Upload
stipecurlin5242
View
215
Download
0
Embed Size (px)
Citation preview
8/10/2019 Simulation of Hydroelectric System Control
1/24
Simulation of hydroelectric
system control
Dewi Jones
8/10/2019 Simulation of Hydroelectric System Control
2/24
Simulation of hydroelectric system control
Dewi Jones
Report GW002
October 2008
GWEFR CyfTechnium CAST
Ffordd Penlan
Parc Menai
Bangor
Gwynedd LL57 4HJ
Wales
Tel: +44 (0) 2921 251768
Email:[email protected]
http://www.gwefr.co.uk
Care has been taken in the preparation of this report but all advice, analysis, calculations, information, forecasts and
recommendations are supplied for the assistance of the relevant client and are not to be relied upon as authoritative or as in
substitution for the exercise of judgement by that client or any other reader. Neither GWEFR Cyf, nor any of its personnel
engaged in the preparation of this Report shall have any liability whatsoever for any direct or consequential loss arising from
the use of this Report or its contents and give no warranty or representation (express or implied) as to the quality or fitness for
the purpose of any process, product or system referred to in the Report.
Copyright in this Report remains the sole property of GWEFR Cyf.
mailto:[email protected]:[email protected]:[email protected]://www.gwefr.co.uk/http://www.gwefr.co.uk/http://www.gwefr.co.uk/mailto:[email protected]8/10/2019 Simulation of Hydroelectric System Control
3/24
Contents
1 Introduction ........................ ........................ .................... ..................... ...................... .................... ...................... ..... 1
2 Outline of the simulation ........................ ...................... ..................... ...................... .................... ..................... ... 1
2.1 Physical layout ...................... ..................... ..................... ...................... .................... ..................... ................. 1
2.2 Model summary ..................... ....................... ..................... ..................... ...................... .................... ............. 3
3 Simulation of hydraulic system with fixed rate GV opening ................. ..................... ...................... ..... 4
4 Lumped parameter models ........................ .................... ...................... ...................... .................... .................... 7
4.1 Lumped parameter, inelastic water column model .................... ...................... ..................... ......... 7
4.2 Linearised model ....................... ...................... ..................... ...................... .................... ..................... .......... 9
5 Control system design ....................... ...................... ..................... ...................... .................... ..................... .......... 9
6 Closed loop simulation with Grid connection .................... ..................... ...................... ..................... ...... 126.1 Frequency control mode. ......................... ..................... ...................... ...................... ..................... ......... 13
6.2 Power dialup mode. ....................... ...................... ..................... ...................... ..................... .................... 16
6.3 Fullload rejection. ........................ ..................... ...................... ..................... ..................... ...................... .. 17
7 Conclusion............................................................................................................................................................... 19
8/10/2019 Simulation of Hydroelectric System Control
4/24
8/10/2019 Simulation of Hydroelectric System Control
5/24
1
1 Introduction
This sample report outlines how the generic simulation package offered by GWEFR Cyfcan
provide valuable information about the dynamic response of a proposed hydroelectric installation,
given just the basic information about the Plants physical layout, its primary parameters and
modes of operation.
The objective is to increase understanding of how the proposed hydraulic and electrical systems
affect the dynamic response of the Plant and hence the quality of power generation an approach
advocated in IEEE Standard 12072004 IEEE Guide for the Application of Turbine Governing
Systems for Hydroelectric Generating Units [1].
The following section presents a simplified version of the hydraulic system, composed of a
reservoir supplying two Gridconnected Francis turbine/generators via a common tunnel, a
manifold and two identical penstocks. This is used as the basis of a travellingwave model that
estimates the pressure and flow variations in the water passages under defined rates of opening or
closing of the turbine guide vanes.
Comparisons are made between the responses produced by three different types of model, as
suggested by an expert IEEE Working Group [2]:
Nonlinear distributed parameter, elastic water column the most accurate model butcomputationally intensive;
Nonlinear lumped parameter, inelastic water column requires less computation but doesnot represent travellingwave effects;
Linearised model suitable for control design.
