SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

Embed Size (px)

Citation preview

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    1/116

     Draft Report

    System Impact Study Report

    50 MW Felisa Solar Power Project

    Prepared for:

    By:

    Negros PH Solar Inc.

    Barangay Felisa, Mansilingan, Bacolod City 

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    2/116

    EXECUTIVE SUMMARY 

    This System Impact Study (SIS) is conducted for the 50 MW Felisa Solar Power

    Project of Negros Ph Solar Inc. (NPSI) in Brgy. Felisa Bacolod City. The proposed

    connection for this project is a direct connection to Bacolod 138 kV Substation.

    The project currently has a 200 MW capacity endorsed by the Department of Energy

    (DOE) over phases. The developers have since identified suitable land sites and havemade the requisite arrangements with the landowners for long-term leases. Various

    irradiation, flood, topography and soil studies have already been conducted with

    positive results. In addition many of the local and national approvals and permits

    have since been obtained including local LGU endorsements. Technical layouts and

    routing plans have also been identified and secured.

    Currently there might be some “anticipated constraint” in the submarine

    interconnection between Negros and Cebu islands due to various projects being

    planned for but many of which may not get implemented. In light of this ‘constraint”

    the capacity of the project was reduced to 50 MW for this current phase for ease of

    implementation.

    This project has been developed and structured to allow for a quick expansion of

    another 60 MW in Phase II. The key milestone for this expansion would be the

    alleviation of the potential congestion along the Cebu-Panay submarine cable. This

    alleviation would be evident when either the submarine cable is reinforced or when the

    various other projects included in the base data is formally terminated.

    In December 2014, Italy's Prysmian was awarded this US$111 million project by the

    NGCP for the design, supply, installation, and commissioning of a submarine power

    cable link to connect Negros and Panay islands in the Philippines. The CNP-1 cable

    connection is the first stage of a larger development plan by NGCP, aimed at

    h C b N d P l d h h d h h

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    3/116

    Magalona on the Negros side. Delivery and commissioning is scheduled for the first

    half of 2016. Phase II (60MW) of the solar plant will be implemented after CNP-1 iscommissioned.

    In addition, in April 2015 NGCP announced plans to invest P1.6 billion to upgrade a

    transmission facility in Cebu that forms part of a broader Visayan backbone project to

    implement the Cebu substation 230 kilovolt (kV) upgrade project, this project

    represents the second stage of the Cebu-Negros-Panay (CNP) 230 kV backbone project

    further strengthening the grid in the Visayas. NGCP’s CNP project is generally

    intended to accommodate all additional capacity from new power plants that will be

    built in the Visayas.

    With the anticipated alleviation in congestion, NPSI will be implementing the 60 MW

    Phase II expansion of this solar in the second half of 2016 and request that this be

    recognized for planning purposes.

    Description Phase I

    Phase II

    (once CNP-1 is

    completed or

    when capacity

    avails itself)

    Size MW 50.00 60.00

    Time Frame 2015/2016 2016/2017

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    4/116

    This study was performed in accordance with the Philippines Grid Code (PGC) and

    NGCP requirements. The purposes of this study are as follows:

    1.  Analyze the steady-state, stability, and short circuit conditions of the grid with

    the project;

    2.  Determine any upgrades to the transmission system that would be required to

    mitigate any adverse impacts that the project could otherwise pose on the

    reliability and operating characteristics of the transmission system inaccordance with the PGC, NGCP standards and generally accepted

    international transmission utility practices;

    3. 

    Determine any upgrades required to mitigate any degradation to transmission

    transfer capability; and

    4.  Determine any upgrades required to mitigate any degradation to system

    dynamic stability.

    The primary area of concern of this study is the area around NGCP’s Bacolod

    Substation. Generated power from the proposed power plant will be transmitted to

    Visayas grid through this substation.

    In addition to the standard requirements of the PGC, the ERC had issued Resolution

    No. 7 Series of 2013 imposing new requirements for intermittent power plants such as

    this project. This proposed power plant should comply with those requirements,

    compliance thereto should be demonstrated by field tests during testing and

    commissioning.

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    5/116

    S TEADY S TATE  

    Steady state thermal and voltage analyses were conducted to examine the comparative

    system performance with and without the proposed project. The baseline performance

    is based on the system without the proposed project. System performance was re-

    evaluated with the project and compared with the baseline system. This approach

    exposes the impact of the project on the system utilizing the criteria set by the PGC.

    Steady state analysis was evaluated using a scenario where power plants at close

    proximity to the project were dispatched to its maximum feasible levels for years 2016

    and 2021. Peak load for 2016 and 2021 were respectively, 1,854.8 MW and 2,279.5

    MW. Simulation at this dispatch scenario enabled the examination of the transmission

    system to reliably operate with the proposed project integrated to the system.

    Based on the steady state results the project’s connection to the grid poses no

    significant adverse impact on the reliability and operating characteristics of Visayas

    grid. There was no significant voltage or thermal violations of reliability criteria

    associated with the entry of the project considering its priority dispatch incentive

    under the RE Law.

