    Date: 26/02/2013

    Observation of Status of Escalator and Lift Works:

    12 nos escalator not yet commence installation at sector 2 4 nos lift not yet commence work at sector 2

    Item Location Observation Note

    1.

    S2 L3 GL: 23/G2

    Glass Lifts S2-PL4 & S2-PL5

    Assembly of lifts yet to commence awaiting erection of steel structure.

    Civil WorksConstruction of Level 3bfloor which is above the lift locations is

    yet to complete i.e. installation of lifts isnot possible.

    Escalator S2-ESC6

    Escalator assembled and ready forinstallation. The possibility of the

    intermediate beam obstructing the erection

    of the escalator is yet to be confirmed.

    2.

    S2 L3 GL: 21-22/F

    Service Lift S2-SL-5

    Assembly of lifts yet to commence. Civil WorksConstruction of the lift core

    is yet to commence.

    3.

    S2 L3 GL: 19a/F-G1

    Escalator S2-ESC1

    Escalator length is about 800mm longerthan the length between the landings.

    JV yet to resolve the discrepancy.

  • 7/29/2019 Site Observation Report Sample

    2/6

    Item Location Observation Note

    4.

    S2 L3 GL: 22-23/F

    Escalator S2-ESC8

    Escalatorassembled and ready forinstallation.

    Civil Work- Insufficient width at upperlanding. No action yet to rectify the

    problem.

    5.

    S2 L3 GL: 23-24/F

    Escalator S2-ESC9

    Escalatorassembled and ready forinstallation.

    Civil WorkInsufficient width at lowerpit and insufficient width at upper landing.

    No action yet to rectify the problem.

    6.

    S2 L2 GL: 21-22/B

    Escalator S2-ESC3 & S2-ESC4

    Escalatorassembled and ready forinstallation.

    Civil WorkSize of pits are not adequate.No action yet to rectify the problem.

  • 7/29/2019 Site Observation Report Sample

    3/6

    Item Location Observation Note

    7.

    S2 L3 GL: 24-25/B-C

    Vehicle Lift S2-VL1

    No access from Level 3 to Lift MotorRoom.

    8.

    S2 L3 GL: 25/F

    Passenger Lift S2-PL6

    Assembly of lifts yet to commence. Civil WorksConstruction of the lift core

    is to be expedited.

    9.

    S2 L2 GL: 26-27/G2-H

    Escalators S2-ESC10, S2-ESC11, S2-

    ESC13 & S2-ESC14

    Escalatorassembled and ready forinstallation.

    Civil WorkMismatched of lengthsbetween landings and lengths of

    escalators.

  • 7/29/2019 Site Observation Report Sample

    4/6

    Item Location Observation Note

    10.

    S2 L2 GL: 25-26/G-G1

    Escalators S2-ESC12

    Escalatorassembled and ready forinstallation.

    Civil WorkCorridor wall obstructing theinstallation of the escalator. Pit yet to be

    constructed. No action yet to rectify theproblem.

    11.

    S2 L3 GL: 25-26/G1-G2

    Escalators S2-ESC7

    Escalatorassembled and ready forinstallation.

    Civil WorkIntermediate beamobstructing the erection of the escalator.

    No action yet to rectify the problem.

    12.

    Passenger Lift S2-PL7 & S2-PL7

    Water tightness problem interruptinstallation of lift equipments inside the

    lift cores.

  • 7/29/2019 Site Observation Report Sample

    5/6

    Item Location Observation Note

    13.

    S2 L2 G/L: 27a/G-F

    Escalators S2-ESC7

    Installation work commence today.

  • 7/29/2019 Site Observation Report Sample

    6/6

    Date: 26/02/2013

    Observation of Status of Escalator and Lift Works:

    4 nos escalator installation is in progress at sector 6 2 nos glass lift steel structure works are in progress at sector 6

    Item Location Observation Note

    1.

    S6 L2 G/L: 22a/J1a

    Escalators S6-ESC1 (cover with plastic

    sheet)

    Installation - work in progress Power Supplyoutstanding cabling work

    Glass Lift S6-PL1

    Steel Structure work in progress Installation of lift in progress

    2.

    S6 L2 G/L: 22a/J1a

    Escalators S6-ESC2 (cover with plastic

    sheet)

    Steel Structure work in progress Power Supplyoutstanding cabling work

    Glass Lift S6-PL2

    Steel Structure work in progress Installation of lift in progress

    3.

    S6 L2 G/L: 22b-23b/H4-H6

    Escalators S6-ESC3 & S6-ESC4

    Work in progress