Standard tuning rules are applied to design a PID controller based on the linearised model.
The resulting governor is integrated with models for the hydraulics, turbine/generator and Grid to
study system performance for 3 scenarios:
Closed loop frequencycontrol mode Dialup power mode with feedforward Full load rejection
The report provides constructive input to the requirements capture stage of the project and
forthcoming design efforts.
2 Outlineofthesimulation
2.1 Physicallayout
Figure 1 shows the general layout of the hydraulic system assumed in the model. The reservoir is
connected by a long supply tunnel to a manifold that separates into two identical penstocks, which
feed identical turbine/generators. The tailrace is not included in the model at this stage. Note that
the layout is not quite symmetrical because the water path to Unit #2 has additional length due to
the manifold. The dimensions are shown in Figure 2.
8/10/2019 Simulation of Hydroelectric System Control
6/24
2
Figure1Generallayoutofthehydraulicsystem.
Figure2Cross-sectionandplanviewsshowingdimensions(datumtakenatturbineinlet).
513m
880m
10m
9.5
m
130m
3.3m
10m
80m
9.5m
130m
3.3m
8/10/2019 Simulation of Hydroelectric System Control
7/24
3
2.2 Modelsummary
Hydraulicsystem:
The 4 pipe sections are modelled using the Method of Characteristics [3] which is used to compute
the time variation of piezometric pressure and uniform flow at 100 discrete points in the network.
All head losses except for friction are considered negligible. There are 5 boundary conditions:
The head at the reservoir outlet is considered constant. At the branch between tunnel, manifold and penstock #1 the head is constrained to be
identical for all 3 branches and continuity of flow is applied.
Similar conditions are applied at the junction between the manifold and penstock #2. Both turbines are modelled as idealised lossless control components where the relationship
between head and flow is given by:
2
2u tb
VH A
G
=
(2.1)
where Hu= head across the turbine
V = flow through the turbine
Atb= turbine constant
G = guide vane opening (0 : 1)
For a flow, Q, the mechanical output power of a turbine is given by:
m u
P QH g= (2.2)
Electricalsystem
It is assumed that the generators are Gridconnected and represented by a linearised version of the
classic swing equations as given, for example, by Kundur [4]:
( )
( )0
1
2r m e D r
se r L
P P KHs
KP Ps
=
=
(2.3)
where:
G= Grid frequency
r= Unit (electrical) speed
PL= load change on Grid
Pm= turbine mechanical power
Pe= generator electrical power
0, r= rated and actual Unit speed
Ks= synchronising coefficient
KD= speed damping coefficient
H = inertia constant
s = Laplace variable
8/10/2019 Simulation of Hydroelectric System Control
8/24
8/10/2019 Simulation of Hydroelectric System Control
9/24
5
Figure 3 shows that the flow velocity increases in penstock #1 as GV #1 opens with a small dip in
the velocity in penstock #2 over the same period. Opening GV #1 causes the pressure at the turbine
inlet to fall and, after a brief delay while the pressure wave travels through the 2 penstocks and the
manifold, hydraulic coupling causes the pressure at turbine #2 to decrease. The response also
exhibits a poorly damped oscillation with a period of 0.7s as the travelling wave traverses the
tunnel. These effects are reflected in the generated power. Turbine #1 is subject to a brief time
delay before the required power increase begins while turbine #2 is perturbed from its set level.
Figure3Variationofpressurehead,penstockflowandmechanicalpowerwithGV#1openingin2.6s.
Figure 4 shows the head and flow profiles in the pipe network shortly after the simulation isinitiated. The pressure head increases, because of elevation, along the length of the tunnel and then
flattens out over the length of the penstock (the red line shows the pressure in penstock #1). The
small notch of lower velocity between 880 and 960m is located at the manifold, which only carries
the flow to penstock #2. An animated version of Figure 4 shows the pressure wave travelling up
and down the tunnel as the simulation proceeds.
