49
8/12/2019 Slide4 -Sesbs Perspectives _sesb (1) http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 1/49

Slide4 -Sesbs Perspectives _sesb (1)

Embed Size (px)

Citation preview

Page 1: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 1/49

Page 2: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 2/49

• SUPPLY AND DEMAND GROWTH

• CAPITAL INVESTMENT & OPERATING

SUBSIDY

• WAY FORWARD

 – FUTURE DEVELOPMENT

 – RENEWABLE ENERGY DEVELOPMENT

 – DEMAND SIDE MANAGEMENT

 – ENERGY EFFICIENCY

• CONCLUSION

Presentation Contents

2

Page 3: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 3/49

SUPPLY & DEMAND GROWTH

3

Page 4: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 4/49

4

SANDAKANKOTA KINABALU

LAHAD DATU

TAWAU

SEMPORNA

KUDAT

KOTA BELUD

BEAUFORT

WP LABUAN

KENINGAU

PANGI

PAPAR

TENOMLABUAN

28MW

TAWAU

41 MW

TG.ARU

95MW

• LLS BECOME A FEDERAL AGENCY UNDER THE

MINISTRY OF ENERGY, TELECOMMUNICATION AND POST

• ISOLATED SMALL SYSTEM• MOSTLY DIESEL GEN SET WITH ONE HYDRO

• GRID SYSTEM COVERING WEST COAST ONLY

• <50% ELECTRICITY COVERAGE

MD 69.3MW

MD 12.3MW

MD 16MW

MD 23.6MW

LAHAD DATU

7 MW

SEMPORNA

2 MW

MD 1.5MW

MD 3.5MW

KUDAT

6MW

MD 2.5MW

MD 1.5MW

KENINGAU4 MW

MD 2.8MW

SANDAKAN

42 MW

•ESTIMATED OVERALL MAXIMUM DEMAND : 134MW

•NO. OF CUSTOMERS : 109,716

KOTA BELUD

2MW

ELECTRICITY SUPPLY SYSTEM SABAH 1984

SESB INSTALLED CAPACITY

MAXIMUM DEMAND

LEGEND

TENOM PANGI HIDRO

66 MW

4

Page 5: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 5/49

5

SANDAKAN

KOTA KINABALU

LAHAD DATU

SEMPORNA

BEAUFORT

WP LABUAN

KENINGAU

PANGI

PAPAR

TENOM

TENOM PANGI HYDRO

66 MW

PATAU-PATAU

(112 MW)

MELAWA

44 MW

ARL

50 MW

GANTISAN

38 MW

TAWAU

50 MW

SERUDONG

37.5 MW

TAWAU

TG.ARU

27 MW

POWERTRON

136 MW

MELANGKAP

1 MW

BOMBALAI

1 MWMEROTAI

1.3 MW

SAYAP

1 MW

KUDAT

K.BELUD

LAHAD DATU

20.35MW

KOTA BELUD

8.9MW

MD 244.9MW

MD 5.26MW

MD 5.1MW

MD 45.5MW

MD 39.7MW

• LLS WAS PRIVATIZED ON 1ST SEPTEMBER 1998

 AND CALLED SABAH ELECTRICITY SDN. BHD.

