accounts Payable ..................................................................................... 168.7.5 Sales Tax Payable.....................................................................................16

    8.8 Sales Tax ......................................................................................................... 168.9 Ratio/Financial Analysis ..................................................................................168.10 Alternative Investment Opportunity .................................................................17

    9 Financial Analysis ................................................................................................... 189.1 Project Costs ....................................................................................................189.2 Projected Income Statement .............................................................................199.3 Projected Balance Sheet ...................................................................................209.4 Projected Cash Flow Statement ........................................................................ 219.5 Revenues.......................................................................................................... 229.6 Cost of Sales ....................................................................................................239.7 Working Capital...............................................................................................249.8 Ratio Analysis..................................................................................................25

    10 Requirement for the License ................................................................................26

  • 8/3/2019 SMEDA CNG Filling Station

    4/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    1

    DISCLAIMER

    The purpose and scope of this information memorandum is to introduce the subject

    matter and provide a general idea and information on the said area. All the material

    included in this document is based on data/information gathered from various sources

    and is based on certain assumptions. Although, due care and diligence has been taken to

    compile this document, the contained information may vary due to any change in any of

    the concerned factors, and the actual results may differ substantially from the presented

    information. SMEDA does not assume any liability for any financial or other loss

    resulting from this memorandum in consequence of undertaking this activity. The

    prospective user of this memorandum is encouraged to carry out additional diligence

    and gather any information he/she feels necessary for making an informed decision.

    For more information on services offered by SMEDA, please contact our website:

    www.smeda.org.pk

    DOCUMENT CONTROL

    Document No. PREF-34

    Revision 2

    Prepared by SMEDA-Punjab

    Issue Date May, 2002

    Revised on May, 2005

    Issued by Library Officer

  • 8/3/2019 SMEDA CNG Filling Station

    5/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    2

    1 INTRODUCTION TO SMEDA

    The Small and Medium Enterprise Development Authority (SMEDA) was established withthe objective to provide fresh impetus to the economy through the launch of an aggressiveSME support program.

    Since its inception in October 1998, SMEDA had adopted a sectoral SME developmentapproach. A few priority sectors were selected on the criterion of SME presence. In depthresearch was conducted and comprehensive development plans were formulated afteridentification of impediments and retardants. The all-encompassing sectoral developmentstrategy involved recommending changes in the regulatory environment by taking intoconsideration other important aspects including finance, marketing, technology and humanresource development.

    SMEDA has so far successfully formulated strategies for sectors including, fruits andvegetables, marble and granite, gems and jewelry, marine fisheries, leather and footwear,

    textiles, surgical instruments, transport and dairy. Whereas the task of SME development ata broader scale still requires more coverage and enhanced reach in terms of SMEDAs

    areas of operation.

    Along with the sectoral focus a broad spectrum of business development services is alsooffered to the SMEs by SMEDA. These services include identification of viable businessopportunities for potential SME investors. In order to facilitate these investors, SMEDAprovides business guidance through its help desk services as well as development of projectspecific documents. These documents consist of information required to make well-researched investment decisions. Pre-feasibility studies and business plan development aresome of the services provided to enhance the capacity of individual SMEs to exploit viablebusiness opportunities in a better way.

    This document is in the continuation of this effort to enable potential investors to make

    well-informed investment decisions.

    2 PURPOSE OF THE DOCUMENT

    The objective of the pre-feasibility study is primarily to facilitate potential entrepreneurs tofacilitate investment and provide an overview about CNG Filling Station business. Theproject pre-feasibility may form the basis of an important investment decision and in orderto serve this objective, the document covers various aspects of the business conceptdevelopment, start-up, production, marketing, and finance and business management. Thedocument also provides sectoral information, brief on government policies andinternational scenario, which have some bearing on the project itself.This particular pre-feasibility is regarding CNG Filling Station which comes under

    Petroleum sector.

  • 8/3/2019 SMEDA CNG Filling Station

    6/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    3

    3 CRUCIAL FACTORS & STEPS IN DECISION MAKING FOR INVESTMENT

    33..11 KKeeyy SSuucccceessss FFaaccttoorrss

    Following factors are the key in making this project profitable:

    Location of the project will play a pivotal role in the successful running of the CNGstation. The daily turnover of the cars largely depends on this important factor.

    Selection of proper equipment is another key for carrying out the successful operationsof the proposed project.

    33..22 OOppppoorrttuunniittiieess

    The proposed project would have a number of competitive advantages:

    The project will provide cheaper fuel to its customers compared to the petroleumproducts which are already on the higher side.

    Government has exempted the imposition of sales tax and custom duties on the importof CNG kits and CNG plant and equipment,

    HDIP, a non-profitable organization working under the umbrella of Ministry ofPetroleum and Natural Resources, provides consultancy services to the interestedparties for setting up the CNG filling stations.

    33..33 TThhrreeaattss

    The proposed project will be facing the following threat:

    Market saturation over a longer period of time due to a large number of entrants

    Threat of increase in the prices of the natural gas by the government

    4 PROJECT PROFILE

    44..11 OOppppoorrttuunniittyy RRaattiioonnaallee

    Due to the environment friendly nature and low cost of natural gas, HydrocarbonDevelopment Institute of Pakistan (HDIP) has recognized the need and necessity topromote the use of CNG as a fuel in automobiles. HDIP has pioneered the use ofenvironment friendly CNG in road transport as an economically viable fuel, which cansubstitute the imported petroleum products.

    44..22 PPrroojjeecctt BBrriieeff

    The business of CNG filling station has marked its place in the country through growthduring the last few years. This growth has opened up new opportunities and more CNGfilling stations are being setup all over Pakistan. The prime reason for this is the low cost ofthe fuel. Along with that, CNG fuel is less hazardous to the environment as compared tothe traditional petroleum fuel.