This is a very simple model of the hydraulic system (it should be emphasised that it is not a
substitute for a full study for structural engineering purposes) but quite satisfactory for
representing the dynamics within the tolerance required for a control systems study. Clearly, in
this particular example, the pressure variation is within bounds and quite satisfactory in thisrespect.
480
490
500
510
520
pressurehead(m)
2
3
4
5
6
7
penstockvelocity(m/s)
penstock #1
penstock #2
0 5 10 15
100
150
200
250
300
mechanicalpower(MW
)
time (s)
turbine #1
turbine #2
turbine #1
turbine #2
branch
8/10/2019 Simulation of Hydroelectric System Control
10/24
6
Figure4Pressureandflowprofilesinthetunnelandpenstocks.
Figure5Variationofpressurehead,penstockflowandmechanicalpowerwithGV#1openingin1.0s.
0 200 400 600 800 10000
100
200
300
400
500
pressurehead(m)
0 200 400 600 800 10000
1
2
3
4
5
6
7
flowvelocity(m/s)
0 200 400 600 800 1000
Pressure head variation (normalised to max and min of range)
distance along pipe (m)
440
460
480
500
520
540
pressurehead(m)
2
3
4
5
6
7
penstockvelocity(m/s)
penstock #1
penstock #2
0 5 10 15
100
150
200
250
300
mechanicalpower(MW)
time (s)
turbine #1
turbine #2
turbine #1
turbine #2
branch
8/10/2019 Simulation of Hydroelectric System Control
11/24
7
The result in Figure 5 was obtained by decreasing the opening time of GV #1 to 1.0s. This leads to a
much larger variation in penstock pressure head, which falls to 11.5% below and rises to +4.5%
above the static head. There is a corresponding variation of the mechanical power produced by the
turbines, with perturbation peaks for turbine #2 of 9.7% and +6.7% of the steadystate value.
4
Lumpedparameter
models
4.1 Lumpedparameter,inelasticwatercolumnmodel
The model presented in this section is derived from the block diagram in Sec. 2.6 of [2]. The water
column is considered rigid so travellingwave effects are omitted. The inertia of the water column
is represented by parameters known as the water starting times. The model is multivariable, so
hydraulic coupling effects are retained. It is also nonlinear and suitable for use when simulating
large excursions of the variables.
The water starting time for a section of pipe of length is defined as:
bW
b
VT
gH
=
(4.1)
For the layout of Figure 1, the relationship between the head and flow rate variation in the two
penstocks is:
1 3 11 1
1 1 2 42 2
1
1
W W W
W W W W
T T Th q
T T T T h q
+ = + +
(4.2)
where:
h1, h2are the turbine heads
q1, q2are the turbine flows
TW1is the water starting time for the tunnel (0.145s)
TW2is the water starting time for the manifold (0.014s)
TW3, TW4are the water starting time for penstock #1 and #2 respectively (both 0.198s).
Inverting this relationship allows it to be embedded in a Simulink block diagram, as shown in
Figure 6, which incorporates the nonlinear turbine characteristics and head losses due to friction.
The simulation was run with GV #2 set to operate at a fixed power of 288MW. GV#1 was set for an
initial output power of 280MW and then opened linearly over 2.6s to produce a steady state power
of 310MW. The distributed parameter model was run for the same conditions and Figure 7 shows
that there is a good match between the power outputs. Because the simulation is run here with Unit
#1 operating at a higher power level than in Figure 5, both models predict an initial decrease of
output power at turbine #1 (the characteristic nonminimumphase response). The obvious
discrepancy of course is the absence of the travelling wave oscillation from the response predicted
by the inelastic water column model. The difference becomes more evident as the GV opening or
closing times become shorter.
8/10/2019 Simulation of Hydroelectric System Control
12/24
8
Figure6Simulinkblockdiagramfortheinelasticwatercolumnmodel.
Figure7Comparisonofresponsesfordistributedparameterandlumpedparametermodels.
Inelastic water column , multiple penstock model in p .u. representation .
Based on Figure 8 of the IEEE Wkg Group paper .
