44
Dr. Ing. Luigi Vanfretti, Rujiroj Leelaruji, Wei Li, and Tetiana Bogodorova Docent and Assistant Professor Smart Transmission Systems Lab. Electric Power Systems Department KTH Royal Institute of Technology, Sweden E-mail: [email protected] Web: http://www.vanfretti.com Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Embed Size (px)

DESCRIPTION

•About the test systems:-The specifications used in this work have been proposed by B4-57.-The specifications used to define the test system are preliminary and will be reviewed by the B4 WGs.

Citation preview

Page 1: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Dr. Ing. Luigi Vanfretti,

Rujiroj Leelaruji, Wei Li, and Tetiana Bogodorova

Docent and Assistant Professor Smart Transmission Systems Lab.

Electric Power Systems Department KTH Royal Institute of Technology, Sweden

E-mail: [email protected] Web: http://www.vanfretti.com

Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and

Opal-RT

Page 2: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Acknowledgement

• The work presented here was carried out by three different PhD students:

- Wei Li (PSCAD)

- Tetiana Bogodorova (EMTP-RV)

- Rujiroj Leelaruji (Opal-RT Model: Matlab/Simulink/SPS + Lib.)

- They worked very hard for several weeks!

• We would like to thank the following persons for their support in using the models:

- Luc-Andre Gregoire (Opal-RT)

- Sebastien Dennetiere (RTE)

- Juan Carlos Garcia Alonso (Manitoba HVDC Research Center)

Page 3: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

To start

• Be nice… : “No one loves the messenger who brings bad

news”

• About the test systems:

- The specifications used in this work have been proposed by B4-57.

- The specifications used to define the test system are preliminary and will be reviewed by the B4 WGs.

• Exercise judgment

- Comparisons of highly detailed and complex models in three completely different software environments are difficult

- A ‘one-to-one’ agreement should not be expected

- All models can be improved, this study aims to show where improvement is needed

- We make no statements of what is right or wrong, we just present the results

- Even with the limitations of each of the current models, they are actually quite detailed and of high quality.

Page 4: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

To start

• Be nice… : “No one loves the messenger who brings bad

news”

• About the test systems:

- The specifications used in this work have been proposed by B4-57.

- The specifications used to define the test system are preliminary and will be reviewed by the B4 WGs.

• Exercise judgment

- Comparisons of highly detailed and complex models in three completely different software environments are difficult

- A ‘one-to-one’ agreement should not be expected

- All models can be improved, this study aims to show where improvement is needed

- We make no statements of what is right or wrong, we just present the results

- Even with the limitations of each of the current models, they are actually quite detailed and of high quality.

Page 5: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Outline

• Brief description of the models - Opal-RT (Matlab/Simulink + SimPowerSystems and eMegaSim from

Opal-RT)

- PSCAD from Manitoba HVDC Research Center

- EMTP-RV from PowerSys and EMTP DCG

• Models differences

• Simulation Studies

- Description and aim of the simulation studies

- Selected results (all results available for scrutiny)

• General simulation challenges when using the benchmark models

• Recommendations and Further Work

Page 6: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Brief Description of the Models – Cigre DC Grid Test System

Types of Conv. Controls

Droop Cntrl

Droop Cntrl P Cntrl

VF Cntrl

Not Specified DC-DC Conv.

P Cntrl

Droop Cntrl

Page 7: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Test System in Opal-RT (Layout from Hypersim)

No DC/DC converter

Embedded VBE model means that the detail MMC cell model is implemented but without the cell capacitor balancing control (see the OPAL-RT presentation)

Page 8: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Test System in Opal-RT (Top level model)

Page 9: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Subsystem of A1

MMC Converter

Subsystem A0 to A1

Test System in Opal-RT (Subsystems)

Page 10: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Test System in PSCAD

Page 11: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Test System in PSCAD

Converter A1 Converter controller

VSC control MMC PWM

Page 12: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Test System in EMTP-RV