  • 8/3/2019 SMEDA CNG Filling Station

    7/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    4

    44..33 IInnttrroodduuccttiioonn ttoo CCNNGG

    Natural Gas is one of the most valuable natural resources abundantly available in ourcountry. The people of Pakistan have been using the petroleum products as a fuel in theirautomobiles, thus spending a huge amount of foreign exchange on import of petroleumproducts. Moreover, the Government of Pakistan has taken certain concrete steps in orderto promote the use of natural gas as a fuel substitute in the automobiles. Due to the effortsmade by the Government and comparatively low prices of gas, more than 600,000*

    vehicles have already been converted to operate on Compressed Natural Gas (CNG)fueling system all over Pakistan.Due to high cost of petroleum products, lots of vehicles are switching over to CNG. Atpresent, there are more than 6701 CNG stations operating in the Country and this number isinsufficient to meet the rising demand of CNG in the coming years.The total project cost for setting up the CNG filling stations has been estimated at Rs.31.13million. It includes land, building, CNG equipment and machinery, spares, along with thepreliminary expenses and working capital.Compressed Natural Gas (CNG) is produced when the natural gas is compressed intocylinders to be used as a fuel in the automobiles. The compressed natural gas has been usedas an automobile fuel since 1940, and over the years, the technology has been modified andrefined. In the recent years, the usage of CNG as an automobile fuel has significantlyincreased because of its low cost and environment friendly nature.

    44..44 PPrrooppoosseedd BBuussiinneessss LLeeggaall SSttaattuuss

    The proposed legal structure of the business entity is either sole proprietorship orpartnership. Although selection totally depends upon the choice of the entrepreneur but thisfinancial feasibility is based on a Sole Proprietorship.

    44..55 PPrroojjeecctt CCoosstt

    The cost of project has been estimated as Rs.31.13 million including land, civil works,CNG equipment and office equipment. Preliminary expenses and gas security charges areestimated at Rs.0.82 million and Rs.1.8 million respectively. The CNG equipmentcomprises of gas compressor, dual hose dispenser, electric control panel, and storagecascades/cylinders.

    TTaabbllee 44--11 PPrroojjeecctt IInnvveessttmmeenntt

    Fixed Investment Rs. 30,750,140

    Working Capital Rs. 377,390

    Total Investment Rs. 31,127,530

    The proposed pre-feasibility is based on the assumption of 50% debt and 50% equity.However this composition of debt and equity can be changed as per the requirement of theinvestor.The project seems to be viable with the following returns on investment.

    1Source: International Association of Natural Gas Vehicles (IANGV) Feb, 2005 Statistics

  • 8/3/2019 SMEDA CNG Filling Station

    8/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    5

    TTaabbllee 44--22 PPrroojjeecctt RReettuurrnnss

    Internal rate of return (project) 23.1%

    Internal rate of return (equity) 45.1%

    Net Present Value @ 20% Rs. 3,401,246

    Payback period based on cash inflows 4 years

    44..66 VViiaabbllee EEccoonnoommiicc SSiizzee

    A minimum of 202 cars is required to be filled daily in order to operate at breakeven.Considering the market trends and number of vehicles being converted into CNG fuelingsystem, initially the project would be able to attract and serve at-least 202 vehicles per day.

    44..77 PPrrooppoosseedd CCaappaacciittyy

    The equipment for CNG filling station that has been considered for preparing this pre-feasibility study is of British origin. This equipment is relatively more efficient and

    effective of the all types of equipment available in the market. Various other types ofequipment are also available at a lower price. The chosen equipment is capable of refueling50 vehicles per hour. Twin hose dispenser accompanies this equipment and it handlesrefueling of two vehicles at a time.

    44..88 PPrrooppoosseedd LLooccaattiioonn

    The proposed locations for the CNG Filling stations in Lahore are as follows

    Multan Road, Lahore

    Wapda Town, Lahore

    Model Town, Link Road, Lahore

    Johar Town, PIA ColonyThe said project may also be established in commercial area of any other city.

    44..99 CCNNGG PPoolliiccyy

    The Government of Pakistan has offered number of incentives for encouraging the use ofCNG in the country. Some of these are summarized below:

    Strong Government commitment to promote usage of CNG

    Liberal policy of providing license for CNG retailing

    Deregulated market price of CNG (for the consumers)

    Priority of providing natural gas connection to CNG stations

    Exemption of import duty and sales tax till June 2005 on import of machinery andequipment, CNG kits and cylinders

  • 8/3/2019 SMEDA CNG Filling Station

    9/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    6

    This has provided a boost to the industry, and so far, more than 600,000 vehicles have beenconverted to CNG and 6702 CNG stations are operational. According to InternationalAssociation for Natural Gas Vehicles (IANGV) statistics, Pakistan is ranked third in theCNG-using countries after Argentina and Brazil.

    44..1100 CCNNGG CCoonnssuullttaannccyy SSeerrvviicceess

    HDIP is also offering consultancy services to the investors, which include the whole rangeof activities like formation of company, selection of site, legal formalities, design ofstation, specifications of the equipment, selection of equipment, selecting and appointingthe contractor, training of manpower, commissioning and supervision, etc.

    5 MARKET ANALYSIS

    The commercial application of CNG technology now forms an important element ofGovernments petroleum policy, which is reflected in the efforts made by the governmentfor installing 670 CNG stations in the country and converting 600,000 vehicles on CNGfueling system till February 2005.

    55..11 TTaarrggeett CCuussttoommeerrss

    The target customers for the proposed project would be the vehicles running on CNG fuel.

    55..22 MMaarrkkeett DDeemmaanndd

    At present there are more than 600,000 vehicles, which have been converted to CNG fuel,and a large number of vehicles are further being converted.

    Due to the increasing prices of petroleum products, the trend of converting cars to CNGfueling system has been on a rise. However, there exist a large number of people who were

    reluctant to convert their vehicles from petrol to gas due to safety concerns. Recently, manycar manufacturers have started manufacturing the cars with built-in CNG fueling system.This change has led to enhancing the confidence in the minds of the general publicregarding the safety concerns, and now, more people are inclined towards purchasing thesefactory-fitted CNG fueling system cars.

    55..33 MMaarrkkeett SSuuppppllyy

    Total number of CNG stations in Pakistan is only 670, which is quite low for meeting thegrowing demand of CNG. Apart from these 670 CNG stations, many new CNG stations arebeing setup across the country.

    55..44 IInndduussttrryy GGrroowwtthh

    There has been a tremendous growth in the CNG sector over the yeas. The total number ofvehicles on CNG was 100,000 and CNG filling stations was 150 at the end of year 2000.The number of CNG vehicles and CNG filling stations has increased to 210,000 vehicles

    2 As on Feb, 2005

  • 8/3/2019 SMEDA CNG Filling Station

    10/32

  • 8/3/2019 SMEDA CNG Filling Station

    11/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    8

    66..44 IInncceennttiivveess

    66..44..11 SSaalleess TTaaxx

    The import of CNG equipment is exempted from sales tax vide SRO No.38 (1)/98 dated21st January 1998 till June, 2005.

