Upload
negros-solar-ph
View
221
Download
0
Embed Size (px)
Citation preview
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
1/116
Draft Report
System Impact Study Report
50 MW Felisa Solar Power Project
Prepared for:
By:
Negros PH Solar Inc.
Barangay Felisa, Mansilingan, Bacolod City
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
2/116
EXECUTIVE SUMMARY
This System Impact Study (SIS) is conducted for the 50 MW Felisa Solar Power
Project of Negros Ph Solar Inc. (NPSI) in Brgy. Felisa Bacolod City. The proposed
connection for this project is a direct connection to Bacolod 138 kV Substation.
The project currently has a 200 MW capacity endorsed by the Department of Energy
(DOE) over phases. The developers have since identified suitable land sites and havemade the requisite arrangements with the landowners for long-term leases. Various
irradiation, flood, topography and soil studies have already been conducted with
positive results. In addition many of the local and national approvals and permits
have since been obtained including local LGU endorsements. Technical layouts and
routing plans have also been identified and secured.
Currently there might be some “anticipated constraint” in the submarine
interconnection between Negros and Cebu islands due to various projects being
planned for but many of which may not get implemented. In light of this ‘constraint”
the capacity of the project was reduced to 50 MW for this current phase for ease of
implementation.
This project has been developed and structured to allow for a quick expansion of
another 60 MW in Phase II. The key milestone for this expansion would be the
alleviation of the potential congestion along the Cebu-Panay submarine cable. This
alleviation would be evident when either the submarine cable is reinforced or when the
various other projects included in the base data is formally terminated.
In December 2014, Italy's Prysmian was awarded this US$111 million project by the
NGCP for the design, supply, installation, and commissioning of a submarine power
cable link to connect Negros and Panay islands in the Philippines. The CNP-1 cable
connection is the first stage of a larger development plan by NGCP, aimed at
h C b N d P l d h h d h h
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
3/116
Magalona on the Negros side. Delivery and commissioning is scheduled for the first
half of 2016. Phase II (60MW) of the solar plant will be implemented after CNP-1 iscommissioned.
In addition, in April 2015 NGCP announced plans to invest P1.6 billion to upgrade a
transmission facility in Cebu that forms part of a broader Visayan backbone project to
implement the Cebu substation 230 kilovolt (kV) upgrade project, this project
represents the second stage of the Cebu-Negros-Panay (CNP) 230 kV backbone project
further strengthening the grid in the Visayas. NGCP’s CNP project is generally
intended to accommodate all additional capacity from new power plants that will be
built in the Visayas.
With the anticipated alleviation in congestion, NPSI will be implementing the 60 MW
Phase II expansion of this solar in the second half of 2016 and request that this be
recognized for planning purposes.
Description Phase I
Phase II
(once CNP-1 is
completed or
when capacity
avails itself)
Size MW 50.00 60.00
Time Frame 2015/2016 2016/2017
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
4/116
This study was performed in accordance with the Philippines Grid Code (PGC) and
NGCP requirements. The purposes of this study are as follows:
1. Analyze the steady-state, stability, and short circuit conditions of the grid with
the project;
2. Determine any upgrades to the transmission system that would be required to
mitigate any adverse impacts that the project could otherwise pose on the
reliability and operating characteristics of the transmission system inaccordance with the PGC, NGCP standards and generally accepted
international transmission utility practices;
3.
Determine any upgrades required to mitigate any degradation to transmission
transfer capability; and
4. Determine any upgrades required to mitigate any degradation to system
dynamic stability.
The primary area of concern of this study is the area around NGCP’s Bacolod
Substation. Generated power from the proposed power plant will be transmitted to
Visayas grid through this substation.
In addition to the standard requirements of the PGC, the ERC had issued Resolution
No. 7 Series of 2013 imposing new requirements for intermittent power plants such as
this project. This proposed power plant should comply with those requirements,
compliance thereto should be demonstrated by field tests during testing and
commissioning.
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
5/116
S TEADY S TATE
Steady state thermal and voltage analyses were conducted to examine the comparative
system performance with and without the proposed project. The baseline performance
is based on the system without the proposed project. System performance was re-
evaluated with the project and compared with the baseline system. This approach
exposes the impact of the project on the system utilizing the criteria set by the PGC.
Steady state analysis was evaluated using a scenario where power plants at close
proximity to the project were dispatched to its maximum feasible levels for years 2016
and 2021. Peak load for 2016 and 2021 were respectively, 1,854.8 MW and 2,279.5
MW. Simulation at this dispatch scenario enabled the examination of the transmission
system to reliably operate with the proposed project integrated to the system.
Based on the steady state results the project’s connection to the grid poses no
significant adverse impact on the reliability and operating characteristics of Visayas
grid. There was no significant voltage or thermal violations of reliability criteria
associated with the entry of the project considering its priority dispatch incentive
under the RE Law.