•THE WEST COAST GRID SYSTEM GREW• GENERATION MIX CONSIST OF HYDRO 17%, GAS

31% & OIL 52%

• INTRODUCTION OF IPP WITH 1ST PLANT

COMMISSIONED ON 31ST OCTOBER 1995

MD 13.73MW

MD 3 MW

•ESTIMATED OVERALL MAXIMUM DEMAND : 373MW

•NO. OF CUSTOMERS : 262,696

KUDAT

13.9MW

SEMPORNA

4 MW

KIAU

0.4MW

SESB INSTALLED CAPACITY

MAXIMUM DEMAND

IPP INSTALLED CAPACITY

SANDAKAN

41 MW

ELECTRICITY SUPPLY SYSTEM SABAH 1998

LIBARAN

64.4 MW

CARABAU

2 MW

LEGEND

5

Page 6: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 6/49

6

TENOM PANGI

66 MW

PATAU-PATAU

112 MW

TELUK SALUT

212 MW

ARLT50 MW

SBPC

112 MW GANTISAN, SANDAKAN

38 MW

BATU SAPI, SANDAKAN

45 MW

LABUK, SANDAKAN

9.4 MW

TAWAU

64 MW

LAHAD DATU

21.5 MW

SEMPORNA

6 MW

TSH BIOENERGY

14 MW

SUTERA

38 MW

RUGADING

205 MW SIM-SIM RENTAL SETS

20 MW

TAWAU PASIR PUTIH

RENTAL SETS

21.2 MW

KK RENTAL

SETS 21.7MW

SEGUNTUR BIOENERGY

& KINA BIOPOWER 23

MW

LAHAD DATU POIC

RENTAL SETS

20 MW

LIBARAN

64.4 MW

• WEST & EAST COASTS INTER-CONNECTED

IN 2007

• GENERATION MIX CONSIST OF HYDRO 9%,GAS 67%, BIOMASS 3% & OIL 21%

• ELECTRIFICATION COVERAGE OF 81.5%

SANDAKAN

KOTA KINABALU

L. DATU

TAWAU

SEMPORNA

KUDAT

KOTA BELUD

BEAUFORT

WP LABUAN KENINGAU

PANGI

KOTA MARUDU

KUNAK

PAPAR

TENOM

K. KINABATANGAN

SEGALIUD

DAM RD

KALUMPANG

•SYSTEM MAXIMUM DEMAND ACHIEVED : 830MW

•NO. OF CUSTOMERS : 464,053

•SAIDI CY: SECTOR 1 (307.66) ; SECTOR 2 (632.28); SECTOR 3 (990.80)

•SABAH SAIDI YTD :494.57

SESB INSTALLED CAPACITYIPP INSTALLED CAPACITY

ELECTRICITY SUPPLY SYSTEM SABAH ( As of Dec 2011)

MELA WA44 MW

ESAJADI SG.KADAMAIAN

2.1 MW

ESAJADI SG.PANGAPUYAN

4.8 MW

LEGEND

SERUDONG

37.5 MW

SPC

34 MW

6

Page 7: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 7/497

Wood-Based IndustryCluster 

Business LinkCentres

Industrial Corridor 

Sabah Oil and GasTerminal

Sipitang Energy IntensiveCluster 

POIC Sandakan

POIC Lahad Datu

Minerals Based Industry

MANUFACTURING: Sabah will leverage its natural resources as feedstock

to capture value in downstream activities

Incentives

Page 8: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 8/49

500

1000

1500

2000

2500

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Load Forecast (MW)

Load Forecast (MW)

~ 900 MW

~ 2500 MW!

Load Forecast 2012-2030

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030Load

Forecast

(MW)

918 1,001 1,074 1,152 1,223 1,312 1,387 1,476 1,546 1,634 1,714 1,808 1,887 1,978 2,059 2,162 2,257 2,369 2,474

8

Page 9: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 9/49

CAPITAL INVESTMENT

&

OPERATING SUBSIDY

9

Page 10: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 10/49

LAHAD DATU

PANGI

TENOM

KOTA KINABALU

KENINGAU

BEAUFORT

WP LABUAN

KOTA BELUD

PAPAR 

SANDAKAN

TAWAU

SEMPORNA

KUDAT• Over the last 15 years a total of RM 5.3 Billion had been invested by the Government and Private

Investor in the development of Generation, Transmission, Distribution Projects And IPP/SREP projects.

•IN 2010 a special budget allocation of RM 419.5 Mill

for the ‘SAIDI 700’ was approved by the Government.

Subsequently RM200Mill in 2011 under ‘SAIDI 477’ and

RM88Mill in 2012 for  ‘SAIDI 367’.

867

703

328

Capital Investment (CAPEX)

725

27

290

48

150

729

357

1103

Capex Funding

10

4,030.00

1,986.58 1,855.80

2,867.23

687.38 494.64

-

1,000.00

2,000.00

3,000.00

4,000.00

5,000.00

2006 2007 2008 2009 2010 2011

SESB SAIDI CY2006 - 2011

SAIDI

Page 11: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 11/49

11

SANDAKAN

KOTA KINABALU

LAHAD DATU

TAWAU

SEMPORNA

KUDAT

KOTA BELUD

BEAUFORT

WP LABUAN

KENINGAU

PANGI

PAPAR 

TENOM

Cost of Production (OPEX)

11

29.08

New tariffeff. 15

July 2011

Page 12: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 12/49

12

SANDAKAN

KOTA KINABALU

LAHAD DATU

TAWAU

SEMPORNA

KUDAT

KOTA BELUD

BEAUFORT

WP LABUAN

KENINGAU

PANGI

PAPAR 

TENOM

Operating Subsidy

• Since Privatization, SESB had been operating at a lost due to the high IPP and

Fuel Payment

• To ease SESB financial burden, the Government had subsidized the fuel oil

consumed, whereby SESB will be reimbursed for fuel payment on Medium Fuel

Oil (MFO) and Diesel Fuel Oil (DFO) above the prices of RM 0.42/liter and RM0.495/liter respectively used by both IPP and SESB.

