Upload
hathuy
View
216
Download
0
Embed Size (px)
Citation preview
SIDEWALK MASTER
PLAN APRIL 2003
ST. ALBANS TOWN, VERMONT . I
This plan was produced by Engineered Solutions, Inc. and
· Kathleen Ryan,Landscape Architect of Burlington, VT
Table of Contents TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April 2003
Introduction .... ... .... ... ....... ....... ... .... .... ........ .. ..... ... ..... ....... ... .... ..... ..... .......... .... ... ...... .... ... .... ......... .... . 1
Decision Making Criteria ......... ....... .. ..... ..... ...... .... .. .. .... ... .. ... .. .. ..... .... ... ....... ........ ... .... ... ...... ....... ...... 3
Origins and Destinations ... ..... .... ... ............ .............. .. ....... ..... ...... ... .... .. ... ... ...... .. .... ...... ... .......... .. ..... . 7
Area A - Exit 20 Highgate Commons ........ ... ........ ....................... ........ ..... .......... .... ....... ... ................. .. ......... ....... 9 Area B - Hardack and NW Regional Medical ...... .......... ......... .. ........ .. ...... ....... .... .... ................ .. ....... ... .......... ..... 9 Area C - Co/ins Perley ...... ................ .. .......................... .. .. ..... ........ .............. ............. ... ................ .................... I 0 Area D - Industrial Park ........ .. ........................................... .. .......................... ... .. .. .. ... .... ...... ............... ........ .... I 0 Area E- West Side ..... ... ...... ..... ..... ........ ...... ... .. ........ .. ..... .. ... ...... .... .... ... .... .. ... ..... .... ....... ........ ... ..... .. ........ .... .... 11 A rea F - St. Albans Bay ............... .. .. ............... .. ..................... .... ....... .. ... .. ... ..................................................... II
Sidewalk Corridors .. ... ... ..... .. .... ..... ............ ... ......... .. .. ... ..... .. ........... .................. ........... ....... ....... ..... 13
Priorities & Recommendations .......................... ..... ......... .... .. .. ....... .... ........ .. .... .... .. ..... ....... ..... ... ..... 15
Step 1 - Base Score .... ........... ...... ..... .... ..... ...... ... .. .. ... ..... .. ... .. .... .. .......... ... .. ... ... .... ... ..... .. .... ...... ....... ... ............ .. I6 Step 2 - Performance Criteria Score .. .. .. .. ... .. .. .. .. .... ..... .. .. .. ......... .... .. ... .......... ........ .. .. .... ....... .... .. .... ........ ......... I6 Step 3- Feasibility Criteria Factor .... .. .... .................... .. ... ...... ...... ...... .. ....... .. .. .. .... .. ... ........ .. ........ .. ................. 16 Step 4 - Priority Score ............................ .. .............. ....... ...... ................ .. .................. .. .. .. ...... ... ...... ........... ........ . I6 Algorithm Results ............. .. ... .. .................... .. .............. ............. .. .. ...... .. .............. ........... .... ........................... ... 17
Pedestrian Facilities Design ...................................... ... ... ...... ......... .. .... ........ ..... .. ....... .............. .... ... 19
Qualities of pedestrian friendly development ... ...... ... .... .. .. ... .... .. ......... .... .. ............... .................... ... ... .. ...... .. ..... 19 Sidewalk Design ..... .. ........ ........ .... .... .. .. ......... ..... ... .... .. .................. .... ........... ............ ..... .... ..... ... ........ .. ........ .... 20 Design Challenges and Examples ........ .. ................ ..... .. .. ... ....... .... ..... ... ............... .......... .. .... .. ...... ........ .... ..... ... 22 Pedestrian Friendly Growth Centers ....... ... ....... .. ... ... ... .... .. ..... .. ............ ... .................................. .... .... ..... .. .. ... .. 24 Operations and Maintenance ... ... ..... ... ...... .. ........ .......... ... .. .... ......... .. ....... ....... ....... .... ........ ........ ...... .. ...... ... .... . 25
Conclusion ....... ... .... ... .... .. .... ........... .... ....... ... ........... ..... ... ......... ..... ......... .. ..... .... .......... ......... ... ....... 27
Appendix A Sidewalk Segment Fact Sheets
Appendix B Data and Analysis
Appendix C Prioritized Sidewalk Corridors
Table of Contents Page i
Introduction TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
idewalks are more than just a place to walk. They are an integral part of a transportation corridor
and help to define the character of the adjacent neighborhoods. This is a concept the Town of St.
Albans (Town) clearly understands. Through efforts like crosswalk delineation at the bay, the Fairfax
Street Sidewalk Feasibility Study and zoning regulations that require pedestrian facility easement, the
Town is taking steps toward a more pedestrian friendly landscape.
To this end Engineered Solutions, Inc. (ESI) and Kathleen Ryan, Landscape Architect were hired to
asses town-wide pedestrian needs and opportunities. Through public meetings, site visits and
discussions with citizens and local officials we gained an appreciation for the current pedestrian travel
patterns and were able to see opportunities for improvement to both safety and mobility. We have
identified over 20 possible pedestrian corridors that form a web connecting 6 discrete areas of Town
with each other and the City of St. Albans (City).
This Sidewalk Master Plan (Plan)
identifies each potential sidewalk
corridor and judges it against a set
of criteria that provides a measure
of its feasibility via a simple
scoring system. These scores are
weighted and factored to create a
prioritized list of potential
sidewalk projects around Town.
The methodology, established to
generate these priorities,
identifies those sidewalk
segments that provide the
greatest benefit for the lowest
cost as the highest priorities.
The following sections outline
the methods, assumptions and
data used to develop this priority system. The conclusion
of the Plan includes recommended sidewalk projects as well as
St. Albans Town Potential Sidewalk Corridors
potential funding sources and general recommendations for design components that encourage
pedestrian traffic.
Introduction Page z
Decision Makin~ Criteria TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
s with any planning effort, a wide variety of factors affect the decision making process. For the
purpose of this project we have identified a general set of parameters and separated them into 2
basic categories: Performance Criteria and Feasibility Criteria. Values were assigned to each criterion
in both categories that reflect the goals of the Town to create a logical pedestrian network. The
following paragraphs describe these criteria and why each is important. Their relative importance is
reflected by the value attributed to each in the prioritization system described in the Prioritization and
Recommendations section on page 15.
erjormance Criteria were established to assess the ability of a proposed sidewalk to directly
address the needs of the pedestrian. For each criterion, the green box indicates the question
which is asked to address the criterion.
A) "High Density" Residential Collector- This criterion establishes the ability of the sidewalk
segment to service "high density" residential neighborhoods. This simple yes/no question is important
for two key reasons: I) it identifies those corridors that will directly serve residential areas providing
added safety and convenience for children
and the elderly and 2) it serves to
segregate those segments that may be
better served by a bike/recreation path.
This single decision dictates both the
expected use of the facility and thus
design and cost. For the purposes of this
Question asked ...
{])oes tftis sitfewaf{seement collect petfestrian traffic from a "fti(jft aensity" resilfentiai area ornei(jft6orliootf?