S TABILITY
This evaluation consisted of application of faults on the system with the project using
peak base cases. The dynamic stability of the system during and after these faulted
conditions should conform to the requirements of the PGC. In addition, voltage,
frequency and power fluctuations or oscillations should dampen within the prescribedperiod. Machine angle should also exhibit acceptable coherence.
In all tested fault conditions the project would pose no significant adverse impact on
the stability of the system.
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
6/116
S HORT C IRCUIT
Short-circuit analysis was conducted to determine the impact of the project on the
existing fault current levels in all substations. In this study, it was assumed that fault
duty of the circuit breakers installed in the system are as follows:
Simulation results indicate that the entry of the proposed project will not result to
fault levels beyond the fault duties of the existing circuit breakers.
C ONCLUSION
This study revealed that the addition of NPSI’s Phase I, the 50 MW Felisa Solar Power
Project has no significant impact on the reliability, stability and operating
characteristics of the Visayas power transmission system.
The proposed power plant could be safely and reliably integrated to Visayas grid.
Phase II 60 MW of NPSI project will be implemented once CNP-1 is commissioned or
when there is capacity in the grid when other projects are do not materialize.
Volage Level
Rated Short
CircuitCurrent (kA)
69kV 230 kV 40
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
7/116
TABLE OF CONTENTS
Executive Summary
Steady State
Stability
Frequency Assessment
Short Circuit
Conclusion
1. Background Information ................................................................................................. 10
2. Study Assumptions ......................................................................................................... 12
A. Demand Forecast ..................................................................................................... 12
B. Generation Expansions ................................................................................................ 12
C. Transmission Expansions ......................................................................................... 14
D. Grid Code Requirements ......................................................................................... 15
3. Proposed Connection Arrangement and System Modelling ............................................ 19
4. Load Flow Assessment .................................................................................................... 23
A. Thermal Assessment – Adequacy in Normal Conditions (Peak Conditions) ........... 24
B. Thermal Assessment – Adequacy in Single Outage Conditions (Peak Conditions) ..... 25
C. Voltage Assessment in Normal Conditions (Peak) .................................................. 26
D. Voltage Assessment in Single Outage Condition (Peak Conditions) ....................... 27
5. Fault Level Analysis ....................................................................................................... 28
6. Stability Assessment ....................................................................................................... 30
7. Frequency Assessment .................................................................................................... 32
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
8/116
LIST OF TABLES
Table 1. Demand Projections for Visayas ............................................................................. 12
Table 2. Generator Capacity Additions for Visayas ............................................................. 13
Table 3. Power Circuit Breaker Fault Duty Rating ............................................................. 15
Table 4. Requirements at Different Frequency Range .......................................................... 17
Table 5. Lumped Generator Specifications ........................................................................... 20
Table 6. Generator Transformer Data .................................................................................. 21
Table 7. Transmission Line Data .......................................................................................... 21
Table 8. Dynamics Data for 50 MW Lumped Generator Units ............................................ 22
Table 9. Dynamics Data for the Electrical Controls ............................................................. 23
Table 10. 2016 Thermal Assessment (Peak, Normal Loading) ............................................. 24
Table 11. 2021 Thermal Assessment (Peak, Normal Loading) ............................................. 24
Table 12. 2016 Thermal Assessment (Peak, N-1 Loading) ................................................... 25
Table 13. 2021 Thermal Assessment (Peak, N-1 Loading) ................................................... 25
Table 14. 2016 Voltage Assessment (Peak, Normal Loading) ............................................... 26
Table 15. 2021 Voltage Assessment (Peak, Normal Loading) ............................................... 26
Table 16. 2016 Voltage Assessment (Peak, N-1 Loading) ..................................................... 27
Table 17. 2021 Voltage Assessment (Peak, N-1 Loading) ..................................................... 28
Table 18. Short Circuit Rating of Selected Substations in the Grid ..................................... 29
Table 19. Short Circuit MVA at Power Plant S/S (Peak Loading) ..................................... 29
Table 20. Summary of Dynamic Stability Simulations with Power Plant ............................ 31
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
9/116
LIST OF FIGURES
Figure 1. Generation Capacity Additions in Visayas ............................................................ 13
Figure 2. Transmission Expansion Projects in Visayas ......................................................... 14
Figure 3. Low Voltage Withstand Capability Requirement for Large Photovoltaic Systems 18
Figure 4. Connection Scheme for the Project ....................................................................... 19
Figure 5. Geographic Location of the Project ....................................................................... 20
Figure 6. Equivalent Model of the Grid in the Vicinity of the Project ................................. 22
Figure 7. Frequency Assessment, 2016 Peak Base Case ....................................................... 33
Figure 8. Frequency Assessment, 2021 Peak Base Case ....................................................... 33
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
10/116
1. BACKGROUND INFORMATION
Negros Ph Solar Inc. (NPSI) has embarked on developing this project by committing
significant resources and time to identify and secure key project specifics to ensure
project viability prior to applying for the various government permits and approvals.
