Simulation of Hydroelectric System Control

Embed Size (px)

Citation preview

  • 8/10/2019 Simulation of Hydroelectric System Control

    1/24

    Simulation of hydroelectric

    system control

    Dewi Jones

  • 8/10/2019 Simulation of Hydroelectric System Control

    2/24

    Simulation of hydroelectric system control

    Dewi Jones

    Report GW002

    October 2008

    GWEFR CyfTechnium CAST

    Ffordd Penlan

    Parc Menai

    Bangor

    Gwynedd LL57 4HJ

    Wales

    Tel: +44 (0) 2921 251768

    Email:[email protected]

    http://www.gwefr.co.uk

    Care has been taken in the preparation of this report but all advice, analysis, calculations, information, forecasts and

    recommendations are supplied for the assistance of the relevant client and are not to be relied upon as authoritative or as in

    substitution for the exercise of judgement by that client or any other reader. Neither GWEFR Cyf, nor any of its personnel

    engaged in the preparation of this Report shall have any liability whatsoever for any direct or consequential loss arising from

    the use of this Report or its contents and give no warranty or representation (express or implied) as to the quality or fitness for

    the purpose of any process, product or system referred to in the Report.

    Copyright in this Report remains the sole property of GWEFR Cyf.

    mailto:[email protected]:[email protected]:[email protected]://www.gwefr.co.uk/http://www.gwefr.co.uk/http://www.gwefr.co.uk/mailto:[email protected]
  • 8/10/2019 Simulation of Hydroelectric System Control

    3/24

    Contents

    1 Introduction ........................ ........................ .................... ..................... ...................... .................... ...................... ..... 1

    2 Outline of the simulation ........................ ...................... ..................... ...................... .................... ..................... ... 1

    2.1 Physical layout ...................... ..................... ..................... ...................... .................... ..................... ................. 1

    2.2 Model summary ..................... ....................... ..................... ..................... ...................... .................... ............. 3

    3 Simulation of hydraulic system with fixed rate GV opening ................. ..................... ...................... ..... 4

    4 Lumped parameter models ........................ .................... ...................... ...................... .................... .................... 7

    4.1 Lumped parameter, inelastic water column model .................... ...................... ..................... ......... 7

    4.2 Linearised model ....................... ...................... ..................... ...................... .................... ..................... .......... 9

    5 Control system design ....................... ...................... ..................... ...................... .................... ..................... .......... 9

    6 Closed loop simulation with Grid connection .................... ..................... ...................... ..................... ...... 126.1 Frequency control mode. ......................... ..................... ...................... ...................... ..................... ......... 13

    6.2 Power dialup mode. ....................... ...................... ..................... ...................... ..................... .................... 16

    6.3 Fullload rejection. ........................ ..................... ...................... ..................... ..................... ...................... .. 17

    7 Conclusion............................................................................................................................................................... 19

  • 8/10/2019 Simulation of Hydroelectric System Control

    4/24

  • 8/10/2019 Simulation of Hydroelectric System Control

    5/24

    1

    1 Introduction

    This sample report outlines how the generic simulation package offered by GWEFR Cyfcan

    provide valuable information about the dynamic response of a proposed hydroelectric installation,

    given just the basic information about the Plants physical layout, its primary parameters and

    modes of operation.

    The objective is to increase understanding of how the proposed hydraulic and electrical systems

    affect the dynamic response of the Plant and hence the quality of power generation an approach

    advocated in IEEE Standard 12072004 IEEE Guide for the Application of Turbine Governing

    Systems for Hydroelectric Generating Units [1].

    The following section presents a simplified version of the hydraulic system, composed of a

    reservoir supplying two Gridconnected Francis turbine/generators via a common tunnel, a

    manifold and two identical penstocks. This is used as the basis of a travellingwave model that

    estimates the pressure and flow variations in the water passages under defined rates of opening or

    closing of the turbine guide vanes.

    Comparisons are made between the responses produced by three different types of model, as

    suggested by an expert IEEE Working Group [2]:

    Nonlinear distributed parameter, elastic water column the most accurate model butcomputationally intensive;

    Nonlinear lumped parameter, inelastic water column requires less computation but doesnot represent travellingwave effects;

    Linearised model suitable for control design.

    Standard tuning rules are applied to design a PID controller based on the linearised model.