A

A

B

B

C

C

D

D

E

E

F

F

G

G

H

H

I

I

J

J

K

K

L

L

M

M

N

N

O

O

1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

9 9

1 10 0

500 MW

100 MW

1000 MW

400 MW

600 MW

500 MW

1700 MW

1300 MW

1100 MW

1700 MW

600 MW

100 MW

1500 MW

1500 MW

CIGRE DC Grid test system - August 2012

Notes :

Every converters are configured as bipoles with earth return

Mixed configurations (monopole and bipole) can be used

Converter models : Detailed Equivalent - Type5 - 21 levels

Average value model is used for DC-DC converter B5

Converters Controls :

A1, B1, B2, B3 : P/Vdc droop control and Q control on AC side

C1, C2, D1, F1 : P control and Q control on AC side

E1 : V/f control

Double click to select the test case

1. Steady state solution

2. Steady State Power Through Converters

3. Fault on AC grid

3.1. Line opening

3.1.1. Trip and reclose of Line 1: A0_A1_2 – A1_A0_2

3.1.2. Trip and reclose of Line 2: B0_B3 – B3_B0

3.1.3. Trip and reclose of Line 3: C2_C1

3.2. Balanced 3 phase faults:

3.2.1. Fault on Line 1: A0_A1_2 – A1_A0_2

3.2.2. Fault on Line 2: B0_B3 – B3_B0

3.2.3. Fault on Line 3: C2_C1

3.3. Unbalanced 3 phase faults:

3.3.1. Fault on Line 1: A0_A1_2 – A1_A0_2

3.3.2. Fault on Line 2: B0_B3 – B3_B0

3.3.3. Fault on Line 3: C2_C1

4. Response due to reference changes:

4.1. Change in Pref at VSC_A1 (Droop Control): from 0.73 to 0.63

4.2. Change in Pref at VSC_B2 (Droop Control): form -1 to -0.9

4.3. Change in Pref at VSC_C1 (P control): from 1 to 0.9

4.4. Change in Pref at VSC_F1 (P control): from 1 to 0.9

4.5. Change in Pref at VSC_E1 (VF control): from -1 to -0.9

4.6. Change in Vref at B2 (Vf control): from 1 to 1.02

5. DC Faults

5.1. Trip and reclose of Line 1: A1_B1_1 – B1_A1_1

5.2. Trip and reclose of Line 2: B5_B1 – B1_B5

5.3. Trip and reclose of Line 3: B2_B3 – B3_B2

5.4. Trip and reclose of Line 4: A1_C2 – C2_A1

+

AC_C1

+

AC_C2

+

AC_D1

+

B0

+

AC_F1

DCline_2X1780MCM_200km

DC

line

_2

X1

78

0M

CM

_5

00

km

DC

line

_2

X2

31

2M

CM

_3

00

km

DC

line

_2

X1

78

0M

CM

_4

00

km

DC

line

_2

X1

78

0M

CM

_4

00

km

DCline_2X1780MCM_100km

ACline_3X795MCM_200km

ACline_3X795MCM_200km

P Q Load_E1

155kVRMSLL

100MW

0.1MVAR

ACline_3X795MCM_300km

ACline_3X795MCM_300km

PQ_C2

PQ_C1PQ_A1

PQ_B3

PQ_B1

P Q Load_B1

380kVRMSLL

900MW

0.1MVAR

PQ_B3_B2_1

PQ_B3_B2_2

PQ_B3_B0

PQ_B2_B0