This project has been under-development for the last 6 months with the proper siteselection and technical evaluation and local stakeholders’ engagement and relationship
building being developed to ensure project viability. The initial findings are very
optimistic. Necessary government permits were already secured.
This approach allows all the stakeholders, DOE, NGCP, Landowners, LGU’s, etc. to
have better comfort and visibility that our Service Contract will crystalize into a real
project and not remain “in development” for years.
NPSI is a wholly owned Filipino corporation and was set up to fully focus on developing
the Philippine Solar market. The founder Ms. Maricel Montfort, a highly successful
native of Cadiz and currently residing in Bacolod and Manila, is a long-standing citizen
who has had extensive working experience abroad and has returned back to the
Philippines to take an active part in improving the lives of the local Filipinos through
various infrastructure projects. Ms. Montfort is currently active with several large
infrastructure and social developments throughout the Philippines. These include
medical facilities, orphanages, water-treatment/purification projects and land &
property investments. Being a very successful business lady, she is able to fully fund
the professional and proper development of these projects.
NPSI has identified Bacolod City as a suitable site for the Solar project. Bacolod has
a stable climate with adequate sunlight throughout the year and minimal risk of heavy
typhoons or flooding. Land is plentiful and the local government agencies are
supportive of such an initiative
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
11/116
Land Status:
a) Identified and secured approximately 150 hectares with the landowners. Many
of the landowners are prominent local business people with good local standing.
Land Options have been signed for most of them and the rest will be complete
shortly and landowners are backing this project fully. NPSI has very good
relationships with all the landowners. In total NPSI aims to secure
approximately 280 hectares to build up to 200 MW.
b) NPSI had engaged professionals to conduct
•
Irradiation Studies
• Flood studies
•
Topographical surveys• Soil studies
• Connection routing and
• Plant layout design
The site has ideal road access and is relatively flat with little flood risk. The
lands will not be an inconvenience any inhabitants. The landlords havecommitted to ensure the site will be problem free and we will engage their local
individuals where possible.
c) The lands identified are outside the CARP jurisdiction and we have obtained
proper legal advice as well as advice from the local LGU’s on the proper
procedure to ensure that the site is Solar ready. This has already been factored
in our evaluation.
d) The land titles have also been checked for any risk of foreclosure or
encumbrances being attached.
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
12/116
The proposed connection would involve construction of approximately 3.5 km 138 kV
transmission line, a take-off substation at the power plant site and modifications at a
bay in Bacolod Substation to accommodate entry of the proposed power plant.
Conductors for this line should be 795 MCM ACSR equipped with appropriate
communication facility to convey revenue meter reading to NGCP’s Bacolod
Substation.
2.
STUDY ASSUMPTIONS
A. DEMAND FORECAST
Based on the 2013 Transmission Development Plan (TDP), there would relatively be
a significant increase in demand in Visayas Grid. Table 1 shows the demand
projections for the entire grid. Of greater interest for this proposed project is the
demand in Negros Island where the proposed facility will be injecting its power to the
grid. Bacolod Substation will be the main corridor of this project.
B. GENERATION EXPANSIONS
Table 1. Demand Projections for Visayas
Source: 2013 Transmission Development Plan
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
13/116
Figure 1. Generation Capacity Additions in Visayas
Table 2. Generator Capacity Additions for Visayas
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
14/116
C. TRANSMISSION EXPANSIONS
Major developments in Negros island included in the 2013 TDP are as follows:
1. Negros-Panay Interconnection Uprating
2. Negros V Transmission Line Project
3.
Visayas Substation Expansion I (Kabangkalan 1 x 50 MVA)
4.
Visayas Substation Reliability I (Amlan 1 x 50 MVA, Bacolod 1 x 100 MVA
and Cadiz 1 x 50 MVA)
These proposed developments shown in Figure 2 as well as generation expansions were
included in the base cases and were considered in the assessments.
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
15/116
D. GRID CODE REQUIREMENTS
The proposed project’s performance was evaluated based on the criteria set by the
Philippine Grid Code, utilizing grid dispatch scenario where power plants near the
project were set at maximum dispatch to reflect the worst impact of the project to the
grid. Steady state voltage and thermal analyses examined system performance without
the proposed project in order to establish a baseline data. System performance was
re-evaluated with the project and compared with the previous baseline performance todemonstrate the impact of the project on area transmission reliability.
The voltage limits adopted in this study were in compliance with the PGC which
requires that during normal and single outage contingency conditions, the voltage
should be within the range of 0.95 to 1.05 per unit. For the thermal limits, normal
thermal ratings shall not be violated under all-lines-in and single outage contingency
conditions. The steady state analysis was performed with both pre-contingency and
post-contingency solution parameters that allow adjustment of load tap-changing
transformers (LTCs), static var devices (SVDs) including switched capacitors and
phase angle regulators (PARs).