    The resulting governor is integrated with models for the hydraulics, turbine/generator and Grid to

    study system performance for 3 scenarios:

    Closed loop frequencycontrol mode Dialup power mode with feedforward Full load rejection

    The report provides constructive input to the requirements capture stage of the project and

    forthcoming design efforts.

    2 Outlineofthesimulation

    2.1 Physicallayout

    Figure 1 shows the general layout of the hydraulic system assumed in the model. The reservoir is

    connected by a long supply tunnel to a manifold that separates into two identical penstocks, which

    feed identical turbine/generators. The tailrace is not included in the model at this stage. Note that

    the layout is not quite symmetrical because the water path to Unit #2 has additional length due to

    the manifold. The dimensions are shown in Figure 2.

  • 8/10/2019 Simulation of Hydroelectric System Control

    6/24

    2

    Figure1Generallayoutofthehydraulicsystem.

    Figure2Cross-sectionandplanviewsshowingdimensions(datumtakenatturbineinlet).

    513m

    880m

    10m

    9.5

    m

    130m

    3.3m

    10m

    80m

    9.5m

    130m

    3.3m

  • 8/10/2019 Simulation of Hydroelectric System Control

    7/24

    3

    2.2 Modelsummary

    Hydraulicsystem:

    The 4 pipe sections are modelled using the Method of Characteristics [3] which is used to compute

    the time variation of piezometric pressure and uniform flow at 100 discrete points in the network.

    All head losses except for friction are considered negligible. There are 5 boundary conditions:

    The head at the reservoir outlet is considered constant. At the branch between tunnel, manifold and penstock #1 the head is constrained to be

    identical for all 3 branches and continuity of flow is applied.

    Similar conditions are applied at the junction between the manifold and penstock #2. Both turbines are modelled as idealised lossless control components where the relationship

    between head and flow is given by:

    2

    2u tb

    VH A

    G

    =

    (2.1)

    where Hu= head across the turbine

    V = flow through the turbine

    Atb= turbine constant

    G = guide vane opening (0 : 1)

    For a flow, Q, the mechanical output power of a turbine is given by:

    m u

    P QH g= (2.2)

    Electricalsystem

    It is assumed that the generators are Gridconnected and represented by a linearised version of the

    classic swing equations as given, for example, by Kundur [4]:

    ( )

    ( )0

    1

    2r m e D r

    se r L

    P P KHs

    KP Ps

    =

    =

    (2.3)

    where:

    G= Grid frequency

    r= Unit (electrical) speed

    PL= load change on Grid

    Pm= turbine mechanical power

    Pe= generator electrical power

    0, r= rated and actual Unit speed

    Ks= synchronising coefficient

    KD= speed damping coefficient

    H = inertia constant

    s = Laplace variable

  • 8/10/2019 Simulation of Hydroelectric System Control

    8/24

  • 8/10/2019 Simulation of Hydroelectric System Control

    9/24

    5

    Figure 3 shows that the flow velocity increases in penstock #1 as GV #1 opens with a small dip in

    the velocity in penstock #2 over the same period. Opening GV #1 causes the pressure at the turbine

    inlet to fall and, after a brief delay while the pressure wave travels through the 2 penstocks and the

    manifold, hydraulic coupling causes the pressure at turbine #2 to decrease. The response also

    exhibits a poorly damped oscillation with a period of 0.7s as the travelling wave traverses the

    tunnel. These effects are reflected in the generated power. Turbine #1 is subject to a brief time

    delay before the required power increase begins while turbine #2 is perturbed from its set level.

    Figure3Variationofpressurehead,penstockflowandmechanicalpowerwithGV#1openingin2.6s.

    Figure 4 shows the head and flow profiles in the pipe network shortly after the simulation isinitiated. The pressure head increases, because of elevation, along the length of the tunnel and then

    flattens out over the length of the penstock (the red line shows the pressure in penstock #1). The

    small notch of lower velocity between 880 and 960m is located at the manifold, which only carries

    the flow to penstock #2. An animated version of Figure 4 shows the pressure wave travelling up

    and down the tunnel as the simulation proceeds.

    This is a very simple model of the hydraulic system (it should be emphasised that it is not a

    substitute for a full study for structural engineering purposes) but quite satisfactory for

    representing the dynamics within the tolerance required for a control systems study. Clearly, in

    this particular example, the pressure variation is within bounds and quite satisfactory in thisrespect.