Pinel
1
no-load
flow
0
inverse water
starting time
matrix
iTmat * uvec
friction
head loss 2
qhf
friction
head loss 1
qhf
damping 1
1
damping
1
Product 5
Product 4
Product 3
Product 2
Product 1
Product
P.U. base
power
Pb
P.U. base
head
1
Integrator 1
1
s
Integrator
1
s
Dw2
0
Dw1
0
Divide 1
Divide
G2
2
G1
1
h2
q1
q2
Pm1
Pm2
h1
0 1 2 3 4 5 6 7 8 9 10275
280
285
290
295
300
305
310
315
time (s)
Mechanicalpower(MW)
Unit #1 inelas
Unit #2 inelas
Unit #1 dist
Unit #2 dist
8/10/2019 Simulation of Hydroelectric System Control
13/24
9
4.2 Linearisedmodel
It is useful to have a linear model so that classical control system methods can be applied to
designing a basic controller. Using standard techniques, equations (4.2) and (2.1) can be linearised
to give a small signal state space model of the usual form:
x Ax Bu
y Cx Du
= +
= +
(4.3)
In perunit form, changes in output power (Pm) are related to changes in flow (q) and guide vaneposition (G) around a fixed operating point (G0) by:
01 011 11 12 1 11 12 1
02 022 21 22 2 21 22 2
1 1 1
2 2 2
1 / 0 1 / 02 2
0 1 / 0 1 /
3 0 2 0
0 3 0 2
m
m
G Gq a a q a a G
G Gq a a q a a G
P q G
P q G
= +
=
(4.4)
where the terms a11... a22are the elements of the inverse of the water starting time matrix in (4.2).
Equation (4.4) is a linear relationship whose characteristics change with the selected GV openings
of the two turbines which define the operating points G 01and G02.
Finally, following Sec. 3 in reference [2], the generator model of equation (2.3) can be appended to
the hydraulic model of equation (4.4) to relate changes in Unit speed (r) to GV position (G). Thecomposite model is then in a suitable form for designing a closed loop speed control system.
5 Controlsystemdesign
The crosscoupling terms in equation (4.4) reflect the intrinsic hydraulic coupling of the penstocks
in the physical system. It is known that significant coupling leads to loss of stability margin, so
Jones [6] has proposed a multivariable controller which takes this into account. However, the
traditional (and simpler) strategy of treating the penstocks as being separate is adopted here. This
allows tuning rules for a singleinput singleoutput (SISO) system to be applied to the design of a
basic PID governor for speed control when supplying an isolated load a procedure recommended
in Section F.3 of [1].
A Simulink block diagram for the SISO linearised model and governor is shown in Figure 8 (the
power feedback loop is eliminated by setting the droop gain to zero). Tuning the gains K i, Kpand Kd
for satisfactory closed loop response is done by applying the rules proposed by Hagihara et al [7],
[2] as follows:
"transient droop" Rt= 1/Kp= 5TW/ 8H "transient droop washout time constant" TR= Kp/ Ki= 3.333*TW Kd= TWKp/ 3
8/10/2019 Simulation of Hydroelectric System Control
14/24
10
Figure8Blockdiagramofthelinearsystemarrangedforclosedloopspeedcontrol.
Setting the operating point at 100% and knowing the Units inertia constant (H) and the water
starting time, taken here as TW= (TW1+ Tw3) = 0.343s for the tunnel and penstock #1, allows the
gains to be evaluated as Ki= 16.1, Kp= 18.4 and Kd= 2.1.
It is common to include an additional pole in a PID compensator to limit high frequency noise due
to the derivative term. Placing it at
=100 r/s means that it has only a minor effect on the closed
loop dynamics.
The open loop Bode plot for the Plant, compensator and forward loop is shown in Figure 9, which
conforms to the typical pattern for a hydroelectric Plant see [2] and sections F1.4.1 and F.3 in [1].