• Under the fuel pass through mechanism for IPP running on MFO, the IPP are

required to pay for the used of MFO at market priced, SESB will pay the IPP

based on the weighted average cost of fuel (RM/GJ) delivered to the IPP, SESB

will then be reimbursed to cost of fuel base on the fuel support subsidymechanism.

12

Page 13: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 13/49

11.707 11.707

4.922

4.210 -

-

20.365

20.365

14.221

26.720

10.685

10.685

10.685

1.859

1.859

1.859

-

10.000

20.000

30.000

40.000

50.000

60.000

70.000

80.000

Oil & Gas at Market Price Oil only at Market Price After Fuel subsidy

   s   e   n    /    k   W

    h

SESB COST OF SUPPLY BY COST COMPONENT FY2010

Fuel Cost (SESB) Petronas Foregone Gas Revenue (SESB) Payment IPP

Petronas Foregone Gas Revenue (IPP) O&M (non fuel) Finance Cost

31.69 sen/kWh

44.62 sen/kWh

75.54 sen/kWh

Fuel Oil (diesel & MFO) subsidy

12.93 sen/kWh

Petronas Foregone Gas Revenue

30.92 sen/kWh

Page 14: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 14/49

Total Operating Income

Fuel Support Subsidy

Payment to IPP

Fuel Cost (SESB)

O & MTariff Support Subsidy

662 706 724 828 867 977 1116

466

529 585 635 747 774 815

186

277338

390

406 341

469

304

273

296

326

366 446

431

246

499

436

535

426

521

48

   R   M    M

   I   L   L   I   O   N

Actual Financial Status 2004 - 2011

14

•TOTAL FUEL SUBSIDY BY GOVERNMENT

SINCE 2005 IS AT RM 3,211 MILL

1108 880

418

499

548

Page 15: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 15/49

FINANCIAL PROJECTIONS WITH TARIFF INCREASE

Page 16: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 16/49

FINANCIAL PROJECTIONS WITH TARIFF INCREASE

NEVERTHELESS GOV SUBSIDY STILL REQUIRED (FUEL SUBSIDY AND TSS)

LNG subsidized at RM6.40 per mmBTU

FINANCIAL YEAR 2012 2013 2014 2015 2016 2017 2018 2019 2020

REVENUE

Sale of Electricity 1,383  1,492  1,796  1,923  2,053  2,405  2,554  2,706  3,146 

Transfer from consumer contribution 46  43  41  39  38  34  30  26  23 

Goods and Services 33  33  30  27  29  29  29  30  29 

Total Revenue 1,462  1,569  1,866  1,990  2,120  2,469  2,613  2,762  3,197 

OPERATING COST

  Fuel Cost (SESB) 743 1,033 863 45 9 14 11 16 22

  Payment to IPP 860  885  997  1,308  1,441  1,431  1,648  1,668  1,643 

O & M 458  504  547  594  673  669  734  803  836 Total Operating Costs 2,061  2,422  2,406  1,947  2,123  2,115  2,393  2,486  2,501 

Operating Profit/(Loss) (598)  (853)  (540)  43  (2)  354  220  276  696 

Fuel subsidy (diesel & MFO) 641  870  729  33  -  -  -  -  - 

Tariff Support Subsidy 111  160  15  148  262  -  111  94  - 

Transfer from Govt development grant 43  40  38  35  33  32  30  29  27 

Other Operating Income 16  17  17  17  17  17  17  18  18 

Interest on Loan (70)  (91)  (118)  (126)  (160)  (184)  (224)  (258)  (285) 

Net Profit/(Loss) before tax 143  143  141  150  151  219  154  158  456 

RORB 5% 5% 5% 5% 5% 5% 5% 5% 5%

SUMMARY INCOME STATEMENT

RM Million

Assumption:

1 20% Capex funded by Government Soft loan

2 Gas at subsidized price (RM/mmBTU) 6.40

3 LNG Price (2015 to 2020) (RM/mmBTU) 6.40

4 Tariff Increase in 2014 12%, 2017 10% and 2020 10%

Page 17: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 17/49

GOVERNMENT SUBSIDIES & FOREGONE

REVENUE FOR GAS  – LNG at market price

Assumption:

1 20% Capex funded by Government Soft loan

2 Gas at subsidized price (RM/mmBTU) 6.40

3 LNG Price (2015 to 2020) (RM/mmBTU) 47.47

4 Tariff Increase in 2014 12%, 2017 10% and 2020 10%

5 LNG plant using KPSB tariff

Page 18: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 18/49

GOVERNMENT SUBSIDIES & FOREGONE

REVENUE FOR GAS  – LNG at RM6.40/mmBTU

641

870729

33 - - - - -

111

160

15

860 972

658

820 808

403

1,202

1,309

1,524

1,968

2,106

2,2492,118

2,253

2,385

 -

 500

 1,000

 1,500

 2,000

 2,500

2012 2013 2014 2015 2016 2017 2018 2019 2020

   R   M    M

   i   l   l   i   o   n

Fuel subsidy (diesel & MFO) Tariff Support Subsidy Petronas Foregone Revenue For Gas & LNGAssumption:

1 20% Capex funded by Government Soft loan

2 Gas at subsidized price (RM/mmBTU) 6.40

3 LNG Price (2015 to 2020) (RM/mmBTU) 6.404 Tariff Increase in 2014 12%, 2017 10% and 2020 10%

5 LNG plant using KPSB tariff

Page 19: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 19/49

Issues and Challenges in Meeting the Electricity Demand

1919

Page 20: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 20/49

• 2nd tiered (CRF) IPP with financial problem & deteriorating performance

• Too much dependency on natural gas (pipeline supplied) – DSM & Load Sheeding if gas curtailment happened

 – gas estimated to dominate 74% of Sabah Generation Mix in FY2015

• Prohibition in implementing 5 fuel-policy & Limited Future Generation

Resources

 – Rejection of Coal Fired Power Plant in Sabah – Limited gas allocation to Energy Sector

 – Limited hydro resources

• Escalation of fossil fuel generation cost

 – Retraction of fuel subsidy

 – high IPP tariff 

 – high alternative fuel cost i.e LNG

• Funding challenge for hydro projects

 – higher CAPEX however minimal operation cost

 – Stringent International financing requirement

• Reliability issue of RE plants (mini hydro, biomass)20

OTHER OPERATIONAL ISSUES & CHALLENGES

Page 21: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 21/49

WAY FORWARD

21

Page 22: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 22/49

Page 23: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 23/49

650

1150

1650

2150

2650

3150

3650

4150

4650

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

MWSESB Generation Plant-Up to Meet Demand & enhance Gen mix

 T  N B  T  e l   u k  E  w

 a 6  4  M W +  K  a l   a n  s  a 5  M W

 K  i   m a n  i   s  3  0  0  M W

 +  S  P  R 1   0  0  M W+  T  e n  o m P  a n  g i  

 U p g r  a d  e 8  M W  (   D  e c  o m m .

 S  E  S  B  O i   l   4  5  M W +  M o b  i   l   e S  e t  6  M W +  S  u t  e r  a H . D  G  2  0  M W +  B  u y

 b  a c  k  o p t  i   o n  G  e n 

 s  e t  8  0  M W +  G  T  S  2  0  M W  R  e h  a b  i   l   i   t  a t  i   o n  )  

Legend:Dependable Capacity (MW)

Load Demand (MW)

 N e w

 E  C  G  a s  3 

 0  0  M W  (   D  e c  o m m . S  E  S  B  O i   l   P  l   a n  t 1   2  5  M W )  

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030Load Forecast

(MW)  918 1,001 1,074 1,1521,223 1,312 1,387 1,476 1,5461,634 1,714 1,808 1,887 1,978 2,059 2,162 2,257 2,369 2,474

Dependable

Capacity (MW)  1,207 1,266 1,504 1,5041,680 1,633 1,747 1,747 1,8411,980 2,085 2,150 2,250 2,440 2,440 2,690 2,690 2,790 2,880

R. Margin (%)   31% 26% 40% 31% 37% 24% 26% 18% 19% 21% 22% 19% 19% 23% 19% 24% 19% 18% 16%LOLE

(days/year)  0.745 1.504 0.099 0.4270.055 0.489 0.204 0.891 1.4090.770 0.748 1.248 1.121 0.168 0.726 0.037 0.237 0.336 0.456

 C  a s  h  H o r  s  e1   0  M W +  A F  I  E  8  . 2  M W +  E  c  o

- B  i   o m a s  s 

 2  0  M W +  G  T  S  2  0  M W  R  e h  a b  i   l   i   t  a t  i   o n 

 (   D  e c  o m m . A R  L  4  8  M W )  