    66..44..22 CCuussttoommDDuuttyy

    The CNG equipment is also exempted from the custom duties as per the above-referredSRO.

    66..55 RReegguullaattoorryy RReeqquuiirreemmeennttss

    66..55..11 QQuuaalliittyy CCeerrttiiffiiccaattee

    SRO.38 (1)/98 dated 21st January 1998 has been amended on April 11, 2002 and theQuality Certificate from original manufacturer has been made mandatory. This certificateshould state that the equipment meets the safety standard as laid down in Pakistan CNG

    Rules 1992. The designated third party inspector witnesses this Quality Certificate. Thecost of third party inspection is $500.

    66..55..22 LLiissttooffEEqquuiippmmeenntt

    The list of equipment and their various manufacturers has also been mentioned in the sameamended SRO whose import is exempted from custom duty and sales tax.

    66..55..33 IInnccoommee TTaaxx oonn tthheeIImmppoorrttooffCCNNGGEEqquuiippmmeenntt

    Income Tax, at the rate of 6%, is payable by the importer on the import of CNG equipment.

    66..66 IInnccoommee TTaaxxThe income of the CNG filling station is not exempted from the income tax. The investorhas to pay tax on his/her income according to the nature of the business entity. The currentproject is being operated as a private limited company, so the income tax is payable at therate of 45%.

  • 8/3/2019 SMEDA CNG Filling Station

    12/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    9

    7 THE PROJECT CONCEPT

    77..11 PPrroojjeecctt CCoosstt

    The details of the cost of project are as follows:

    TTaabbllee 77--11 PPrroojjeecctt CCoossttss

    Item Rupees

    Land (9,000 Sq. ft) 17,000,000

    Building Civil Works 1,700,000

    CNG Equipment 8,732,100

    Stores & Spares 513,040

    Office Equipment 100,000

    Furniture & Fixtures 85,000

    Gas Security 1,800,000

    Preliminary Expenses 820,000

    Working Capital 377,390

    Total 31,127,530

    77..22 PPrroojjeecctt FFiinnaanncciinngg

    The total cost of the project is Rs.31.13 million including the working capital of Rs.0.377million. The sponsors of the project will contribute Rs.15.56 million and the bank willfinance the remaining amount of Rs.15.56 million.

    77..33 PPrroojjeecctt DDeettaaiillss

    77..33..11 LLooccaattiioonn

    For setting up a CNG filling station, location is the prime factor. As per the requirements ofthe Government of Pakistan, the filling station must be situated in a commercial area. CNGfilling stations are not allowed to be installed in the residential areas.

    77..33..22 LLaanndd

    A minimum of nine thousand (9000) square feet of land with at least 75 feet front openingis required for installing CNG filling station. An amount of Rs.17 million has beenallocated for the acquisition of nine thousand square feet of commercial land in Lahore in

    in the areas of Model Town Link Road or Multan Road. A comparison of costs ofcommercial land in various other areas of Lahore is given below for reference purpose.

  • 8/3/2019 SMEDA CNG Filling Station

    13/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    10

    TTaabbllee 77--22 AApppprrooxxiimmaattee CCoosstt ooffLLaanndd iinn tthhee PPrrooppoosseedd AArreeaass

    Location Price Range for 9,000 Sq.ft

    Gulberg, M. M. Alam Road. Rs.16,000,00018,000,000

    Main Boulevard Rs. 30,000,00032,000,000

    Main Ferozpur Raod Rs.10,000,00012,000,000Model Town Link Road Rs.7,000,0009,000,000

    Multan Road Rs.2,000,00010,000,000

    Johar Town, PIA Colony Rs.18,000,00035,000,000

    In this report, prices of commercial land for Lahore city has been considered, however,prices may considerably vary in the other cities like Quetta, Karachi, Hyderabad, Multan,Faisalabad, Islamabad, Peshawar etc.

    77..33..33 BBuuiillddiinngg

    There are certain civil works required to be carried out at the proposed location. The civil

    works would be carried out on an area of 2250 square feet. The rest of the area will befloored with tuff tiles. Civil work includes the following:

    Office

    Control Room

    Compressor and Cascade/Cylinder Storage Room

    Shed for Dispenser

    Toilet/washroom

    Underground Gas Piping and Power Cables

    Flooring

    The total cost of construction is estimated at Rs.1.7 million. Details for the said cost are as

    follows:

    TTaabbllee 77--33 CCoonnssttrruuccttiioonn CCoosstt ((AAmmoouunntt iinn RRuuppeeeess))

    Description Cost per Sq. ft. Cost

    Office, control room, compressor and cylinder storageroom, shed and toilet/washroom (2,250 sq.ft)

    500 1,125,000

    Underground gas piping - 200,000

    Flooring (6,750sq.ft) 45 303,750

    Contingencies - 71,250

    Total Cost - 1,700,000

    Explosives department has laid down certain specifications for the compressor andcascade/cylinders storage room, which are as follows:

    1. Minimum one meter distance is required between walls and compressor.2. Minimum distance of one meter should be kept between compressor and

    cascade/cylinders.

  • 8/3/2019 SMEDA CNG Filling Station

    14/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    11

    3. Fire rated walls3 must be used in the compressor and cylinder storage room.4. Roof of the compressor and storage room should not be of permanent nature4.

    77..33..44 MMaatteerriiaallIInnppuuttss

    There are two main inputs required for the CNG filling station, one is the natural gas andthe other is electricity. The sponsor of the project is required to obtain both the connections

    from the relevant authorities i.e. WAPDA and Sui Northern Gas Pipelines Limited(SNGPL) or Sui Southern Gas Pipelines Limited (SSGPL). The cost associated withobtaining the gas connection is Rs.75, 000/-. In addition to this, a minimum securitydeposit of Rs.1.8million is also required to be deposited with the concerned authority.Bank guarantee is also acceptable in case of gas security. An amount of Rs.0.35 million isrequired for obtaining electricity connection. There is no security deposit required for theelectricity connection.

