Upload
truongthuan
View
218
Download
2
Embed Size (px)
Citation preview
1
Unique Challenges Related toMarina Brownfields Development
St. Augustine Case Study
Presented to
2005 Florida Brownfields ConferenceOctober 11, 2005
Proprietary and ConfidentialThe RETEC Group, Inc.
Site Background Site Operations
Manufactured gas plant from 1885 intothe late 1950s
Produced and distributed gas for lightingand heating
Ownership Atlanta Gas Light Company &
predecessors from 1885 to 1989
City of St Augustine from 1989 until 2005
Currently: San Sebastian Partners
Liability Owners Atlanta Gas Light Company holds Majority
Share
City of St. Augustine holds Minor Share
Two Distinct Phases of Work
2
Proprietary and ConfidentialThe RETEC Group, Inc.
Regulatory Setting
EPA Region IV Superfund Program Engineering Evaluation/ Cost Analysis (EE/CA) – Accelerated Investigation and
Feasibility Process
Administrative Order on Consent
Work Performed Under a Removal Action Army Corps of Engineers (ACOE) – Dredge and Fill Permit – Key component for both
phases of work
Other Regulatory Agencies Involved NOAA, FDEP, US Fish & Wildlife, SJWM
Expedient review of documents allowed for a compressed
schedule
Phase I - 2001 Removal Action
3
Proprietary and ConfidentialThe RETEC Group, Inc.
Objectives for Phase I
Remove soil to cleanup levels protective offuture construction workers that will performredevelopment work
Source removal to manage groundwater impacts
Tools used to meet objectives: Vertical Cut-line
30 feet source zone, 8 feet uplands, 3 feet marsh
Horizontal Endpoints Locate engineering controls beyond horizontal
limits of impacts identified in investigation
Institutional controls and restrictive covenants Restrict use of groundwater
Post remediation HASP to protect futureconstruction workers
Site Plan forRemediation
Proprietary and ConfidentialThe RETEC Group, Inc.
Technical Challenges
Large environmental earthwork project
Sequence excavation and transport of 85,000 tonsof coal tar-impacted saturated zone soil on achallenging downtown site
Deep excavation into a shallow groundwater table Excavation in a tidally influenced marsh adjacent to
a river
Rain – Hurricane season
Air monitoring protective of community
Temporary marsh restoration/replanting
Work was performed on an Aggressive Schedulewith a tightly controlled budget
4
Proprietary and ConfidentialThe RETEC Group, Inc.
Design and Construction Challenges Two Cofferdams
Dam the River
Support Riberia Street and a 30 foot excavation Factors of safety- withstand 15-inch rainfall in 24 hours
Choreographed sheeting installation with utilityshutdowns
Pump Tests - Dewatering System Two stage wellpoint system 120 wellpoints and 8 deep
dewatering wells
Complicated geology - permeable shell hash, Overlainby clean sand, a clay aquitard, and fine silty sands toground surface
Logistics Traffic, decontamination, confirmation sampling,
stormwater control, flooding, demolition, asbestos, andunderground obstructions
Proprietary and ConfidentialThe RETEC Group, Inc.
City of St. Augustine –In Kind Services and Partner
Initial Cost Share Agreement – cost basis for inkind services
Backfill
Water Treatment – 400K gal/day by POTW
Traffic Control Invaluable logistical support from the City Manager’s
Office
Collaboration of Phase I partners built
momentum for Phase II success
5
Proprietary and ConfidentialThe RETEC Group, Inc.
Stakeholder Challenges for Phase II –The Marina Development
Convert a vacant water front parcel into amixed use residential, retail and marinadevelopment
Fulfill the continuing obligations of the Order
Meet EPA’s expectations from aninvestigation design and implementationperspective
The Team succeeded due to the
collaboration of Stakeholders in a
give and take process with willingness toaccept some risk
to assure successof the deal
Proprietary and ConfidentialThe RETEC Group, Inc.
