    SITE INVESTIGATION

    PREPARED BY SARINA

    1

  • 8/10/2019 site invistigate

    2/19

    Site Investigation (SI) is the

    exploration or discovery of the ground

    conditions to enable engineers to

    make informed design decisions.

    2

  • 8/10/2019 site invistigate

    3/19

    OBJECTIVE OF SI

    The British Standard Code of Practice BS 5930:1991gives

    a list of the objects of site investigation as follows:

    1. To assess the general suitability of the siteand environs

    for the proposed works

    2. To enable an adequate and economic designto be

    prepared, including the design of temporary works

    3

    The British Standard Code of Practice BS 5930:1991gives a list of the objects of site investigation as follows:

  • 8/10/2019 site invistigate

    4/19

    3. To plan the best method of construction

    4. To determine the changes that may arise in the

    ground and environmental conditions, either naturallyor as a result of the works, and the effect of such

    changes on the works, and the environment in general

    4

  • 8/10/2019 site invistigate

    5/19

    STAGE OF SI

    1. DESK STUDY

    2. SITE RECONNAISSANCE

    3. DETAILED SITE EXPLORATION AND SAMPLING4. FIELD TEST / IN-SITU TESTING

    5. LABORATORY TESTING

    6. REPORT

    5

  • 8/10/2019 site invistigate

    6/19

    This is essentially the collection of a wide

    variety of information relating to the site.

    e.g. maps, drawings; details of existing orhistoric development, local authorityinformation; geological maps, memoirs,

    records; details of utilities, services,restrictions, right-of way, ownership ofadjacent property; aerial photograph.

    6

  • 8/10/2019 site invistigate

    7/19

    An early examination of the site by appropriateexperts is most desirable.

    eg. Geologist, land surveyor, soils engineer,hydrologist etc.

    Information should be collected on the overall

    site layout, topography, basic geology; detailsof access, entry and height restrictions

    7

  • 8/10/2019 site invistigate

    8/19

    HOW MANY BH OR OTHER SI METHOD CRITERIA OF TERMINATING BH

    FIELD TEST;CRITERIA & FREQUENCY

    SAMPLING TYPE; CRITERIA & FREQUENCY REFERENCE NOTE;FOR BUILDING & ROADS

    PROJECT

    DOCUMENTATION; DRAWINGS

    8

  • 8/10/2019 site invistigate

    9/19

    Projek Jarak

    9m)

    Kedalaman

    Bangunan satu

    tingkat

    10 - 30 6 -9 m dari dasar asas

    Bangunan Multi

    Storey

    15- 30 2 kali lebar struktur

    Lebuh raya 250 -

    500

    Minimum 1- 1.5m di bawah

    subdred

    Empangan tanah 40 -80 Minimum 12- 15 m atau 3 m

    dalam batuan keras

    ( No & Depth of Bore hole )

    9

    PROJECT DISTANCE

    (m)

    DEPTH

    Sigle storey 10 - 30 6 -9 m from foundationbase

    Multi Storey 15- 30 2 X Structure width

    Highway 250 - 500 Minimum 1- 1.5m below

    subgred

    Soil dam 40 -80 Minimum 12- 15 m atau 3

    m in hard rock

  • 8/10/2019 site invistigate

    10/19

    Investigation of detailed geology and sub-surface soil conditions using surface surveys,trial pits, headings, boreholes, sounding,geophysical methods, as appropriate; survey

    of groundwater conditions over a significationperiod of time

    10

  • 8/10/2019 site invistigate

    11/19

    MACINTOSH PROBE

    CONE PENETRATION TEST, CPT

    11

  • 8/10/2019 site invistigate

    12/19

    SHALLOW EXPLORATION

    TRIAL PITS

    TRENCH

    HAND AUGER

    12

  • 8/10/2019 site invistigate

    13/19

    DEEP EXPLORATION

    PENJARAAN TUKUL (PERCUSSION BORING)

    PENGGERUDIAN PUTAR (ROTARY DRILLING)

    PENGGERUDIAN BASAH (WASH BORING)

    13

  • 8/10/2019 site invistigate

    14/19

  • 8/10/2019 site invistigate

    15/19

    PENS MPEL N

    TAK TERGANGGU(UNDISTURBEDSAMPLE)

    * KEKUATAN RICIH

    * PENGUKUHAN

    TERGANGGU

    ( DISTURBED)

    * PENGELASAN TANAH*UJIAN PEMADATAN

    HAD-HAD ATTERBERG

    15

  • 8/10/2019 site invistigate

    16/19

  • 8/10/2019 site invistigate

    17/19

    STANDARTD PENETRATION TEST

    PLATE BEARING TEST

    CONE PENETRATION TEST

    VANE SHEAR TEST

    17

  • 8/10/2019 site invistigate

    18/19

    FOR DESCRIPTION, CLASSIFICATION &CORRELATION - COLOUR, MOISTURECONTENT, SG, POROSITY , LL, PL, PI, SL,

    PARTICLE SIZE

    SHEAR STRENGH TRIAXIAL TEST, DIRECTSHEAR TEST, CONSOLIDATION , PERMEABILITY

    TEST

    CORROSION pH, SULPHATE & CHLORIDE,SALTS

    18

  • 8/10/2019 site invistigate

    19/19

    Details of geological study, includingstructures, stratigraphy and mapping; resultsof borings, etc., including log, references forsamples and stratigraphy interpretations as

    requested; comments and recommendationsrelating to the design and construction of theproposed works; recommendations relatingto further investigating or testing, and toongoing or post-completion monitoring.

    19