Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
SIMULATION OF THE FEED-IN POWER OF DISTRIBUTED PV SYSTEMS
LISA GROSSI(1) • GEORG WIRTH(1) • ELKE LORENZ(2) • ANDREAS SPRING(1) • GERD BECKER(1)
(1) University of Applied Sciences Munich · Department of Electrical Engineering · 80335 Munich · Germany ·
Phone +49 (0) 89 1265-4412 · [email protected]
(2) Carl von Ossietzky Universität Oldenburg · Fakultät V · Institut für Physik · AG Energiemeteorologie · Germany
ABSTRACT: In Southern Germany a high number of photovoltaic (PV) plants feeds into the grid. New load patterns
occur and with them changed grid requirements. Feed-in management is one possibility to maintain grid stability and
safety. Nowadays feed-in management measures are carried out in defined steps (typically: 100%, 60%, 30%, 0% of
PSTC). As the power produced by PV plants depends on the current irradiance situation, the reduction of the feed-in
power according to a predefined level mostly does not lead to the desired effect in the grid. Thus, the network operator
needs detailed knowledge of the condition of the grid in order to be able to carry out targeted regulating measures.
This paper presents a simulation model that allows to model the feed-in power of a distributed PV fleet and to
characterize the consumption in the medium and low voltage grid of the investigated area. On the one hand, the
simulation is carried out on the basis of irradiance data recorded by a spatially distributed high resolution measurement
system. On the other hand, satellite data is used as simulation input. Simulation accuracy of both variants is compared
and their advantages and disadvantages discussed.
Keywords: Grid-Connected, Grid Integration, Grid Management, Grid Stability, Simulation
1 INTRODUCTION
The increasing share of renewable energies in the
German power supply leads to changed grid requirements
that must be met by the network operator to maintain grid
stability and safety [6]. In this context Bayernwerk AG
has initiated the project “Netz der Zukunft” (“Grid of the
Future”) in cooperation with the University of Applied
Sciences München and Technische Universität München.
A medium voltage grid is analysed in order to examine
the impact of photovoltaic (PV) systems on the grid. The
investigated grid is situated in a rural area in Northern
Bavaria and characterized by a very high PV penetration.
Altogether 36 MW of PV capacity are installed. This
amounts to ca. 5.6 kW per house connection. Smart
meters record data at every substation (110-20 kV and
20-0.4 kV) and at many house connections with and
without PV power plants. Thus, highly resolved grid
measurements are available.
In order to determine the behaviour of a distributed PV
fleet, the spatial distribution of the irradiation in the
investigated area is analysed. A special focus thereby is
to characterize the geographic smoothing of the feed-in
power on days with fluctuating cloud covers.
Therefore, a high resolution measurement system records
global irradiation and temperature. The distributed fleet
and the ten measurement stations are spread over an area
of ca. 11x15 km. The acquired data is being used to
simulate the power generation of the distributed PV fleet
in the project area.
A second approach is to use satellite data as simulation
input. The satellite data features a different time and
spatial resolution than the distributed measurement
system.
In the following, the simulation approach in general is
described. Then, the two input data variants are compared
and simulation results are presented.
2 SIMULATION APPROACH
The project area is divided into subareas of which each is
simulated separately. The simulation model is efficiency-
based and uses a PT1 element to model the geographic
smoothing of the feed-in power on days with fluctuating
cloud covers. Its time constant depends on the installed
PV capacity of the corresponding subarea. The approach
is similar to the one presented in [2]. Figure 1 illustrates
the schematic of the simulation process.
Figure 1: Schematic of the simulation process. Each
subarea is simulated separately.
The following variables are used as input: The spatially
distributed measurement devices record global horizontal
irradiance and ambient temperature. First, horizontal
irradiance is converted into global tilted irradiance using
the model presented in Perez et al. [3]. Then, by means of
the recorded ambient temperature, tilted irradiance and
the module-specific parameter γ, the module temperature
is calculated:
The parameter γ depends on the mounting type of the PV
plant [1].