The crossover frequency is about 3r/s. The effect of the righthalf plane zero on the Plant frequency
response is evident in the range 1/TWto 2/TW(3 to 6 r/s), where the increasing phase lag is not
accompanied by a corresponding fall in gain. This limits how much phase lead can be contributedby the compensator over this frequency range, because the associated increase in gain could make
the forward loop gain start to increase. As pointed out in [2], this could easily cause a second
crossover and closed loop instability.
The root locus (see sections F.1.5 & F.1.6 in [1]) for this case is shown in Figure 10. It is possible,
using proportional gain alone, to place the dominant closedloop poles at approximately the same
locations as with the PID controller. However, the step response has a 10% steadystate error and
it is necessary to introduce the integral term to counter it.
Figure 11 shows the closed loop step response to a 0.02 p.u. step demand in speed. The very large
initial dip in the generators speed is due to the very large and rapid GV motion. In practice, a ratelimiter would be included to moderate this action.
hydlin 01.mdl
Simple linearised model
speed
ref
power --> speed
sys2
droop
0
Sum 1
Sum Speed , power
and GV
Power
ref
Governor
power
speed_err
GV
GV --> power
sys1P
S
GV
GV
1
proportional
Kp
integral
Ki
s
derivative
wl*Kd.s
s+wl
Sum1Sum
speed_err
2
power
1
8/10/2019 Simulation of Hydroelectric System Control
15/24
11
Figure9OpenloopBodeplotforthePlant,PIDcontrollerandforwardloop.
Figure10Rootlocusfor(i)thePlantwithproportionalgainonly,(ii)withthePIDcontroller(wherethe
diamondsshowthelocationsofthedominantclosedlooppoles).
-100
-50
0
50
100
Mag
nitude(dB)
10-2
100
102
104
-270
-225
-180
-135
-90
-45
0
45
90
Phase
(deg)
Frequency (rad/sec)
Plant
Compensator
Forward loop
-10 -8 -6 -4 -2 0 2 4 6 8 10-10
-5
0
5
10Root locus for Plant
Real Axis
Imag
inary
Ax
is
-10 -8 -6 -4 -2 0 2 4 6 8 10-10
-5
0
5
10Root locus for Plant + Governor
Real Axis
Imag
inary
Ax
is
8/10/2019 Simulation of Hydroelectric System Control
16/24
12
Figure11StepresponseofthelinearisedmodelwiththegovernortunedusingtheHagihararules.
It is concluded that traditional analysis, using the linearised, SISO inelastic model gives a good
firstcut at a control system, sufficient at least to use in further simulation using the more accuratemodels. This approach is likely to be overly optimistic in estimating how much gain can be
included in the controller. In a multipenstock installation, hydraulic coupling can have a significant
adverse effect on stability. A long penstock has a large water starting time, which encourages the
designer to include as much derivative action as possible, in order to improve closed loop
bandwidth. However, this is precisely the case where travelling wave effects are significant and
controller design becomes more critical. It is at least necessary to test the controller on a model
with elastic water column, which may indicate that the PID gains must be reduced to prevent an
underdamped response or even instability. In such cases, it would desirable to take the travelling
wave effect into account during control system design.
6 ClosedloopsimulationwithGridconnection
In this section, three operational scenarios are considered. The simulations are performed using
the distributed parameter model for the hydraulics and the PID governor designed in the previous
section. In all cases, additional dynamics to represent the GV servo lags are included as the transfer
function:
( ) 2.5 5.26
( ) ( 2.5) ( 5.26)G
G s
u s s s= + + (6.1)
0 1 2 3 4 5 6 7 8-0.04
-0.02
0
0.02
0.04
Speed(pu)
PID gains Ki = 16.1, Kp = 18.4, Kd = 2.11
0 1 2 3 4 5 6 7 8-10
-5
0
5
Power(pu)
0 1 2 3 4 5 6 7 8-2
0
2
4
6
Guidevane(pu)
time (s)
8/10/2019 Simulation of Hydroelectric System Control
17/24
13
6.1 Frequencycontrolmode.
Control of Grid frequency typically involves several regulators, of varying capacity and speed of
response, simultaneously connected to the power system. The role of a hydroelectric station in
frequencycontrol mode is to provide accurate and timely supply of its target power contribution to
the Grid. Stable sharing of the load between all the regulating sources is achieved by including a
speed regulation or droop characteristic in their governors.