    S TABILITY  

    This evaluation consisted of application of faults on the system with the project using

    peak base cases. The dynamic stability of the system during and after these faulted

    conditions should conform to the requirements of the PGC. In addition, voltage,

    frequency and power fluctuations or oscillations should dampen within the prescribedperiod. Machine angle should also exhibit acceptable coherence.

    In all tested fault conditions the project would pose no significant adverse impact on

    the stability of the system.

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    6/116

    S HORT C IRCUIT  

    Short-circuit analysis was conducted to determine the impact of the project on the

    existing fault current levels in all substations. In this study, it was assumed that fault

    duty of the circuit breakers installed in the system are as follows:

    Simulation results indicate that the entry of the proposed project will not result to

    fault levels beyond the fault duties of the existing circuit breakers.

    C ONCLUSION  

    This study revealed that the addition of NPSI’s Phase I, the 50 MW Felisa Solar Power

    Project has no significant impact on the reliability, stability and operating

    characteristics of the Visayas power transmission system.

    The proposed power plant could be safely and reliably integrated to Visayas grid.

    Phase II 60 MW of NPSI project will be implemented once CNP-1 is commissioned or

    when there is capacity in the grid when other projects are do not materialize.

    Volage Level

    Rated Short

    CircuitCurrent (kA)

    69kV 230 kV 40

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    7/116

    TABLE OF CONTENTS 

    Executive Summary

    Steady State

    Stability

    Frequency Assessment

    Short Circuit

    Conclusion

    1. Background Information ................................................................................................. 10

    2. Study Assumptions ......................................................................................................... 12

    A. Demand Forecast ..................................................................................................... 12

    B. Generation Expansions ................................................................................................ 12

    C. Transmission Expansions ......................................................................................... 14

    D. Grid Code Requirements ......................................................................................... 15

    3. Proposed Connection Arrangement and System Modelling ............................................ 19

    4. Load Flow Assessment .................................................................................................... 23

    A. Thermal Assessment – Adequacy in Normal Conditions (Peak Conditions) ........... 24

    B. Thermal Assessment – Adequacy in Single Outage Conditions (Peak Conditions) ..... 25

    C. Voltage Assessment in Normal Conditions (Peak) .................................................. 26

    D. Voltage Assessment in Single Outage Condition (Peak Conditions) ....................... 27

    5. Fault Level Analysis ....................................................................................................... 28

    6. Stability Assessment ....................................................................................................... 30

    7. Frequency Assessment .................................................................................................... 32

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    8/116

     

    LIST OF TABLES 

    Table 1. Demand Projections for Visayas ............................................................................. 12

    Table 2. Generator Capacity Additions for Visayas ............................................................. 13

    Table 3. Power Circuit Breaker Fault Duty Rating ............................................................. 15

    Table 4. Requirements at Different Frequency Range .......................................................... 17

    Table 5. Lumped Generator Specifications ........................................................................... 20

    Table 6. Generator Transformer Data .................................................................................. 21

    Table 7. Transmission Line Data .......................................................................................... 21

    Table 8. Dynamics Data for 50 MW Lumped Generator Units ............................................ 22

    Table 9. Dynamics Data for the Electrical Controls ............................................................. 23

    Table 10. 2016 Thermal Assessment (Peak, Normal Loading) ............................................. 24

    Table 11. 2021 Thermal Assessment (Peak, Normal Loading) ............................................. 24

    Table 12. 2016 Thermal Assessment (Peak, N-1 Loading) ................................................... 25

    Table 13. 2021 Thermal Assessment (Peak, N-1 Loading) ................................................... 25

    Table 14. 2016 Voltage Assessment (Peak, Normal Loading) ............................................... 26

    Table 15. 2021 Voltage Assessment (Peak, Normal Loading) ............................................... 26

    Table 16. 2016 Voltage Assessment (Peak, N-1 Loading) ..................................................... 27

    Table 17. 2021 Voltage Assessment (Peak, N-1 Loading) ..................................................... 28

    Table 18. Short Circuit Rating of Selected Substations in the Grid ..................................... 29

    Table 19. Short Circuit MVA at Power Plant S/S (Peak Loading) ..................................... 29

    Table 20. Summary of Dynamic Stability Simulations with Power Plant ............................ 31

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    9/116

    LIST OF FIGURES 

    Figure 1. Generation Capacity Additions in Visayas ............................................................ 13

    Figure 2. Transmission Expansion Projects in Visayas ......................................................... 14

    Figure 3. Low Voltage Withstand Capability Requirement for Large Photovoltaic Systems 18

    Figure 4. Connection Scheme for the Project ....................................................................... 19

    Figure 5. Geographic Location of the Project ....................................................................... 20

    Figure 6. Equivalent Model of the Grid in the Vicinity of the Project ................................. 22

    Figure 7. Frequency Assessment, 2016 Peak Base Case ....................................................... 33

    Figure 8. Frequency Assessment, 2021 Peak Base Case ....................................................... 33

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    10/116

    1. BACKGROUND INFORMATION 

    Negros Ph Solar Inc. (NPSI) has embarked on developing this project by committing

    significant resources and time to identify and secure key project specifics to ensure

    project viability prior to applying for the various government permits and approvals.