In the next step module efficiency η is determined:
with the parameters α1,α2,α3 describing the part load
behaviour of the modules for a module temperature of
25° C. The parameters depend on the cell type. The
parameter αp corresponds to the temperature coefficient
and describes the module behaviour at module
temperature Tmod. For the simulation model, weighted
average values of α1,α2,α3 and αp representing the
different cell types on the market are used.
Module efficiency η and the installed PV capacity AG
determine the proportional gain Kp. The time constants
have been empirically determined and optimized in
dependency of the size of the subareas. [5] The used
highly resolved data has been recorded in Jülich in
Germany within the framework of the project
HD(CP)²/HOPE. Proportional gain Kp and the time
constant tpt1 are the input parameters of the PT1 element.
Its output is the DC power of the single subareas and
finally the power of the whole distributed PV fleet.
( ( - )) ( - ) (3)
∑ (4)
DC power is converted into AC power using the model
presented by Schmidt and Sauer [4]. Additionally, system
losses of 9.5% are considered [1]
On the basis of the simulated feed-in power and the
cumulated power of the area measured over the 110 kV
substation, that we have at our disposal, a reference load
can be calculated. The load curve is calculated for a clear
sky day and serves as reference for the simulation of
further days. The application of the calculated reference
load requires that the simulation model provides correct
results on a clear day. This assumption has to be made as
no detailed measurement of the load exists. Further,
standard load profiles cannot be applied as too many
special contract customers are situated in the grid area
and strongly influence the area’s load behaviour.
Therefore, simulation accuracy has been validated using
measured PV data. [5] Figure 2 illustrates the simulated
feed-in power, the measured load curve and the resultant
calculated reference load.
Figure 2: Simulated feed-in power (green), cumulated
power of the area measured over the 110 kV
substation (red) and calculated reference load (blue)
on 18 June 2012.
3 THE DISTRIBUTED MEASUREMENT SYSTEM
Ten spatially distributed measurement devices record
global irradiation and temperature. It is a ground based
simulation. Figure 3 illustrates the distributed
measurement in the area.
Figure 3: Ground based measurement points in the
investigated area and the ten subareas. Each subarea
is simulated separately by means of the corresponding
device’s data and installed PV capacity.
Time resolution of the measurement devices amounts to
3 seconds and spatial resolution is ca. 10 km². The single
subareas are simulated using their device’s data and
installed PV capacity and a time constant depending on
the size of the subarea. Figure 4 illustrates a day with
fluctuating cloud cover simulated on the basis of the
distributed measurement. Measurement and simulation
match rather well. In comparison, figure 5 shows the
same day simulated using just one irradiance value. The
simulated curve differs strongly from the measured one.
One measurement device is not sufficient to model the
smoothing effect of the feed-in power of the distributed
PV systems on days with fluctuating cloud covers. The
grid condition is not described properly.
Figure 4: Simulation on the basis of ten distributed
measurement devices. Simulated of PV power
generated by the distributed fleet (green), measured
(red) and simulated (orange) cumulated power of the
area on 26 June 2012. Measurement and simulation
show a high congruence. The spatial smoothing of the
power is represented properly by the simulated curve.
Figure 5: Simulation on the basis of just one
measurement sensor. Simulated power of the
distributed PV fleet (green), measured (red) and
simulated (orange) cumulated power of the area on 26
June 2012. The spatial smoothing of the feed-in
cannot be represented using just one measurement
device as simulation input.
Simulation accuracy is evaluated on the basis of the root
mean squared error (rmse) and average absolute deviation
(aad). Rmse refers to the overall installed PV capacity of
36 MW.
√ ∑
∑
20 days with various cloudiness conditions have been
analysed. Table 1 contains the rmse and aad values. The
mean rmse amounts to 3.37 % and the aad to 0.95 MW.
Table 1: Distributed measurement - Statistical values
describing the simulation accuracy.