    77..33..55 CCNNGGEEqquuiippmmeenntt

    The following equipment is required for a CNG filling station:

    Gas CompressorThe purpose of compressor is to compress the gas enabling it to discharge the gas forrefueling. This compressor requires an input pressure of 8 or 15 PSIG5 from the main gassupply with the outlet pressure of 3,625 PSIG. With this discharge pressure, the equipmentcan refuel 50 vehicles per hour.

    Electric Control PanelElectric control panel is required to operate the gas compressor. This panel will be mountedin the control room.

    Storage CascadeStorage cascades/cylinders are used to store the natural gas.

    Priority Panel for Vehicle PriorityDuring rush hours, the compressor is directly connected to the dispenser, bypassing thestorage cascades/cylinders with the help of priority panel, facilitating the refueling ofvehicles at a faster rate.

    CNG Dispenser high flow dual hoseGas is filled into the vehicles with the help of dispenser. This dual hose dispenser iscapable of handling two vehicles at a time.

    There are various foreign manufacturers providing the CNG filling station equipment. Inthis pre-feasibility report, a British origin compressor6has been selected. This equipment isselected because of its low electricity consumption, higher outlet pressure, low

    maintenance, durable working, longer periods between overhauls and good market reputeand presence.

    3

    with RCC (Reinforced cement concrete) structure4

    Corrugated asbestos might be used as the roof for the compressor and cylinder storage room to prevent thecompressor and cylinders from heat.5

    pounds per square inch gauge pressure6 Ham worthy Compressor, Bellies & Marcum, UK, Model: H430H-WL Capacity: 400 m3/hr

  • 8/3/2019 SMEDA CNG Filling Station

    15/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    12

    Different gas pressures are available in different areas of Pakistan from the main gas supplyline. The pressure of 15 PSIG is not easily available at every location. Where the gaspressure of 15 PSIG is not available, in that situation, the model with inlet pressure of 8PSIG is used, which has been manufactured to operate at a lower gas pressure. However,the consumption of electricity increases.The total capacity of the selected equipment is 400M3 /Hr with a total power load of 93

    KW.

    All the CNG filling station equipment is foreign manufactured and imported on the specificrequirement of the sponsor by the authorized agent. Usually, the equipment is deliveredwithin 12 to 16 weeks from the receipt of purchase order and initial payment. The details ofthis equipment and accessories are available in Annexure # 1.1.1.

    77..33..66 SSuupppplliieerrss

    The Central Board of Revenue (CBR) has specified the list of compressors, storagecylinders, CNG vehicle cylinders, CNG machinery & equipment and conversion kits inSRO 38(1)/98. For the convenience of investor, a list of some of the available equipment

    and machinery is given below:

    TTaabbllee 77--44 SSuupppplliieerrss NNaammee

    Suppliers Name Available Models

    Rix Services, New Zealand 2JJS3G-178, FX-150, 3KX3G-40,6W5G-150

    Compare UK Ltd, UK Gazpack 36, Gazpack37

    Norwalk Company Inc. USA C-75-3, C150-4, NQSV3

    Sulzer Burckhardt Engg. Works Switzerland C40111S, C50214S

    Hamworthy, Bellis & Morcom UK H430H-WL, H280H-WL, V130H-WLSafe s.r.l Italy SW75SE-F1-EM, SW110SE-F1-EM,SW110-F1-EM, SW132-F1-EM,SW90F0, 35-EM

    Hurricane, Grimmer Industries, USA CNG90, CNG 125, CNG250

    Chengdu Jinxing Chemical Machinery andEquiment Factory, China

    ZW-3.45/250JX, ZW-5.0/1-23, ZW-5.52/0.5-250JX

    Chonqing Air Gas Compressor Factory, China L-3.8/1-250, L-3/1-250, L-5/0.56-250,L-2.9/0.56-250, L-4.65/0.56-250,W3.8/0.56-250, W-3.8/1-250

    Intermech Ltd. NewZealand RHINO PAR-75VE 4-8

    RHINO PAR-1-DE 4-82RHINO-PAR 150DE4-10

    Unigas NewZealand Apollo VR-550

    Compare Mahle GmbH, Germany 5409.2NG.EU

    Sicom SRL , Italy 650.250.20-IFDE-23SE

  • 8/3/2019 SMEDA CNG Filling Station

    16/32

  • 8/3/2019 SMEDA CNG Filling Station

    17/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    14

    8 BASIS FOR FINANCIALPROJECTIONS

    88..11 IInnffllaattiioonn RRaattee

    10% inflation rate has been considered while making the projections for cost of sales,

    operational expenses and salaries. The prices for gas, electricity, operational expenses andstaff salaries are increased by 10% every year as a result of inflation.The selling price of gas has been increased by 5% every year.

    88..22 RReevveennuuee AAssssuummppttiioonnss

    88..22..11 NNoo.. ooffCCaarrss

    Based on the survey of some CNG stations in Lahore, the number of cars assumed forrevenue projections is as follows:

    TTaabbllee 88--11 DDeettaaiilleedd PPrroojjeecctteedd IInnccrreeaassee iinn CCaarrss

    Years No. Of Cars

    1 202

    2 303

    3 363

    4 435

    5 522

    6 600

    7 690

    8 7939 911

    10 1,047The average number of cars in the first years is estimated at 202 cars per day, starting from120 cars per day in the first month and going up to 290 cars per day in the 12 th month.. Inthe second year, it has increased to 303 cars per day. After second year, number of cars isincreasing at a rate of 20% till fifth year because the project would be in its growth stage.An increase of 15% has been considered from sixth year, because at that time, the projectwould be at its maturity stage.

    88..22..22 GGaassppeerrVVeehhiiccllee

    Currently, the CNG cylinders with two different capacities are installed in the CNG fittedcars. One type of cylinder has a capacity of 40 kg and the other has a capacity of 50 kg.Gas of 6.6 and 11.12 cubic meter can be filled in the cylinders of 40kg and 50kgrespectively. A weighted average of 9.31 cubic meters of gas per vehicle has been taken forthe revenue calculations.