PQ_B1_B0_1

AC

line

_3

X7

95

MC

M_

20

0k

m

BR

K_

A1

_B

4

DC

DC

_B

5

BR

K_

B4

_A

1

BR

K_

A1

_B

1_

1

BR

K_

A1

_B

1_

2

BR

K_

B1

_A

1_

1

BRK_B5_B1

BRK_B1_B5

BRK_B1 BRK_B1_E1

BR

K_

B1

_A

1_

2

BRK_E1_B1 BRK_E1

BR

K_

E1

_F

1

BR

K_

E1

_D

1

BRK_F1BRK_B3

BR

K_

F1

_E

1

BRK_D1

BRK_C2

BRK_C1BRK_A1

BRK_B3_B2BRK_B2_B3

BRK_B2

PQ_LoadB3

PQ_B3_B1

PQ_B1_B3

PQ_LoadB1

PQ_LoadB2

PQ_B2

PQ_B2_B3_1

PQ_B2_B3_2

PQ_B0_B1_1

PQ_B0_B2

PQ_B0_B3

PQ_AC_C1

PQ

_C

2_

C1

PQ_A1_A0_2

PQ_A0_A1_1

PQ_A0_A1_2

BRK_C2_A1

BRK_A1_C2

BR

K_

D1

_C

2

BR

K_

D1

_E

1

PQ_B0_B1_2

PQ_B1_B0_2

A1_C1_800MM2_200KM

A1_C2_800MM2_200KM

B1_E1_800MM2_200KM

B6_F1_800MM2_100KM

C2

_D

1_

63

0M

M2

_3

00

KM

D1

_E

1_

10

00

MM

2_

20

0K

ME

1_

F1

_6

30

MM

2_

20

0K

M

B2_B3_630MM2_200KM

ACline_3X795MCM_400km

AC

line

_3

X7

95

MC

M_

30

0k

m

P Q

Load_B3

P Q

Load_B2

ACline_3X795MCM_200km

ACline_3X795MCM_200km

MMC

bipole

type4

20 SM

VSC_A1

MMC

bipole

type4

20 SM

VSC_C1

MMC

bipole

type4

20 SM

VSC_C2

MMC

bipole

type4

20 SM

VSC_D1

MMC

bipole

type4

20 SM

VSC_E1

MMC

bipole

type4

20 SM

VSC_F1

MMC

bipole

type4

20 SM

VSC_B1

MMC

bipole

type4

20 SM

VSC_B3

MMC

bipole

type4

20 SM

VSC_B2

AC

ca

ble

_3

X1

85

mm

2_

50

km

V

Vmeter_A1

Test case selectionTest cases 1 & 2

V

Vmeter_C1

V

Vmeter_C2

V

Vmeter_D1

V

Vmeter_E1

V

Vmeter_F1

V

Vmeter_B3

V

Vmeter_B2

V

Vmeter_B1

V

Vmeter_B0

PQ_B0

PQ_A0_A1

PQ_AC1_A1

+

A0

+

AC2V

Vmeter_A0

PQ_A1_A0_1

BR

K_

C2

_D

1

P Q

Load_E1_b

155kVRMSLL

10MW

0.1MVAR

PQ_AC_C2

PQ_AC_D1

PQ_AC_F1

PQ_E1_a

PQ_E1_b

PQ_D1

PQ

_C

1_

C2

PQ_E1

PQ_F1

BR

K_

B5

_2

BRK_B5_1

Page 13: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Test System in EMTP-RV

Converter A1

VSC_1

A

A

B

B

C

C

D

D

1 1

2 2

3 3

4 4

5 5

Start point reactors are disconnected in converters

AC

DC_plus

DC_minus

MMC

monopole

type4

20 SM

VSC_1

MMC

monopole

type4

20 SM

VSC_2

A

A

B

B

C

C

D

D

E

E

F

F

G

G

H

H

I

I

J

J

K

K

1 1

2 2

3 3

4 4

5 5

6 6

7 7

8 8

9 9

1 1

0 0

Scope:

These devices are Exported Masks, do not modify

AC1 2

- 30

Conv erter_Tfos

1/1

Ex ported M as k

p

n

+

4k

,65

00

Sta

r_p

oin

t_re

ac

tor

Page

1-B4

Vdc

scope

Vc 1_up_phA

scope

I_c i rc u lar_phA

f ( u)