    This project has been under-development for the last 6 months with the proper siteselection and technical evaluation and local stakeholders’ engagement and relationship

    building being developed to ensure project viability. The initial findings are very

    optimistic. Necessary government permits were already secured.

    This approach allows all the stakeholders, DOE, NGCP, Landowners, LGU’s, etc. to

    have better comfort and visibility that our Service Contract will crystalize into a real

    project and not remain “in development” for years.

    NPSI is a wholly owned Filipino corporation and was set up to fully focus on developing

    the Philippine Solar market. The founder Ms. Maricel Montfort, a highly successful

    native of Cadiz and currently residing in Bacolod and Manila, is a long-standing citizen

    who has had extensive working experience abroad and has returned back to the

    Philippines to take an active part in improving the lives of the local Filipinos through

    various infrastructure projects. Ms. Montfort is currently active with several large

    infrastructure and social developments throughout the Philippines. These include

    medical facilities, orphanages, water-treatment/purification projects and land &

    property investments. Being a very successful business lady, she is able to fully fund

    the professional and proper development of these projects.

    NPSI has identified Bacolod City as a suitable site for the Solar project. Bacolod has

    a stable climate with adequate sunlight throughout the year and minimal risk of heavy

    typhoons or flooding. Land is plentiful and the local government agencies are

    supportive of such an initiative

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    11/116

    Land Status:

    a)  Identified and secured approximately 150 hectares with the landowners. Many

    of the landowners are prominent local business people with good local standing.

    Land Options have been signed for most of them and the rest will be complete

    shortly and landowners are backing this project fully. NPSI has very good

    relationships with all the landowners. In total NPSI aims to secure

    approximately 280 hectares to build up to 200 MW.

    b)  NPSI had engaged professionals to conduct

    • 

    Irradiation Studies

    •  Flood studies

    • 

    Topographical surveys•  Soil studies

    •  Connection routing and

    •  Plant layout design

    The site has ideal road access and is relatively flat with little flood risk. The

    lands will not be an inconvenience any inhabitants. The landlords havecommitted to ensure the site will be problem free and we will engage their local

    individuals where possible.

    c)  The lands identified are outside the CARP jurisdiction and we have obtained

    proper legal advice as well as advice from the local LGU’s on the proper

    procedure to ensure that the site is Solar ready. This has already been factored

    in our evaluation.

    d)  The land titles have also been checked for any risk of foreclosure or

    encumbrances being attached.

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    12/116

    The proposed connection would involve construction of approximately 3.5 km 138 kV

    transmission line, a take-off substation at the power plant site and modifications at a

    bay in Bacolod Substation to accommodate entry of the proposed power plant.

    Conductors for this line should be 795 MCM ACSR equipped with appropriate

    communication facility to convey revenue meter reading to NGCP’s Bacolod

    Substation.

    2. 

    STUDY ASSUMPTIONS 

    A. DEMAND FORECAST 

    Based on the 2013 Transmission Development Plan (TDP), there would relatively be

    a significant increase in demand in Visayas Grid. Table 1 shows the demand

    projections for the entire grid. Of greater interest for this proposed project is the

    demand in Negros Island where the proposed facility will be injecting its power to the

    grid. Bacolod Substation will be the main corridor of this project.

    B.  GENERATION EXPANSIONS 

    Table 1. Demand Projections for Visayas

    Source: 2013 Transmission Development Plan

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    13/116

    Figure 1.  Generation Capacity Additions in Visayas

    Table 2. Generator Capacity Additions for Visayas

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    14/116

    C. TRANSMISSION EXPANSIONS 

    Major developments in Negros island included in the 2013 TDP are as follows:

    1.  Negros-Panay Interconnection Uprating

    2.  Negros V Transmission Line Project

    3. 

    Visayas Substation Expansion I (Kabangkalan 1 x 50 MVA)

    4. 

    Visayas Substation Reliability I (Amlan 1 x 50 MVA, Bacolod 1 x 100 MVA

    and Cadiz 1 x 50 MVA)

    These proposed developments shown in Figure 2 as well as generation expansions were

    included in the base cases and were considered in the assessments.

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    15/116

    D. GRID CODE REQUIREMENTS 

    The proposed project’s performance was evaluated based on the criteria set by the

    Philippine Grid Code, utilizing grid dispatch scenario where power plants near the

    project were set at maximum dispatch to reflect the worst impact of the project to the

    grid. Steady state voltage and thermal analyses examined system performance without

    the proposed project in order to establish a baseline data. System performance was

    re-evaluated with the project and compared with the previous baseline performance todemonstrate the impact of the project on area transmission reliability.

    The voltage limits adopted in this study were in compliance with the PGC which

    requires that during normal and single outage contingency conditions, the voltage

    should be within the range of 0.95 to 1.05 per unit. For the thermal limits, normal

    thermal ratings shall not be violated under all-lines-in and single outage contingency

    conditions. The steady state analysis was performed with both pre-contingency and

    post-contingency solution parameters that allow adjustment of load tap-changing

    transformers (LTCs), static var devices (SVDs) including switched capacitors and

    phase angle regulators (PARs).