 U p p e r  P  a d  a s 1   5  0  M W  (   D  e c  o m m . S  e r  u d  u n  g

 3  6  M W )  

 L  a w a s  H E  P 1   0  0  M W+  T  r  u s  a n 1   3  8  M W +  T  r 

 u s  a n  5 

 6  5  M W  (   D  e c  o m

 m . T  e l   u k  E  w a 6  4  M W )  

 L  i   m b  a n  g I  I  H

 E  P  2  0  0  M W 

 (   D  e c  o m m . T  S  H S  R  E  P 1   0  M W )  

 N e w

 L  N G 1   0  0  M W

 +  N e w C  C  G  T  3  0  0  M W 

 (   D  e c  o m m T  S  C  C 1   9 

 0  M W+  S  B  P  C 1   0  0  M W + 

 S  R  E  P  2  0  M W )  

 T  e r  u s  a n  H E  P  2  5  0  M W

 N e w O C  G  T  6  5  M W

 N e w

 L  N G  C  C 1  

 0  0  M W

 N e w O C  G  T  6  5  M W +  T  r  u s  a n  2  4  0  M W 

 L  i   m b  a n  g I  4  5  M

 W +  T  r  u s  a n  3 1  1   5  M W +  T  e n  o m P  a n  g i   N e w

 2  6  M W  (   D  e c  o m

 m . L  i   b  a r  a n  6  0  M W +  S  P  C  3  4 

 M W )  

 N e w

 L  N G  C  C 1  

 0  0  M W

Start August 2011

Page 24: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 24/49

24

Page 25: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 25/49

Kudat

Mengaris

Sandakan

Lahad Datu

Tawau

Semporna

Kota Belud

Kota Kinabalu

Sipitang

Keningau

Penampang

Segaliud

Dam Road

Kalumpang

Tenom Pangi

Beaufort

Labuan

Kolopis

Papar 35.5km

113km

5.3km

90km

33km50km

255km

46.5km

55km

76km

31.5km

51km

35.5km

40km

68.5km

Ranau

40km

70km

Upper Padas

TambunanKimanis

45km

G

110km

G

Upper Padas 150MWCOD : 2018

Project Cost : RM1.6 Billion

SPR 100 MWCOD : 2014

Project Cost : RM534 Million132kV Transmission Line Cost : RM110 Million

Lok Kawi

25

Kunak

Generation & Transmission Planning Up To 2019

300km

TenomTenom II

Nabawan

Sapi Nangoh

TNB Teluk Ewa 64MWCOD : 2012

Project Cost : RM80 Million

G

G

G

G

Kimanis 300MWCOD : 2014

Project Cost : RM1.5 Billion275kV Transmission Line Cost :

RM146 Million

New CCGT (LNG) 300MW

COD : Year 2016

Project Cost : RM1.172 Billion

275kV Transmission Cost : RM224Million (Including upgrade of

Kalumpang to Segaliud Line to275kV)

132 kV (current)

275 kV (current)

132 kV (future)

275 kV (future)

LEGEND :

Proposed ProjectSouthern Link 275kV Transmission Project

COD : 2017Project Cost : RM800 Million

Generation & Transmission Planning Up to 2019

 Year Load Forecast

(MW)

Cumulative

Capacity (MW)

Reserve

Margin (%)

2012 918 1207 31

2013 1001 1266 26

2014 1074 1504 40

2015 1152 1504 31

2016 1223 1680 37

2017 1312 1633 24

2018 1387 1747 26

2019 1476 1747 18

Page 26: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 26/49

Generation, Transmission & Distribution Projects

0

200

400

600

800

1000

1200

1400

1600

1800

2000

2200

2400

2012 2013 2014 2015 2016 2017 2018 2019 2020

   R   M    M

   I   L

YEAR

IPP/Private Invester Generation Transmission Distribution

224

980

100

256

2701600

200 61

119

25

2034

1172

750

14048

1132

26*Uo to 2013

>9Bill investment

from 2012 to 2020

Page 27: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 27/49

Total Operating Income

Government Support Subsidy

FSS & TSS

Payment to IPP

Fuel Cost (SESB)