The objective is to test the response of the Plant to a simulated speed (frequency) step see section
9.2.9 in [1]. The block diagram for the governor, based on the design in the previous section, is
shown in Figure 12. The block diagram for the complete simulation is shown in Figure 13.
Figure12
Simulink
block
diagram
for
the
governor.
There are two feedback loops:
The electrical power generated by the individual Units is measured by a sensor and filter,
represented by the transfer function 1( 1)s + . The power error (P) is formed as the
difference between a (fixed) reference power and the measured electrical power. This is
fed through a droop gain () to the PI part of the controller.
The frequency error (f) is formed as the difference between the demanded and measuredGrid frequency and also added as an input to the PI part of the controller. The frequencyerror is also fed forward into the GV control signal (u G), via the derivative part of the
controller, in order to reduce system response time.
The GV control is therefore formed as:
( ) ( )G Pu PI PID f = + (6.2)
The sum of the electrical powers from the two generators is used as an input to the Grid model.
PID Governor
control 1
1
prop gain
Kp
power
transducer
1
s
int gain
Ki
droop
droop
Integrator
1
s
FF gain
Kff
D term
wl*Kd.s
s+wl
Pe1
3
power _ref1
2
freq _err
1
8/10/2019 Simulation of Hydroelectric System Control
18/24
Figure13Simulinkblockdiagramforthecompletesimulation
Hydroelectric plant with PID control system .
Hydraulics represented using the Method of Characteristics .
This simulation is called from hydraul _p3.m.
zero
0
select
p.u. base
1/Pb
index
indval
Terminator 1
Terminator
Power
set #1
Power
ref #2
Pe_2
Power
ref #1
ramp Plant
hydraulics
S_moc _v1
Governor 2
freq_err
power_ref2
Pe2
control2
Governor 1
freq_err
power_ref1
Pe1
control1
Generator #2
mech_power
Grid_freq
elec_power
Generator #1
mech_power
Grid_freq
elec_power
GV dynamics
GVC1
GVC2
G1
G2
Freqdem #2
0
Freq
dem #1
G1
G2
GVC1
GVC 2
Pm
H
Q
8/10/2019 Simulation of Hydroelectric System Control
19/24
15
The simulation is initialised with Units #1 and #2 supplying 100MW and 288MW respectively. The
test input is a step frequency change of 0.07Hz (0.14 p.u.). The result is shown in Figure 14.
Figure14Responsetoastepdemandof0.07Hzinfrequency-controlmode;droopof1%.
Raising the Grid frequency by 0.07Hz requires an additional 506MW of power of which 42MW is
picked up by Unit #1.
Figure 14 is known as the systems primary response characteristic. For generators on the England
& Wales Grid, a typical specification requires 70 90% of the target power output to be achieved
within 10s of the occurrence of the event leading to the frequency deviation [8]. This system
achieves 36.5MW (87%) of its target contribution in 10s, which is within the specified range.
Developing a more detailed specification (see [9]) and a more accurate simulation will yield an
improved assessment of the systems capability.
0 5 10 15 20 25100
110
120
130
140
Unit#1power(M
W)
Freq. loop PID gains Ki = 16.1, Kp = 18.4, Kd = 2.11
mechanical
electrical
0 5 10 15 20 25280
285
290
295
Unit#2p
ower(MW)
mechanical
electrical
0 5 10 15 20 250
0.5
1
Guidevane(pu)
Unit #1
Unit #2
0 5 10 15 20 25
1
1.05
1.1x 10
-3
Grid stiffness = 0.083 pu
Gridfreq(pu)
time (s)
8/10/2019 Simulation of Hydroelectric System Control
20/24
16
6.2 Powerdialupmode.
In this mode, the goal is to change the generated power rapidly in response to a dialledin
operator request see section 9.2.4 in [1]. Instead of applying a step reference change directly to
the PID, it is preferable to generate a ramp power reference (whose slope is essentially determined
by the maximum allowable GV opening rate) and to feed this forward directly to the GV control via
a gain Kffas well as to the PID.