    For short circuit studies, resulting three phase fault should not exceed the levels shown

    in Table 3. These ratings are the standard fault duty rating of circuit breakers

    connected to the grid.

    Voltage Level

    Rated Short Circuit Current

    (kA)

    69kV 230 kV 40

    Table 3. Power Circuit Breaker Fault Duty Rating

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    16/116

    1.  The Grid remains stable after any Single Outage Contingency for all forecasted

    Load conditions; and

    2. 

    The Grid remains controllable after a Multiple Outage Contingency. In the

    case of Grid separation, no total blackout should occur in any Island Grid.

    In this study however, only stability under single outage contingency conditions were

    evaluated.

    Applied faults were cleared (normal clearing) in compliance with the requirements of

    the PGC Section 4.5.2.3 as follows:

    1.  85 ms for 500 kV;

    2.  100 ms for 230 kV and 138 kV; and

    3. 

    120 ms for voltages less than 138 kV

    Delayed clearing were simulated in accordance with the requirements of the PGC

    which states:

    “The circuit breaker fail protection shall be designed to initiate the tripping of

    all the necessary electrically-adjacent circuit breakers and to interrupt the faultcurrent within the next 50 milliseconds, in the event that the primary protection

    system fails to interrupt the fault current within the prescribed Fault Clearance

    Time”

    In addition to the standard PGC requirements, the Energy Regulatory Commission

    (ERC) had issued Resolution No. 7 series of 2013 entitled “Resolution Adopting and

    Approving Addendum to Amendment No. 1 of the Philippine Grid Code, Establishing

    the Connection and Operational Requirements for Variable Renewable Energy (VRE)

    Generating Facilities”. Under Article II Section 2 of this addendum, additional

    requirements for large photovoltaic generation systems were prescribed as follows:

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    17/116

    Generating Limit Power Output

    The proposed power plant should continuously supply active and reactive power

    depending on the availability of primary source within the frequency range of 59.7-

    60.3 Hz. It should be capable of interchanging reactive power at connection point

    within ±5% voltage variation. Outside this range and up to ±10% voltage variation,

    a reduction in active and/or reactive power may be allowed up to 5% of the generator’s

    declared data.

    Frequency Withstand Capability

    Table 4 shows the allowable power plant frequency response.

    Reactive Power Capability

    The proposed power plant should be capable of supplying reactive power output at its

    Table 4. Requirements at Different Frequency Range

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    18/116

    Performance during Network Disturbances

    The allowable voltage ride-through for the power plant is shown in Figure 3.

    Voltage Control System

    The proposed power plant shall be capable of contributing voltage control bycontinuous regulation of the reactive power supplied to the grid under power factor

    control mode wherein power factor is maintained at the connection point or voltage

    control mode wherein voltage at the high voltage busbar of the proposed power plant

    is maintained at a constant set-point.

    Figure 3. Low Voltage Withstand Capability Requirement for Large Photovoltaic

    Systems

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    19/116

    Power Quality

    With the proposed power plant connected to the system and under normal operating

    state, the Flicker Severity and Total Harmonic Distortion at the connection point shall

    not exceed the values prescribed by the PGC

    The proposed power plant will demonstrate compliance with these requirements

    through testing to be conducted pursuant to Section 3.2.3.

    3. PROPOSED CONNECTION ARRANGEMENT AND SYSTEM

    MODELLING 

    In Figure 4 is shown the proposed connection for the project. This connection consistsof 138 kV transmission line directly connected to Bacolod 138 kV Substation. The

    project will be equipped with a take-off substation at the power plant site connected

    to a main bay at Bacolod Substation. The project’s geographic location is shown in

    Figure 5.

    Proposed Power Plant

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    20/116

    The technical specifications used to model the proposed connection assets of NPSI

    solar power plant project are shown in Table 5 to Table 7.

    Power

    C biliReactive Capability at

    R k

    Table 5. Lumped Generator Specifications

    Figure 5. Geographic Location of the Project

    3.5 km 138 kV transmission line

    Take-off Substation

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    21/116

    The grid model or base cases used in this study for years 2016 and 2021 were provided

    by NGCP. Both base cases were derived from the Transmission Development Plan

    and considered transmission line and generator expansion plans for the period covered.The scenario represented was peak loading condition, maximizing dispatch of power

    plants in the vicinity of the project. Off-peak scenarios were not considered in the

    assessment since the proposed power plant is not expected to operate during off-peak.

