07.11.2012 1 Итоги работы Министерства транспорта и коммуникаций Республики Казахстан за 2011 год и задачи на 2012 год National Secretariat of IGC TRACECA in the Republic of Kazakhstan EU TRACECA Project “Logistics Processes and Motorways of the Sea II” Ministry of Transport and Communications of the Republic of Kazakhstan SILK WIND THE ROUTE OF MULTIMODAL BLOCK TRAIN (PROJECT PROGRESS PRESENTATION) SILK WIND THE ROUTE OF MULTIMODAL BLOCK TRAIN (PROJECT PROGRESS PRESENTATION) Ministry of Finance of the Republic of Kazakhstan Customs Control Committee

SILK WIND - TRACECA ORG

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SILK WIND - TRACECA ORG

07.11.2012 1

Итоги работы Министерства транспорта и коммуникаций Республики Казахстан 

за 2011 год и задачи на 2012 год

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

EU TRACECA Project “Logistics Processes and Motorways of the Sea II”

Ministry of Transport and Communications

of the Republic of Kazakhstan

SILK WIND THE ROUTE OF MULTIMODAL BLOCK TRAIN 

(PROJECT PROGRESS PRESENTATION)  

SILK WIND THE ROUTE OF MULTIMODAL BLOCK TRAIN 

(PROJECT PROGRESS PRESENTATION)  

Ministry of Finance of the Republic of KazakhstanCustoms Control Committee

Page 2: SILK WIND - TRACECA ORG

07.11.2012 National Secretariat of IGC TRACECA in the Republic of Kazakhstan 2

SILK WIND BLOCK TRAIN ROUTE

ZHEZKAZGAN‐BEINEU

Dostyk stationPRC border

NEW PORT, ALYAT

BAKU‐TBILISI‐KARS

MARMARAY RAIL TUBE TUNNEL

KAZAKHSTAN – CASPIAN SEA – BLACK SEA

Page 3: SILK WIND - TRACECA ORG

07.11.2012 3

PROJECT PROGRESS

INTERACTION WITH THE COUNCIL OF TURKIC SPEAKING STATES 

Agreement on interaction and cooperationon project implementation with TurkicCouncil has reached at the meeting of TurkicCouncil

(Meeting of Ministers in charge of Economy, 14.08.2012, Baku, Azerbaijan)

Interest and support to development oftransport link from Turkey via Georgia andAzerbaijan to Kazakhstan and further toChina was also expressed by the Heads ofStates at the Turkic Council Summit

(23.08.2012, Bishkek, Kyrgyzstan)

The issues of simplification of customs clearance procedures for Silk Wind train also discussed during the firstmeeting of the Heads of customs services of Turkic Council, where the parties have agreed to actively participatein project implementation

(05.10.2012, Nakhchivan, Azerbaijan)

“We have agreed to arrange meeting of Ministers of transport and communications of our countries to prepare the launch of the transport link  ‐ from Turkey, through Georgia and Azerbaijan to Kazakhstan and further to China. This is a major railway line, we decided to actively work on it” 

Nursultan Nazarbayev, Turkic Council Summit, 23.08.2012, Bishkek, Kyrgyzstan

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

Page 4: SILK WIND - TRACECA ORG

07.11.2012 4

PROJECT PROGRESS 

KAZAKHSTAN – AZERBAIJAN  IGC, September 2012 ,  Astana 

National Secretariat of IGC TRACECA of Kazakhstan

During negotiations of the ninth meeting of Kazakhstan‐Azerbaijan intergovernmental commission for 

economic cooperation Azerbaijan side has supported 

the «Silk Wind» project ‐Kazakhstan proposal to create a block‐

train of multimodal transport

Page 5: SILK WIND - TRACECA ORG

07.11.2012 5

SIGNING OF THE MEMORANDUM

Memorandum on the principles of joint activity on development of 

transport networks and organization of cargo transportation

within the implementation of the Silk Wind project is proposed to sign 

on November 28, 2012 in Izmir, Turkey

under Organization of the Black Sea Economic Cooperation (BSEC) 

international conference “Facilitation of Transport and Trade in the Black Sea, the Central Asia and the 

Middle East Regions” 

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

PROJECT PROGRESS

Page 6: SILK WIND - TRACECA ORG

07.11.2012 6

OBSTACLES AND TASKS

MAIN EXISTING ROUTES BETWEEN EU, CA AND PRC

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

Page 7: SILK WIND - TRACECA ORG

07.11.2012 7

TRANSPORT COSTS AND TIME COMPARISONS

Dostyk-Novorossisk-Istanbul$2966/TEU12-13 days

Sea routeLyanyungan-Hamburg

3100$/TEU45-60 days Chongqing-Duisburg

8600$/40ft.16-18 days

Taraz-Hamburgvia Riga - $6220/TEU (33-32 days)via Poti- $6896/TEU (40-42 days)

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

OBSTACLES AND TASKS

*rate does not include costs related to customs declaration, forwarding, lay-out and otherexpenses

Page 8: SILK WIND - TRACECA ORG

07.11.2012 8

SILK WIND BLOCK TRAIN ROUTE

EUROPE

AKTAU

DOSTYK

PRC

Silk Wind

ALTYNKOL

Существующая ж/д линия

Dostyk-Zhezkazgan-Beineu-Aktau-Baku-Akhalkalaki-Kars-Istanbul

$2489/ TEU*11-12 days

COMPETETIVE TARRIF AND APPROPRIATE TIME FRAME 

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

*rate does not include costs related to customs declaration, forwarding, lay-out and otherexpenses