'Yes or !No
decision, "High Priority" residential areas are those areas zoned as Residential or
Commercial/Residential by the Town of St. Albans Zoning Map.
B) Access to Public Transit - The creation of a sidewalk that is integrated with Public Transportation
serves to support both the increased use of the sidewalk as well as public transit. Because typical public
transit users do not drive to bus stops, the
bus stop can be made much more viable if
it is serviced by sidewalks. If a proposed
sidewalk intersects the route of the
Northwest Vermont Public Transit bus
route, it is considered to provide access to
public transit.
Question asked ...
{])oes tftis sitfewaf{seement prcrvitfe access to or support tfte eJ(jstinfJ pu.6ftc transit systems in St. }lfDans?
'Yes or !No
Decision Makjng Criteria Page 8
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
-:) Area to Area Linkage - For the purposes of
this plan, the Town has been divided into six
discrete "areas." These areas were developed
based on pedestrian traffic generation, existing
infrastructure and general land uses. Each of the
six areas is described in detail in the Origins and
Destinations section beginning on page 7.
Question asked ...
(])oes tliis sid"ewaflsetpnent coffect petfestrian traffic fimn one "area" to anotlier "area"?
'Yes or :No
Establishing a sidewalk's ability to provide Area to Area linkage helps to further define the function of
the sidewalk within the Town. This criterion provides a measure of its ability to serve Town-wide
mobility goals in addition to the more local goals already assessed by Performance Criteria A
Segments are considered to provide Area to Area linkage if at least one end of the segment intersects an
area boundary.
D) City Linkage- The ability to link pedestrian
corridors between the City and Town is an
important component in building a cohesive
community across municipal boundaries. Also, 1 "'cause the City is laced with sidewalks, tying a
.:>•lOrt segment of sidewalk in Town to the City's
sidewalk systems can leverage the existing City
Question asked ...
(])oes tliis sid"ewaflsepent fint witli tlie City sid"ewafl system?
'Yes or :No
infrastructure for use by the Town at a minimal cost. To implement these sidewalks the town will need
to coordinate with the city to ensure a smooth and logical junction. Some sections may require
construction of stretches within the city.
E) Priority Destinations - General pedestrian
traffic origins and destinations are defined based
on the "area" as discussed in item C.
Additionally, within each area, specific
destinations that require special consideration are
considered "Priority Destinations." These
Priority Destinations are municipal, civic and
Question asked ...
How many CJ!riority (])estinatifms are seroetf 6y tlie proposetf sid"ewaflfin~
rz'otaf :Num6er
social destinations which function better with convenient pedestrian service. They can describe either a
specific location or a cluster of similar uses in the vicinity of each other.
The following general seven categories ofPriority Destinations were developed:
Hospital/Health Care; Schools; Post Office; Municipal Offices; Shopping; Employment; Recreation
For each sidewalk segment the total number or priority destination was determined, with a maximum of
score of7 (1 point for each destination).
Page 4 I Decjsion Making Criter ia
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
easibility Criteria, based on general expected permitting requirements and project cost, were
established to balance the sidewalk needs of the Town with the realistic limitations of project
development. Specifically, the two Feasibility Criteria established were:
A) Permitting/ROW I Access Conflicts B) Cost
A) Permitting/ROW /Access Conflicts -
Based on cursory review of available
information, potential limitations along
each corridor were assessed. These
criteria were assessed based on existing
statewide wetlands mapping, right-of-way
(ROW) information from the Town,
Question asked ...
u-Yiat is tlie feve( of potentia£ pennittiniJ aruf linuf use conjf1Ct associatea witli tliis segment?
Su6stantia( :Motferate, or :Minor
adjacent land uses and landforms (hilly, flat, etc.). Sidewalk segments were considered to have
substantial conflicts if it appeared that construction of the segment would extend well beyond the ROW,
there were obvious drainage concerns, and/or impacts to neighboring land uses or natural systems (ie.
wetlands). Moderate conflicts generally involved segments located in a wide ROW but they happen to
share that ROW with a wetland or other protected feature. Minor conflicts involve those segments that
appear to have relatively few permitting limitations on their construction. This, however, does not mean
that significant technical challenges may be encountered.
Question asked ...
B) Cost - As in any project, cost is a
critical factor in deciding the appropriate
course of action. For the purposes of this
Plan, the estimated construction and
design cost has been categorized as
follows:
u-Yiat is tlie refatic;e cost of tlie project?
Low Cost Medium Cost High Cost
0- $30,000 $30,000- $150,000 $150,000 +
These values are based on the assumption that low cost project could be executed with limited
planning/design and with Town funding; medium cost projects are also relatively simple but grant
funding may be necessary for design and construction; and high cost projects will probably require grant
funding. Cost estimates were generated based on per linear food construction costs for 3 types of
facility :
Concrete Sidewalk: Bituminous Recreation Path: Share the Road:
$90/LF $60/LF $20/LF
Decision Makipg Qr jterja Page ,5
Ori~ins and Destinations TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
o as to gain an understanding of the flow oflife in St. Albans Town, we held two pubic meetings, and
visited local business and Town officials on multiple occasions. The result of this was the division of
the Town into six discrete areas that serve as general origins and destinations for both vehicular and
pedestrian traffic. Each of these areas has both internal and external pedestrian traffic generators and all
areas (except Area F) interface with the city sidewalk system. The map below shows the location of each
area and the following paragraphs describe the character and land uses in each area.
Origins and Destinations Page z
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Important Origins and Destinations in St. Albans
Commercial/Services Grocery and Shopping Centers at Exit 20
Lake Street Shops St Albans Bay Stores
Recreation St Albans Bay Beach
Collins Pearly Sports Complex Hardack Recreation Area
Cohen Park
Schools St. Albans Town Central School
Bellows Free Academy Callaghan Memorial School (private)
Community College ofVT
Civic Town Offices - St Albans Bay
Transit Route
Health Northwest Medical Center
Fairfield Street medical offices Fisher Pond Rd (Route 1 04) Medical Offices
Employment Eveready Plant Industrial Park
Exit 20 CommerciaVGrowth Center/lndustrial Zone Exit 19 CommerciaVGrowth Center
fage B Origip s ap d Destinations
April2003
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Area A -Exit 20 Highgate Commons
Area A is defined by the Route 7 corridor from the
northern city boundary extending beyond Exit 20 and to
the Swanton town line. This Area is predominantly
commercial with large "national brand" retail shopping
centers in the vicinity of Exit 20 and a variety oflocally
owned businesses clustered near the City/Town
boundary. · Area A connects to the City via Main Street
and does not directly interact with the other defined
Areas of this plan.
Area B - Hardack and NW Regional Medical
Area B is the area of Town immediately adjacent to the
northwest corner of the City. The Area is bounded on
the west by the City, on the east by I-89, on the north by
Hardack Recreation center and on the south by Upper
Welden Street, but not including it. This Area is
anchored to the City by Congress and Fairfield Streets
and appears to have relatively discrete uses based on the
presence of the Hospital and the Hardack Recreation
Area. Area B connects to Area C via Vermont 104 to the
south.