O & M

1522 1644 1765 1886 2008 2133 2261

1012 1185

1294 1738 1764 1725

481156

136

7679 81

101550

586598

710774

930

652 458

496

837

916 954

1008

   R   M   M   I   L

   L   I   O   N

Projected Financial Status 2012 - 2020

27

•FUTURE SUBSIDY NEEDED FROM

GOVERNMENT FOR NEXT 9 YEARSRM 6,853 MILL

1749

104

1012

1005

23921395

985

326

492527

1658

651

Page 28: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 28/49

RENEWABLE ENERGY DEVELOPMENT

28

Page 29: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 29/49

Page 30: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 30/49

30

SANDAKANK..KINABALU

LAHAD DATU

TAWAU

SEMPORNA

KUDAT

KOTA BELUD

BEAUFORT

WP LABUAN

KENINGAU

PANGI

KOTA MARUDU

KUNAK 

PAPAR 

TENOM

SEGALIUD

DAM R D

SIPITANG

SREP Kina Biopower, Sandakan (10MW)

COD = January 2009

SREP Seguntor Bioenergy Sandakan (10MW)

COD =March 2009

SREP Kalansa, Beluran (5.0MW)

Status : Under Construction

KALUMPANG

RANAU

RENEWABLE ENERGY PROJECT IN SABAH

SREP by KK Powergreen Sdn Bhd

Sg Kadamaian, Kota Belud (4.5MW)

Status : REPPA Negotiation Ongoing

SREP Eco-Biomass (20MW)

POIC Lahad DatuStatus : Under Construction

SREP by Afie Power Sdn Bhd

Sg Mulau & Sg. Mantaranau, Kiulu (8.9 MW)

Status : Under Construction

SREP Warisan Harta, Sg. Mantaranau, Ranau

(5.0MW)

Status : REPPA approved for signing

SREP TSH Bioenergy, Kunak (10MW)

COD = Feb 2005

SREP Cash Horse Sdn. Bhd (10MW))

KM38-40 Sandakan-Kota Kinabatangan Road

Status : Under Construction

Completed Projects

Under Construction

Approved Projects

36.5MW

73.9MW

9.5MW

Total Exportable

Capacity119 .9MW

SREP by Esajadi Power Sdn BhdSg Kadamaian, Kota Belud (2.0MW )

COD : 02 August 2009

SREP by Esajadi Power Sdn Bhd

Sg Pangapuyan, Kota Marudu (4.5MW)

COD : January 2011

LEGEND :

OPERATIONAL SREP PROJECTS

Biomass Plant

Mini Hydro Plant

30.0 MW

6.5 MW

Exportable Capacity

SREP Tawau Green Energy(30.0MW)

Status : Under Construction

Page 31: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 31/49

 – A mechanism that allows electricity that is produced from

indigenous RE resources to be sold to power utilities at a fixedpremium price and for specific duration governed by

Renewable Energy Act 2011 commencing 1 December 2011.

 – The implementation agency is the Sustainable EnergyDevelopment Authority (SEDA)

 – The type of RE will cover as such and limited to a maximum of 

30MW per site:-

• Biogas,

• Biomass,

• Mini Hydro and

• Solar PV

•  Geothermal? 31

FEED-IN TARIFF (FIT) MECHANISM

Page 32: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 32/49

• Financial Aspect – Sufficiency of RE fund for payment

 – Commitment of payment for whole concession from SEDA (ie ~RM300 Mill)

 – Other sources of fund (ie state gov contribution)

 – Quantum of contribution from customer in Sabah (only RM10Mill per annum)

 – Cash flow issue of SESB (ie timely reimbursement from SEDA)