    To reflect the priority dispatch scenario in the model, dispatch of conventional

    synchronous machines in Negros and Panay areas were slightly reduced. In actualapplication, these conventional plants’ dispatch will vary due to the intermittence of

    the proposed power plant. Power plants with adjusted dispatch are as follows:

    1.) Palinpinon Geothermal Power Plant (Negros)

    Description Tap RatioPresent

    Tap

    MVA

    Rating

    Tap

    StepsR (pu)

    X (pu)

    based on

    System

    MVA

    Grid

    Transformers

    22/138

    D/YCenter 65 5 0 0.178620

    Line Name Type LengthRate

    (MVA)R (pu) X (pu) B (pu)

    NPSI take-off –

    138 kV tapping

    138 kV, 795

    MCMACSR

    3.5 km 196 0.001580 0.008740 0.002290

    Table 6. Generator Transformer

    Table 7. Transmission Line Data

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    22/116

    The 50 MW generator was modeled as lumped unit using “PVGU1” in the dynamic

    stability study while the electrical controls was modelled as “PVEU1”. Parameters

    for the models are shown in Table 8 and Table 9 respectively. Other system dynamics

    data were provided by NGCP.

    Figure 6. Equivalent Model of the Grid in the Vicinity of the Project

    Proposed 50 MW

    Solar Power Plant

    Table 8.  Dynamics Data for 50 MW Lumped Generator Units

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    23/116

    4. LOAD FLOW ASSESSMENT 

    The results of the simulation for thermal adequacy are presented in Sections 4.A. and

    4.B. while that for the voltages are shown in Sections 4.C. and 4.D.

    Under normal loading conditions, considering the priority dispatch of intermittent RE

    Generators, thermal loading of elements in the grid will remain within PGC required

    limits. The number of grid loading violations during single-outage contingency

    Table 9. Dynamics Data for the Electrical Controls

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    24/116

    A.  THERMAL ASSESSMENT – ADEQUACY IN NORMAL CONDITIONS

    (PEAK CONDITIONS)

    The results of the simulations are given in Table 10 and Table 11 for the 2016 and

    2021 base cases respectively.

    Monitored ElementMVA

    Rating

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    MVA % MVA %

    1 Solar Hi-Bacolod 138 kV 196.00 N/A 50.90 25.97

    2 Samboan-Pondol 138 kV 108.04 84.91 78.59 93.47 86.51

    3 Pondol-Amlan 138 kV 196.00 84.72 43.22 93.26 47.584 Amlan Hi-Amlan SP 196.00 132.92 67.82 152.74 77.93

    5 Amlan-Mabinay 138 kV 196.00 15.33 7.82 24.71 12.61

    6 Kabankalan-Bacolod 138 kV 196.00 10.64 5.43 20.00 10.20

    7 Bacolod-E. B. Magalona 138 kV L1 196.00 20.20 10.31 14.44 7.37

    8 Bacolod-E. B. Magalona 138 kV L2 392.00 34.56 8.82 24.32 6.20

    9 EB Magalona-Barotac Viejo 138 kV 108.00 49.57 45.90 44.02 40.76

    10 Barotac Viejo-Dingle 138 kV 196.00 47.40 24.18 57.33 29.2511 Barotac Viejo-Concepcion 138 kV 392.00 95.44 24.35 90.28 23.03

     

    Monitored ElementMVA

    Rating

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    MVA % MVA %

    1 Solar Hi-Bacolod 138 kV 196.00 N/A 50.94 25.99

    2 Samboan Pondol 138 kV 108 04 69 60 64 42 89 32 82 67

    Table 10. 2016 Thermal Assessment (Peak, Normal Loading)

    Table 11. 2021 Thermal Assessment (Peak, Normal Loading)

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    25/116

    B.  THERMAL ASSESSMENT – ADEQUACY IN SINGLE OUTAGE

    CONDITIONS (PEAK CONDITIONS)

    Thermal N-1 adequacy assessments are given in and Table 12 and Table 13 for 2016

    and 2021 base cases. The quantity of grid loading violations during this contingency

    conditions essentially remained the same.

    Monitored ElementMVA

    Rating

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    MVA % MVA %

    1 Solar Hi-Bacolod 138 kV 196.00 N/A 50.97 26.01

    2 Samboan-Pondol 138 kV 108.04 165.96 153.61 182.54 168.963 Pondol-Amlan 138 kV 196.00 164.93 84.15 181.44 92.57

    4 Amlan Hi-Amlan SP 196.00 212.78 108.56 232.55 118.65

    5 Amlan-Mabinay 138 kV 196.00 55.29 28.21 65.46 33.40

    6 Kabankalan-Bacolod 138 kV 196.00 51.14 26.09 61.64 31.45

    7 Bacolod-E. B. Magalona 138 kV L1 196.00 85.03 43.38 57.49 29.33

    8 Bacolod-E. B. Magalona 138 kV L2 392.00 64.93 16.56 54.67 13.95

    9 EB Magalona-Barotac Viejo 138 kV 108.00 98.30 91.02 69.33 64.1910 Barotac Viejo-Dingle 138 kV 196.00 94.75 48.34 116.50 59.44

    11 Barotac Viejo-Concepcion 138 kV 392.00 190.35 48.56 180.17 45.96

     

    Monitored ElementMVA

    Rating

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    MVA % MVA %

    1 S l Hi B l d 138 kV 196 00 N/A 50 94 26 09

    Table 13. 2021 Thermal Assessment (Peak, N-1 Loading)

    Table 12. 2016 Thermal Assessment (Peak, N-1 Loading)

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    26/116

    C.  VOLTAGE ASSESSMENT IN NORMAL CONDITIONS (PEAK)

    Voltage assessment conducted on the system indicated that the entry of the project

    will not result to voltage violations in the grid. Table 14 and Table 15 present the

    results of voltage assessment for the 2016 and 2021 base cases respectively.