April2003
Origins apd Destinations Page 9
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
4rea C - Colins Perley
1n recognizing the relationship between the school and
the Colins Perley Sports complex, Area C is the only
defined area that stretches into the City to address
specific traffic generators. Area A is contains relatively
dense residential housing and the Colins Perley Sports
complex within the Town and the High School and the
Technical Center in the City. The area is bounded on the
west by the City, on the east by I-89, on the north by
Upper Welden Street and on the south by Fairfax Street.
Connections to the City are made at Upper Welden, the
State Highway Access Road, Potter Street and Fairfax
Street. Connections to other Areas exist at Vermont 104
(Area B) and Fairfax Street (Area D). A major obstacle
April2003
in this Area is the State Highway Access Road that bisects it. There are currently no pedestrian
accommodations along the road and the only point of crossing is its intersection with Main Street.
Area D - Industrial Park
Iea D is characterized by diverse land use. There are a
variety of industrial, commercial and residential uses
within this area. The area is bounded on the west by
Bronson Road, on the east by Main Street on the north by
the City and on the South by the Industrial Park.
Connections to the City from this area are made at Main
Street, Nason Road and Huntington Street. Area D has a
direct connection with Area C via Industrial Park Road.
PagelO Origins and Destinations
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Area E - West Side
Area E is comprised of two existing roadways extending
westerly from the City. Pearl Street and Newton Street
both extend from the City into residentially zoned areas
that are largely undeveloped. There are also areas of
this region zoned for industrial use primarily related to
the existing railroad facilities. Area E does not connect
directly with any other Town Areas.
Area F - St Albans Bay
The village area of St. Albans Bay is defined as Area F.
Its limits extend to the Bay on the West to Patten Crosby
Road on the east and from the Town Beach on the north
to Deslaruier Road on the south. Area F is comprised of
a compact village area with mixed commercial and
residential uses surrounded by a network of residential
streets. Although an important component of St.
Albans, Area F is an island, insulated from the activities
of the other defined areas. Areaf St. Albans Bay
Origins and Destinatjons I Page 11
~k t> Ke~t/tt-~
lr!l ~&q~ num kr~tf flaJeS,
OtJ'i1n,.I1J Wtf-1. f4-Je. It 1
d~ /,kAnt pa.jeS
Sidewalk Corridors TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Within each area, logical sidewalk corridors were established that linked ~reas together with each other
and the City. Generally these segments are located within existing roadway corridors and along existing
roadways. Because this plan is focused on pedestrian facilities, potential recreational corridors along
Lake Street, Route 36 and Hathaway Point Road were not included. Additionally, routes previously
deemed impractical (i.e. Bridge at Thorpe Street/Grice Brook) were not considered beyond points of
discussion.
The segments included are those considered to provide reasonable pedestrian movement with the Town
and interconnection with the City and Town:. The following map and table identify the 24 segments
considered by this plan. For each segment identified, a Fact Sheet (Appendix A) was developed that
details its general character and function.
A-1 Main Street A-2 Route 7 - Exit 20 B-1 Congress Street B-2 Hardaek B-3 Fisher Pond Road B-4 Fairfield Street B-5 Vermont 104 North C-1 Upper Welden C-2 Vermont 104 C-3 Fairfax Street C-4 Colins Perley Access C-5 lntentate Aeeess Road C-6 Vermont 104 South D-1 Industrial Park D-2 Nason Street D-3 Nason Road City Link D-4 Green Mountain Drive D-5 Power Line D-6 Lake Street (Town) E-1 Pearl Street E-2 Lower Newton F-1 Georgia Shore F-l Lake Street (Bay) F-3 BayPark
Sidewalk Corridors I Page 13
. J
J
Priorities & Recommendations TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
The decision making algorithm developed for this project strives to provide a documentable and
reproducible system to support the Town Planning process. The algorithm is housed in a simple Excel
spreadsheet/database that will allow the Town to modify the values within the algorithm to match the
evolving needs of the Town. With a little effort, additional criteria can even be introduced into the
process allowing the model to remain valid over time.
The results of this algorithm provide the Town with a prioritized list of sidewalk corridors that can guide
the Town in the development of a sidewalk network. This list and an associated map are show on Page
13 and in Appendix C. Descriptions of specific sidewalk types, lengths, costs, etc. are detailed on the
Sidewalk Fact Sheets located in Appendix A. Other general design and planning considerations are
presented in the following section: Pedestrian Facility Design.
The algorithm is basically a two stage process where the fist stage is additive, accumulating a score
based on performance of the segment. The second stage then applies a factor to these performance
scores based on the feasibility of actually proceeding with that option. The following paragraphs briefly
describe the function of the algorithm and provide some insight into its operation. Detailed descriptions
of the specific criteria are located in the Decision Making Criteria section starting on page 3.
A> High Density Residential Collector?
Add 25 points
C) Area to Area Linkage
Add 5 points
A> Permitting. ROW, Access, Etc. Conflicts?
Substantial Conflict 90% Moderate Conflict 1 OO% M inor Conflict 115%
3 Score: = A x B
Step 4: Priority Score
Sidewalk Master Plan Prioritization
Add 5 points
D) City Linkage
Add 13 points
8) Cost Low Cost (0- SJo,oool 115% Medium Cost (s3o,ooo-1so,ooo) 105% High Cost rs1so,ooo +> 100%
St. Albans, Vermont
E) Total Number of Priority Destinations
Hospital Schools
Post Office Municipal Offices
Shopping Employment
Recreation Area
Priority Score = Step 2 Score x Step 3 Score
Priorities & Recommendations Page 15
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
in the 40-70 range may be a sidewalk that could provide a valuable pedestrian service but is more
expensive and/or difficult to build. These sidewalks, however, could be critical parts of the Town's
pedestrian infrastructure and should continue to be pursued as long-term goals.
Segments that received a score of0-40 fall in the Concept Planning category. Although planning should
not be directly pursued on these segments, the Town should remain aware that these are logical
pedestrian routes and if the opportunity presents itself to develop them, it should be taken. Impact fees
or other mechanisms paid by developers of adjacent land could be used to fund such sidewalks.
Algorithm Results
The results of the processing of the Algorithm are shown on the map below. The algorithm is detailed in
Appendix B and the individual scores are summarized on the Fact Sheets in Appendix A. Because the
algorithm is housed in a simple spreadsheet, as the Town's (and City's) needs and resources evolve
these criteria and scores can be adjusted, resulting in a new priority rating. Also, additional sidewalk
segments can be added, analyzed and compared to the other segments.
