11 : 21 : 2011
lighting revisions via CBU W L A K E S H O R E R E S I D E N C E H A L L
Sketch 1
Notes:
Reconfiguration of fixture type LF5 in the spaceQuantity is unchanged. Revised fixtures are represented in red color lines.No cost implications
11 : 21 : 2011
lighting revisions via CBU W L A K E S H O R E R E S I D E N C E H A L L
Sketch 2
Notes:
Delete all four (4) fixtures type LH3Add two (2) fixture types LF5No Cost implications with this change
11 : 21 : 2011
lighting revisions via CBU W L A K E S H O R E R E S I D E N C E H A L L
Sketch 4
Notes:
Reconfiguration of fixture type LH2. Blue color dots indicate location of fixtures in current documents. Red color represents proposed revised location of the fixtures.
No cost implications
11 : 21 : 2011
lighting revisions via CBU W L A K E S H O R E R E S I D E N C E H A L L
Sketch 7
Notes:
Orientation of fixture LC5E is represented in the sketch.
No cost implications
11 : 21 : 2011
lighting revisions via CBU W L A K E S H O R E R E S I D E N C E H A L L
Sketch 8
Notes:
Reconfiguration of LS4 fixtures (11 in total)Red dots represents the revised location on a grid that is evenly centred on window