Date
(2012)
Root mean square
error [%]
Average absolute
deviation [MW]
01 June* 4.01 1.21
02 June 2.97 0.86
03 June* 2.66 0.79
04 June 3.34 1.12
05 June 3.33 0.99
07 June 6.39 2.04
09 June 3.03 0.95
11 June* 3.40 0.92
13 June 3.51 1.07
15 June* 2.24 0.66
19 June* 2.36 0.75
20 June* 3.05 0.86
21 June* 4.00 1.15
22 June* 3.63 1.07
25 June* 5.25 1.47
26 June* 3.52 1.00
28 June 2.72 0.77
01 July 2.89 0.87
04 July 3.51 0.95
21 Aug 1.63 0.44
Average 3.37 0.95
4 SIMULATION ON THE BASIS OF SATELLITE
DATA
Nowadays satellite data is already used to determine PV
feed-in on transmission network level for trade and
balancing. For this work the satellite method is applied to
the investigated medium voltage grid which is a
comparatively small area. The raw data is provided by
EUMETSAT and recorded by a geostationary MSG
satellite in a time resolution of 15 minutes and a spatial
resolution of ca. 1.2 x 2.2 km. The University of
Oldenburg uses the Heliosat method to convert raw into
cloud and irradiance data. Figure 6 shows the
investigation area and the contained satellite pixels. The
PV systems in the area (blue) are assigned to the single
satellite pixels and each pixel is simulated separately by
means of its measured data, the respective installed PV
capacity and a time constant corresponding to the spatial
resolution of the pixels. 43 pixels are used to simulate the
investigated area. Using satellite data as simulation input,
20 days are analysed as well.1 Table 2 shows the
corresponding rmse and aad values. The mean rmse amounts to 5.57 % and the aad to 1.85 MW
1 As no satellite data is available on 21 August, it is
replaced by 5 July.
Figure 6: Investigation area and measurement points
(red) covered by satellite. The blue markers indicate
PV systems.
Table 2: Satellite data - Statistical values describing
the simulation accuracy.
Date
(2012)
Root mean square
error [%]
Average absolute
deviation [MW]
01 June 6.77 2.09
02 June 5.35 1.61
03 June 5.03 2.76
04 June 4.86 1.57
05 June 3.92 1.19
07 June 5.71 1.83
09 June 8.43 2.87
11 June 4.94 1.23
13 June 5.88 1.88
15 June 4.09 1.49
19 June 6.67 2.17
20 June 4.02 1.83
21 June 5.79 1.71
22 June 6.49 2.21
25 June 4.34 1.77
26 June 5.81 1.85
28 June 6.74 2.10
01 July 8.33 2.26
04 July 3.66 1.19
05 July 4.56 1.35
Average 5.57 1.85
5 COMPARISON OF THE TWO APPROACHES
The evaluation of the 20 exemplary days shows that the
simulation on the basis of the distributed ground based
measurement features a higher accuracy than the one
based on satellite data. This is mainly due to the fact that
cloud shadows cannot be precisely assigned to one single
pixel. To determine the cloud shadows, an average height
of the clouds is assumed leading to inaccuracies in a
small scale simulation. The advantage of satellite data is
that no measurement system has to be built up and
maintained. The data is available anyway. Figure 7
illustrates a cloudy day simulated with the data of the
distributed measurement. Figure 8 shows the same day
based on the satellite data. Measurement and simulation
show a good match. Simulated load flow is located
slightly below the measured curve.
Figure 7: Simulation on the basis of the ten ground
based distributed measurement devices in 15 minute
resolution. Simulated power of the distributed PV
fleet (green), measured (red) and calculated (orange)
cumulated power of the area on 26 June 2012. Data
from the distributed measurement is used as input.
Figure 8: Simulation on the basis of satellite data.
Simulated power of generated by the distributed PV
fleet (green), measured (red) and calculated (orange)
cumulated power of the area on 26 June 2012 based
on the satellite data.
Figure 9 shows the simulation accuracy of the distributed
system in 3 second resolution depending on the number
of measurement devices used as simulation input. Only
days marked with an asterisk (*) in Table 1 are evaluated.
