Projects at SiDet and their RequestsProjects at SiDet and their Requests

There are currently 6 silicon projects planned at SiDet: BTeV pixels, BTeV strips, CMS pixels, CMS strips, DØ-2b, CDF-2b

Each project presented their request at a liaison meeting. Presentations can be found at http://sidet.fnal.gov/liaison/

Based on those requests, a possible use of the Lab space for the various projects is presented in the following slides.

Office space for the projects is also addressed

Slide 3

Lab DLab D

Boundary conditions: Accommodate CMS, CDF and DØ 2b production Minimal perturbation with regard to CMM equipment Projects needs not far developed yet

Proposal CMS strip production takes place in current wirebonding area DØ 2b production takes place in North area

» Can retain all CMM’s in that area for the time being CDF production takes place on East wall

» Can retain all CMM’s in that area too for the time being Wirebonding relocated to semi-cleanroom

Disposition of CMM’s can be deferred to a later date when 2b plans of groups are firmed up

Slide 4

Lab D Proposed LayoutLab D Proposed Layout

CMS

CDF

Wirebonding

Slide 5

Lab D Wirebonding Proposed LayoutLab D Wirebonding Proposed Layout

Wirebonding room more centrally located

Pass-through boxes to burn-in room, corridor (new repair location), lab D production areas

Infrastructure modifications SiDet will refurbish ceiling SiDet will add

humidification control

SiDet will add card reader access

Retain one probestation in semi cleanroom

Slide 6

Lab D Semi CleanroomLab D Semi Cleanroom

If proposal accepted to move wirebonding into semi-cleanroom, will need to move equipment

CDF» Probestations» Logs, sensors

DØ Equipment» Two laser stands» One probestation

CDF will have to find a new location for all CDF equipment

One DØ laser stand can move to the double trailer

Move all probestations to Lab A

Slide 7

Bubble and Double TrailerBubble and Double Trailer

Concentrate all repair stations in bubble (no repair work in burn-in space anymore)

CMS pixel work will relocate to the double trailer

DØ Laser stand can move to double trailer

Repair S

tatio

ns

CMS Pixels

DØ Laser Stand

Slide 8

Burn-in SpaceBurn-in Space

Available space is ~1200 square feet (no more repair stations) Allocation:

CDF retains 500 square feet DØ retains 200 square feet with the understanding that they have priority

and first choice once the AB-Bridge is completed CMS is allocated 500 square feet with possibility to expand later if

necessary

CDF CMS

Slide 9

Cross ConnectCross Connect

Each project gets one “window” office and one cubicle in the re-arranged office area

Facility will provide one direct phone line and four ethernet lines per cubicle

3 more offices

Slide 10

Lab C CleanroomLab C Cleanroom

CDF has agreed to move out of Lab C North section completely DØ wishes to retain at least 10% test area

Use of Lab C areas is at the discretion of the facility until the 2b plans of both collider experiments are firmed up. DØ can retain 10% test area

Slide 11

Lab C SouthLab C South

DØ wishes to retain the 10% test area

If a 3m CMM is required for 2b assembly, a Zeiss machine will have to be removed.

Slide 12

Lab C NorthLab C North

CDF has agreed to move cooling stand to burn-in stand and vacate north clean room

CDF is considering another 1.5m B&S machine to replace one G&L dcc machine

Slide 13

Lab A Proposal Lab A Proposal

Move probestations into Lab A with other probestations for pixel work Cleanroom currently focused on BTeV and CMS pixel prototyping

probestations