    480

    490

    500

    510

    520

    pressurehead(m)

    2

    3

    4

    5

    6

    7

    penstockvelocity(m/s)

    penstock #1

    penstock #2

    0 5 10 15

    100

    150

    200

    250

    300

    mechanicalpower(MW

    )

    time (s)

    turbine #1

    turbine #2

    turbine #1

    turbine #2

    branch

  • 8/10/2019 Simulation of Hydroelectric System Control

    10/24

    6

    Figure4Pressureandflowprofilesinthetunnelandpenstocks.

    Figure5Variationofpressurehead,penstockflowandmechanicalpowerwithGV#1openingin1.0s.

    0 200 400 600 800 10000

    100

    200

    300

    400

    500

    pressurehead(m)

    0 200 400 600 800 10000

    1

    2

    3

    4

    5

    6

    7

    flowvelocity(m/s)

    0 200 400 600 800 1000

    Pressure head variation (normalised to max and min of range)

    distance along pipe (m)

    440

    460

    480

    500

    520

    540

    pressurehead(m)

    2

    3

    4

    5

    6

    7

    penstockvelocity(m/s)

    penstock #1

    penstock #2

    0 5 10 15

    100

    150

    200

    250

    300

    mechanicalpower(MW)

    time (s)

    turbine #1

    turbine #2

    turbine #1

    turbine #2

    branch

  • 8/10/2019 Simulation of Hydroelectric System Control

    11/24

    7

    The result in Figure 5 was obtained by decreasing the opening time of GV #1 to 1.0s. This leads to a

    much larger variation in penstock pressure head, which falls to 11.5% below and rises to +4.5%

    above the static head. There is a corresponding variation of the mechanical power produced by the

    turbines, with perturbation peaks for turbine #2 of 9.7% and +6.7% of the steadystate value.

    4

    Lumpedparameter

    models

    4.1 Lumpedparameter,inelasticwatercolumnmodel

    The model presented in this section is derived from the block diagram in Sec. 2.6 of [2]. The water

    column is considered rigid so travellingwave effects are omitted. The inertia of the water column

    is represented by parameters known as the water starting times. The model is multivariable, so

    hydraulic coupling effects are retained. It is also nonlinear and suitable for use when simulating

    large excursions of the variables.

    The water starting time for a section of pipe of length is defined as:

    bW

    b

    VT

    gH

    =

    (4.1)

    For the layout of Figure 1, the relationship between the head and flow rate variation in the two

    penstocks is:

    1 3 11 1

    1 1 2 42 2

    1

    1

    W W W

    W W W W

    T T Th q

    T T T T h q

    + = + +

    (4.2)

    where:

    h1, h2are the turbine heads

    q1, q2are the turbine flows

    TW1is the water starting time for the tunnel (0.145s)

    TW2is the water starting time for the manifold (0.014s)

    TW3, TW4are the water starting time for penstock #1 and #2 respectively (both 0.198s).

    Inverting this relationship allows it to be embedded in a Simulink block diagram, as shown in

    Figure 6, which incorporates the nonlinear turbine characteristics and head losses due to friction.

    The simulation was run with GV #2 set to operate at a fixed power of 288MW. GV#1 was set for an

    initial output power of 280MW and then opened linearly over 2.6s to produce a steady state power

    of 310MW. The distributed parameter model was run for the same conditions and Figure 7 shows

    that there is a good match between the power outputs. Because the simulation is run here with Unit

    #1 operating at a higher power level than in Figure 5, both models predict an initial decrease of

    output power at turbine #1 (the characteristic nonminimumphase response). The obvious

    discrepancy of course is the absence of the travelling wave oscillation from the response predicted

    by the inelastic water column model. The difference becomes more evident as the GV opening or

    closing times become shorter.

  • 8/10/2019 Simulation of Hydroelectric System Control

    12/24

    8

    Figure6Simulinkblockdiagramfortheinelasticwatercolumnmodel.

    Figure7Comparisonofresponsesfordistributedparameterandlumpedparametermodels.

    Inelastic water column , multiple penstock model in p .u. representation .

    Based on Figure 8 of the IEEE Wkg Group paper .