Sidewalk Segment Prioritization
Pltmnlllll Group lD 1-7 Year Plaanina B-1
-=------- --::-:--:---11-7 Year PlaoniDg B-4 1-7 Year Plaanina C-1 1-7 Year Planning C-3 8-ZO Year Planning C-4 8-ZO Year Plannina ))..3 8-ZO Year Planning D-4
Year Plaanina ))..5 8-ZO Year Planning F-l Concept Planning A-1 Concept Planning A-2 COJIIceJJ)t Planning B-2 Concept Planning B-3 concept Planning B-5 COIIIceJJ)t Planning C-l Concept Planning C-5 l ColllceJJ)t Planning C-6 iConcept Planning ))..1 i(;OJilceJ~P~ng J)..l
JCO,ncejpt Planning D-6 CODitept Planning E-1 Co111ce1J)t Planning E-l Concept Planning F-1 Concept Planning F-3
Nqme Coaaress Street Fairfield Street Upper Welden Fairfu Street CoHos Perley Access Nason Road City Link Green Moantain Drive PowerLme Lake Street (Bay) Route 7- Exit 10 Main Street Hardack Fisher Pond Road Vermont 104 North Vermoat104 Interstate Access Road Vermont 104 South Industrial Park NuoaStreet Lake Street (Town) Pearl Street Lower Newton Georaia Shore Bay Park
A poster size version of this IIIIJP is provided as an attachment to this report.
Pedestrian Facilities Design I Page zz
Pedestrian Facilities Design TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Because sidewalks have the ability of define the character of and area, special consideration needs to be
made in their design. These considerations are generally related to ensuring that the facility provides an
appropriate level of convenience, comfort and safety.
Sidewalks that make direct connections and, are safe, comfortable, and attractive will be more appealing
to pedestrians and thus better utilized. Sidewalks can be very important community spaces and can
improve a residential or commercial neighborhood. If sidewalks are inviting they can bring people
together, provide a useful transportation mode, a recreation mode for walkers and joggers and make the
streets safer.
The Town of St. Albans clearly understands the link between economic vitality of growth centers and
creating a pedestrian environments and corridors. As such, this study is one of several recent efforts by
the Town to improve pedestrian services and facilities. Additionally, to this end, the St Albans Town
Planning Board has begun requiring several developers to include sidewalks in their residential and
commercial projects. The following section provides guidelines and recommendations related to these
supporting these concepts.
Qualities of pedestrian friendly development
Public Transit
Create functional, centrally located and attractive transit
stops within the growth areas and along pedestrian corridors
that lead to growth areas.
RightojWay
Plan rights-of-way of new streets to allow ample room for
wide sidewalks, greenbelts and parallel parking where
appropriate.
Signs
Provide signs and landscaping that relates to a pedestrian
scale and provides direction specifically to pedestrians.
Parking
To avoid long walks across parking lots, minimize parking
lot sizes by considering shared parking to serve several
stores with various peak parking times, when determining
parking requirements. Consider a central parking garage.
Pedestrian Facilities Design Page 19
J
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Crosswalks should be clear and visible to both drivers and pedestrians. Signalized crossings should not
require undue waiting and should allow adequate crossing time.
Slowing vehicle speeds is an effective way to increase pedestrian safety. As drivers slow down they are
more aware of other activities in the roadway corridor and they can respond and stop more quickly.
Research shows that the chance of a vehicle/pedestrian crash being fatal goes from 85% to 5% when
vehicle speed is reduced from 40 to 20 miles per hour.
Landscaping
Street trees are an essential part of creating pedestrian comfort in the streetscape. Street trees enhance
the pedestrian way with shade in summer: the rustle ofleaves, the natural sounds of birds and squirrels
mitigate roadway noises; a year round canopy and enclosure that provides visual and psychological
comfort. Street trees also add to the value of both residential and commercial neighborhoods.
Lighting
Pedestrian lighting encourages the use of the sidewalk system after dark, thereby increasing security by
bringing residents out into the neighborhood at night. Pedestrian lighting can keep residential areas
inviting and growth centers active into the evening hours.
Character of Place
Materials, details and amenities of the sidewalks corridor can be important to the character of an area.
Benches and gathering spots lend opportunities for social interaction.
Traffic Volumes
Traffic volume on a given pedestrian
route is an important consideration in
the design ofthe pedestrian facility.
Very low volume roadways with
shoulders, either paved or gravel can
and do serve pedestrians in rural
areas. As traffic volumes increase,
pedestrians no longer find the
shoulder a comfortable route, and
walking may be more dangerous.
There are no known Vermont traffic
studies that directly link traffic
volume to the safety of pedestrian
using the roadway shoulder. There are
some national bicycle studies that cite
a traffic volume of 2000 vpd as a
St. Albans Town Highway where vehicular traffic exceeds 3, 000 vpd
Roadwav Route 7 north (near shopping center)
Route 7 south of Industrial Park Road
Route 104 - between STASH and Upper Weldon
Route I 04 - between Fairfield and Congress
Fairfield Street - near park and ride
SAASH - west of Route 104
Lake Street - between Brigham Rd and City line
St Albans Bay (Lake Street - east of Church Rd)
Volume* 15, 970
8,000
7,000
5,300
8,150
9,870
7,300
3,430 • Data &om St Albans Trafflc Circulation Study - May 2002 , referenced &om 2001 RPC and
VTransdata
Pedestrian Facilities Design Page 21
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Curbs: use curbs where needed to protect both the structure and the pedestrian.
This narrow greenbelt, with no protective curb, has eroded due to vehicle parking, leaving no buffer for the
pedestrian way. Drainage
Adjacent Property: consider the private property side of the sidewalk
Vehicular
April2003
Vehicle bumpers encroach on the pedestrian realm when this parking lot is full. A green setback, fence or hedge is needed at the property line edge of this
sidewalk Pedestrian Facilities Design I Page 2.'1
j
TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Operations and Maintenance Clearly, the addition of sidewalks will add another dimension to the maintenance activities and
responsibilities of the Town. However, recognizing and preparing for these needs in advance can result
in longer life for the sidewalk system and greater use by the public.
As sidewalks are installed, the Town should record the date of construction and maintain a simple
annual inspection schedule. This annual inspection will help to track maintenance needs and highlight
areas of significant deterioration. Keeping track of this type of information over time will aid the Town
in prioritizing ongoing maintenance.
Two issues that adjacent landowners are often concerned with are green belt maintenance (mowing) and
snow clearing. Both of these issues can be clearly defined with relatively simple policy language.
Because sidewalks will be a relatively new feature for Town residents, it is important to define the
expected roles of the adjoining landowners as well as the responsibilities of the Town.
With respect to the green belts, most Towns have ordinances that require the adjacent land owner to
mow grass in the green belt. However, where trees exist within the greenbelt, the Town will assume the
responsibility of pruning and generally maintaining the trees. Because of this mixed maintenance
approach, there is sometimes confusion regarding who actually owns the green belt. Therefore, it is
important when writing maintenance policy to clearly state that the sidewalk and the greenbelt are
completely within the Town right-of-way and as such are owned by the Town. Practically, this means
that the Town has the right to remove items (signs, poster, banners, benches, etc.) that they feel are
inappropriate or unsafe.
Snowplowing can be dealt with in a similar fashion as greenbelt maintenance. There are two basic
approaches that most Towns employ 1) they assign the responsibility for snow removal to the adjacent
landowner or 2) the Town assumes this responsibility. In practice, option 1) often results in sidewalks
that are impassible for the majority of the winter. However, option 2) would require the purchase of
specialty plowing equipment that may be beyond the financial resources of the Town. St. Albans Town,
however, is in the unique position of surrounding the City. This may allow it to share plowing cost with
the City.