For short circuit studies, resulting three phase fault should not exceed the levels shown
in Table 3. These ratings are the standard fault duty rating of circuit breakers
connected to the grid.
Voltage Level
Rated Short Circuit Current
(kA)
69kV 230 kV 40
Table 3. Power Circuit Breaker Fault Duty Rating
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
16/116
1. The Grid remains stable after any Single Outage Contingency for all forecasted
Load conditions; and
2.
The Grid remains controllable after a Multiple Outage Contingency. In the
case of Grid separation, no total blackout should occur in any Island Grid.
In this study however, only stability under single outage contingency conditions were
evaluated.
Applied faults were cleared (normal clearing) in compliance with the requirements of
the PGC Section 4.5.2.3 as follows:
1. 85 ms for 500 kV;
2. 100 ms for 230 kV and 138 kV; and
3.
120 ms for voltages less than 138 kV
Delayed clearing were simulated in accordance with the requirements of the PGC
which states:
“The circuit breaker fail protection shall be designed to initiate the tripping of
all the necessary electrically-adjacent circuit breakers and to interrupt the faultcurrent within the next 50 milliseconds, in the event that the primary protection
system fails to interrupt the fault current within the prescribed Fault Clearance
Time”
In addition to the standard PGC requirements, the Energy Regulatory Commission
(ERC) had issued Resolution No. 7 series of 2013 entitled “Resolution Adopting and
Approving Addendum to Amendment No. 1 of the Philippine Grid Code, Establishing
the Connection and Operational Requirements for Variable Renewable Energy (VRE)
Generating Facilities”. Under Article II Section 2 of this addendum, additional
requirements for large photovoltaic generation systems were prescribed as follows:
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
17/116
Generating Limit Power Output
The proposed power plant should continuously supply active and reactive power
depending on the availability of primary source within the frequency range of 59.7-
60.3 Hz. It should be capable of interchanging reactive power at connection point
within ±5% voltage variation. Outside this range and up to ±10% voltage variation,
a reduction in active and/or reactive power may be allowed up to 5% of the generator’s
declared data.
Frequency Withstand Capability
Table 4 shows the allowable power plant frequency response.
Reactive Power Capability
The proposed power plant should be capable of supplying reactive power output at its
Table 4. Requirements at Different Frequency Range
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
18/116
Performance during Network Disturbances
The allowable voltage ride-through for the power plant is shown in Figure 3.
Voltage Control System
The proposed power plant shall be capable of contributing voltage control bycontinuous regulation of the reactive power supplied to the grid under power factor
control mode wherein power factor is maintained at the connection point or voltage
control mode wherein voltage at the high voltage busbar of the proposed power plant
is maintained at a constant set-point.
Figure 3. Low Voltage Withstand Capability Requirement for Large Photovoltaic
Systems
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
19/116
Power Quality
With the proposed power plant connected to the system and under normal operating
state, the Flicker Severity and Total Harmonic Distortion at the connection point shall
not exceed the values prescribed by the PGC
The proposed power plant will demonstrate compliance with these requirements
through testing to be conducted pursuant to Section 3.2.3.
3. PROPOSED CONNECTION ARRANGEMENT AND SYSTEM
MODELLING
In Figure 4 is shown the proposed connection for the project. This connection consistsof 138 kV transmission line directly connected to Bacolod 138 kV Substation. The
project will be equipped with a take-off substation at the power plant site connected
to a main bay at Bacolod Substation. The project’s geographic location is shown in
Figure 5.
Proposed Power Plant
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
20/116
The technical specifications used to model the proposed connection assets of NPSI
solar power plant project are shown in Table 5 to Table 7.
Power
C biliReactive Capability at
R k
Table 5. Lumped Generator Specifications
Figure 5. Geographic Location of the Project
3.5 km 138 kV transmission line
Take-off Substation
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
21/116
The grid model or base cases used in this study for years 2016 and 2021 were provided
by NGCP. Both base cases were derived from the Transmission Development Plan
and considered transmission line and generator expansion plans for the period covered.The scenario represented was peak loading condition, maximizing dispatch of power
plants in the vicinity of the project. Off-peak scenarios were not considered in the
assessment since the proposed power plant is not expected to operate during off-peak.
To reflect the priority dispatch scenario in the model, dispatch of conventional
synchronous machines in Negros and Panay areas were slightly reduced. In actualapplication, these conventional plants’ dispatch will vary due to the intermittence of
the proposed power plant. Power plants with adjusted dispatch are as follows:
1.) Palinpinon Geothermal Power Plant (Negros)
Description Tap RatioPresent
Tap
MVA
Rating
Tap
StepsR (pu)
X (pu)
based on
System
MVA
Grid
Transformers
22/138
D/YCenter 65 5 0 0.178620
Line Name Type LengthRate
(MVA)R (pu) X (pu) B (pu)
NPSI take-off –
138 kV tapping
138 kV, 795
MCMACSR
3.5 km 196 0.001580 0.008740 0.002290
Table 6. Generator Transformer
Table 7. Transmission Line Data
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
22/116
The 50 MW generator was modeled as lumped unit using “PVGU1” in the dynamic
stability study while the electrical controls was modelled as “PVEU1”. Parameters
for the models are shown in Table 8 and Table 9 respectively. Other system dynamics
data were provided by NGCP.