    Pinel

    1

    no-load

    flow

    0

    inverse water

    starting time

    matrix

    iTmat * uvec

    friction

    head loss 2

    qhf

    friction

    head loss 1

    qhf

    damping 1

    1

    damping

    1

    Product 5

    Product 4

    Product 3

    Product 2

    Product 1

    Product

    P.U. base

    power

    Pb

    P.U. base

    head

    1

    Integrator 1

    1

    s

    Integrator

    1

    s

    Dw2

    0

    Dw1

    0

    Divide 1

    Divide

    G2

    2

    G1

    1

    h2

    q1

    q2

    Pm1

    Pm2

    h1

    0 1 2 3 4 5 6 7 8 9 10275

    280

    285

    290

    295

    300

    305

    310

    315

    time (s)

    Mechanicalpower(MW)

    Unit #1 inelas

    Unit #2 inelas

    Unit #1 dist

    Unit #2 dist

  • 8/10/2019 Simulation of Hydroelectric System Control

    13/24

    9

    4.2 Linearisedmodel

    It is useful to have a linear model so that classical control system methods can be applied to

    designing a basic controller. Using standard techniques, equations (4.2) and (2.1) can be linearised

    to give a small signal state space model of the usual form:

    x Ax Bu

    y Cx Du

    = +

    = +

    (4.3)

    In perunit form, changes in output power (Pm) are related to changes in flow (q) and guide vaneposition (G) around a fixed operating point (G0) by:

    01 011 11 12 1 11 12 1

    02 022 21 22 2 21 22 2

    1 1 1

    2 2 2

    1 / 0 1 / 02 2

    0 1 / 0 1 /

    3 0 2 0

    0 3 0 2

    m

    m

    G Gq a a q a a G

    G Gq a a q a a G

    P q G

    P q G

    = +

    =

    (4.4)

    where the terms a11... a22are the elements of the inverse of the water starting time matrix in (4.2).

    Equation (4.4) is a linear relationship whose characteristics change with the selected GV openings

    of the two turbines which define the operating points G 01and G02.

    Finally, following Sec. 3 in reference [2], the generator model of equation (2.3) can be appended to

    the hydraulic model of equation (4.4) to relate changes in Unit speed (r) to GV position (G). Thecomposite model is then in a suitable form for designing a closed loop speed control system.

    5 Controlsystemdesign

    The crosscoupling terms in equation (4.4) reflect the intrinsic hydraulic coupling of the penstocks

    in the physical system. It is known that significant coupling leads to loss of stability margin, so

    Jones [6] has proposed a multivariable controller which takes this into account. However, the

    traditional (and simpler) strategy of treating the penstocks as being separate is adopted here. This

    allows tuning rules for a singleinput singleoutput (SISO) system to be applied to the design of a

    basic PID governor for speed control when supplying an isolated load a procedure recommended

    in Section F.3 of [1].

    A Simulink block diagram for the SISO linearised model and governor is shown in Figure 8 (the

    power feedback loop is eliminated by setting the droop gain to zero). Tuning the gains K i, Kpand Kd

    for satisfactory closed loop response is done by applying the rules proposed by Hagihara et al [7],

    [2] as follows:

    "transient droop" Rt= 1/Kp= 5TW/ 8H "transient droop washout time constant" TR= Kp/ Ki= 3.333*TW Kd= TWKp/ 3

  • 8/10/2019 Simulation of Hydroelectric System Control

    14/24

    10

    Figure8Blockdiagramofthelinearsystemarrangedforclosedloopspeedcontrol.

    Setting the operating point at 100% and knowing the Units inertia constant (H) and the water

    starting time, taken here as TW= (TW1+ Tw3) = 0.343s for the tunnel and penstock #1, allows the

    gains to be evaluated as Ki= 16.1, Kp= 18.4 and Kd= 2.1.

    It is common to include an additional pole in a PID compensator to limit high frequency noise due

    to the derivative term. Placing it at

    =100 r/s means that it has only a minor effect on the closed

    loop dynamics.

    The open loop Bode plot for the Plant, compensator and forward loop is shown in Figure 9, which

    conforms to the typical pattern for a hydroelectric Plant see [2] and sections F1.4.1 and F.3 in [1].

    The crossover frequency is about 3r/s. The effect of the righthalf plane zero on the Plant frequency

    response is evident in the range 1/TWto 2/TW(3 to 6 r/s), where the increasing phase lag is not

    accompanied by a corresponding fall in gain. This limits how much phase lead can be contributedby the compensator over this frequency range, because the associated increase in gain could make

    the forward loop gain start to increase. As pointed out in [2], this could easily cause a second

    crossover and closed loop instability.