    Monitored Substations

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    (kV) (p.u.) (kV) (p.u.)

    3 [NPHS_HI 138.000] N/A 1.0142 139.95

    227601 COLON 138.00 136.80 0.9913 0.9903 136.66

    227700 SAMBOAN 138.00 137.31 0.9950 0.9917 136.85

    235500 BACOLOD 69.000 70.46 1.0212 1.0196 70.35

    235501 BACOLOD 69.000 70.46 1.0212 1.0196 70.35

    237100 PONDOL 138.00 138.48 1.0035 1.0017 138.23

    237101 PONDOL 138.00 138.48 1.0035 1.0017 138.23

    237200 AMLAN HI 138.00 137.99 0.9999 0.9984 137.78

    237201 AMLAN SP 138.00 137.99 0.9999 0.9984 137.78

    237300 MAB HI 138.00 138.86 1.0062 1.0042 138.58

    237400 KABANKAL 138.00 139.35 1.0098 1.0078 139.08

    237500 BACOLOD 138.00 140.18 1.0158 1.0143 139.97

    237800 EBMAG1 138.00 140.90 1.0210 1.0213 140.94

    237801 EBMAG2 138.00 141.06 1.0222 1.0211 140.91

    247100 BTC VIEJ 138.00 141.20 1.0232 1.0217 140.99

    247200 DINGLE 138.00 140.03 1.0147 1.0134 139.85

    247700 CNCPCION 138.00 141.51 1.0254 1.0244 141.37

    Table 14.  2016 Voltage Assessment (Peak, Normal Loading)

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    27/116

    235501 BACOLOD 69.000 1.0074 69.51 1.0044 69.30

    237100 PONDOL 138.00 1.0033 138.46 1.0003 138.04

    237101 PONDOL 138.00 1.0033 138.46 1.0003 138.04237200 AMLAN HI 138.00 0.9991 137.88 0.9963 137.49

    237201 AMLAN SP 138.00 0.9991 137.88 0.9963 137.49

    237300 MAB HI 138.00 1.0032 138.44 0.9999 137.99

    237400 KABANKAL 138.00 1.0052 138.72 1.0019 138.26

    237500 BACOLOD 138.00 1.0084 139.16 1.0056 138.77

    237800 EBMAG1 138.00 1.0183 140.53 1.0164 140.26

    237801 EBMAG2 138.00 1.0215 140.97 1.0197 140.72247100 BTC VIEJ 138.00 1.0233 141.22 1.0216 140.98

    247200 DINGLE 138.00 1.0107 139.48 1.0098 139.35

    247700 CNCPCION 138.00 1.0330 142.55 1.0320 142.42

    D. 

    VOLTAGE ASSESSMENT IN SINGLE OUTAGE CONDITION (PEAK

    CONDITIONS)

    Results of voltage assessment during contingency conditions are shown in Table 16

    and Table 17 for the 2016 and 2021 base cases respectively. No deviations from the

    PGC prescribed limits are expected upon the entry of the proposed project to the grid. 

    Monitored Substations

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    Min Max Min Max3 [NPHS_HI 138.000] N/A 0.9961 1.0242

    227601 COLON 138.00 0.9754 0.9971 0.9748 0.9958

    227700 SAMBOAN 138.00 0.9743 1.0043 0.9694 1.0035

    235500 BACOLOD 69.000 0.9970 1.0326 1.0006 1.0304

    Table 16. 2016 Voltage Assessment (Peak, N-1 Loading)

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    28/116

    247200 DINGLE 138.00 1.0045 1.0210 1.0033 1.0203

    247700 CNCPCION 138.00 1.0149 1.0282 1.0140 1.0280

    Monitored Substations

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    Min Max Min Max

    3 [NPHS_HI 138.000] 0.9612 1.0155

    227601 COLON 138.00 0.9999 1.0132 0.9973 1.0107

    227700 SAMBOAN 138.00 0.982 1.0042 0.9716 1.0028

    235500 BACOLOD 69.000 0.964 1.0245 0.9574 1.0195

    235501 BACOLOD 69.000 0.964 1.0245 0.9574 1.0195

    237100 PONDOL 138.00 0.9888 1.0067 0.9862 1.0046

    237101 PONDOL 138.00 0.9879 1.0067 0.9853 1.0046

    237200 AMLAN HI 138.00 0.9879 1.0027 0.9853 1.0003

    237201 AMLAN SP 138.00 0.9879 1.0027 0.9853 1.0003

    237300 MAB HI 138.00 0.9805 1.01 0.9838 1.0075

    237400 KABANKAL 138.00 0.9801 1.0153 0.9777 1.0125

    237500 BACOLOD 138.00 0.9675 1.0199 0.9613 1.0155

    237800 EBMAG1 138.00 0.9901 1.0279 0.9866 1.0262

    237801 EBMAG2 138.00 0.9689 1.0287 0.9627 1.0259

    247100 BTC VIEJ 138.00 1.0054 1.0301 1.0046 1.0275

    247200 DINGLE 138.00 0.9941 1.0168 0.9975 1.0154

    247700 CNCPCION 138.00 1.0221 1.0371 1.0217 1.0355

    5.  FAULT LEVEL ANALYSIS 

    Table 17. 2021 Voltage Assessment (Peak, N-1 Loading)