Other features that will need ongoing attention and maintenance may be: crosswalk paint, handicap
ramps, signing, lighting, driveway adjustments, etc.
Pedestrian Facilities Design I Page 25
J
Conclusion TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Clearly the Town of St. Albans has recognized the long-term value of sidewalks and has taken many
steps recently to facilitate their planning. The Town's current policy of requiring developers to install
sidewalks is a great step towards building a walkable community. However, there are many sections of
Town which have already been developed without sidewalks. So the Town is left with the question: "If
we're going to build sidewalks, where should we start?"
This Sidewalk Master Plan addresses this question through a decision making process that identifies the
origins and destination of pedestrian traffic and potential feasibility limitations. The decision making
process was developed such that it encourages the construction of sidewalks in relatively dense areas of
Town that are interconnected with the City Sidewalk system. This approach ensures that the money
invested in sidewalks will serve the most possible residents as well as leverage the mobility of the City's
sidewalk network.
To this end, the Project Team has identified 23 potential sidewalk corridors for analysis and
prioritization. A database was created that details the characteristics of each sidewalk and prioritizes
them based on Performance and Feasibility Criteria. (This database was linked to Arc View GIS to create the mapping presented in this report.) By documenting both the data and decision making
process in this database, the Town now has a tool that can be used for ongoing planning. For example,
as time goes by and sidewalks are built, the remaining sidewalks can be reprioritized, criteria can be
adjusted or new criteria can be introduced that reflect the evolving needs of the Town.
For each of the sidewalk segments considered, a Fact Sheet is presented in Appendix A. These show the
location of the segment, summarize prioritization criteria and show a conceptual typical section. Due to
the broad nature of this project, some data has been generalized and significant additional planning will
be needed to completely define the nature of each corridor. However, for the sake of this project, the
level of data presented is sufficient to make general conclusions and recommendations regarding the
Town's approach to sidewalk planning.
Based on the analysis in this Report, there are four sidewalk corridors that should receive additional
planning attention in the next 7 years: Congress Street, Fairfield Street, Upper Welden Street and Fairfax
Street. Notice that each of these sidewalk corridors would tie directly to the City of St. Albans sidewalk
system. Therefore, the City must be an integral part of the planning for the construction of each of these
segments. It is estimated that the cost of design and construction of all these sidewalks would be in the
range of$850,000- $1,000,000. However, with the appropriate planning, grant funds could be obtained
to cover the majority of these costs. Appendix C summarizes the segment priorities and associated cost.
Sidewalks are an important part of any community. It is our hope that this document and the database
tool will be a valuable component of the Town's ongoing sidewalk planning efforts.
Qgnclusjon P«ge 27
J
J
Appendix A: Sidewalk Segment Fact Sheets TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
?l1efol!mFing appcndhc coniains a Fact Sheet for each
sideH'a!k segmem discussed in this Jldaster Plan. Each Fact
,)'heel contains ii(/onnatiun related to the existing
conditions of the sef!.ment, its use and potential
improvements. !he expected cos·t.\". and implementation
Priori(v Score ore aiso inciitded on each sheet
Appendix A Sidewalk Segment Fact Sheets
J
J
J
lonlng
i C1)
.....:l
Segment A-1: MainStreet TOWN OF ST. ALBANS
CfiY Commercii/
Conm~'Rt:'S
Ugl,t/ntluSit)'
Heavy lnduury Rur.URf.>!..~IC'nli.ll
RcsidNl!idf
(O(IS('IVdLiofl
Wo!l!'r
La~ Silo(('
SIDEWALK MASTER PLAN
Segment A-1: Route 7- Exit 20
- Segment Description -Segment A -1 extends from the town/city boundary to the intersection of Route and Parah Drive. The sidewalk is
expected to be on the east side of Route 7 and passes the Rail Trail Head and Eveready. For the majority of the
corridor there is little development adjacent to Route 7. However, the entire length is zoned for commercial use.
Approximately BOO .feet of sidewalk would need to be constructed in the City to support this segment.
-Pnont, Sc . D onng ata-
"'lil 1ii ~ 'a .... C':S jg gp ....
0 = .s 0 ·-= 0
April2003
~ :S ~8 u 0 -~ _e.o .g ~ 'E 2: (.J ·€S (.J =ts '§ ·~ Priority Ranking ·~ ~ 5h 00. ~ C1) ~~ 0~ .....:l (.J 0 ·s ~ ~ 0 0
'lil :a ;;:s ..... ~ .e ;E '~ §~ 1ii ;E~ "' Cl)J:z.. ~8 C1) C':S ~u ~ u J:z.. 8 ~
C1) ,:l.;
~ ~
3,500 $315,000 $47,250 10 N y N N 2 21 1.05 1.0 22 Concept Planning
- Conceptual Cross Section -
Segment A-1: Main Street
.J
J
i (I)
.....:l
Segment A-2: Route7-Exit20 TOWN OF ST. ALBANS
Conce;Jlud/Sidrwa/b
Propmccl Cil}' Slck•wal ·
Cfll'
Commf!rcl,t/
Comm.'Rcs
Ugb1 tndu5 /f)'
He<n·y lndusrry
RurJJRr!.i<h>n/i,l/
RcsitkntW
ConS('N.:nion
l abo5hoft'
SIDEWALK MASTER PLAN
--- Segment Description ---
Segment A-2: Route 7- Exit 20
Continuing north from segment A -1, A-2 would produce pedestiran access along Route 7 from Parah Road to a
point beyond Exit 20. This sidewalk would bisect the developing growth center and provide a pedestrian link
between the various services in this area. Sidewalks are proposed for both sides of Route 7.
-- P . "t S D t non conn~ a a---
'"Olii til ~ Cil .... t':l ~ gp ....
(I) 0 0 0 1:: .9
April2003
'+=! 0 0 .~ ~~ ~ _e,O .g ~ ~~ u u =t>
~! ;.:s '§ '8 .g ~ 'E l5 ~ Priority Ranking
.@> r.l.l ~~ §~ -~ ~ 0 0 . ~ ;;;.:s ~ ·c;jo .€' ·~:: ·.c til ·~:: u
Cll ~ Cll (I)~ ~r.l.l Cll 0 (I) t':l ~u ~ u ~ 0 ~u o::1
(I) ~ u 0 0
4,200 $378,000 I $56,700 10 N y N y 3 37 1.0 1.0 37 Concept Planning
-~---- --·- ..
I Tr....tb.M I I
Center11M
I Slxrod rlghto(Jf-•ay .. 99 fee t
--- Conceptual Cross Section ---
Segment A-2: Boute 7 - Exit 20
i Cl)
.....:l
1,300
J
Segment B -1: Congress Street TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment B-1: Congress Street
- Segment Description -Segment B-1 is located on the north side of Congress Street and extends .from the Town/City boundary to the
entrance of the Hardack Recreational Area. The adjacent land uses are residential with a significant senior
citizen population. Approximately 800 feet of sidewalk would be built in City to support the Town sidewalk.