1

2

(u [1]+u[2])/2

Page

1-B

4

V_

Se

co

nd

ary

_T

ran

sfo

Page

1-B

4,

1-J

4

I_S

ec

on

da

ry_

Tra

ns

fo

Page

1-B

4,

1-H

3

V_

Pri

ma

ry_

Tra

ns

fo

Page

1-B

4,

1-H

4

I_P

rim

ary

_T

ran

sfo

scope

Vc 20_up_phA

scope

Vc 1_low_phA

scope

Vc 20_low_phA

scope

Vref_phA

Va_ref

Vb_ref

Vc _ref

PageV_Sec ondary _Trans fo

Page

1-B4, 1-C1

I_Sec ondary _Trans fo

Page1-B4, 1-B1

V_Prim ary _Trans fo

Page1-B4, 1-B1

I_Prim ary _Trans foia

v av a

ia

scope

V�_Prim ary _phA

scope

I�_Prim ary _phA

scope

V�_Sec ondary _phA

scope

I�_Sec ondary _phA

PageVdc scope

Vdc

Va_ref

Vb_ref

Vc _ref

+

-

Vdc _m eas

Page1-J 4

Vabc _refPage1-B1, 1-H3 V_Prim ary _Trans fo

Page1-B1, 1-H4 I_Prim ary _Trans fo

Page1-C1 V_Sec ondary _Trans fo

Page1-C1, 1-J 4 I_Sec ondary _Trans fo

PageS_up_A

Page i_up_A

Page i_ low_A

Page i_up_B

Page i_ low_B

Page i_up_C

Page i_ low_C

PageS_low_A

PageS_up_B

PageS_low_B

PageS_up_C

PageS_low_C

PageVc _up_A

PageVc _low_A

Page1-D4

Vabc _ref

Pagei_up_A

Pagei_ low_A

Page Vc _up_C

Page Vc _up_B

Page Vc _up_A

Page Vc _low_C

Page Vc _low_B

Page Vc _low_A

PageVc _up_C

PageVc _up_B

PageVc _up_A

PageVc _low_C

PageVc _low_B

PageVc _low_A

MMC ControlCCSC+CBA

Gate

signals

Va_ref

Vb_ref

Vc_ref

Vc_low_A

Vc_up_A

Vc_up_B

S_up_A

Vc_low_B

Vc_up_C S_up_C

Vc_low_C S_low_C

S_up_B

S_low_B

S_low_A

theta

i_up_C

i_up_B

i_low_C

i_low_B

i_up_A

i_low_A

Capa.

Voltages

Current

Arms

M M C_Contro l

Pagei_up_A

Pagei_ low_A

Pagei_up_B

Pagei_ low_B

Pagei_up_C

Pagei_ low_C

Page S_up_A

Page S_low_A

Page S_up_B

Page S_low_B

Page S_up_C

Page S_low_C

Vc 1

Vc 20

Vc 1

Vc 20

Page

1-H4

P_m eas

Page

1-H4

Q_m eas

scope

P_m eas

scope

Q_m eas

Page

1-D4

P_m eas

Page

1-D4

Q_m eas

Page1-H2 Vdc

i_up_A

P

i_up_B

i_up_C

i_low_A

i_low_B

N

i_low_C

AC

S_up_B

S_up_A Vc_up_A

Vc_up_B

Vc_up_C

Vc_low_C

Vc_low_B

Vc_low_AS_low_A

S_low_B

S_low_C

S_up_C

Capa.

Voltages

Gate

signals

Input Ouput

Current

Arms

Equivalent Equation Model (EEM) MMC 21Levels in DLL

NB:

This DLL works for a step time >1us

EEM _M M C_21L

M M C_20SM

v i

Sec ondary 1

v i

Prim ary 1

VSC Control

V_Secondary_Transfo

I_Secondary_Transfo

Vabc_ref

V_Primary_Transfo

I_Primary_Transfo

Vdc_measVdc

theta

P_measQ_meas

VSC_Contro l

AC_Conv erter

Page 14: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Main Model Differences

• Opal-RT Model (Matlab/Simulink/SPS + Opal-RT Libraries) - Developed by Opal-RT (Luc-Angre Gregoire)

- Embedded VBE for VSCs (Type 5 – see Opal-RT presentation)

- No. of sub-modules per valve: two type of converters, 400 (for on-shore) and 20 (for offshore grid)

- DC-DC Converter Model not included (B5 Converter)

- 11 cores running in real-time with the eMegaSim simulator.

• PSCAD Model - Developed by Manitoba HVDC Research Center.

- Detailed (equivalent Norton) models of VSC (Type 4 – all gate signals).

- No. of sub-modules per valve: Two type of converters, one is 38 (MMC PWM) and the other is 98 (MMC)

- DC-DC Converter Model not included (B5 Converter)

• EMTP-RV Model - Developed by RTE (Sebastien Dennetiere)

- Detailed (equivalent Norton) models of VSCs (Type 4 – all gate signals).