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    29/116

    Substation

    Peak Load Condition

    Without

    Silay Solar

    With

    Silay Solar

    2016 2021 2016 2021

    3 [NPHS_HI 138.000] N/A 13,807.40 N/A 13,540.00

    237500 [BACOLOD 138.00] 8,279.20 8,143.70 8,361.50 8,009.80

    235501 [BACOLOD 69.000] 10,118.20 9,956.30 10,200.30 9,779.30

    235500 [BACOLOD 69.000] 10,118.20 9,956.30 10,200.30 9,779.30

    237800 [EBMAG1 138.00] 6,700.40 6,613.40 6,730.80 6,472.00

    237801 [EBMAG2 138.00] 9,896.80 9,761.90 10,025.70 9,658.50

    247100 [BTC VIEJ 138.00] 10,450.30 10,307.70 10,599.50 10,218.90

    247700 [CNCPCION 138.00] 9,917.10 9,806.70 10,073.60 9,773.70

    247200 [DINGLE 138.00] 10,987.80 10,858.90 11,179.00 10,780.30

    237400 [KABANKAL 138.00] 5,771.00 5,701.80 5,759.00 5,578.90

    237300 [MAB HI 138.00] 5,737.40 5,679.60 5,712.20 5,559.60

    237200 [AMLAN HI 138.00] 8,287.90 8,227.60 8,279.20 8,111.80

    237201 [AMLAN SP 138.00] 8,287.90 8,227.60 8,279.20 8,111.80

    237100 [PONDOL 138.00] 7,434.40 7,379.90 7,417.20 7,266.50

    227700 [SAMBOAN 138.00] 7,453.70 7,388.90 7,448.20 7,273.00

    227601 [COLON 138.00] 20,813.60 20,750.50 22,803.90 22,552.80

    Short Circuit MVA and X/R

    at Solar 69kV Bus

    Peak Load Condition2016 2021

    MVA X/R MVA X/R

    1,650.15 4.8616 1,618.19 4.43667

    Table 18. Short Circuit Rating of Selected Substations in the Grid

    Table 19. Short Circuit MVA at Power Plant S/S (Peak Loading)

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    30/116

    6. STABILITY ASSESSMENT

    Stability analysis assessed the impact of the project to the transient stability

    performance of the grid. The analysis was based on the assumptions and methodology

    described in the previous sections. The stability plots are included in the Appendices.

    The 3-phase faults were applied on transmission line segments followed by

    tripping/outage of the segments at normal and delayed clearing times.

    The segments where faults were applied are as follows:

    1.  Fault at Solar Hi-Bacolod 138 kV Line with Tripping

    2.  Fault at Bacolod-EBMAG1 138 kV Line with Tripping

    3. 

    Fault at Bacolod-EBMAG2 138 kV Line with Tripping4.  Fault at Bacolod-Kabankalan 138 kV Line with Tripping

    5.  Fault at Bacolod 138/69 kV Transformer (T2) with Tripping

    6. 

    Fault at Bacolod-BRGS TAP 69 kV Line with Tripping

    7.  Fault at Bacolod 138/69 kV Transformer (T1) with Tripping

    8.  Fault at Kabankalan-Mabinay HI 138 kV Line with Tripping

    9. 

    Fault at Amlan HI-Mabinay HI 138 kV Line with Tripping

    Bus faults applied to the system are as follows:

    1.  Bus Fault at NPHS_HI 138 kV Bus (3)

    2. 

    Bus Fault at BACOLOD 138 kV Bus (237500)

    3.  Bus Fault at EBMAG1 138 kV Bus (237800)

    4. 

    Bus Fault at EBMAG2 138 kV Bus (237801)

    5 Bus Fault at KABANKAL 138 kV Bus (237400)

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    31/116

    The results of the stability simulation indicated acceptable response of the system

    parameters with the proposed facility integrated, damping mostly within the first ten

    (10) seconds after the application of fault. The summary of dynamic stability

    simulations is shown in Table 20 for scenarios with the power plant.

    Applied Fault

    Status of Grid

    2016 Base Case 2021 Base Case

    Normal

    Clearing

    Delayed

    Clearing

    Normal

    Clearing

    Delayed

    Clearing

    BUS FAULTS

    1. 

    Bus Fault at NPHS_HI 138 kV Bus (3) Stable Stable Stable Stable

    2.  Bus Fault at BACOLOD 138 kV Bus (237500)Stable Stable Stable Stable

    3. 