    The root locus (see sections F.1.5 & F.1.6 in [1]) for this case is shown in Figure 10. It is possible,

    using proportional gain alone, to place the dominant closedloop poles at approximately the same

    locations as with the PID controller. However, the step response has a 10% steadystate error and

    it is necessary to introduce the integral term to counter it.

    Figure 11 shows the closed loop step response to a 0.02 p.u. step demand in speed. The very large

    initial dip in the generators speed is due to the very large and rapid GV motion. In practice, a ratelimiter would be included to moderate this action.

    hydlin 01.mdl

    Simple linearised model

    speed

    ref

    power --> speed

    sys2

    droop

    0

    Sum 1

    Sum Speed , power

    and GV

    Power

    ref

    Governor

    power

    speed_err

    GV

    GV --> power

    sys1P

    S

    GV

    GV

    1

    proportional

    Kp

    integral

    Ki

    s

    derivative

    wl*Kd.s

    s+wl

    Sum1Sum

    speed_err

    2

    power

    1

  • 8/10/2019 Simulation of Hydroelectric System Control

    15/24

    11

    Figure9OpenloopBodeplotforthePlant,PIDcontrollerandforwardloop.

    Figure10Rootlocusfor(i)thePlantwithproportionalgainonly,(ii)withthePIDcontroller(wherethe

    diamondsshowthelocationsofthedominantclosedlooppoles).

    -100

    -50

    0

    50

    100

    Mag

    nitude(dB)

    10-2

    100

    102

    104

    -270

    -225

    -180

    -135

    -90

    -45

    0

    45

    90

    Phase

    (deg)

    Frequency (rad/sec)

    Plant

    Compensator

    Forward loop

    -10 -8 -6 -4 -2 0 2 4 6 8 10-10

    -5

    0

    5

    10Root locus for Plant

    Real Axis

    Imag

    inary

    Ax

    is

    -10 -8 -6 -4 -2 0 2 4 6 8 10-10

    -5

    0

    5

    10Root locus for Plant + Governor

    Real Axis

    Imag

    inary

    Ax

    is

  • 8/10/2019 Simulation of Hydroelectric System Control

    16/24

    12

    Figure11StepresponseofthelinearisedmodelwiththegovernortunedusingtheHagihararules.

    It is concluded that traditional analysis, using the linearised, SISO inelastic model gives a good

    firstcut at a control system, sufficient at least to use in further simulation using the more accuratemodels. This approach is likely to be overly optimistic in estimating how much gain can be

    included in the controller. In a multipenstock installation, hydraulic coupling can have a significant

    adverse effect on stability. A long penstock has a large water starting time, which encourages the

    designer to include as much derivative action as possible, in order to improve closed loop

    bandwidth. However, this is precisely the case where travelling wave effects are significant and

    controller design becomes more critical. It is at least necessary to test the controller on a model

    with elastic water column, which may indicate that the PID gains must be reduced to prevent an

    underdamped response or even instability. In such cases, it would desirable to take the travelling

    wave effect into account during control system design.

    6 ClosedloopsimulationwithGridconnection

    In this section, three operational scenarios are considered. The simulations are performed using

    the distributed parameter model for the hydraulics and the PID governor designed in the previous

    section. In all cases, additional dynamics to represent the GV servo lags are included as the transfer

    function:

    ( ) 2.5 5.26

    ( ) ( 2.5) ( 5.26)G

    G s

    u s s s= + + (6.1)

    0 1 2 3 4 5 6 7 8-0.04

    -0.02

    0

    0.02

    0.04

    Speed(pu)

    PID gains Ki = 16.1, Kp = 18.4, Kd = 2.11

    0 1 2 3 4 5 6 7 8-10

    -5

    0

    5

    Power(pu)

    0 1 2 3 4 5 6 7 8-2

    0

    2

    4

    6

    Guidevane(pu)

    time (s)

  • 8/10/2019 Simulation of Hydroelectric System Control

    17/24

    13

    6.1 Frequencycontrolmode.

    Control of Grid frequency typically involves several regulators, of varying capacity and speed of

    response, simultaneously connected to the power system. The role of a hydroelectric station in

    frequencycontrol mode is to provide accurate and timely supply of its target power contribution to

    the Grid. Stable sharing of the load between all the regulating sources is achieved by including a

    speed regulation or droop characteristic in their governors.