- nont onng P. Sc . D at a-
-oiil .....
~ ca .... c<:S ~ .... "' ~ = bO .9 Cl) 0 0 0 ·-= 0
April2003
~ u ·~ _po ·m EJ ·€~ tijU u .g ~ u u =-u :.= .s:S
..... ·~(~ & Priority Ranking
. .§ ~ ~ tr.J ~ Cl)
~E-< .....:l u 0 ·~ ~ 0 0 ..... := ..... ~ c<:S.....:l .£ "' "' 0
"' 0 Cl) c<:S ~u ~ u ~u ,:0 Q
$117,00 $17,500 10 y y N y
· ~::.
A-. "' Cl)
Q
2
§~ iil ·~:: u Cl)~ A-.tr.J
~ 0 A-. u
59 1.15 1.05 71
Three rod right-of-way:: 49.5 feet
adjusl c:l'fllet lltl e loc.Uonlr necnury
--- Conceptual Cross Section ---
1-7 Year Planning
Segment B- t: Congress Street
i (1)
...:I
1,200
J
J
Segment B-2: Hardack TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Segment B-2: Hardack
--- Segment Description ---Segment B-2 would provide an off-road and defined pedestrian access route to Hardack Recreational Area. A
bike path style path may be most appropriate at this location.
--o1il 1il ~ c;l 1-<
ell 0
~~ (1) 0 0 ·-~:~ 0 u ·~ ~u u u ='G
.@> r:n :.=
·~ ~ .g.!l ~E-< (1) ..... - ;~
"' "' "' 0 [.1.18 (1) ell ~u ~ Q t:O
$72,00 $10,800 10 N N N
nonr, orm~ P' 't Sc D at a-
~ ...:I
.E' u
N
Stone dust shared use path
~ = ..oo "§ ·~ .g ~
§~ ·= ·-~:~ p.. ~ J:l..
Q
1 13
1-< b.l) .s ·~ ~ ·€ ~ u & "§ ~ 0 0 ..... ·= u (l)J:l.. "' p..r:n 0 p.. u
1.15 1.05 16
Trtlveled way approximately 28 feet
Slgnage, alerts drivers to pedestrians crossing
Priority Ranking
Concept Planning
\
- Conceptual Cross Section ~
Segment B-2: Hardack
1 C1)
.....:!
2,700
Segment B-3: FisherPondRoad TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment B-3: Fisher Pond Road
--- Segment Description ---Segment B-3 is envisioned as a bike path style sidewalk on the west side of VI' 104 between Fairfield Street and
Congress Street. The area is zoned form commercial and residential uses. Currently, there is little development
on this section of VI' 104.
--- nont, conn~ a a---P. "t S D t
-c"lil "lil ~ ca ..... ~ 0.0 ..... 0 = .9 0 ".+:::! 0
April2003
]~ ~ ~~ u 0 .~ _oo .g ~ ·~ ~ () ·€ ~ () =t ~~ "§ "8 & Priority Ranking
. ~ 6b rn .g~ . .s •.-4 §~ ·~ ~ 0 0 ~ ...... - C"I:S .....:I .5' ·~::·~ ...... · ~:: () ......
Cll 0 <n ~rn Cll 0 <n C"I:S
~ ~ <n Cl)IJ;. 0 ~u C1)
~ ~u u C1) IJ;. ~ 0 0 u
$162,00 I $24,300 10 N N N N 2 16 0.9 1.0 14 Concept Planning
West side of ROW = 49.5 feet cente'rllne
Segment B-3: Fisber Pond Road
_j
i Q)
....:l
900
Segment B-4: Fairfieldstreet TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment JJ-.4: Fairfield Street
-- Segment Description ---The Fairfield Street Extension, segment B-4, would serve to connect the activities at the TIT 1 04/Fair.field Street
intersection with the City and Northwest Regional Medical Center. This area is zoned for commercial use and
tlriis sidewalk would provide pedestrian links between future uses. Approximately 350 foet of sidewalk would
need to be built in the City to complete the link
-- non onn~ a a---P ' 't Sc • D t
-c"li'l ......
~ ~ ..... ~ ~ .....
"' ~ = b!) $ Q) 0 0 0 ".J:l 0
April2003
~~ u .~ .co -~ :s .g ~ ~~ u (.) =ts
~~ ;.::i ·s ·s .g ~ ~ Priority Ranking Sb 00 ~2 §~ "§ ~ J:.L. 0 0 .......... . ~ ..... Q) ..... - ~....:l .€' "' "' "' 0 "' 0 Q) ~ ~u ~ u l:ilu o:1 Q
$81,000 $12,150 10 y y N y
;f -~ 1i'l · ~ (.) Q)J:.I... t:l-..00
J:.L. 0 Q) t:l-4 u Q
2 59 1.15 1.05 71
Three rod right-of-way= 49.5 feet
travollano accornodates posatlve or negative grade che nge
adjust centertlne locaUon If nee. .... ry
14ft
travel lane
--- Conceptual Cross Section ---
1-7 Year Planning
1:: <::0.\~i,t,· varle~~- ft _: _
greenbelt
Segment B-4: Fairfield Extension
J
J
j Cl)
.....:l
1,000
Segment B-5: Vermont 104North TOWN OF ST. ALBANS SIDF.WA T.K M ASTRR. f'T.A N
Segnrent~5:Vernwnt1041Vorlh
- Segment Description ---Segment B-5 would be located on the west side ofVI' 104 and is the link between Area A and Area B.
Additionally, it serves to connect Upper Weldon Street and Fairfield Street. This segment is surrounded by
parcels zoned for commercial use. This sidewalk would serve to connect developments here with other areas of
Town and the City.
--- Pnont Sc • D onn~ at a- -
"01il 1il ~ ca ~-< ~ ~ 1-<
Cl) 0 0 0 d S!
Anril 200~
~~ ·.p 0 (.) .-;; ~ _e.O -~ ~ -€~ ~u u (.) d"i3
~! .....
'l(~ .g ~ & Priority Ranking .g ~ ~ tZl ~2 .....:l
§~ -~ ~ 0 0 .......... ~ ~8
C~~.....:l _e. ·~:: '.:::1 1il · ~:: (.)
rll 0 'ti:! ell
~ u ~ rll r;...
Cl)r;...
8 ~IZ!.
ll.lu Cl) Ill
Cl) ~ 0 0
$60,000 $9,000 10 N y y N 3 29 1.15 1.05 35 Concept Planning
Six rod rlght-ot-~y = 99 feet ~----------------------- --~- -------
!
- Conceptual Cross Section -
Segment B-5: Vermont 104 North
~ fl)
~ ,J
1,300
J
Segment C-1: UpperWelden TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
SegmentC-1: Upper Welden
-- Segment Description ---Segment C-1 extends the sidewalk on Upper Weldon Street to VT 104. This area is zoned for commercial use.