    Bus Fault at EBMAG1 138 kV Bus (237800)Stable Stable Stable Stable

    4.  Bus Fault at EBMAG2 138 kV Bus (237801)Stable Stable Stable Stable

    5.  Bus Fault at KABANKAL 138 kV Bus (237400)Stable Stable Stable Stable

    6. 

    Bus Fault at MAB HI 138 kV Bus (237300)Stable Stable Stable Stable

    7.  Bus Fault at AMLAN SP 138 kV Bus (237201)Stable Stable Stable Stable

    8. 

    Bus Fault at DINGLE 138 kV Bus (247200) Stable Stable Stable Stable

    LINE FAULTS

    1.  Fault at Solar Hi-Bacolod 138 kV Line with TrippingStable Stable Stable Stable

    2 F lt t B l d EBMAG1 138 kV Li ith T i i

    Table 20. Summary of Dynamic Stability Simulations with Power Plant

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    32/116

    6.  Fault at Bacolod-BRGS TAP 69 kV Line with

    Tripping Stable Stable Stable Stable

    7. 

    Fault at Bacolod 138/69 kV Transformer (T1) with

    Tripping Stable Stable Stable Stable

    8. 

    Fault at Kabankalan-Mabinay HI 138 kV Line with

    Tripping Stable Stable Stable Stable

    9. 

    Fault at Amlan HI-Mabinay HI 138 kV Line with

    Tripping Stable Stable Stable Stable

    7. 

    FREQUENCY ASSESSMENT 

    Frequency assessment evaluates if the loss of the proposed power plant will not cause

    the frequency to drop below 59.4 Hz frequency limit set by PGC. For 2016 and 2021

    base cases, the frequency will not fall as low as 59.4 Hz. The outage of the proposed

    power plant will not result to Automatic Load Dropping (ALD). Figure 7 and Figure

    8 shows the results of frequency assessments for 2016 and 2021 base cases respectively.

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    33/116

    Figure 7. Frequency Assessment, 2016 Peak Base Case

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    34/116

    8. SUMMARY AND CONCLUSIONS 

    This study was conducted to assess the impact of the proposed 50 MW Felisa Solar

    Power Project on the reliability, stability and operating characteristics of the Visayas

    Grid. Steady state, stability and short-circuit conditions were analyzed. Proposed

    connection for this project is a direct connection to Bacolod 138 kV Substation.

    Steady state assessment with the project in-service showed no significant voltage or

    thermal violations of reliability criteria. Considering the priority dispatch of

    intermittent RE Generators, thermal loading of elements in the grid will remain within

    PGC required limits.

    Short circuit analyses concluded that the project did not alter adversely the short

    circuit duties of the baseline system.

    Transient stability assessment simulated a set of faults. None of the faults tested

    showed unstable response of the system with the project integrated.

    Frequency assessment showed that the system frequency will not drop as low as 59.4

    Hz with the outage of the proposed power plant. Automatic Load Dropping is not

    expected during this loss-of-generation scenario.

    As a general conclusion, this System Impact Study revealed that the addition of NPSI’s

    first project phase, the 50 MW Felisa Solar Power Project has no significant system

    impact to the stability, reliability, and operating characteristics of the Visayas Grid.

    The proposed project could be safely and reliably integrated to Visayas. Subsequent

    phases of the project will be implemented upon NGCP’s reinforcement of thesubmarine interconnection.

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    35/116

    APPENDICES 

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    36/116

    Appendix A

    2016 Bus Fault Normal Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    37/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    38/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    39/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    40/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    41/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    42/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    43/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    44/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    45/116

    Appendix B

    2016 Bus Fault Delayed Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    46/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    47/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    48/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    49/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    50/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    51/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    52/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    53/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    54/116

    Appendix C2016 Line Fault Normal Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    55/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    56/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    57/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    58/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    59/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    60/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    61/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    62/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    63/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    64/116

    Appendix D2016 Line Fault Delayed Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    65/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    66/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    67/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    68/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    69/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    70/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    71/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    72/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    73/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    74/116

    Appendix E2021 Bus Fault Normal Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    75/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    76/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    77/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    78/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    79/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    80/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    81/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    82/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    83/116

    Appendix F2021 Bus Fault Delayed Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    84/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    85/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    86/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    87/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    88/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    89/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    90/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    91/116

    Appendix G

    2021 Li F l N l Cl i

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    92/116

    2021 Line Fault Normal Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    93/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    94/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    95/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    96/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    97/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    98/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    99/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    100/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    101/116

    Appendix H

    2021 Line Fault Delayed Clearing

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    102/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    103/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    104/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    105/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    106/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    107/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    108/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    109/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    110/116

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    111/116

    Appendix I

    Power Flow Plots 

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    112/116

    2016 Peak Base Case, Normal Loading, Without the Proposed Plant

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    113/116

     

    2016 Peak Base Case, Normal Loading, With the Proposed Plant

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    114/116

     

    2021 Peak Base Case, Normal Loading, Without the Proposed Plant

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    115/116

     

    2021 Peak Base Case, Normal Loading, With the Proposed Plant

  • 8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf

    116/116