PORTFOLIO COMMITTTEE:Briefing by Broadband Infraco on Progress made on issues emanating from the Annual Report 2011/2012
R 1.8 Billion Shareholder Funds
WACS connectivity
R504.2 M R36.7 M
Integrating SADC
R317.2 M
Broadband expansion
Operations Enabling Government through SITA
R89.9 M R444.5 M
Slide 3
.
Expanding Access
Slide 4
.
Expanding Access
Slide 5
Appointment of Key Personnel
.
Update on Key Performance Indicators 2011/2012
CompletedAll Executives positions filled
KPI STATUS COMMENT
Development of Product Portfolio
Debt Fund
Business Operations Strategy
Project put into commercial use
Carrier Ethernet Layer 2 developed
No debt funding sourced
Re-engineered and optimised Capital Project Management processes
This forms part of 2013/2014 programme
Completed
Work in Progress
Continuous monitoring
Work in Progress
Continuous monitoringProject Time Variance Instituted Capital Projects
governance structures
Slide 6
FIN
AN
CIA
L S
US
TA
INA
BIL
ITY
Funding is required to address the fundamental issues of the Broadband Infraco these include:
Expand the network to the broader market other than Neotel.Enhance the integrity of the network.Expand the network in rural area and other areas to address market inefficiencies.
MTEF application of R4.0b was made for increase access in all nine provinces over 5 years was made and for improving the integrity of the national backhaul.Over R530m is expected from DST on project of national interest including SKAA capital investment plan and funding plan have been developed
.
CU
ST
OM
ER
S
Critical to sustainability of the business
Network performance improvement
Increase capacity utilisation
Continuous engagement with customers:
Neotel MSA contract
Extension of Vodacom contract
MTC capacity expansion
MTN Trial
International Sales strategy developed
Priorities
Slide 7
MA
RK
ET
PO
SIT
ION
Expand footprint in district by connecting municipalities and extending to rural areas
Two Proof of Concepts (PoC) completed with MetroFibre Network and BXC for Carrier Ethernet services
WACS is connected to National Backhaul
Provision of International telecommunication services
.
CA
PIT
AL
EX
PE
DIT
UR
E
Optimised Network Master Plan addressing the integrity of the Network
Connecting with other operators
Addressing Network vulnerabilities
Capacity upgrade
Capital Build programme over 10 years
Programme for compliance with SHEQ regulations in place
Technology evolution and technology life cycle on existing old network equipment
Yzerfontein primary route to the WACS has been completed
.
Priorities
Slide 8
SU
PP
LY
CH
AIN
MA
GE
ME
NT
Supplier Development and Localisation : based on CSDP guideline issued by Executive Authority
Suppliers are evaluated on the following: BBBEE Black People Living with
Disabilities (BPLD) Black Youth Owned (BYO) Black Women Owned and Black
Owned Skills Development Electricians Engineers Project Management Local content Items such as fibre and related
accessories Target 100%
.
INT
ER
NA
L C
ON
TR
OL
EN
VIR
ON
ME
NT
This is a continuous process of ensuring adherence to policies, procedures and legislations.
Culture of compliance is being enhanced.
Where there are policy gaps, these are being addressed and new or revised policies are being developed.
Priorities
Slide 9
SH
AR
EH
OL
DE
RS
Performance management
As provider of capital, report on financial performance and overall sustainability of the company
Support on future plans and expansions
Regular sessions with both shareholders DPE and IDC at different levels.
Support from the Shareholder i.e. DPE on funding request and aligning the business to make government a key customer of Broadband Infraco
.
RE
GU
LA
TO
RS
Licence condition and compliance thereof
Continuous engagement on regulatory framework
Spectrum and access potentials
Submitted inputs to the amendments to the ECA
Submitted status on the roll out for obligations
Continuous engagement with the Regulator
Priorities
Improvements on the HR
Slide 10
HR
PO
LIC
IES
ST
AF
F T
UR
NO
VE
R R
AT
E 2
01
2
Change Management Programme
Other interventions
Fostering organisational culture change
Improve employee competencies
Improve overall organisation performance
Continuous Staff Engagement
Senior management forum has been established for constructive and robust discussions with staff.
Significant improvement on staff morale and confidence
Security around PoP
Slide 11
Concerns
Wire Mesh is an old security technology and prone to cutting and break-ins.
Status
A programme is being developed to address security of the PoP’s.