Figure 6. Equivalent Model of the Grid in the Vicinity of the Project
Proposed 50 MW
Solar Power Plant
Table 8. Dynamics Data for 50 MW Lumped Generator Units
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
23/116
4. LOAD FLOW ASSESSMENT
The results of the simulation for thermal adequacy are presented in Sections 4.A. and
4.B. while that for the voltages are shown in Sections 4.C. and 4.D.
Under normal loading conditions, considering the priority dispatch of intermittent RE
Generators, thermal loading of elements in the grid will remain within PGC required
limits. The number of grid loading violations during single-outage contingency
Table 9. Dynamics Data for the Electrical Controls
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
24/116
A. THERMAL ASSESSMENT – ADEQUACY IN NORMAL CONDITIONS
(PEAK CONDITIONS)
The results of the simulations are given in Table 10 and Table 11 for the 2016 and
2021 base cases respectively.
Monitored ElementMVA
Rating
Peak Load Condition
Without
Silay Solar
With
Silay Solar
MVA % MVA %
1 Solar Hi-Bacolod 138 kV 196.00 N/A 50.90 25.97
2 Samboan-Pondol 138 kV 108.04 84.91 78.59 93.47 86.51
3 Pondol-Amlan 138 kV 196.00 84.72 43.22 93.26 47.584 Amlan Hi-Amlan SP 196.00 132.92 67.82 152.74 77.93
5 Amlan-Mabinay 138 kV 196.00 15.33 7.82 24.71 12.61
6 Kabankalan-Bacolod 138 kV 196.00 10.64 5.43 20.00 10.20
7 Bacolod-E. B. Magalona 138 kV L1 196.00 20.20 10.31 14.44 7.37
8 Bacolod-E. B. Magalona 138 kV L2 392.00 34.56 8.82 24.32 6.20
9 EB Magalona-Barotac Viejo 138 kV 108.00 49.57 45.90 44.02 40.76
10 Barotac Viejo-Dingle 138 kV 196.00 47.40 24.18 57.33 29.2511 Barotac Viejo-Concepcion 138 kV 392.00 95.44 24.35 90.28 23.03
Monitored ElementMVA
Rating
Peak Load Condition
Without
Silay Solar
With
Silay Solar
MVA % MVA %
1 Solar Hi-Bacolod 138 kV 196.00 N/A 50.94 25.99
2 Samboan Pondol 138 kV 108 04 69 60 64 42 89 32 82 67
Table 10. 2016 Thermal Assessment (Peak, Normal Loading)
Table 11. 2021 Thermal Assessment (Peak, Normal Loading)
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
25/116
B. THERMAL ASSESSMENT – ADEQUACY IN SINGLE OUTAGE
CONDITIONS (PEAK CONDITIONS)
Thermal N-1 adequacy assessments are given in and Table 12 and Table 13 for 2016
and 2021 base cases. The quantity of grid loading violations during this contingency
conditions essentially remained the same.
Monitored ElementMVA
Rating
Peak Load Condition
Without
Silay Solar
With
Silay Solar
MVA % MVA %
1 Solar Hi-Bacolod 138 kV 196.00 N/A 50.97 26.01
2 Samboan-Pondol 138 kV 108.04 165.96 153.61 182.54 168.963 Pondol-Amlan 138 kV 196.00 164.93 84.15 181.44 92.57
4 Amlan Hi-Amlan SP 196.00 212.78 108.56 232.55 118.65
5 Amlan-Mabinay 138 kV 196.00 55.29 28.21 65.46 33.40
6 Kabankalan-Bacolod 138 kV 196.00 51.14 26.09 61.64 31.45
7 Bacolod-E. B. Magalona 138 kV L1 196.00 85.03 43.38 57.49 29.33
8 Bacolod-E. B. Magalona 138 kV L2 392.00 64.93 16.56 54.67 13.95
9 EB Magalona-Barotac Viejo 138 kV 108.00 98.30 91.02 69.33 64.1910 Barotac Viejo-Dingle 138 kV 196.00 94.75 48.34 116.50 59.44
11 Barotac Viejo-Concepcion 138 kV 392.00 190.35 48.56 180.17 45.96
Monitored ElementMVA
Rating
Peak Load Condition
Without
Silay Solar
With
Silay Solar
MVA % MVA %
1 S l Hi B l d 138 kV 196 00 N/A 50 94 26 09
Table 13. 2021 Thermal Assessment (Peak, N-1 Loading)
Table 12. 2016 Thermal Assessment (Peak, N-1 Loading)
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
26/116
C. VOLTAGE ASSESSMENT IN NORMAL CONDITIONS (PEAK)
Voltage assessment conducted on the system indicated that the entry of the project
will not result to voltage violations in the grid. Table 14 and Table 15 present the
results of voltage assessment for the 2016 and 2021 base cases respectively.