    The objective is to test the response of the Plant to a simulated speed (frequency) step see section

    9.2.9 in [1]. The block diagram for the governor, based on the design in the previous section, is

    shown in Figure 12. The block diagram for the complete simulation is shown in Figure 13.

    Figure12

    Simulink

    block

    diagram

    for

    the

    governor.

    There are two feedback loops:

    The electrical power generated by the individual Units is measured by a sensor and filter,

    represented by the transfer function 1( 1)s + . The power error (P) is formed as the

    difference between a (fixed) reference power and the measured electrical power. This is

    fed through a droop gain () to the PI part of the controller.

    The frequency error (f) is formed as the difference between the demanded and measuredGrid frequency and also added as an input to the PI part of the controller. The frequencyerror is also fed forward into the GV control signal (u G), via the derivative part of the

    controller, in order to reduce system response time.

    The GV control is therefore formed as:

    ( ) ( )G Pu PI PID f = + (6.2)

    The sum of the electrical powers from the two generators is used as an input to the Grid model.

    PID Governor

    control 1

    1

    prop gain

    Kp

    power

    transducer

    1

    s

    int gain

    Ki

    droop

    droop

    Integrator

    1

    s

    FF gain

    Kff

    D term

    wl*Kd.s

    s+wl

    Pe1

    3

    power _ref1

    2

    freq _err

    1

  • 8/10/2019 Simulation of Hydroelectric System Control

    18/24

    Figure13Simulinkblockdiagramforthecompletesimulation

    Hydroelectric plant with PID control system .

    Hydraulics represented using the Method of Characteristics .

    This simulation is called from hydraul _p3.m.

    zero

    0

    select

    p.u. base

    1/Pb

    index

    indval

    Terminator 1

    Terminator

    Power

    set #1

    Power

    ref #2

    Pe_2

    Power

    ref #1

    ramp Plant

    hydraulics

    S_moc _v1

    Governor 2

    freq_err

    power_ref2

    Pe2

    control2

    Governor 1

    freq_err

    power_ref1

    Pe1

    control1

    Generator #2

    mech_power

    Grid_freq

    elec_power

    Generator #1

    mech_power

    Grid_freq

    elec_power

    GV dynamics

    GVC1

    GVC2

    G1

    G2

    Freqdem #2

    0

    Freq

    dem #1

    G1

    G2

    GVC1

    GVC 2

    Pm

    H

    Q

  • 8/10/2019 Simulation of Hydroelectric System Control

    19/24

    15

    The simulation is initialised with Units #1 and #2 supplying 100MW and 288MW respectively. The

    test input is a step frequency change of 0.07Hz (0.14 p.u.). The result is shown in Figure 14.

    Figure14Responsetoastepdemandof0.07Hzinfrequency-controlmode;droopof1%.

    Raising the Grid frequency by 0.07Hz requires an additional 506MW of power of which 42MW is

    picked up by Unit #1.

    Figure 14 is known as the systems primary response characteristic. For generators on the England

    & Wales Grid, a typical specification requires 70 90% of the target power output to be achieved

    within 10s of the occurrence of the event leading to the frequency deviation [8]. This system

    achieves 36.5MW (87%) of its target contribution in 10s, which is within the specified range.

    Developing a more detailed specification (see [9]) and a more accurate simulation will yield an

    improved assessment of the systems capability.

    0 5 10 15 20 25100

    110

    120

    130

    140

    Unit#1power(M

    W)

    Freq. loop PID gains Ki = 16.1, Kp = 18.4, Kd = 2.11

    mechanical

    electrical

    0 5 10 15 20 25280

    285

    290

    295

    Unit#2p

    ower(MW)

    mechanical

    electrical

    0 5 10 15 20 250

    0.5

    1

    Guidevane(pu)

    Unit #1

    Unit #2

    0 5 10 15 20 25

    1

    1.05

    1.1x 10

    -3

    Grid stiffness = 0.083 pu

    Gridfreq(pu)

    time (s)

  • 8/10/2019 Simulation of Hydroelectric System Control

    20/24

    16

    6.2 Powerdialupmode.

    In this mode, the goal is to change the generated power rapidly in response to a dialledin

    operator request see section 9.2.4 in [1]. Instead of applying a step reference change directly to

    the PID, it is preferable to generate a ramp power reference (whose slope is essentially determined

    by the maximum allowable GV opening rate) and to feed this forward directly to the GV control via

    a gain Kffas well as to the PID.