This sidewalk would connect the residential city streets with businesses in Town. Approximately 250 feet of
sidetralkwould be needed in the City to complete the link
-- nont, onnl! P .. Sc D ata---
-elii 1ii ~ Cil 1-< CIS ~ 0.0 1-<
0 = g fl) 0 0 ·-~:~ 0
April2003
~~ ~ u u '! _e..O ._g ~ ·g ~ .g ~ !~
u =-u :.= 'l(~ ~ Priority Ranking 6b 00 ~ fl)
~~ §~ '§ ~ ~ 0 0 ........... .... ::::= . ~ fl) CIS~ -~ ·~:: -~ 1ii £~ ....
"' "' 0 "' fl)~ "' 0 fl) CIS ~u ~ u A-t fl) ~ 0 l:ilu 0 a:1 0 A-t u
$117,000 $17,550 10 y y N y 3 62 1.15 1.05 75 1-7 Year Planning
Three rod rlght-of·way = 49.5 feet --------· --·---
adjust ""lt'f11ne . loelllonlrntcnuty
14 It
1ravel lane travel lane
-- Conceptual Cross Section ---
Segment C- t: Unper Welden
i C1)
~
2,300
Segment C-2: Vermont 104 TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment C-2: Vermont 104
-- Segment Description ---Segment C-2 bisects a large commercially zoned area to connect Upper Weldon Street with the Collins Perley
Recreational Center. The primary intent of this segment is to provide a safo pedestrian route from the High
School to Collins Perley. This sidewalk is envisioned as a bike path style sidewalk on the west side of the street
lflilh concrete sidewalk to be installed on the east side as development occurs.
--Pnont S D conn!! at a---
-c1il 1il ~ ca ..... ell ~ ..... C1) 0 0 0 = .s
April2003
·i!; ·.= 0 u ·~ ~~ :S c-o ·E' ~ «jU u u =ts ;.:::1 '§ 'j .g ~ & Priority Ranking
. .§ ~ ~ IZl .g C1)
~E-< ~
§~ ·~ ~ 0 0 .......... ~ ..... := ell~ .Q · ~:: 'ijl 1il ·~:: u .....
"'8 ,::~.;00 "' 0 "' ell
~ ~ u ,::~.; C1) 1:.1.. (!)1:.1..
8 ll-1u C1) t:Q ,::~.;
Cl 0
$138,000 $20,700 10 N y N N 1 18 1.0 1.05 19 Concept Planning
_______ ., ,od rlgh~~f.=."'! ....
- Conceptual Cross Section --
Segment C-2: v ermont 104
Segment C-3: FairfaxStreet TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Segment C-3: Fairfax Street
- - Segment Description ---Segment C-3 is currently the subject of a feasibility study for the construction of a sidewalk. Fairfax Street links
a large recreational area with the City and Collins Perley Recreation Area.
- n on t orm l! P' Sc ' D at a-
"'t;j ......
~ c:! ..... c<:S ~ .....
"' ~~ ~ = ·~!; ~ W:
Q) 0 0 0 ·g .s u 'j ,e.. o .g ~ lijU u u ;.:::1 '§ ·~ .g ~
~ Priority Ranking 5b 00 Q) u . .§ ~ :g~ ~E-<
.s ..... u 0 '§ ~ 0 0 Q) Q)
c<:S.....:l 8 · ~:: ·..:::~ §~ t;j ·~:: u .....:l
..... "' "' 0 ~00 "' 0 "' c<:S ~u ~
~ ~ p;., Q)p;.,
8 Q) ll.lu Q J:!l Q ~
4,700 $423,000 $63,450 10 y y y y 3 67 1.15 1.0 77 1-7 Year Planning
J
--- Conceptual Cross Section ---J
Segment C-3: Fairfax Street
• J
i (].)
....:~
900
J
Segment C-4: Collins Perley Access TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment C-4: CoUins Perley Access
-- Segment Description ---Segment C-4 is a small stretch of path that provides a "back way" into the Perley Collins Complex. The access
is currently recognized by an opening in the fonce and a sign describing the use of the field. Improvements to
this route lVould provide a stable and dependable link for the neighborhood.
--- nont conn!! a a---P .. S D t
"'"Iil .....
~ ~ .... ~ ~ bO ....
"' = .s (].) 0 0 0 ·.::s 0
April2003
~~ :S u '! _e.o ·~ :s ·E' ~ ~u u u =t3 ;.::::l '§ ·~ .g ~ & Priority Ranking
. .§ ~ .§ 00 ~~ ~~ ....:~
§~ ·~ ~ 0 0 ...... .... (].) ..... - ~....:~
"' "' "' 0 "' 0 (].) ~ ~u !1 ~u o:l ~
$18,000 $2,700 10 y N N
Stono dual
c ·= '.j:j ..... ·= u ..... ll-t "' (I.) Jl.< "' ll-.00 u Jl.< 0 (].)
ll-t u 0
N 1 38 1.15 1.15 50 8-20 Year Planning
~~-----M-~_mK __ •~_"_uo_' -_Y_·_~~ __ -_•_·•_•·_"_"'--~-------~
Traveled way approxlmatoly 28 feet
Slgrn~ge alerts drivers to pedestrians crossing
\
Segment C-4: Collins Perley Access
J
J
i 0
.....:!
J
$4,000
J
_j
Segment C-5: Interstate Access Road TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment C-5: Interstate Access Road
-- Segment Description ---A sidewalk along the interstate access road (Segment C-5) would connect Main Street and VT 104 and would
provide a link between the City, Schools, and Collins Perley Recreational Area. However, unlike other similar
corridors, there would not be access to the path except at its terminal points.
--- non conng a a---P . •t S D t
-otii til ~ ca ..... C':S 1:9 .....
0 = bll .s 0 0 0 '+=! 0
April2003
~~ :$ u -~
_e.o -~ ~ .g ~ ~:: u u =t) ;.::1 ·g ·:e .g ~ ~ Priority Ranking .§> 00 .g~
~E-< .....:! u 0 -~ ~ 0 0 ...........
• 1:9 0 ...... - co:s....:! ,e. ·= ·-= §~ til ·= u Cll 0 Cll til Cll 0 ...... ~ Cll 0~ ~00
0 C':S ~u ~ u ~ 8 ~u a:l 0 ~ Q Q
$360,000 $54,000 10 N N N y 2 29 0.9 1.0 26 Concept Planning
Three rod right-ot-way= 49.5 feet
14ft . --· _____ ,__ _ _ travellano travellane
--- Conceptual Cross Section ---
Segment C-5: Interstate Access Road
J
~ Q) ~
2,000
Segment C-6: Vermont 104 South TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Segment C-6: Vermont 104 South
-- Segment Description ---Segment C-6 provides a pedestrian corridor along vr 104 on the east to support the burgeoning development at
this location. The area is zoned commercial and showing signs of imminent growth.
't:ltil til a ~ 1-< 0 Q)8 u 0 ·-= 0 u '! -~ ~
u =t> :..::= 6b v.l -8Q)
~E-< ~ ..... := ...... t/}8 tl} 0 tl}
~ ~u Q) Ill 0
$180,000 $27,000 10 N y
- nont onng P' . Sc . D at a-
~~ ~ gp :S = _e-O .g a 'E !S .§ -~ ~
§~ -~ ~ .... ..... ~~ _e. ·~::.
