Fairway Design on Finnish CoastCouple of Case Studies
M.Sc.(Civ.Eng) Esa Sirki
FMA/Fairways Division
8/11/2019 Sirkia Fairway Design
2/24
Why is the fairway design an issue here?
Finnish coast is determined by four facts that makefairway design and construction different thanelsewhere:
1. Shallowness of coast
2. Wide archipelago
3. Rocky/bedrock bottom Finland has the oldestbedrock in Europe
4. Nowadays the cohesive materials are oftencontaminated
These facts leads to Long, curvy fairways
Lots and lots of AtoN
Expensive dredging
8/11/2019 Sirkia Fairway Design
3/24
8/11/2019 Sirkia Fairway Design
4/24
Other Finnish Specialties There is around 30 000 AtoN
Finnish special AtoNs:
Fixed side markers:
8/11/2019 Sirkia Fairway Design
5/24
Other Finnish Specialties There is around 30 000 AtoN
Finnish special AtoNs:
Leading lines and lights:
8/11/2019 Sirkia Fairway Design
6/24
Other Finnish Specialties There is around 30 000 AtoN
Finnish special AtoNs:
Ice Buoys
8/11/2019 Sirkia Fairway Design
7/24
Case Kustaanmiekka:
Gateway to HelsinkiSouthern Harbour
8/11/2019 Sirkia Fairway Design
8/24
8/11/2019 Sirkia Fairway Design
9/24
Fairway dimensions:
Minimum width: 80 m(3,27*B @ Kustaanmiekkastrait)
Sweeping depth 11,0 m
maximum draught 9,6 m;UKC of 1,4 meters
Vessels with larger draught
than design vessel areusually smaller ro-rovessels from southerncargo harbour
Case Kustaanmiekka:Gateway to Helsinki Southern Harbour
8/11/2019 Sirkia Fairway Design
10/24
Case Kustaanmiekka:Gateway to Helsinki Southern Harbour
Aluksen squat nopeuden funktiona
Gulievin menetelm, poikkileikkaustyyppi B
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0
Nopeus (solmua)
Squat(m)
Painuma(squat)vara Muu liikevara Klivara Haraustason alapuoleinen vesi Pohja SQUAT
8/11/2019 Sirkia Fairway Design
11/24
Kustaanmiekka strait challenging
alignment Fairway goes straight thru UN world heritage area ofSuomenlinna sea fortress
Fairway was built to current stage 1980s Sea bottom is bedrock need of underwater blasting inconstruction phase
Because of fortress, the width is very limited andalignment cannot be changed
Asymmetrical cross section leads to suction effectsbetween vessel and bedrock side banks
Navigational challenges
8/11/2019 Sirkia Fairway Design
12/24
8/11/2019 Sirkia Fairway Design
13/24
Green area > 12,0 m
Yellow 12,0 11,0 m
Red 11,0 10,0 m
Blue < 10,0 m
Sweeping depth 11,0 m(yellow is still safe)
8/11/2019 Sirkia Fairway Design
14/24
3D-image of Kustaanmiekka strait
Cross section is restricted channel or it may be definedeven as a canal
Leads to challenging navigational situations because ofsuctions caused by asymmetrical trench cross section
Most simulated single point on Finnish coast
Environmental facts do not allow improvements but
need of them has faded thanks to new Port of Vuosaari
8/11/2019 Sirkia Fairway Design
15/24
Next case: Rauma 10,0 m channel
Total fairway length is 26 km (14,4 M)
8/11/2019 Sirkia Fairway Design
16/24
8/11/2019 Sirkia Fairway Design
17/24
Area of interest - Kovankivet
160 m wide restricted channel
Excavated in bedrock
Trench height approx 10 m highest
Single most dangerous spot on Finnish coast
Asymmetrical cross section Multiple simulations done
Prevailing wind direction SW to NW
Several blackouts that has lead to groundings
AtoN equipment:
Leading lines with 7,2 m panels and high powerlights; 6 fixed markers; 5 ice buoys
8/11/2019 Sirkia Fairway Design
18/24
N
3D-Image of Kovankivet
8/11/2019 Sirkia Fairway Design
19/24
Design of Rauma Deepening
future project
New project that aims to deepening of Rauma fairway,
general design 2008 Aim is to deepen the fairway for vessels up to 12,0 m
draught
Alignment remains same, new minimum width 144 m
New sweeping depth of 14,0 / 13,5 m
Leads quite massive dredging of around 2 million cubicmeters, around 10% of rock
~500 000 m3 of polluted cohesive material that needs
special dumping ground or -reservoir Budget up to 40 M total (incl. port investments ~10 M)
High hopes to get new deepened channel running 2012
8/11/2019 Sirkia Fairway Design
20/24
Latest New Fairway Vuosaari
a Typical Finnish Approach Channel
Fairway was built to
new Port of Vuosaari2002-2004
Fairway leads fromHelsinki lighthouse to thePort of Vuosaari,
total 33 km (~18 M) 3 straight sections,all with leading lights
3 fixed side markers
23 ice buoys
All AtoN are lighted
Lights of buoys aresynchronized
8/11/2019 Sirkia Fairway Design
21/24
Vuosaari Approach Channel - design
Design Vessel:
Containership
L = 230 m
B = 33 m
T = 11,0 m
One lane traffic
in last 4 km
Fairway dimensions
Minimum width 200 m (6 B)
Radius of turn 1150 m
Sweeping depth 13,0 / 12,5 m
Dimensioning speed 15 / 12 kn
Aluksen squat nopeuden funktiona.Huuska-ICORELS, kertoimet 1.7, 2.0 ja 2.4.
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0Nopeus (solmua)
Squa
t,m
Painuma(squat)vara Muu liikevara Klivara Haraustason alapuoleinen vesi
SQUAT (Co = 1.7) SQUAT (Co = 2.0) SQUAT (Co = 2.4) Pohja
8/11/2019 Sirkia Fairway Design
22/24
Vuosaari Approach Channel last 5 km
Minimum width (200 m)
Waiting area
Possible other
channel, ifconsidered necessary
8/11/2019 Sirkia Fairway Design
23/24
Vuosaari Approach Channel
construction phase
Vuosaari approach channel was built by Wasa Dredging Oy
and Terramare Oyj.
Amount of excavation: soil ~500 000 m3, rock ~250 000 m3
Total budget 6 M