    In general, the feedforward and PID gains would be optimised for this specific mode of operation

    but in this simulation the PID settings are kept at their previous values, with K ff= 1. Unit #1 is

    commanded to increase its output from 100MW to 205MW by ramping the GV control to its new

    setting in 2.6s. This case is similar to Figure 3 but not identical because of the intervening GV

    dynamics (6.1). The results are presented in Figure 15.

    Figure15ResponsetoarampGVinputindial-upmode.

    The graph shows that the required power change is achieved in 3s although there is an overshoot

    of 28 MW (27%) followed by a long decay to the final value. Experiment shows that both overshootand settling time could be improved by reducing the feedforward gain.

    0 5 10 15 20 25100

    150

    200

    250

    Unit#1power(MW

    )

    Power ramp PI gains Ki = 16.1, Kp = 18.4. Feedforward Kff = 1

    mechanical

    electrical

    0 5 10 15 20 25270

    280

    290

    300

    Unit#2p

    ower(MW)

    mechanicalelectrical

    0 5 10 15 20 250

    0.5

    1

    Guidevane(pu)

    Unit #1

    Unit #2

    0 5 10 15 20 25

    1

    1.2

    1.4

    x 10-3 Grid stiffness = 0.083 pu

    Gridfreq(pu)

    time (s)

  • 8/10/2019 Simulation of Hydroelectric System Control

    21/24

    17

    6.3 Fullloadrejection.

    The objective here is to assess performance when the system is disconnected suddenly from the

    Grid, perhaps because of some fault condition (see section 9.2.3 in [1]). When the Grid breaker

    trips, the reaction torque on the turbine vanishes and the excess torque causes it to accelerate, with

    a risk of overspeeding, unless prompt action is taken to close the GV. However, the rate at which

    the GV can be closed is limited by overpressure transients in the penstock.

    The block diagram of Figure 16 includes a logic signal that simulates the Grid breaker by

    disconnecting the feedback loops for electrical power and Grid frequency from the

    turbine/generator block. It also initiates an open loop rampdown of both GV controls at a rate of

    1/12 p.u./s.

    Figure16Simulinkblockdiagramforsimulatingloadrejection.

    In Figure 17, the electrical power reduces instantaneously to zero when the breaker is tripped and

    both GVs begin to close at a fixed rate, causing the mechanical power produced by the turbines to

    decrease. During the closure interval, Unit #1 peaks at 5% overspeed and Unit #2 at 20% over

    speed; the Grid frequency decreases to its nominal value. Figure 19 shows the predicted volumetric

    flow and head at the two turbine inlets. The flows decrease more or less in proportion to the GV

    opening, as expected. As the closure begins, there is a sharp increase in turbine head which starts a

    travellingwave oscillation of identical amplitude in both penstocks, because they are hydraulically

    coupled. Once GV #1 is fully closed, the mean level of the oscillation decreases and a further

    reduction occurs once GV #2 closes, leaving a longlived oscillation around the static head. Whetheror not the pressure variation is acceptable depends on the structural strength of the installation.

    Hydroelectric plant simulation for total load rejection .

    Hydraulics represented using the Method of Characteristics .

    This simulation is called from hydraul _p3.m.

    select

    p.u. base

    change

    1/100

    p.u. base

    1/Pb

    earth

    breaker

    Terminator 1

    Terminator

    Plant

    hydraulics

    S_moc_v1Grid model

    rs

    Generator #2

    mech_power

    Grid_freq

    breaker

    elec_power

    Generator #1

    mech_power

    Grid_freq

    breaker

    elec_power

    GV ref #2

    ramp

    GV ref #1

    ramp

    GV dynamics

    GVC1

    GVC2

    G1

    G2

    GV

    set #2

    GV

    set #1

    Pe2

    Pe1G1

    G2

    GVC2

    GVC1 PmPelec grid_freqgrid_freq

    H

    Q

    elec_ power

    1

    sync

    torque

    wb*Ks

    selectinertia

    1/(2*H)

    earth

    damping

    coefficient

    KD

    Integrator 1

    1

    s

    Integrator

    1

    s

    breaker

    3

    Grid_freq

    2

    mech_ power

    1

    sp1

  • 8/10/2019 Simulation of Hydroelectric System Control

    22/24

    18

    Figure17Fullloadrejection:GVclosureandpoweratbothUnits.