REDEVELOPMENT
Regulat
ors
Propert
y Owner
(City
of St. A
ugustine)
Development Team
Responsible
Parties
6
Proprietary and ConfidentialThe RETEC Group, Inc.
Technical Team—Focal Point forthe Collaborative Process
RETEC ensured that the technical details met the goals of the regulatory, legal anddevelopment teams
Provide a transparent technical vision to manage environmental components in anunderstandable manner
Investigation – Pre-sampling 3-D modeling from investigation boring logs:
Lithological contouring
Chemical contouring that associates impacts with types of soil
Supports a cutline approach based on analytical results
Visual observation during remediation
Proprietary and ConfidentialThe RETEC Group, Inc.
Liability Management Processfor Redevelopment
Legal Teams balanced risk for theirindividual clients and created contracts toestablish financial responsibility for majorcost components
Melding of legal and technical inputs intolegal documents Provides a framework for a thorough and
collaborative identification of the risks andliabilities – who is responsible for what
Legal documents are Three PartAgreement and Cost AllocationAgreement
7
Proprietary and ConfidentialThe RETEC Group, Inc.
Three Party Agreement
Identify the party responsible for managing the individual elements of the workfor major components such as: Environmental work plans and design verses marina design and construction
Environmental oversight to assure compliance with the Order
Permits and licenses
Transportation, disposal or reuse of soils
Established a clear enforceable contract: Mutual Release
Indemnification
Insurance
Proprietary and ConfidentialThe RETEC Group, Inc.
Cost Allocation Agreement
Identifies who pays for what based on incremental cost of environmental workvs “clean” civil work
RETEC’s Role Develop technical specifications for excavation, material management, segregation of
different classes of soil, and transportation and disposal
Plans with sequenced cut-lines in 3-foot horizons
Define impacts remaining at vertical limits Over excavate 2 feet, or
Install scour resistant cap
Technical graphic representation of the environmental work facilitated an understanding of the incremental cost
of a marina development with environmental impacts
8
Proprietary and ConfidentialThe RETEC Group, Inc.
Cost Negotiations and Economic Balance
RETEC and legal team conceptualized a unit cost approach
Development team used a lump sum bid approach
$500,000 Divergence in expected cost from bids vs. Engineers Estimate Utilized subcontractor interviews and information exchange to narrow the cost
gap to less than $50K from the Engineer’s Estimate
Maximize sequencing to gain benefits from “Clean” Contractor Piggy back cofferdam construction with entrance channel dredging – minimize
mobilization fees and maximize volume of work by a single contractor
Proprietary and ConfidentialThe RETEC Group, Inc.
The Collaborative Effort Allowed the Teamto Overcome Various Challenges
Clear regulatory leadership from EPA and other agencies includingNOAA, the Corps of Engineers, and FDEP
Financial backing from AGLC, the City, and the San SebastianPartners
Legal expertise which provided a contractual relationship toperform the work
Technical leadership to satisfy the requirements of the AOC andgain approval from EPA
9
Proprietary and ConfidentialThe RETEC Group, Inc.
Proprietary and ConfidentialThe RETEC Group, Inc.
10
Proprietary and ConfidentialThe RETEC Group, Inc.
Regulators
EPA
NOAA
Corps of Engineers Permit Modification
SJWMD
FDEP
Ensure compliance with the order whileapplying the cleanup criteria to the sitespecific details of the redevelopment
Construction Worker Risk – 2001 RA
Ecological Risk – 2005 Marina Work –Continuing obligation from the Order Ecological receptors at the new base
elevation of the marina
Probable Effects Level and ThresholdEffects Level
Proprietary and ConfidentialThe RETEC Group, Inc.