- No. of sub-modules per valve: 21

- Type 2 (DM) also available.

- Simplified DC-DC Converter included

- Documented modification from specification: Parameters are modified in the AC side B0 and B1 line length is 200 km, 2 circuit lines (instead of 1 line of 400 km)

• Type 4 Definition - Reduction in each arm to limit the number of electrical nodes (based on the integration method – 1 arm, 1

equivalent)

Page 15: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Simulation Studies: Steady State and Time Domain

• Simulation goals:

- Determine the steady state performance of the test systems

- Determine the dynamic performance of the test systems and terminals due to small perturbations, switching events (at DC), and faults (at AC)

• Simulation studies proposed (22):

- Steady State Analysis (3)

- Faults on AC Systems:

• Line opening (3)

• Balanced 3-phase faults (3)

• Unbalanced 3-phase faults (3)

- Response due to control reference changes

• Perturbation in Pref at all controllers (5), Vref (1)

- DC Faults: DC Line switching

• DC line openings (4)

• Studies carried out: Opal-RT (21), PSCAD (16), EMTP-RV (22)

• Count: 59 simulations – 3 steady state, 56 time domain

Page 16: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Model/User Limitations: Simulations that could not be carried out

• Opal-RT

- Change in Vref at DCDC_B5 (Simulation 4) Response due to reference changes

•PSCAD

- Change in Pref at VSC_E1 (Simulation 4) Response due to reference changes

• Model needs to be modified by adding a load at E1.

• We ran out of time to do this.

- Change in Vref at DCDC_B5 (Simulation 4) Response due to reference changes

• Converter B5 is an empty block

- All DC Faults

• Could not figure out how to disable some internal breakers in the converters.

• EMTP-RV

- All simulations were be executed.

Page 17: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Requirements to run the models

• Opal-RT - OPAL-RT real-time simulator OR license to run the

compiled model in the PC (localhost license)

- RT-Lab version 10.4.4.130, MATLAB Simulink 2011b (32-bit).

- MMC libraries from Opal-RT

- 11 processors

(eMegaSim simulator at KTH SmarTS Lab has 24).

• • PSCAD - Compiler: PSCAD requires a FORTRAN compiler. In these simulation we use Intel® Visual

Fortran Composer XE 2011 (v12) compiler (trial license).

- Version of the software: PSCAD X4 (4.5.0.0) Professional edition (trial license).

- Third party tools: If having the error of “WSock32.lib file missing”, the Windows platform headers and libraries need to be installed by the users.

- A VSC_MMC_lib file comes together with the model.

• EMTP-RV - EMTP-RV V2.4

- MMC Toolbox

• FOR ALL OF THE ABOVE: PATIENCE!!! (and money…)

Page 18: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Steady State Analysis

• We consider the “harmonic steady state”, not power flow solution.

• Procedure: -run the simulation until it reaches a “steady state”

• Opal-RT and PSCAD models offer a “meter”.

• For EMTP-RV:

0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2

-1

-0.5

0

0.5

1

1.5

2

x 109

time (s)

y

PLOT

BRK_B2_B3/p1/p_t@control@1

Steady State

EMTP-RV

SPS Meters

Page 19: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

0,8

0,9

1

1,1

A0 A1 B0 B1 B2 B3 B4 B5 B6 C1 C2 D1 E1 F1

AC

Vo

ltag

e (

pu

)

AC Bus

Design Specification Opal-RT PSCAD EMTP-RV

Steady State Solutions AC and DC Bus Voltages

DC Buses

AC Bus AC Bus

0,8

0,9

1

1,1

A0 A1 B0 B1 B2 B3 B4 B5 B6 C1 C2 D1 E1 F1

DC

Vo

ltag

e (

pu

)

DC Bus

Design Specification Opal-RT PSCAD EMTP-RV

Page 20: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Steady State Power Through Converters

Steady State Power through Converters

1100

600

400

1000

100

500

1700

500

1300

1100

PAC_A1

PAC_C1

PAC_D1

PAC_C2

PAC_E1

PAC_F1 PAC_B3

PAC_B1

PAC_B2 PDC_B5_out

PDC_B5_in

Page 21: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Comparison of Desired Flows: Design spec. with actual power through converters (max. value between input and output)

• The Opal-RT model matches the specification with no differences. • There is a very reasonable agreement between the design specification EMTP-

RV. Differences are likely due to tuning of model parameters.