Page 9: SILK WIND - TRACECA ORG

07.11.2012 9

KAZAKHSTANDostyk station – Aktau port Distance (km) Approximate cost (USD/TEU)

Dostyk‐MangyshlakKazakhstan Temir Zholy JSC

3828 953

Mangyshlak – port AktauKazkortranservice JSC

18 120

Aktau portCargo fee 

‐ 77

Aktau‐Baku sea freight 490  500

Additional charges

Average charge for lay‐over of transit carriage

80

Forwarding service 50

Transit customs declaration and other overhead costs

15

TOTAL 1795

SILK WIND BLOCK TRAIN ROUTE

COMPETETIVE TARRIF AND APPROPRIATE TIME FRAME 

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

Page 10: SILK WIND - TRACECA ORG

07.11.2012 10

REGULARITY OF FERRY SERVICE AT THE CASPIAN SEA

The only more or less regular service being the railferry and Ro‐Ro line run by CASPAR to/from Bakuperformed with rail ferries of 28 or 52 wagon capacityand small, out‐dated Ro‐Ros of 33 truck capacity (TIR)*

Lack of schedule for line Ro‐Ro services*

Lack of separate berths intended only for containerand Ro‐Ro vessels in Aktau port result in waiting timesfor Ro‐Ro vessels at roads *

According to the USAID report, the lack oftransparency in charging and pricing policy of Bakuport and CASPAR significantly affects the regularity oftransportations and attractiveness of the Caucasuscorridor in general **

* Analysis  of «Logmos II» Project Experts**USAID Competitiveness analysis of the Caucasus Transit Corridor, August 2012

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

OBSTACLES AND TASKS

Page 11: SILK WIND - TRACECA ORG

07.11.2012 11

TRANSPORT DOCUMENT FOR INTERNATIONAL RAIL CARGO TRANSPORTATIONS

Switching railway consignment note from SMGS to CIM on the Georgia/Turkey border; or use of common SMGS/CIM railway consignment note

Introduction of advance information exchange system between customs authorities and participants of transportation process of the member‐states (WG, Agreement)

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

OBSTACLES AND TASKS

Page 12: SILK WIND - TRACECA ORG

07.11.2012 12

DIALOG WITH CHINA AND BUSINESS

Promotion of the train

Organization of the ground  for dialogue (forum) at TRACECA platform with participation of forwarding companies and small‐medium business  of EU, Western Regions of PRC and TRACECA member‐states

* Source: USAID Competitiveness analysis of the Caucasus Transit Corridor, August 2012

Forecast of potential cargo*

Chinese cargo to Europe via CA and Caucasus 1 mln.t/year

CA cargo via Baltic ports 0,5 mln.t/year

CA transit cargo via Caucasus  7,7 mln.t/year by rail;  1,2 mln.t./year by road

Turkish cargo to CA via Novorossiysk and Volga‐Don 1,5 mln.t/year

Transit cargo via Turkey and Iran to CA  2,0 mln.t/year

Uzbek import via North corridor 0,3 mln.t/year

Kazakh import (dry cargo) 0,2 mln.t/year

OBSTACLES AND TASKS

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

Page 13: SILK WIND - TRACECA ORG

07.11.201213

TRANSIT ATTRACTIVINESS AND LOGISTICS (LPI 2012)

Source: Index LPI 2012, World Bank

2,692,48

2,77 3,51

116 86

77 27

OBSTACLES AND TASKS

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

Page 14: SILK WIND - TRACECA ORG

07.11.2012 14

DEVELOPMENT OF THE ROUTE

CENTRAL ASIA‐CASPIAN SEA‐BLACK SEA

Ст. Достыкгр.КНР

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

Page 15: SILK WIND - TRACECA ORG

07.11.2012 15

ACTION PLAN

National Secretariat of IGC TRACECA in the Republic of Kazakhstan

№ Action Form of completion Period of execution

1. Establishment of Working Group on implementation and contribution to planning, development and efficient executionof the «Silk Wind» project with the involvement of Permanent Secretariat of IGC TRACECA and EU technical assistance projects 

Establishment of Working Group under the Permanent Secretariat of IGC TRACECA including representatives of concerned authorities of the Parties

I quarter 2013 

2. Interaction with the customs authorities and national railway operators to introduce advance information exchange system between customs and the participants of the transportation process of the Parties

Introduction of the advance information exchange system between customs and the participants of the transportation process of the Parties

IV  quarter  2012.‐IV  quarter  2013

3. Drafting and approval of interagency Agreement on cooperation in advance information exchange between customs authorities 

Approval of the Agreement incorporating suggestions of the Parties 

I‐II  quarter  2013

4. Drafting and approval of interagency Agreement on development of cargo transportation in the direction ofKazakhstan‐Caspian Sea‐ Black Sea 

Approval of the Agreement incorporating suggestions of the Parties

IV  quarter  2012 –III  quarter  2013 

5. Signing of interagency Agreement on development of cargo transportation in the direction of  Kazakhstan‐Caspian Sea‐Black Sea

Signing of the Agreement II  quarter  2013

6. Signing of  interagency Agreement on cooperation in advance information exchange between customs authorities of the Parties

Signing of the Agreement IV  quarter  2013 

Page 16: SILK WIND - TRACECA ORG

Thank you for attention!

07.11.2012 16National Secretariat of IGC TRACECA in the Republic of Kazakhstan