    Figure18Fullloadrejection,showingspeedincreaseforbothUnitsanddropinGridfrequency.

    0 5 10 15 200

    50

    100

    150

    Unit#1power(MW)

    mechanical

    electrical

    0 5 10 15 200

    100

    200

    300

    Unit#2power(MW)

    mechanical

    electrical

    0 5 10 15 200

    0.2

    0.4

    0.6

    0.8

    1

    time (s)

    Guidevane(pu)

    Unit #1

    Unit #2

    0 5 10 15 200

    0.05

    0.1

    0.15

    0.2

    Generatorspeed(pu)

    Unit #1

    Unit #2

    0 5 10 15 20-4

    -2

    0

    2

    4

    6

    8

    10x 10

    -4 Grid stiffness = 0.083 pu

    Gridfreq(pu)

    time (s)

  • 8/10/2019 Simulation of Hydroelectric System Control

    23/24

    19

    Figure19Fullloadrejection:pressureandflowinthetwopenstocks.

    7 Conclusion

    The generic models used here provide a wealth of predictive information early in the project, based

    on a small set of critical parameters. Although model validation, by comparison with the real

    installation, would usually not be possible at this stage, the methods adhere to industry standards

    and are well tried and tested on other Plant. The main points of the study are:

    basic prediction of pressure and flow variation in the conduit, which can be used to enhanceruleofthumb calculations and precede detailed hydraulic analysis;

    development of lumped and distributed parameter models to predict system performance; development of a basic PID governor; simulation under different operational scenarios:

    o in frequencycontrol mode, the primary response characteristic is shown to comply

    with specification;

    o in power dialup mode, feedforward allows a very rapid change of power level to

    be made;

    o

    during full load rejection, the Unit overspeed is limited to 20% during GV closure.

    0 5 10 15 20510

    515

    520

    525

    530

    535

    540

    545

    Headatturbine(m)

    Unit #1

    Unit #2

    0 5 10 15 200

    10

    20

    30

    40

    50

    60

    time (s)

    Flowatturbine(m3/s)

    Unit #1

    Unit #2

  • 8/10/2019 Simulation of Hydroelectric System Control

    24/24

    Clearly, predictions made on the basis of simplified models have a margin of error and need to be

    treated with caution. Nevertheless, they provide valuable results that can be used to make better

    informed decisions on later stages of the project. The generic package reported here is only the

    first stage of simulation based design. There is ample scope for extension and refinement of the

    models as more details of the installation become available.

    References

    1 Std 12072004, 'IEEEGuidefortheApplicationofTurbineGoverningSystemsforHydroelectric

    Generating

    Units', New York, IEEE 2004.2 IEEE, W. G.: 'Hydraulic turbine and turbine control models for system dynamic studies',

    IEEETransPowerSystems, 1992, 7,(1), pp. 167179.

    3 Larock, B. E., Jeppson, R. W. and Watters, G. Z.: 'Hydraulics of Pipeline Systems', 1999 (CRCPress).

    4 Kundur, P.: 'Power System Stability and Control', 1994 (McGraw Hill).

    5 Jones, D. I.: 'Dynamic parameters for the National Grid', Proc

    IEE

    Gener.

    Transm.

    Distrib.,2005, 152,(1), pp. 5360.

    6 Jones, D. I.: 'Multivariable control analysis of a hydraulic turbine', TransInstMC, 1999, 21,

    (2/3), pp. 122136.

    7 Hagihara, S., Yokota, H., Goda, K., et al.: 'Stability of a hydraulic generating unit controlled by

    PID governor', IEEETransonPowerApparatus&Systems, 1979, PAS-98,(6), pp. 2294

    2298.8 Erinmez, I. A., Bickers, D. O., Wood, G. F., et al.: 'NGC experience with frequency control in

    England and Wales provision of frequency response by generators'. Proc IEEE Power

    Engineering Society Winter Meeting, New York. 1999, pp 590596.9 Jones, D. I., Mansoor, S. P., Aris, F. C., et al.: 'A standard method for specifying the response of

    hydroelectric plant in frequencycontrol mode', ElectricPowerSystemsResearch, 2004, 68,

    (1), pp. 1932.