Difference with the Spec.

0

200

400

600

800

1000

1200

1400

1600

1800

A1 B1 B2 B3 B5 C1 C2 D1 E1 F1

Po

wer (

MW

)

Converter

Opal-RT PSCAD EMTP-RV Design Specification (Desired Flow)

Models need to be

verified

Page 22: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Steady State Solutions (Harmonic Steady State) – AC and DC Flows

Steady State Solns.

AC Flows

DC Flows

Page 23: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Design Spec. PSCAD EMTP-RV Opal-RT

AC and DC Flows

Page 24: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

0,00

500,00

1000,00

1500,00

2000,00

2500,00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Design Spec. Opal-RT PSCAD EMTP-RV

Results Absolute Values Shown

Line no. From Bus To Bus Design Spec.

1 A1ac A0ac 600,00

2 A1dc B1dc 1500,00

3 A1dc B4dc 800,00

4 C1dc A1dc 600,00

5 C2dc A1dc 600,00

6 B0ac B1ac 400,00

7 B0ac B2ac 400,00

8 B0ac B3ac 400,00

9 B1ac B3ac 400,00

10 B4dc B1dc 300,00

11 B1dc E1dc 500,00

12 B2ac B3ac 200,00

13 B3dc B2dc 200,00

14 B5dc B2dc 1100,00

15 B6dc B3dc 700,00

16 F1dc B6dc 700,00

17 C1ac C2ac 100,00

18 C2dc D1dc 200,00

19 D1dc E1dc 800,00

20 E1dc F1dc 200,00

Directly Connected to

Slack Bus

600577279,80609

15001194,90340,601127,20

800199,61320,50530,40

6004,40277,80595,90

6005,90158,50250,40

400- 434,1013,70622,70

4001017422,90486,20

400772377,602436

400741,30688,80834,60

300- 198,34120,301251,00 500

104,38321,00316,60

20058,64176,5034,35

200836,80153,291886

11000433720,20

700841,47217,602301

700887,98245,402301

100- 10,47137,28149

200- 64,274,60151,20

800586,83524836

200432,121381805

Flow from B2 to F1

Page 25: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

• In some of the AC measurement, the output was filtered after power computation. For the DC case, only the instantaneous power without filtering was used.

Source of errors in power measurements in Opal-RT model

Also, the power in each AC line was deducted from the measurement of each converter. There is a lot of room for error in doing this way. Next version of the model should include more measurement to avoid such error.

Page 26: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

• In some of the AC measurement, the output was filtered after power computation. For the DC case, only the instantaneous power without filtering was used.

Source of errors in power measurements in Opal-RT model

Also, the power in each AC line was deducted from the measurement of each converter. There is a lot of room for error in doing this way. Next version of the model should include more measurement to avoid such error.

Page 27: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Faults on AC Systems

AC Faults

Line 1

Line 2

Line 3

Page 28: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Faults on AC Systems

AC Faults

Line 1

Line 2

Line 3

All changes applied at t=1 sec after harmonic steady state soln. Balanced (3 phase) [or unbalanced] fault is applied at left-hand (or upper) side bus of the line. Ideal AC breakers are placed on each side of the line. The line is opened after 2 cycles (0.04sec), after this to cycles the fault is cleared by opening the breakers on left hand side and right hand side simultaneously, and closing them simultaneously after 2 cycles.