  • 8/3/2019 SMEDA CNG Filling Station

    18/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    15

    TTaabbllee 88--22 AAvveerraaggee VVoolluummee

    Cylinder Type Volume

    (cubic meters)

    Percentage Use

    40 kg 6.6 40%

    50 kg 11.12 60%Weighted Average Volume 9.31 cubic meters

    88..33 DDeepprreecciiaattiioonn oonn AAsssseettss

    88..33..11 AAccccoouunnttiinngg PPrrooffiitt

    Depreciation on the assets has been charged at the following rates for the calculation ofaccounting profits:

    TTaabbllee 88--33 DDeepprreecciiaattiioonn RRaatteess

    Building 5%CNG Plant & Equipment 10%

    Office Equipment 20%

    Furniture & Fixture 10%

    88..33..22 TTaaxxaabbllee PPrrooffiitt

    For the purpose of calculating taxable profit, depreciation is calculated on the rates as perthe Income Tax Law, which is as follows:

    TTaabbllee 88--44 TTaaxx AAddjjuussttmmeennttss

    Land 0%Building 5%

    CNG Plant & Equipment 10%

    Office Equipment 10%

    Furniture & Fixture 10%

    88..44 FFiirrsstt YYeeaarr AAlllloowwaannccee

    Other than the normal depreciation allowances, first year allowance is also provided on thenewly installed CNG plant and equipment for the purpose of providing benefit to theentrepreneur. The first year allowance is calculated at 40% of written down value of CNG

    plant and equipment.

    88..55 MMuullttiippllee SShhiifftt AAlllloowwaannccee

    In addition to normal depreciation and first year allowances, multiple shift allowance isalso provided for the plant and machinery, which operates on double or triple shift basis. Inthis proposed project, CNG plant will run on two-shift basis during the whole year. Somultiple shift allowance is calculated and added to the depreciation of CNG plant and

  • 8/3/2019 SMEDA CNG Filling Station

    19/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    16

    equipment for all the ten years. Multiple shift allowance has been taken as 66.6% of thenormal depreciation allowance.

    88..66 AAmmoorrttiizzaattiioonn ooffPPrreelliimmiinnaarryy EExxppeennsseess

    Preliminary expenses amounting to Rs.820, 000/- will be amortized at the rate of 20% perannum.

    88..77 WWoorrkkiinngg CCaappiittaall

    Working capital is calculated on the basis of following assumptions:

    88..77..11 AAccccoouunnttssRReecceeiivvaabblleess

    Mostly, the sale of CNG is on cash basis. However, some CNG stations do offer a creditfacility to reputable companies on agreed terms and conditions. Therefore, receivables areestimated at 6% of the total sales amount.

    88..77..22 AAddvvaanncceess ttooEEmmppllooyyeeeess

    Advances to employees are calculated on the basis of 30 days of both payroll and staffbenefits.

    88..77..33 AAccccrruueeddUUttiilliittiieess aannddPPoowweerr EExxppeennsseess

    Normally, it would take 20 days to deposit the utilities (electricity, water and telephone)bills. Therefore, utility expenses for 20 days have been taken as the basis for workingcapital computation.

    88..77..44 AAccccoouunnttss PPaayyaabbllee

    Cost of gas and electricity for 20 days has been considered in calculating accounts payable.

    88..77..55 SSaalleess TTaaxx PPaayyaabbllee

    Every company is required to deposit the amount of sales tax collected from the consumers,within 14 days. The same has been taken as the basis for calculating the amount of sales taxpayable.

    88..88 SSaalleess TTaaxx

    The sales tax levied by Government of Pakistan is charged to the customers at the rate of15% on the sale of gas. These funds are deposited after every 14 days in favor ofGovernment of Pakistan.

    88..99 RRaattiioo//FFiinnaanncciiaall AAnnaallyyssiissThe figures for the rate of return on investment and return on equity are averaged for thefirst five years to make it more reasonable.

  • 8/3/2019 SMEDA CNG Filling Station

    20/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    17

    88..1100 AAlltteerrnnaattiivvee IInnvveessttmmeenntt OOppppoorrttuunniittyy

    The cost of land is the major portion of investment in this project. If any investor does nothave enough resources for the acquisition of land, he/she also has another alternativecourse of action to setup the CNG station without acquiring the land.

    The investor can make investments only in the purchase of CNG plant and equipment and

    install this equipment with any existing petrol pump. In this case, the investment forinstalling the CNG equipment will be made by the investor and the space will be providedby the dealer/owner of the existing petrol pump. The investor will pay 15% commission onthe total revenue to the dealer/owner of the petrol pump. Moreover, the investor can alsoavail lease facility from any leasing company on the purchase of CNG plant andequipment.

  • 8/3/2019 SMEDA CNG Filling Station

    21/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    18

    9 FINANCIAL ANALYSIS

    99..11 PPrroojjeecctt CCoossttss

    P r o j e c t C o s t

    R s. R s.

    A s s e t s

    La n d 1 7 ,0 0 0 ,0 0 0

    B u ild in g - C iv i l W o rk s 1 ,70 0 ,0 0 0C N G E q u ip m e n t 1 3 3 ,9 0 0$ 8 , 732 , 100

    S to re & Sp a re s 8 ,0 0 0$ 5 1 3 , 0 4 0

    O ffic e E q u ipm e n t 1 0 0 ,0 0 0Fu rn itu re & F ix tu re 8 5 ,0 0 0 28 , 130 , 140

    A d v a n c e s & S e c u r i t i e s

    G a s S e cu r ity (D ep e n d s o n th e S N G PL a ss e ssm e n t) 1 ,8 0 0 ,0 0 0

    P r e l im i n a r y E x p e n s e sG a s C o n n ec t io n s & In sta lla tio n C h a rg e s (SN G P L ) 7 5 ,0 0 0E le c tr ic ity C o nn e ct io n s C ha rg e s 3 5 0 ,0 0 0

    Lo ca l E x pe n s e s 1 0 0 ,0 0 0L ice n se fro m M O P 2 5 ,0 0 0

    R eg is tra t io n o f Co m pa ny (A utho r ize d C a pita l 1 0 m il l io n ) 8 5 ,0 0 0

    In sp e c t io n F ee (H D IP ) 3 5 ,0 0 0

    O th e r A pp ro va ls (N O C s ) 1 0 0 ,0 0 0T ra ve ll in g & C o n ve ya nc e 2 0 ,0 0 0

    O th e r E x p e n s e s 3 0 ,0 0 0 8 2 0 , 0 0 0

    W o r k i n g C a p i t a l 3 7 7 , 3 9 0

    T o t a l A s s e t s 3 1 ,1 2 7 ,5 3 0R s .T o t a l C a p i t a l E m p l o y e d B y :

    B a n k L o a n 5 0 % 1 5 ,5 6 3 ,7 6 5

    E qu ity 5 0 % 1 5 ,5 6 3 ,7 6 5T o t a l C a p i t a l 3 1 ,1 2 7 ,5 3 0R s .