In general, the feedforward and PID gains would be optimised for this specific mode of operation
but in this simulation the PID settings are kept at their previous values, with K ff= 1. Unit #1 is
commanded to increase its output from 100MW to 205MW by ramping the GV control to its new
setting in 2.6s. This case is similar to Figure 3 but not identical because of the intervening GV
dynamics (6.1). The results are presented in Figure 15.
Figure15ResponsetoarampGVinputindial-upmode.
The graph shows that the required power change is achieved in 3s although there is an overshoot
of 28 MW (27%) followed by a long decay to the final value. Experiment shows that both overshootand settling time could be improved by reducing the feedforward gain.
0 5 10 15 20 25100
150
200
250
Unit#1power(MW
)
Power ramp PI gains Ki = 16.1, Kp = 18.4. Feedforward Kff = 1
mechanical
electrical
0 5 10 15 20 25270
280
290
300
Unit#2p
ower(MW)
mechanicalelectrical
0 5 10 15 20 250
0.5
1
Guidevane(pu)
Unit #1
Unit #2
0 5 10 15 20 25
1
1.2
1.4
x 10-3 Grid stiffness = 0.083 pu
Gridfreq(pu)
time (s)
8/10/2019 Simulation of Hydroelectric System Control
21/24
17
6.3 Fullloadrejection.
The objective here is to assess performance when the system is disconnected suddenly from the
Grid, perhaps because of some fault condition (see section 9.2.3 in [1]). When the Grid breaker
trips, the reaction torque on the turbine vanishes and the excess torque causes it to accelerate, with
a risk of overspeeding, unless prompt action is taken to close the GV. However, the rate at which
the GV can be closed is limited by overpressure transients in the penstock.
The block diagram of Figure 16 includes a logic signal that simulates the Grid breaker by
disconnecting the feedback loops for electrical power and Grid frequency from the
turbine/generator block. It also initiates an open loop rampdown of both GV controls at a rate of
1/12 p.u./s.
Figure16Simulinkblockdiagramforsimulatingloadrejection.
In Figure 17, the electrical power reduces instantaneously to zero when the breaker is tripped and
both GVs begin to close at a fixed rate, causing the mechanical power produced by the turbines to
decrease. During the closure interval, Unit #1 peaks at 5% overspeed and Unit #2 at 20% over
speed; the Grid frequency decreases to its nominal value. Figure 19 shows the predicted volumetric
flow and head at the two turbine inlets. The flows decrease more or less in proportion to the GV
opening, as expected. As the closure begins, there is a sharp increase in turbine head which starts a
travellingwave oscillation of identical amplitude in both penstocks, because they are hydraulically
coupled. Once GV #1 is fully closed, the mean level of the oscillation decreases and a further
reduction occurs once GV #2 closes, leaving a longlived oscillation around the static head. Whetheror not the pressure variation is acceptable depends on the structural strength of the installation.
Hydroelectric plant simulation for total load rejection .
Hydraulics represented using the Method of Characteristics .
This simulation is called from hydraul _p3.m.
select
p.u. base
change
1/100
p.u. base
1/Pb
earth
breaker
Terminator 1
Terminator
Plant
hydraulics
S_moc_v1Grid model
rs
Generator #2
mech_power
Grid_freq
breaker
elec_power
Generator #1
mech_power
Grid_freq
breaker
elec_power
GV ref #2
ramp
GV ref #1
ramp
GV dynamics
GVC1
GVC2
G1
G2
GV
set #2
GV
set #1
Pe2
Pe1G1
G2
GVC2
GVC1 PmPelec grid_freqgrid_freq
H
Q
elec_ power
1
sync
torque
wb*Ks
selectinertia
1/(2*H)
earth
damping
coefficient
KD
Integrator 1
1
s
Integrator
1
s
breaker
3
Grid_freq
2
mech_ power
1
sp1
8/10/2019 Simulation of Hydroelectric System Control
22/24
18
Figure17Fullloadrejection:GVclosureandpoweratbothUnits.