Page 29: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Balanced Fault on Line 3: C1_C2

0 0.2 0.4 0.6 0.8 10

0.5

1

AC

Volt

age

Bu

sC

1

Opal-RT PSCAD EMTP-RV

0 0.2 0.4 0.6 0.8 10.9

1

1.1

1.2

DC

Volt

age

Bu

sC

1

0 0.2 0.4 0.6 0.8 10.7

0.8

0.9

1

1.1

AC

Volt

age

Bu

sC

2

0 0.2 0.4 0.6 0.8 10.8

1

DC

Volt

age

Bu

sC

2

T ime - (sec)

0 0.2 0.4 0.6 0.8 10

500

1000

P.

toC

on

.C

1

Opal-RT PSCAD EMTP-RV

0 0.2 0.4 0.6 0.8 1-2000

0

2000

P.

from

Conv.

C1

0 0.2 0.4 0.6 0.8 10

500

1000

P.

toC

on

.C

2

0 0.2 0.4 0.6 0.8 1-1500

-1000

-500

0

500

P.

from

Conv.

C2

T ime - (sec)

Page 30: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Response Due to Reference Changes

Response to Ref. Changes

∆Pref=-0.1 Droop Cntrl

∆Pref=-0.1 Droop Cntrl

∆Pref=-0.1 P Cntrl

∆Pref=-0.1 P Cntrl

∆Pref=+0.1 VF Cntrl

∆Vref=+0.02 Const. V

Page 31: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Faults on DC Grid

DC Faults

Line 1

Line 2

Line 3

Line 4

Page 32: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

General Simulation Challenges

• Opal-RT - Separate subsystems in order to run in real-time

- Need a model compiler for the specific architecture of the system and software configuration.

- Model modifications during real-time simuation

• Con.: No possibilities of modifying the circuit model for real-time simulation, but ok for off-line (although this takes out the advantage of having an RT simulator)

• Pros.: – Control parameters can be modified while real-time simulation is running.

– RT simulator can be used in “Simulation Accelerator” mode when no I/O is used (faster than real-time)

- Capacitor Balancing:

• Detailed MMC cell model was used.

• However, the DC voltage of each capacitor is adjusted to the average value of the sum of the cell capacitor voltage.

• The capacitor voltage balancing control system is therefor not implemented (but available).

Page 33: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

General Simulation Challenges

• PSCAD

- Errors that are difficult to figure out:

• Example1:Component ‘***’ does not have a corresponding definition.

• Solution: loading the library has to do before loading the model.

• Example2: ***No rule to make target ‘***.mak’. Stop

• Solution: install suitable compiler (GNU Fortran compiler is not suitable)

Page 34: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

• PSCAD

- Aspects not documented that make it difficult to use the model

• In link tab of project setting, the user must manually add these sub-directories to the directory specified by the User Library Path input in the Workspace dialog. In this simulation, we need to choose ‘if12 (Intel Visual Fortran compiler versions 12)’.

• De-blocking the converter control for several seconds at the beginning of the simulation, which is not indicated when providing this model.

• Some newly developed components do not have help information. For example, the DC breaker.

Page 35: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

General Performance Observed (ONE Specific Case)

• Opal-RT (50 µsec time step)

A. Approximately 1 sec

B. Simulation time: Real time. (1 sec. = 1 sec.)

•PSCAD (20 µsec time step)

A. Approximately 5 sec

B. Simulation time: about 1 hr for a 15s simulation

(Initialization Work Around - if system is left unchanged: start from a snapshot (snapshot for initialization)

• EMTP-RV (40 µsec time step)

A. Approximately 0.5 sec.

B. Simulation time: 258.625 sec for 2 second simulation.

A. Simulation “t” to reach a steady state

B. Time effort to carry out one simulation

Page 36: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Recommendations and Further Work

• The three models simulated are very complex and detailed, and will certainly be useful for DC Grid studies.

• We make the following recommendations for improvements on the current models!

• Documentation:

- Currently the EMTP-RV and SPS models are designed only for the scenarios presented.

- Documentation on the models (details) are needed for preparing other studies.

• Model Harmonization:

- The DC Grid benchmark models need to:

• Be harmonized in terms of steady state solution

• Controller implementation should be identical

- For large DC Grid studies, the focus is not on converter performance, and detailed representation of the VSCs might be unnecessary

• The use of a common average value model for the VSC is recommended, but this must be validated with detailed models

• (Detailed models are only necessary for internal protection and performance analysis)

Page 37: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Recommendations and Further Work

•Validation:

- Component validation

• Validation across different simulation environments should start at the component level for comparison studies to be meaningful: – Controller validation should be first (check controller response to

isolated inputs – compare outputs)

– VSC validation (for AVM), DC Line models and breaker models

– Independent validation of AC grid portions

• Component level validation with “real” measurements would be AWESOME! – Some suppliers and R&D centers have comparisons with actual

hardware or analog set ups, but it is not public.