    1 U S $ = 6 0 .5 0R s .

    P r o j e c t R e t u r n s

    IR R % 2 3 .1 %

    N P V @ 2 0 % R s. 3 ,4 0 1 ,2 4 6P a y B a ck P e rio d Y r s . 4

  • 8/3/2019 SMEDA CNG Filling Station

    22/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    19

    99..22 PPrroojjeecctteedd IInnccoommee SSttaatteemmeenntt

    Statement Summaries

    Income StatementYear 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

    202 Cars 303 Cars 363 Cars 435 Cars 522 Cars 600 Cars 690 Cars 793 Cars 911 Cars 1047 Cars

    Gross Sales 13,139,090 20,375,524 25,673,161 32,303,626 40,702,568 49,123,789 59,316,976 71,580,116 86,342,950 104,194,426

    Less: Sales Tax 1,714,651 2,659,006 3,350,347 4,215,623 5,311,685 6,410,655 7,740,865 9,341,205 11,267,755 13,597,373Net Sales 11,424,439 17,716,518 22,322,813 28,088,003 35,390,883 42,713,135 51,576,110 62,238,911 75,075,195 90,597,054

    Cost of Sales 5,516,754 8,937,181 11,766,663 15,474,153 20,382,143 25,720,252 32,478,303 40,992,720 51,725,438 65,304,354

    Gross Profit 5,907,685 8,779,338 10,556,150 12,613,850 15,008,740 16,992,883 19,097,807 21,246,191 23,349,757 25,292,699

    Operating Expenses:Operating Expenses 2,032,005 2,147,885 2,284,084 2,441,762 2,622,282 2,896,712 3,120,922 3,374,100 3,658,487 3,976,614

    Depreciation 986,710 890,289 803,698 725,883 810,345 731,953 661,391 597,852 540,615 489,037Amortization of Preliminary Exp. 164,000 164,000 164,000 164,000 164,000 - - - - -

    3,182,715 3,202,174 3,251,782 3,331,646 3,596,627 3,628,665 3,782,313 3,971,951 4,199,101 4,465,652Operating Profit 2,724,970 5,577,164 7,304,369 9,282,204 11,412,113 13,364,218 15,315,494 17,274,240 19,150,656 20,827,048

    Interest on Loan 1,089,464 1,852,088 1,416,303 980,517 544,732 108,946 - - - -

    Interest on Lease - - - - - - - - - -1,089,464 1,852,088 1,416,303 980,517 544,732 108,946 - - - -

    Profit before Tax 1,635,507 3,725,076 5,888,066 8,301,687 10,867,382 13,255,272 15,315,494 17,274,240 19,150,656 20,827,048Taxation (See working) 57,122 487,101 2,126,398 2,976,423 3,841,159 4,687,398 5,415,542 6,105,492 6,764,544 7,351,985

    Profit after Tax 1,578,384 3,237,975 3,761,668 5,325,264 7,026,222 8,567,874 9,899,952 11,168,748 12,386 ,112 13,475,063Balance B/F - 1,578,384 4,816,359 8,578,027 13,903,291 20,929,514 29,497,388 39,397,339 50,566,087 62,952,199

    Retained Earnings 1,578,384 4,816,359 8,578,027 13,903,291 20,929,514 29,497,388 39,397,339 50,566,087 62,952,199 76,427,262- - - - - - - - - -

    Balance C/F 1,578,384 4,816,359 8,578,027 13,903,291 20,929,514 29,497,388 39,397,339 50,566,087 62,952,199 76,427,262

  • 8/3/2019 SMEDA CNG Filling Station

    23/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    20

    99..33 PPrroojjeecctteedd BBaallaannccee SShheeeett

    Statement Summaries

    Balance SheetYEAR Start up 1 2 3 4 5 6 7 8 9 10

    FIXED ASSETS 27,617,100 26,630,390 25 ,740,101 24,936,403 24 ,210,520 24,94 4,4 76 24,212,523 23,55 1,132 22,95 3,280 22,41 2,665 21, 923,628

    27,617,100 26,630,390 25 ,740,101 24,936,403 24 ,210,520 24,94 4,4 76 24,212,523 23,55 1,132 22,95 3,280 22,41 2,665 21, 923,6 28

    Preliminary Expenses 820,000 656,000 492,000 328,000 164,000 - - - - - -

    28,437,100 27,286,390 26 ,232 ,101 25,264,403 24 ,374,520 24,94 4,4 76 24,212,523 23,551,132 22,953,280 22,41 2,665 21, 923,6 28OTHER ASSETS

    Security 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000

    - - - - - - - - - - -

    1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000 1,800,000

    CURRENT ASSETS

    Accounts Receivables - 793,364 1,230,314 1,550,195 1,950,556 2,457,700 2,966,190 3,581,674 4,322,147 5,213,555 6,291,462

    Advances to Employees - 87,450 96,195 105,815 116,396 128,036 140,839 154,923 170,415 187,457 206,203

    Stores & Spares 513,040 513,040 513,040 513,040 513,040 513,040 513,040 513,040 513,040 513,040 513,040

    Cash & Bank Balances 377,390 1,042,927 1,999,944 3,469,418 6,398,351 9,535,653 17,094,942 27,451,315 38,994,185 51,680,102 65,388,343

    890,430 2,436,781 3,839,493 5,638,468 8,978,343 12,63 4,4 28 20,715,011 31,700,953 43,999,787 57,59 4,154 72, 399,0 47

    TOTAL ASSETS 31,127,530 31,523,171 31,871,594 32,702,872 35 ,152 ,863 39,37 8,9 04 46,727,534 57,052,084 68,753,067 81,80 6,819 96, 122,6 75

    - - - - - - - - - - -

    CAPITAL EMPLOYED REPRESENTED BY:

    SHARE CAPITAL

    1,556,377 Shares @ Rs.10/- each 15,563,765 15,563,765 15 ,563,765 15,563,765 15 ,563,765 15,56 3,7 65 15,563,765 15,56 3,765 15,56 3,765 15,56 3,765 15, 563,765