Figure18Fullloadrejection,showingspeedincreaseforbothUnitsanddropinGridfrequency.
0 5 10 15 200
50
100
150
Unit#1power(MW)
mechanical
electrical
0 5 10 15 200
100
200
300
Unit#2power(MW)
mechanical
electrical
0 5 10 15 200
0.2
0.4
0.6
0.8
1
time (s)
Guidevane(pu)
Unit #1
Unit #2
0 5 10 15 200
0.05
0.1
0.15
0.2
Generatorspeed(pu)
Unit #1
Unit #2
0 5 10 15 20-4
-2
0
2
4
6
8
10x 10
-4 Grid stiffness = 0.083 pu
Gridfreq(pu)
time (s)
8/10/2019 Simulation of Hydroelectric System Control
23/24
19
Figure19Fullloadrejection:pressureandflowinthetwopenstocks.
7 Conclusion
The generic models used here provide a wealth of predictive information early in the project, based
on a small set of critical parameters. Although model validation, by comparison with the real
installation, would usually not be possible at this stage, the methods adhere to industry standards
and are well tried and tested on other Plant. The main points of the study are:
basic prediction of pressure and flow variation in the conduit, which can be used to enhanceruleofthumb calculations and precede detailed hydraulic analysis;
development of lumped and distributed parameter models to predict system performance; development of a basic PID governor; simulation under different operational scenarios:
o in frequencycontrol mode, the primary response characteristic is shown to comply
with specification;
o in power dialup mode, feedforward allows a very rapid change of power level to
be made;
o
during full load rejection, the Unit overspeed is limited to 20% during GV closure.
0 5 10 15 20510
515
520
525
530
535
540
545
Headatturbine(m)
Unit #1
Unit #2
0 5 10 15 200
10
20
30
40
50
60
time (s)
Flowatturbine(m3/s)
Unit #1
Unit #2
8/10/2019 Simulation of Hydroelectric System Control
24/24
Clearly, predictions made on the basis of simplified models have a margin of error and need to be
treated with caution. Nevertheless, they provide valuable results that can be used to make better
informed decisions on later stages of the project. The generic package reported here is only the
first stage of simulation based design. There is ample scope for extension and refinement of the
models as more details of the installation become available.
References
1 Std 12072004, 'IEEEGuidefortheApplicationofTurbineGoverningSystemsforHydroelectric
Generating
Units', New York, IEEE 2004.2 IEEE, W. G.: 'Hydraulic turbine and turbine control models for system dynamic studies',
IEEETransPowerSystems, 1992, 7,(1), pp. 167179.
3 Larock, B. E., Jeppson, R. W. and Watters, G. Z.: 'Hydraulics of Pipeline Systems', 1999 (CRCPress).
4 Kundur, P.: 'Power System Stability and Control', 1994 (McGraw Hill).
5 Jones, D. I.: 'Dynamic parameters for the National Grid', Proc
IEE
Gener.
Transm.
Distrib.,2005, 152,(1), pp. 5360.
6 Jones, D. I.: 'Multivariable control analysis of a hydraulic turbine', TransInstMC, 1999, 21,
(2/3), pp. 122136.
7 Hagihara, S., Yokota, H., Goda, K., et al.: 'Stability of a hydraulic generating unit controlled by
PID governor', IEEETransonPowerApparatus&Systems, 1979, PAS-98,(6), pp. 2294
2298.8 Erinmez, I. A., Bickers, D. O., Wood, G. F., et al.: 'NGC experience with frequency control in
England and Wales provision of frequency response by generators'. Proc IEEE Power
Engineering Society Winter Meeting, New York. 1999, pp 590596.9 Jones, D. I., Mansoor, S. P., Aris, F. C., et al.: 'A standard method for specifying the response of
hydroelectric plant in frequencycontrol mode', ElectricPowerSystemsResearch, 2004, 68,
(1), pp. 1932.