Monitored Substations
Peak Load Condition
Without
Silay Solar
With
Silay Solar
(kV) (p.u.) (kV) (p.u.)
3 [NPHS_HI 138.000] N/A 1.0142 139.95
227601 COLON 138.00 136.80 0.9913 0.9903 136.66
227700 SAMBOAN 138.00 137.31 0.9950 0.9917 136.85
235500 BACOLOD 69.000 70.46 1.0212 1.0196 70.35
235501 BACOLOD 69.000 70.46 1.0212 1.0196 70.35
237100 PONDOL 138.00 138.48 1.0035 1.0017 138.23
237101 PONDOL 138.00 138.48 1.0035 1.0017 138.23
237200 AMLAN HI 138.00 137.99 0.9999 0.9984 137.78
237201 AMLAN SP 138.00 137.99 0.9999 0.9984 137.78
237300 MAB HI 138.00 138.86 1.0062 1.0042 138.58
237400 KABANKAL 138.00 139.35 1.0098 1.0078 139.08
237500 BACOLOD 138.00 140.18 1.0158 1.0143 139.97
237800 EBMAG1 138.00 140.90 1.0210 1.0213 140.94
237801 EBMAG2 138.00 141.06 1.0222 1.0211 140.91
247100 BTC VIEJ 138.00 141.20 1.0232 1.0217 140.99
247200 DINGLE 138.00 140.03 1.0147 1.0134 139.85
247700 CNCPCION 138.00 141.51 1.0254 1.0244 141.37
Table 14. 2016 Voltage Assessment (Peak, Normal Loading)
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
27/116
235501 BACOLOD 69.000 1.0074 69.51 1.0044 69.30
237100 PONDOL 138.00 1.0033 138.46 1.0003 138.04
237101 PONDOL 138.00 1.0033 138.46 1.0003 138.04237200 AMLAN HI 138.00 0.9991 137.88 0.9963 137.49
237201 AMLAN SP 138.00 0.9991 137.88 0.9963 137.49
237300 MAB HI 138.00 1.0032 138.44 0.9999 137.99
237400 KABANKAL 138.00 1.0052 138.72 1.0019 138.26
237500 BACOLOD 138.00 1.0084 139.16 1.0056 138.77
237800 EBMAG1 138.00 1.0183 140.53 1.0164 140.26
237801 EBMAG2 138.00 1.0215 140.97 1.0197 140.72247100 BTC VIEJ 138.00 1.0233 141.22 1.0216 140.98
247200 DINGLE 138.00 1.0107 139.48 1.0098 139.35
247700 CNCPCION 138.00 1.0330 142.55 1.0320 142.42
D.
VOLTAGE ASSESSMENT IN SINGLE OUTAGE CONDITION (PEAK
CONDITIONS)
Results of voltage assessment during contingency conditions are shown in Table 16
and Table 17 for the 2016 and 2021 base cases respectively. No deviations from the
PGC prescribed limits are expected upon the entry of the proposed project to the grid.
Monitored Substations
Peak Load Condition
Without
Silay Solar
With
Silay Solar
Min Max Min Max3 [NPHS_HI 138.000] N/A 0.9961 1.0242
227601 COLON 138.00 0.9754 0.9971 0.9748 0.9958
227700 SAMBOAN 138.00 0.9743 1.0043 0.9694 1.0035
235500 BACOLOD 69.000 0.9970 1.0326 1.0006 1.0304
Table 16. 2016 Voltage Assessment (Peak, N-1 Loading)
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
28/116
247200 DINGLE 138.00 1.0045 1.0210 1.0033 1.0203
247700 CNCPCION 138.00 1.0149 1.0282 1.0140 1.0280
Monitored Substations
Peak Load Condition
Without
Silay Solar
With
Silay Solar
Min Max Min Max
3 [NPHS_HI 138.000] 0.9612 1.0155
227601 COLON 138.00 0.9999 1.0132 0.9973 1.0107
227700 SAMBOAN 138.00 0.982 1.0042 0.9716 1.0028
235500 BACOLOD 69.000 0.964 1.0245 0.9574 1.0195
235501 BACOLOD 69.000 0.964 1.0245 0.9574 1.0195
237100 PONDOL 138.00 0.9888 1.0067 0.9862 1.0046
237101 PONDOL 138.00 0.9879 1.0067 0.9853 1.0046
237200 AMLAN HI 138.00 0.9879 1.0027 0.9853 1.0003
237201 AMLAN SP 138.00 0.9879 1.0027 0.9853 1.0003
237300 MAB HI 138.00 0.9805 1.01 0.9838 1.0075
237400 KABANKAL 138.00 0.9801 1.0153 0.9777 1.0125
237500 BACOLOD 138.00 0.9675 1.0199 0.9613 1.0155
237800 EBMAG1 138.00 0.9901 1.0279 0.9866 1.0262
237801 EBMAG2 138.00 0.9689 1.0287 0.9627 1.0259
247100 BTC VIEJ 138.00 1.0054 1.0301 1.0046 1.0275
247200 DINGLE 138.00 0.9941 1.0168 0.9975 1.0154
247700 CNCPCION 138.00 1.0221 1.0371 1.0217 1.0355