    UNAPP. PROFIT/(LOSS) - 1,578,384 4,816,359 8,578,027 13,903,291 20,929,5 14 29,497,388 39,397,339 50,566,087 62,952,199 76, 427,262

    15,563,765 17,142,149 20,38 0,124 24,14 1,792 29,46 7,056 36,49 3,2 79 45,061,153 54,96 1,104 66,12 9,852 78,51 5,964 91, 991,0 27

    LONG TERM LIABILITIES

    Finance Lease - - - - - - - - - - -

    Long Term Loan 15,563,765 14,007,389 10 ,894 ,636 7 ,781,883 4,669,130 1,556,377 - - - - -15,563,765 14,007,389 10 ,894 ,636 7 ,781,883 4,669,130 1,556,377 - - - - -

    CURRENT LIABILITIES

    Creditors - 296,952 482,429 636,806 839,426 1,108,042 1,400,973 1,772,231 2,240,459 2,831,228 3,579,282

    Utility Bills Payable - 10,000 11,000 12,100 13,310 14,641 16,105 17,716 19,487 21,436 23,579

    Sales Tax Payable - 66,681 103,406 130,291 163,941 206,566 249,303 301,034 363,269 438,190 528,787

    - 373,633 596,834 779,197 1,016,677 1,329,249 1,666,381 2,090,980 2,623,215 3,290,855 4,131,648

    TOTAL 31,127,530 31,523,171 31,871,594 32,702,872 35 ,152 ,863 39,37 8,9 04 46,727,534 57,052,084 68,753,067 81,80 6,819 96, 122,6 75

  • 8/3/2019 SMEDA CNG Filling Station

    24/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    21

    99..44 PPrroojjeecctteedd CCaasshh FFllooww SSttaatteemmeenntt

    Statement SummariesCash Flow Statement

    YEAR 1 2 3 4 5 6 7 8 9 10SOURCESFROM OPERATION

    Profit Before Tax 1,635,507 3,725,076 5,888,066 8,301,687 10,867,382 13,255,272 15,315,494 17,274,240 19,150,656 20,827,048Add: Depreciation 986,710 890,289 803,698 725,883 810,345 731,953 661,391 597,852 540,615 489,037

    Amortization 164,000 164,000 164,000 164,000 164,000 - - - - -

    1,150,710 1,054,289 967,698 889,883 974,345 731,953 661,391 597,852 540,615 489,037

    2,786,217 4,779,365 6,855,764 9,191,570 11,841,727 13,987,225 15,976,885 17,872,091 19,691,271 21,316,085OTHER SOURCES

    - - - - - - - - - -2,786,217 4,779,365 6,855,764 9,191,570 11,841,727 13,987,225 15,976,885 17,872,091 19,691,271 21,316,085

    APPLICATIONRepayments of Loan 1,556,377 3,112,753 3,112,753 3,112,753 3,112,753 1,556,377 - - - -

    Tax Payment 57,122 487,101 2,126,398 2,976,423 3,841,159 4,687,398 5,415,542 6,105,492 6,764,544 7,351,985Dividend Paid

    - Cash - - - - - - - - - -

    1,613,499 3,599,854 5,239,151 6,089,176 8,498,213 6,243,774 5,415,542 6,105,492 6,764,544 7,351,985SURPLUS / (DEFICIT) 1,172,718 1,179,511 1,616,612 3,102,395 3,343,514 7,743,450 10,561,343 11,766,599 12,926,727 13,964,100

    INCREASE/(DECREASE) IN WORKING CAPITAL 507,181 222,493 147,138 173,462 206,212 184,161 204,970 223,729 240,811 255,859

    NET INCREASE/(DECREASE) 665,537 957,017 1,469,474 2,928,933 3,137,302 7,559,290 10,356,373 11,542,870 12,685,916 13,708,241OPENING BANK BALANCES 377,390 1,042,927 1,999,944 3,469,418 6,398,351 9,535,653 17,094,942 27,451,315 38,994,185 51,680,102

    CLOSING CASH BALANCE 1,042,927 1,999,944 3,469,418 6,398,351 9,535,653 17,094,942 27,451,315 38,994,185 51,680,102 65,388,343

    WORKING CAPITAL 507,181 729,674 876,813 1,050,275 1,256,487 1,440,648 1,645,617 1,869,346 2,110,157 2,366,017

    Increase 507,181 222,493 147,138 173,462 206,212 184,161 204,970 223,729 240,811 255,859

  • 8/3/2019 SMEDA CNG Filling Station

    25/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    22

    99..55 RReevveennuueess

    Revenues

    Quantity of Gas Sale per Vehicle

    Annual Increase in the Sale Price of Gas 5%

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

    255

    No . o f C ar s / d ay 202 C ar s 303 C ar s 363 C ar s 435 C ar s 522 C ar s 600 C ar s 690 C ar s 793 C ar s 911 C ar s 1047 C ar s

    Sale of Gas / day (in M3) 1878 2816 3380 4050 4860 5586 6424 7383 8481 9748

    Sale of Gas / month (in M3) 57206 84488 101386 121496 145795 167580 192717 221485 254442 292427

    Sale of Gas / anum (in M3) 686473 1013859 1216631 1457946 1749535 2010960 2312604 2657819 3053308 3509125

    Selling Price of Gas / M3 19.14Rs. 20.10Rs. 21.10Rs. 22.16Rs. 23.26Rs. 24.43Rs. 25.65Rs. 26.93Rs. 28.28Rs. 29.69Rs.

    Total Revenue 13,139,090 20,375,524 25,673,161 32,303,626 40,702,568 49,123,789 59,316,976 71,580,116 86,342,950 104,194,426

    Sales Tax @ 15% 2.50Rs. 2.62Rs. 2.75Rs. 2.89Rs. 3.04Rs. 3.19Rs. 3.35Rs. 3.51Rs. 3.69Rs. 3.87Rs.

    Sales Tax Amount 1,714,651Rs. 2,659,006Rs. 3,350,347Rs. 4,215,623Rs. 5,311,685Rs. 6,410,655Rs. 7,740,865Rs. 9,341,205Rs. 11,267,755Rs. 13,597,373Rs.