The simulation with ten devices features a high accuracy
of about 3.5 % in average. Using only one measurement
sensor leads to low accuracy values as already seen in
figure 5. Average rmse amounts to ca. 11.5 %. The
satellite based simulation features an average rmse of
5.6 %, which is approximately as high as the distributed
simulation in 3 second resolution with 6 measurement
devices.
Figure 9: RMSE of the distributed measurement in
dependency of the number of measurement devices
used as simulation input. 50 % of the values are in the
box. The whisker’s length is maximum 1.5xIQR
(interquartile range). Outliers are plotted red.
6 CONCLUSION
The presented simulation model allows us to determine
the behaviour of the spatially distributed PV fleet in the
investigation area. On its basis it is possible to analyse
the effects of various meteorological conditions on the
distribution network. The spatial smoothing of the feed-in
power of the distributed fleet is modeled well.
The ground based distributed measurement system
features a spatial resolution of ca. 10 km² and a time
resolution of 3 seconds. The method enables to
characterize the load flow of the medium voltage grid
with a high accuracy and offers the network operator
detailed knowledge of the grid condition. Simulation
accuracy with ten measurement devices amounts to ca.
3 % in average.
The spatial resolution of the satellite data is higher than
the measurement system’s resolution and amounts to
1.2 x 2.2 km. Its time resolution is limited to 15 minutes.
For applications regarding power engineering this fact
represents not necessarily a disadvantage as many
applications work in this time intervals. Improvement
potential exists in the precise assignment of cloud
shadows to satellite pixels. Simulation accuracy amounts
in average to 5.6 % on the 20 mostly variable days.
Satellite data represent a reliable, always available and
low maintenance source of irradiance data. A distributed
system offers an individually adaptable measurement
regarding spatial and time resolution, but it also involves
workload and expense.
Anyway, both methods provide high accuracy and
detailed knowledge to the network operator. Moreover,
they can be transferred to any grid area with high PV
penetration. On the basis of the characterization of the
grid condition, the network operator is able to take
targeted regulating measures to ensure quality and
security of supply.
7 ACKNOWLEDGEMENTS
The authors want to thank the Bayernwerk AG for
supplying measurement data, in particular the asset
management department for their invaluable technical
support. Likewise we want to thank Prof. Dr. Andreas
Macke, Director of the Leibniz Institute for Tropospheric
Research, Bomidi Lakshmi Madhavan, and Dr. John
Kalisch for supplying the irradiance data of the Jülich
measurement campaign.
[1] Lorenz E., Scheidsteger T., Hurka J., Heinemann D.,
Kurz C., Regional PV power prediction for improved
grid integration, Progress in Photovoltaics, Special Issue:
25th EU PVSEC WCPEC-5, Valencia, Spain, 2010,
Volume 19, Issue 7, pages 757–771, November 2011.
[2] Marcos J., Marroyo L., Lorenzo E., Alvira D., Izco
E., From irradiance to output power fluctuations: the pv
plant as a low pass filter. Prog. Photovolt: Res. Appl.
2011: 19: 505–510
[3] Perez R., Seals R., Ineichen P., Stewart R., Menicucci
D., A new simplified version of the Perez diffuse
irradiance model for tilted surfaces. Solar Energy 1987:
39: 221-231.
[4] Schmidt H, Sauer DU.,Wechselrichter-
Wirkungsgrade. Sonnenenergie 1996; 4: 43–47 (in
German).
[5] Wirth G., Modellierung der Netzeinflüsse von
Photovoltaikanlagen unter Verwendung meteorologischer
Parameter, Dissertation, Carl von Ossietzky Universität
Oldenburg, Submitted Jun/2014.
[6] Wirth G., Spring A., Becker G., Pardatscher R.,
Witzmann R., Brantl J., Garhamer M., Effects of a High
PV Penetration on the Distribution Grid. 27th European
Photovoltaic Solar Energy Conference and Exhibition,
Frankfurt, September 2012.