5. FAULT LEVEL ANALYSIS
Table 17. 2021 Voltage Assessment (Peak, N-1 Loading)
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
29/116
Substation
Peak Load Condition
Without
Silay Solar
With
Silay Solar
2016 2021 2016 2021
3 [NPHS_HI 138.000] N/A 13,807.40 N/A 13,540.00
237500 [BACOLOD 138.00] 8,279.20 8,143.70 8,361.50 8,009.80
235501 [BACOLOD 69.000] 10,118.20 9,956.30 10,200.30 9,779.30
235500 [BACOLOD 69.000] 10,118.20 9,956.30 10,200.30 9,779.30
237800 [EBMAG1 138.00] 6,700.40 6,613.40 6,730.80 6,472.00
237801 [EBMAG2 138.00] 9,896.80 9,761.90 10,025.70 9,658.50
247100 [BTC VIEJ 138.00] 10,450.30 10,307.70 10,599.50 10,218.90
247700 [CNCPCION 138.00] 9,917.10 9,806.70 10,073.60 9,773.70
247200 [DINGLE 138.00] 10,987.80 10,858.90 11,179.00 10,780.30
237400 [KABANKAL 138.00] 5,771.00 5,701.80 5,759.00 5,578.90
237300 [MAB HI 138.00] 5,737.40 5,679.60 5,712.20 5,559.60
237200 [AMLAN HI 138.00] 8,287.90 8,227.60 8,279.20 8,111.80
237201 [AMLAN SP 138.00] 8,287.90 8,227.60 8,279.20 8,111.80
237100 [PONDOL 138.00] 7,434.40 7,379.90 7,417.20 7,266.50
227700 [SAMBOAN 138.00] 7,453.70 7,388.90 7,448.20 7,273.00
227601 [COLON 138.00] 20,813.60 20,750.50 22,803.90 22,552.80
Short Circuit MVA and X/R
at Solar 69kV Bus
Peak Load Condition2016 2021
MVA X/R MVA X/R
1,650.15 4.8616 1,618.19 4.43667
Table 18. Short Circuit Rating of Selected Substations in the Grid
Table 19. Short Circuit MVA at Power Plant S/S (Peak Loading)
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
30/116
6. STABILITY ASSESSMENT
Stability analysis assessed the impact of the project to the transient stability
performance of the grid. The analysis was based on the assumptions and methodology
described in the previous sections. The stability plots are included in the Appendices.
The 3-phase faults were applied on transmission line segments followed by
tripping/outage of the segments at normal and delayed clearing times.
The segments where faults were applied are as follows:
1. Fault at Solar Hi-Bacolod 138 kV Line with Tripping
2. Fault at Bacolod-EBMAG1 138 kV Line with Tripping
3.
Fault at Bacolod-EBMAG2 138 kV Line with Tripping4. Fault at Bacolod-Kabankalan 138 kV Line with Tripping
5. Fault at Bacolod 138/69 kV Transformer (T2) with Tripping
6.
Fault at Bacolod-BRGS TAP 69 kV Line with Tripping
7. Fault at Bacolod 138/69 kV Transformer (T1) with Tripping
8. Fault at Kabankalan-Mabinay HI 138 kV Line with Tripping
9.
Fault at Amlan HI-Mabinay HI 138 kV Line with Tripping
Bus faults applied to the system are as follows:
1. Bus Fault at NPHS_HI 138 kV Bus (3)
2.
Bus Fault at BACOLOD 138 kV Bus (237500)
3. Bus Fault at EBMAG1 138 kV Bus (237800)
4.
Bus Fault at EBMAG2 138 kV Bus (237801)
5 Bus Fault at KABANKAL 138 kV Bus (237400)
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
31/116
The results of the stability simulation indicated acceptable response of the system
parameters with the proposed facility integrated, damping mostly within the first ten
(10) seconds after the application of fault. The summary of dynamic stability
simulations is shown in Table 20 for scenarios with the power plant.
Applied Fault
Status of Grid
2016 Base Case 2021 Base Case
Normal
Clearing
Delayed
Clearing
Normal
Clearing
Delayed
Clearing
BUS FAULTS
1.
Bus Fault at NPHS_HI 138 kV Bus (3) Stable Stable Stable Stable
2. Bus Fault at BACOLOD 138 kV Bus (237500)Stable Stable Stable Stable
3.