    9.31 Cubic Meter

  • 8/3/2019 SMEDA CNG Filling Station

    26/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    23

    99..66 CCoosstt ooffSSaalleess

    Cost of Sales

    Rate of Gas 6.50Rs. /Cubic Meter

    Consumption of Electricity 0.186 KW /Cubic Meter

    Rate of Electricity 6.92Rs. /KWHr

    Maintenance 0.25Rs. /Cubic Meter

    Annual Increase 10%Year 1 Year 2 Year 3 Year 4 Year 5 Year6 Year 7 Year 8 Year 9 Year 10

    No. of Cars / day 202 Cars 303 Cars 363 Cars 435 Cars 522 Cars 600 Cars 690 Cars 793 Cars 911 Cars 1047 Cars

    Annual Gas Sold (in M3) 686,473 1,013,859 1,216,631 1,457,946 1,749,535 2,010,960 2,312,604 2,657,819 3,053,308 3,509,125

    Electricity Consumed in KWH 127,684 188,578 226,293 271,178 325,414 374,039 430,144 494,354 567,915 652,697

    Rate of Gas 6.50Rs. 7.15Rs. 7.87Rs. 8.65Rs. 9.52Rs. 10.47Rs. 11.52Rs. 12.67Rs. 13.93Rs. 15.33Rs.

    Rate of Electricity 6.92Rs. 7.61Rs. 8.37Rs. 9.21Rs. 10.13Rs. 11.14Rs. 12.25Rs. 13.48Rs. 14.83Rs. 16.31Rs.

    Cost of Sales

    Cost of Gas Sold 4,462,074 7,249,092 9,568,801 12,613,420 16,649,714 21,051,363 26,629,974 33,665,690 42,542,734 53,783,169

    Cost of Electricity 883,062 1,434,624 1,893,704 2,496,246 3,295,045 4,166,149 5,270,178 6,662,575 8,419,377 10,643,904

    Maintenance 171,618 253,465 304,158 364,487 437,384 502,740 578,151 664,455 763,327 877,281

    Cost of Sales 5,516,754 8,937,181 11,766,663 15,474,153 20 ,382,143 25,720,252 32,478,303 40,992,720 51,725,438 65,304,354

  • 8/3/2019 SMEDA CNG Filling Station

    27/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    24

    99..77 WWoorrkkiinngg CCaappiittaall

    Working Capital

    1 2 3 4 5 6 7 8 9 10

    Total No. of Days 360 Days

    Current Assets Basis

    Receivables Sales 25 793,364 1,230,314 1,550,195 1,950,556 2,457,700 2,966,190 3,581,674 4,322,147 5,213,555 6,291,462

    Advances to Employees Payroll+Benefits 30 87,450 96,195 105,815 116,396 128,036 140,839 154,923 170,415 187,457 206,203Stores & Spares Stock - - - - - - - - - - -

    TOTAL CURRENT ASSETS 880,814 1,326,509 1,656,010 2,066,952 2,585,736 3,107,029 3,736,597 4,492,562 5,401,012 6,497,665

    Current Liabil itiesAccrued Utilities & Power

    Expenses Utilities Expenses 20 10,000 11,000 12,100 13,310 14,641 16,105 17,716 19,487 21,436 23,579

    Accounts Payable Cost of Gas & Electricity 20 296,952 482,429 636,806 839,426 1,108,042 1,400,973 1,772,231 2,240,459 2,831,228 3,579,282

    Sales Tax Payable Sales Tax 14 66,681 103,406 130,291 163,941 206,566 249,303 301,034 363,269 438,190 528,787

    TOTAL CURRENT LIABILITIES 373,633 596,834 779,197 1,016,677 1,329,249 1,666,381 2,090,980 2,623,215 3,290,855 4,131,648

    NET WORKING CAPITAL 507,181 729,674 876,813 1,050,275 1,256,487 1,440,648 1,645,617 1,869,346 2,110,157 2,366,017

  • 8/3/2019 SMEDA CNG Filling Station

    28/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    25

    99..88 RRaattiioo AAnnaallyyssiiss

    Ratio Analysis

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

    Profitability Ratios

    Gross Profit 51.71% 49.55% 47.29% 44.91% 42.41% 39.78% 37.03% 34.14% 31.10% 27.92%

    Operating Profit 23.85% 31.48% 32.72% 33.05% 32.25% 31.29% 29.69% 27.75% 25.51% 22.99%

    Net Profit before tax 14.32% 21.03% 26.38% 29.56% 30.71% 31.03% 29.69% 27.75% 25.51% 22.99%

    Profit after Tax 13.82% 18.28% 16.85% 18.96% 19.85% 20.06% 19.19% 17.94% 16.50% 14.87%

    Return on Investment (ROI 5.01% 10.16% 11.50% 15.15% 17.84% 18.34% 17.35% 16.24% 15.14% 14.02%

    Return on Equity (ROE) 9.21% 15.89% 15.58% 18.07% 19.25% 19.01% 18.01% 16.89% 15.78% 14.65%

    Earning per Share (EPS) 1.05Rs. 2.39Rs. 3.78Rs. 5.33Rs. 6.98Rs. 8.52Rs. 9.84Rs. 11.10Rs. 12.30Rs. 13.38Rs.

    Dividend per Share -Rs. -Rs. -Rs. -Rs. -Rs. -Rs. -Rs. -Rs. -Rs. -Rs.

    Liquidity Ratios

    Current Ratio 6.52 6.43 7.24 8.83 9.50 12.43 15.16 16.77 17.50 17.52

    Debt Ratios

    Debt Ratio (of total assets) 44.44% 34.18% 23.80% 13.28% 3.95% 0.00% 0.00% 0.00% 0.00% 0.00%

    Debt Equity 81.7% 53.5% 32.2% 15.8% 4.3% 0.0% 0.0% 0.0% 0.0% 0.0%

    Interest Coverage Ratio 2.50 3.01 5.16 9.47 20.95 122.67 0.00 0.00 0.00 0.00

  • 8/3/2019 SMEDA CNG Filling Station

    29/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    26

    10 REQUIREMENT FOR THE LICENSE

  • 8/3/2019 SMEDA CNG Filling Station

    30/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    27

  • 8/3/2019 SMEDA CNG Filling Station

    31/32

    Pre-Feasibility Study CNG Filling Station

    PREF-34/May, 2005/Rev 2

    28

    Annexure 10 Requirement for the License

  • 8/3/2019 SMEDA CNG Filling Station

    32/32

    Pre-Feasibility Study CNG Filling Station

    29