• Administration & Management

 – Priority of FiT quota to the existing/REPPA signed RE

 – New REPPA / Migration of existing REPPA

 – Land Acquisition i.e. ROW

 – Public Awareness

• Technical Aspect – Power System Study

 – Protection Coordination Study

 – RE critical contribution in Sabah Generation Capacity

 – Metering & Billing

 – Reliability of RE plant32

FEED-IN TARIFF (FIT) – ISSUES & CHALLENGES

Page 33: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 33/49

33

N

o Type of RE

No. Of

Proposal

Proposed

Capacity (MW) Potential COD

1   Biomass 13 211.5++ 2014

2   Biogas 1 2 2013

3   Solar 12 90.05 2013

4  Municipal

Waste  1 TBA TBA

5   Hydro 3 30++ 2015

GRAND TOTAL 20 333.55++

RE DEVELOPMENT POTENTIAL UNDER FiT IN SABAH

RE P li & A i Pl T

Page 34: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 34/49

-

5,000

10,000

15,000

20,000

25,000

        2        0        1        1

        2        0        1        2

        2        0        1        3

        2        0        1        4

        2        0        1       5

        2        0        1        6

        2        0        1       7

        2        0        1        8

        2        0        1        9

        2        0        2        0

        2        0        2        1

        2        0        2        2

        2        0        2        3

        2        0        2        4

        2        0        2       5

        2        0        2        6

        2        0        2       7

        2        0        2        8

        2        0        2        9

        2        0        3        0

        2        0        3        1

        2        0        3        2

        2        0        3        3

        2        0        3        4

        2        0        3       5

        2        0        3        6

        2        0        3       7

        2        0        3        8

        2        0        3        9

        2        0        4        0

        2        0        4        1

        2        0        4        2

        2        0        4        3

        2        0        4        4

        2        0        4       5

        2        0        4        6

        2        0        4       7

        2        0        4        8

        2        0        4        9

        2        0       5        0

   M   W

Year

National Cumulative RE Installed Capacity (& Ratio to Peak Demand)

RE (RE Policy & Action Plan)

RE (Business as Usual)

2020:

2,080 MW (11%)

2030:

4,000 MW (17%)

2050:

21.4 GW (73%)

2015:985 MW (6%)

34

2030

3.5 GW

BAU 2050: < 2,000 MW

2050

11.5 GW

1090%

increase of BAU

RE Policy & Action Plan: Targets

Source: Ministry of Energy, Green Technology and Water, Energy Commission

Sabah will play a vital

role in achieving

National RE Target

500

400

300

200

100

41.5MW

4.5%

171.75MW

17.2%

392.75MW

36.6%

452.75MW

39.3%

2012 2013 2014 2015

Sabah Projected Cumulative

RE Capacity (& Ratio to Peak Demand)

Page 35: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 35/49

DEMAND SIDE MANAGEMENT

35

Page 36: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 36/49

500

1000

1500

2000

2500

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030

Load Forecast (MW)

10% reduce (MW)

15% reduce (MW)

Load Demand Forecast (MW)

Demand Side Management By 10%

Demand Side Management t by 15%

Planning Way Forward -Lowering Load Forecast with Scenario DSM/EE

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030Load

Forecast

(MW)

918 1,001 1,074 1,152 1,223 1,312 1,387 1,476 1,546 1,634 1,714 1,808 1,887 1,978 2,059 2,162 2,257 2,369 2,474

Reduce Load

Forecast

10% reduce

(MW)

851 928 993 1063 1125 1205 1269 1346 1403 1477 1541 1618 1678 1748 1806 1883 1950 2032 2103

Reduce Load

Forecast

15% reduce(MW)

848 921 982 1046 1101 1172 1226 1290 1333 1389 1432 1483 1514 1549 1565 1594 1604 1618 1610

36

Page 37: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 37/49

Page 38: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 38/49

Planning Way Forward -Lowering Load Forecast with Scenario DSM/EE

• Another Method For Energy Conservation Is To Do Of Peak Consumption (Peak

Shifting)

•This Will Balance The Daily Base And Peak Load

Promote Demand Side Management with Load Shifting (Peak / Off Peak)

350

450

550

650

750

01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

   D   e   m   a   n    d    (   M   W    )

Time (Hr)

System Profile

FILL THE DIP

BY SHIFTING

THE LOAD

REDUCE PEAK DEMAND

Typical DailyLoad Profile

38

Page 39: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 39/49

ENERGY EFFICIENCY PROGRAMMES INSABAH

39

Page 40: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 40/49

Page 41: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 41/49

CONCLUSION

41

Page 42: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 42/49

Conclusion

• For sustainable development and

operation, electricity tariff rationalisation + gov fuel

subsidy must continue

• Renewable energy development leveraging

Sabah abundant resources (FIT and hydro

potentials)

• Demand side management via energy efficiency

42

Page 43: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 43/49

THANK YOU

43

PRACTICE ENERGY EFFICIENCY,

AN ACT OF RESPONSIBLE CONSUMERISM

Page 44: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 44/49

ISSUES AND CHALLENGES

Page 45: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 45/49

Coal Prices in US Dollars/tonne

0.00

20.00

40.00

60.00

80.00

100.00

120.00

140.00

160.00

1987 1990 1993 1996 1999 2002 2005 2008

      U      S      D      /      t    o    n    n    e

Northwest Europe marker price

Japan steam coal import cif priceUS Central Appalachian coal spot price index

globalCoal RB Index (South Africa)

globalCoal NEWC Index (Australia)

JPU

Platts Markers K1 (5900 GAR) (Indon)

Platts Markers K2 (5000 GAR) (Indon)