Bus Fault at EBMAG1 138 kV Bus (237800)Stable Stable Stable Stable
4. Bus Fault at EBMAG2 138 kV Bus (237801)Stable Stable Stable Stable
5. Bus Fault at KABANKAL 138 kV Bus (237400)Stable Stable Stable Stable
6.
Bus Fault at MAB HI 138 kV Bus (237300)Stable Stable Stable Stable
7. Bus Fault at AMLAN SP 138 kV Bus (237201)Stable Stable Stable Stable
8.
Bus Fault at DINGLE 138 kV Bus (247200) Stable Stable Stable Stable
LINE FAULTS
1. Fault at Solar Hi-Bacolod 138 kV Line with TrippingStable Stable Stable Stable
2 F lt t B l d EBMAG1 138 kV Li ith T i i
Table 20. Summary of Dynamic Stability Simulations with Power Plant
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
32/116
6. Fault at Bacolod-BRGS TAP 69 kV Line with
Tripping Stable Stable Stable Stable
7.
Fault at Bacolod 138/69 kV Transformer (T1) with
Tripping Stable Stable Stable Stable
8.
Fault at Kabankalan-Mabinay HI 138 kV Line with
Tripping Stable Stable Stable Stable
9.
Fault at Amlan HI-Mabinay HI 138 kV Line with
Tripping Stable Stable Stable Stable
7.
FREQUENCY ASSESSMENT
Frequency assessment evaluates if the loss of the proposed power plant will not cause
the frequency to drop below 59.4 Hz frequency limit set by PGC. For 2016 and 2021
base cases, the frequency will not fall as low as 59.4 Hz. The outage of the proposed
power plant will not result to Automatic Load Dropping (ALD). Figure 7 and Figure
8 shows the results of frequency assessments for 2016 and 2021 base cases respectively.
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
33/116
Figure 7. Frequency Assessment, 2016 Peak Base Case
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
34/116
8. SUMMARY AND CONCLUSIONS
This study was conducted to assess the impact of the proposed 50 MW Felisa Solar
Power Project on the reliability, stability and operating characteristics of the Visayas
Grid. Steady state, stability and short-circuit conditions were analyzed. Proposed
connection for this project is a direct connection to Bacolod 138 kV Substation.
Steady state assessment with the project in-service showed no significant voltage or
thermal violations of reliability criteria. Considering the priority dispatch of
intermittent RE Generators, thermal loading of elements in the grid will remain within
PGC required limits.
Short circuit analyses concluded that the project did not alter adversely the short
circuit duties of the baseline system.
Transient stability assessment simulated a set of faults. None of the faults tested
showed unstable response of the system with the project integrated.
Frequency assessment showed that the system frequency will not drop as low as 59.4
Hz with the outage of the proposed power plant. Automatic Load Dropping is not
expected during this loss-of-generation scenario.
As a general conclusion, this System Impact Study revealed that the addition of NPSI’s
first project phase, the 50 MW Felisa Solar Power Project has no significant system
impact to the stability, reliability, and operating characteristics of the Visayas Grid.
The proposed project could be safely and reliably integrated to Visayas. Subsequent
phases of the project will be implemented upon NGCP’s reinforcement of thesubmarine interconnection.
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
35/116
APPENDICES
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
36/116
Appendix A
2016 Bus Fault Normal Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
37/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
38/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
39/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
40/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
41/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
42/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
43/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
44/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
45/116
Appendix B
2016 Bus Fault Delayed Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
46/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
47/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
48/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
49/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
50/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
51/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
52/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
53/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
54/116
Appendix C2016 Line Fault Normal Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
55/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
56/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
57/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
58/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
59/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
60/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
61/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
62/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
63/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
64/116
Appendix D2016 Line Fault Delayed Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
65/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
66/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
67/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
68/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
69/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
70/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
71/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
72/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
73/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
74/116
Appendix E2021 Bus Fault Normal Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
75/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
76/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
77/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
78/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
79/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
80/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
81/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
82/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
83/116
Appendix F2021 Bus Fault Delayed Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
84/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
85/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
86/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
87/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
88/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
89/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
90/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
91/116
Appendix G
2021 Li F l N l Cl i
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
92/116
2021 Line Fault Normal Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
93/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
94/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
95/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
96/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
97/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
98/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
99/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
100/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
101/116
Appendix H
2021 Line Fault Delayed Clearing
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
102/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
103/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
104/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
105/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
106/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
107/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
108/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
109/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
110/116
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
111/116
Appendix I
Power Flow Plots
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
112/116
2016 Peak Base Case, Normal Loading, Without the Proposed Plant
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
113/116
2016 Peak Base Case, Normal Loading, With the Proposed Plant
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
114/116
2021 Peak Base Case, Normal Loading, Without the Proposed Plant
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
115/116
2021 Peak Base Case, Normal Loading, With the Proposed Plant
8/17/2019 SIS Negros Ph Solar Inc. 50 MW Solar Project.pdf
116/116