- Point-to-point DC Link:

• Validation is recommended to establish the core differences of a simple DC Grid operation under different control modes in the three different environments.

Page 38: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Recommendations Looking into the Future: Avoid Modeling Ambiguity

• Modeling and Simulation without Ambiguity!

• The efforts in developing these benchmark models is of great value for DC Grid development.

• However, DC Grid development will be hindered due to a lack of ability: - To share (validated) models across different simulation environments.

- Which in turns requires the re-implementation of models in different tolls (very costly!).

- In this case models need to be validated.

• This study has shown that there is a clear need for unambiguous model exchange - Model exchange not referring only to parameter data

- Actual model implementations differ: “what’s inside the box?” is not transparent to the user

- Challenge for users without access to all software (economically prohibitive)

• This problem has existed since about 40 years for conventional AC/DC system design! (J. Belanger)

- DC Grid development should strive to tackle this attitude for common benefit.

Page 39: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Recommendations – Looking into the Future: Avoid Modeling Ambiguity

• Possible solutions to ambiguity

• Modelica-based models:

- Modelica is an OOP modeling language for complex systems

- Modelica models allow the specification of both the model equations and parameters

- A DC Grid model could be entirely defined, without ambiguity, and shared.

- Files could be packaged so that the model inside remains “closed”.

- Caveat: Each simulation environment needs to translate from Modelica to their internal definition (which requires validation). Mapping to GUI, etc…

- However:

- The use of Modelica language for very large AC/DC networks still need to be demonstrated. FP7 Pegase project had very promising results for moderate size networks.

- Usually, network solution used specialized circuit solvers (nodal …) with system topologies and component parameters. Are topology-based specialized solvers available in Modelica?

Page 40: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Proof of concept: Sharing Modelica Power System Models in two different simulation environments

Simulation results in Scilab/Xcos and Dymola, respectively. They are absolutely the same. Courtesy of Wei Li (KTH), Angela Chie and Patrik Panciatici (RTE)

Page 41: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Proof of concept: Sharing Modelica Power System Models in two different simulation environments

Simulation results in Scilab/Xcos and Dymola, respectively. They are absolutely the same. Courtesy of Wei Li (KTH), Angela Chie and Patrik Panciatici (RTE)

Page 42: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Recommendations – Looking into the Future: Avoid Modeling Ambiguity

• Possible solutions to ambiguity (cont’d)

• FMI

- Automotive industry has used the Flexible Mock-up Interface approach. Models are exported in a FMU (Functional Mock-up Unit).

- FMUs can be imported in another environment and executed.

- FMUs from different sources can cooperate at runtime in a co-simulation environment. FMI defines the interfaces for this to happen.

- Caveat: co-simulation environment is needed. Would be difficult to do real-time simulation (in the case of Opal-RT Models).

- OPAL-RT already support co-simulation for loosely coupled systems.

- But

• Co-Simulation is very difficult for tightly coupled system such as AC/DC circuit due to delays since simultaneous solution is required. OPAL-RT has developed SSN for this purpose.

• The use of FMI for electrical network simulation still need to me demonstrated and it may happen that FMI is a good approach for loosely coupled simulation only (control systems and plant models with very different time constants).

Page 43: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Recommendations – Looking into the Future: Avoid Modeling Ambiguity

•Possible solutions to ambiguity (Cont’d)

•CIM-for-EMT

- Would be similar to the Modelica approach, but it would be more difficult to share exact equations (or package them so that they are “closed”).

- As of now, CIM only defines the topology and system parameters, not the model equations

Page 44: Simulation Studies and Experiences of the preliminary CIGRE DC Grid Test System with EMTP-RV, PSCAD and Opal-RT

Thank you! [email protected]

http://www.vanfretti.com