Development Team –San Sebastian Partners
Development Partners
Legal
Architect
Financial Institution Construction Manager/GC
Environmental Consultant
Engineering Marine
Geotech
Surveying
Structural
Remediation Contractor and Subs
Marina and Construction Contractors
Conceptualized the harbor and sitedesign
Establish the parameters for thetechnical team to plan a secondphase of investigation
Design and remediation for the marinadevelopment
Without the developers vision for the site,redevelopment could not occur
11
Proprietary and ConfidentialThe RETEC Group, Inc.
Property Owner (City of St. Augustine)
City Manager
City Council
Public
Legal
Public Works/Engineer/Other
Business Community
Proprietary and ConfidentialThe RETEC Group, Inc.
Responsible Parties
AGLC
City of St. Augustine
Legal
Environmental Consultant Driller
Laboratory
Landfill
Manage environmental liability throughout theredevelopment project while doing the rightthing as corporate/municipal stewards
Understand implications of technicaldecisions in the investigation and designprocess and their impact to risk and cost
Work within budget and schedule constraints
The objectivity, knowledge, and trust in the technical approachwas a key towards successful development
12
Proprietary and ConfidentialThe RETEC Group, Inc.
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3a: Site Lithology at 0 feet NGVD
Sandy fill (blue)
Silty clay muck (red) Silty clay (aqua)Fine to mediumsand (light green)
13
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3b: Site Lithology at -1.5 feet NGVD
Sandy fill (blue)
Silty clay muck (red) Silty clay (aqua)Fine to mediumsand (light green)
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3c: Site Lithology at -3 feet NGVD
Sandy fill (blue)
Silty clay muck (red) Silty clay (aqua)Fine to mediumsand (light green)
14
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3d: Site Lithology at –4.5 feet NGVD
Sandy fill (blue)
Silty clay muck (red) Silty clay (aqua)Fine to mediumsand (light green)
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3e: Site Lithology at –6 feet NGVD
Sandy fill (blue)
Silty clay muck (red) Silty clay (aqua)Fine to mediumsand (light green)
15
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3f: Site Lithology at –7.5 feet NGVD
Sandy fill (blue)
Silty clay muck (red) Silty clay (aqua)
Fine to mediumsand (light green)
Clayey sand (green)
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3g: Site Lithology at –9 feet NGVD
Sandy fill (blue)
Silty clay muck (red) Silty clay (aqua)
Fine to mediumsand (light green)
Clayey sand (green)
16
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3h: Site Lithology at –11 feet NGVD
Silty claymuck (red)
Silty clay (aqua)
Fine to mediumsand (light green)
Clayey sand (green)
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-3i: Site Lithology at –13 feet NGVD
Silty claymuck (red)
Silty clay (aqua)
Fine to mediumsand (light green)
Clayey sand (green)
Sandy clay (gold)
17
Proprietary and ConfidentialThe RETEC Group, Inc.
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9a: Benzo(a)pyrene impact at 0 feet NGVD and above
contour levels at 72, 720, and 7200 ug/kg
72
18
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9b: Benzo(a)pyrene impact at –1.5 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
72
72
72
72720
72
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9c: Benzo(a)pyrene impact at -3 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
72
720
72
72
720
720
72
72
72
72
72
720
19
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9d: Benzo(a)pyrene impact at –4.5 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
720
720
720
72
72072
72072
72
72
720
7200
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9e: Benzo(a)pyrene impact at -6 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
720
72
72
720
7200
7207200
72072007200
720
20
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9f: Benzo(a)pyrene impact at –7.5 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
72
720
720
720
720
72
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9g: Benzo(a)pyrene impact at -9 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
72
720
720
72
720
72
72
72
21
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9h: Benzo(a)pyrene impact at -11 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
72
72
720
72
72
Proprietary and ConfidentialThe RETEC Group, Inc.
Figure 2-9i: Benzo(a)pyrene impact at -13 feet NGVD
contour levels at 72, 720, and 7200 ug/kg
72
72
22
Proprietary and ConfidentialThe RETEC Group, Inc.
Proprietary and ConfidentialThe RETEC Group, Inc.