Natural Gas Prices in US Dollars/mmbtu

0.00

2.00

4.00

6.00

8.00

10.00

12.00

1985 1987 1989 1991 1993 1995 1997 1999 2001 2003 2005 2007

     U     S     D     /    m    m     b     t    u

USA Henry Hub

LNG Japan

European Union cif 

Canada

Key Crude Oil Spot Prices in US Dollars/barrel

0.00

20.00

40.00

60.00

80.00

100.00

120.00

1976 1980 1984 1988 1992 1996 2000 2004 2008

     U     S     D     /     b    a    r    r    e     l

Brent

West Texas Intermediate (WTI)Dubai

Source: BP Statistical Review of World Energy 2007, International Energy Agency, Platts Report & TNB Fuel 

“Oil prices hit record peaks above 126

dollars”  AFP, May 2008

ISSUES AND CHALLENGESFuel price volatility

Trend & Outlook

Page 46: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 46/49

46

• EIA fuel cost projections

indicated that coal andnuclear is going to be

stable and low in the long

run

• Coal in the US is stable

mainly due to domestic

production and high

reserve

• Nuclear fuel is still

expected to be low and

stable despite import of

uranium

• Situation is expected to be

the same for Malaysia

except for coal priceSource: EIA)Source: EIA  – US Energy Price

Trend & Outlook

Fuel Price Historical & Projections in the US

DEPENDANCY ON NATURAL GAS (PIPELINE SUPPLIED)

Page 47: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 47/49

47

DEPENDANCY ON NATURAL GAS (PIPELINE SUPPLIED)

HYDRO SESB

8%HYDRO

IPP/PRIVATE

INVESTER

1%

GAS SESB

11%

GAS

IPP/PRIVATE

INVESTER

63%

OIL SESB

7%

OIL

IPP/PRIVATE

INVESTER

6%

BIOMASS

4%

Generation Mix FY2014/2015

NATIONAL ENERGY POLICIES AND DEVELOPMENT PLAN

Page 48: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 48/49

National Energy

Policy (1979)

•To ensure adequate,

secure and cost-

effective energy

supplies using both

non-renewable and

renewable energy

sources

•To promote efficient

utilisation of energy

•To minimise negative

impacts on the

environment in theenergy supply chain

National

Depletion

Policy(1980)

•To prolong

lifespan of

Malaysia’s oil

reserves for future

security andstability in fuel

supply

Four Fuel

Policy

(1981)

•To pursue balance

utilisation of oil,

gas, hydro and

coal

Five Fuel

Policy

(2001)

•RE as the fifth fuel

in energy supply

mix

National

Green

TechnologyPolicy (2009)

•Green Tech. as the

driver to accelerate the

national economy and

promote sustainable

development

8th Malaysia Plan (2001-2005)

RE as the fifth fuel

Target: 5% RE in energy mix

9th

Malaysia Plan (2006-2010)Target: 300 MW grid-connected RE in Pen. Malaysia

Target: 50 MW grid-connected RE in Sabah

10th Malaysia Plan (2011-2015)

New RE Policy and Action Plan

Target: 985 MW of RE by 2015 (~5.5% of energy mix)

NATIONAL ENERGY POLICIES AND DEVELOPMENT PLAN

Energy Policies

RELIABILITY ISSUE OF RE PLANTS

Page 49: Slide4 -Sesbs Perspectives _sesb (1)

8/12/2019 Slide4 -Sesbs Perspectives _sesb (1)

http://slidepdf.com/reader/full/slide4-sesbs-perspectives-sesb-1 49/49

RELIABILITY ISSUE OF RE PLANTS

Operational SREP Performance (FY2009 - FY2011)

Description SREP TSH SREP Kinabio SREP Seguntor SREP Kadamaian SREP Pangapuyan

Yearly

Contractual

Energy

64,000,000

Average AF

based on

Contractua

l Energy

82,344,000

Average AF

based on

Contractua

l Energy

82,344,000

Average AF

based on

Contractua

l Energy

14,366,400

Average AF

based on

Contractua

l Energy

30,353,400

Average AF

based on

Contractua

l Energy

FY2009 64,440,980 101% 19,155,430 23% 20,738,600 25% 0 0% 0 0%

FY2010 65,232,780 102% 45,134,970 55% 47,197,700 57% 8,532,616 59% 0 0%

FY2011 52,652,130 82% 57,015,680 69% 61,457,870 75% 12,349,657 86% 5,344,018 18%

Notes:-(i) Lower value of energy/AF for Seguntor and Kinabio in FY2009 & Pangapuyan in FY2011 due to plant only COD in the middle of the FY

(ii) TSH achieve more than contractual energy in FY2010 & 2009