SITE INVESTIGATION
PREPARED BY SARINA
1
8/10/2019 site invistigate
2/19
Site Investigation (SI) is the
exploration or discovery of the ground
conditions to enable engineers to
make informed design decisions.
2
8/10/2019 site invistigate
3/19
OBJECTIVE OF SI
The British Standard Code of Practice BS 5930:1991gives
a list of the objects of site investigation as follows:
1. To assess the general suitability of the siteand environs
for the proposed works
2. To enable an adequate and economic designto be
prepared, including the design of temporary works
3
The British Standard Code of Practice BS 5930:1991gives a list of the objects of site investigation as follows:
8/10/2019 site invistigate
4/19
3. To plan the best method of construction
4. To determine the changes that may arise in the
ground and environmental conditions, either naturallyor as a result of the works, and the effect of such
changes on the works, and the environment in general
4
8/10/2019 site invistigate
5/19
STAGE OF SI
1. DESK STUDY
2. SITE RECONNAISSANCE
3. DETAILED SITE EXPLORATION AND SAMPLING4. FIELD TEST / IN-SITU TESTING
5. LABORATORY TESTING
6. REPORT
5
8/10/2019 site invistigate
6/19
This is essentially the collection of a wide
variety of information relating to the site.
e.g. maps, drawings; details of existing orhistoric development, local authorityinformation; geological maps, memoirs,
records; details of utilities, services,restrictions, right-of way, ownership ofadjacent property; aerial photograph.
6
8/10/2019 site invistigate
7/19
An early examination of the site by appropriateexperts is most desirable.
eg. Geologist, land surveyor, soils engineer,hydrologist etc.
Information should be collected on the overall
site layout, topography, basic geology; detailsof access, entry and height restrictions
7
8/10/2019 site invistigate
8/19
HOW MANY BH OR OTHER SI METHOD CRITERIA OF TERMINATING BH
FIELD TEST;CRITERIA & FREQUENCY
SAMPLING TYPE; CRITERIA & FREQUENCY REFERENCE NOTE;FOR BUILDING & ROADS
PROJECT
DOCUMENTATION; DRAWINGS
8
8/10/2019 site invistigate
9/19
Projek Jarak
9m)
Kedalaman
Bangunan satu
tingkat
10 - 30 6 -9 m dari dasar asas
Bangunan Multi
Storey
15- 30 2 kali lebar struktur
Lebuh raya 250 -
500
Minimum 1- 1.5m di bawah
subdred
Empangan tanah 40 -80 Minimum 12- 15 m atau 3 m
dalam batuan keras
( No & Depth of Bore hole )
9
PROJECT DISTANCE
(m)
DEPTH
Sigle storey 10 - 30 6 -9 m from foundationbase
Multi Storey 15- 30 2 X Structure width
Highway 250 - 500 Minimum 1- 1.5m below
subgred
Soil dam 40 -80 Minimum 12- 15 m atau 3
m in hard rock
8/10/2019 site invistigate
10/19
Investigation of detailed geology and sub-surface soil conditions using surface surveys,trial pits, headings, boreholes, sounding,geophysical methods, as appropriate; survey
of groundwater conditions over a significationperiod of time
10
8/10/2019 site invistigate
11/19
MACINTOSH PROBE
CONE PENETRATION TEST, CPT
11
8/10/2019 site invistigate
12/19
SHALLOW EXPLORATION
TRIAL PITS
TRENCH
HAND AUGER
12
8/10/2019 site invistigate
13/19
DEEP EXPLORATION
PENJARAAN TUKUL (PERCUSSION BORING)
PENGGERUDIAN PUTAR (ROTARY DRILLING)
PENGGERUDIAN BASAH (WASH BORING)
13
8/10/2019 site invistigate
14/19
8/10/2019 site invistigate
15/19
PENS MPEL N
TAK TERGANGGU(UNDISTURBEDSAMPLE)
* KEKUATAN RICIH
* PENGUKUHAN
TERGANGGU
( DISTURBED)
* PENGELASAN TANAH*UJIAN PEMADATAN
HAD-HAD ATTERBERG
15
8/10/2019 site invistigate
16/19
8/10/2019 site invistigate
17/19
STANDARTD PENETRATION TEST
PLATE BEARING TEST
CONE PENETRATION TEST
VANE SHEAR TEST
17
8/10/2019 site invistigate
18/19
FOR DESCRIPTION, CLASSIFICATION &CORRELATION - COLOUR, MOISTURECONTENT, SG, POROSITY , LL, PL, PI, SL,
PARTICLE SIZE
SHEAR STRENGH TRIAXIAL TEST, DIRECTSHEAR TEST, CONSOLIDATION , PERMEABILITY
TEST
CORROSION pH, SULPHATE & CHLORIDE,SALTS
18
8/10/2019 site invistigate
19/19
Details of geological study, includingstructures, stratigraphy and mapping; resultsof borings, etc., including log, references forsamples and stratigraphy interpretations as
requested; comments and recommendationsrelating to the design and construction of theproposed works; recommendations relatingto further investigating or testing, and toongoing or post-completion monitoring.
19