~ ..... ll.. Q) Q)~ u ~ ll.. 0
N N 0 15 0.9
. ___ sl~ -~~-~g~:Of·way: s_• '-""-' - - - ·
1-<
.9 u ~ .... tl}
8
1.0
·E' a Priority Ranking 0 0 ·= u ll..v.l
14 Concept Planning
.:·'Y.'· 'C New aiO.W.Jllln•l.llled / ' ' • - ~ by do'lolopor or by Town u•lngaldowal lr. IU"'d
- Conceptual Cross Section ---
Segment C-6: v ermont 104 South
j
J
i Q)
.....:l
Segment D -1: Industrial Park TOWN OF ST. ALBANS
I<"S'""d
Conc.t:phi.JlSic/1.'1\'JIM
SIDEWALK MASTER PLAN
Segment D-1: Industrwl Park
--- Segment Description ---Segment D-1 improves on-road pedestrian use of Industrial Park Road for those walking to work. It also
improves a convenient link between the residential neighborhoods of Nason Street, Fairfax Street and US 7. The
low traffic volume on this road suggest a painted shoulder and "share-the-road" signs would be cost effective
and sufficient to upgrade pedestrian conditions. This area is zonedfor heavy industry.
--- nont, onng P .. Sc • D ata---
"C't;l 1;j ~ c;j .....
<:<:! ~ bl) ..... Q) 0 0 0 ·-= 0 = .9
April2003
u ·w ~~ ~ _e.O -~ l5 -€ ~ JC: u u =-o ;.:::= ;.:s '§ -~ ·.8 ~ & Priority Ranking 5h r:n. ~~ ~Eo-< §~ '§ ~ 0 0 ~ - .... . ~ ~ .8 -~ u ..... ..... - <:<:!~ -~ -~ ~
Cll 0 Cll ~r:n. ~8
Cll <:<:!
~ ~ Q) Q)~
8 Q) ~u u ~ Q 1!:1 Q ~
3,500 $70,000 $10,500 10 N y y N 1 23 1.15 1.05 28 Concept Planning
·-f·----···-·--··--·----··-- ·---=t\ I
~
laveled way approxlmalely24feet ~
Signage alerts drivers to pedestrians In the roadway
\, ...
--- Conceptual Cross Section ---
\
Segment D-1: Industrial Park
i; Q)
....:l
Segment D-2: Nasonstreet TOWN OF ST. ALBANS
I"Sf.•nrf
Con<.t'p!udl 5idew.I/'KS
l'ropowd G ly Si/,.,l.diJ
(/[)'
C(){f)/f}('fril/
Comm!RL>s
ligh l lndlbll"f
1 1<'.111' /tKfu~try
Rur.~I Rf:'Sicl<>rrli.H
SIDF:W A T.K M A R'l'F.R. PT. AN
- Segment Description -
Segment D-2: Nason Street
Segment D-2, extends the sidewalk from Green Mountain Drive west to Bronson Street to serve residential
streets and the mobile home parks. The recommended sidewalk, curb and greenbelt, on the north side of the
street, can be accommodated within the 4-rod right-of-way.
- p· nont Sc onng_ D t a a-
'd~ ~ !!a ]s ~ gp 1-< 0 0 = .s
Anril 200:-l
] ~~
u .-=: :S _po -€s u (.) =ts ~! o13 "§ -~ .g !!a ·E S ~ Priority Ranking
-~ tZl ~ Q)
....:l §~ "§ ~ 0 0 ...........
•VJ :a . ~ ~ c~:~....:l c ·= "fl ~ ·= (.) <ll u Q)~ IJ.;t:/) <ll 0 Q) Cl:l ~u ~ iJ.; Q) ~ 8 ~u Q l:o Q iJ.;
3200 $288,000 $43,200 10 y N N N 1 38 1.0 1.0 38 Concept Planning
Segment D-2: Nason Street
--
i Cl)
.....:l
Segment D-3: NasonRoadCity Link TOWN OF ST. ALBANS
IC'EPflr/
Conrepludl5idt'l\".tlks
l'ropowd 01)' SilitJIJ..
on· (onli»C'f'('idl
Cn.1W!R<'li
lightlndu::.lrr
ll<'d~· fmlu!>lf')'
Rutdi/W5id(' .. 1/idl
Ri,•,kWnliJI ('on<m<rlkm
SIDEWALK MASTER PLAN
Segment D-3: Nason Road City Link
--- Segment Description ---Segment D-3, starting at the City line and extending to Green Mountain Drive links the dense Nason Street
neighborhoods to the City sidewalk system and US 7. The recommended sidewalk, curb and greenbelt, on the
north side of the street, can be accommodated within the 4-rod right-of-way. This area is zoned residential.
--- nont, onnl! P' . Sc • D at a---
"dli'! 1;.! ~ ~ .... c<:S ~ b.O .... 0 = .9 0 ·+::~ 0
April2003
~ ~ ~~ u u .! ..::-o .g ~ ·~ !S u ·E' ~ u =ts ;..::::l s~ ·s ·8 & Priority Ranking 5h 00 .g Cl)
&E-< §~ ·~ ~ 0 0 .... = . ~ Cl) co:s.....:l .~ ·~ .tl 1;.! ·~ u ....... rl.l rl.l 0 ,::1..,00 rl.l Cl)~ rl.l 0 Cl) c<:S ~u ~ u ,::~.., Cl) ~ 0 l:.t-lu 0 a:l 0 ,::~.., u
1200 $108,000 $16,200 10 y N N y I 51 1.15 1.05 62 8-20 Year Planning
-- Conceptual Cross Section -
Segment D-3: Nason Road City Link
J
"i <1)
.....l
Se~ment D-4: GreenMountainDrive TOWN OF ST. ALBANS
Coowpw.J!Sidcw.t!ia
Propo·r.>d Cil)• Sff/C'\v,JJ
(/IY
(OITIIJK'IY'/d/
Comm1kf'!'
l fti•llml~lrr
I '"'nr lndu}lf)' RtJr.t/~den/i.!l
Rt·~ik·nU.ll
(nn'f'fY,I/.inn
SIDF.WALKMAR'l'F.R PLAN
Segment D-4: Green Mountain Drive
- Segment Description ---Segment D-4 improves an on-road pedestrian route along Green Mountain Drive and makes a pedestrian path
link, over an existing grass right-of-way, to Russell St, Lower Weldon and the City sidewalk system. Striping
and 'share-the-road' signs are recommended for Green Mountain Drive and a stone dust shared use path is
recommendedfor the existing right-~f-way.
-- non conng a a---P . "t S D t
'"O"til "til ~ ca ..... ~ ~ ..... 0 ~ =
b() .s Q) 0 0 "-l:! 0
Amil 200:i
~~ 0 •) _e.o ·m ~ .g ~ 1i,jU u 0 =t>
~~ ......
"§ "9 .g ~ ~ Priority Ranking . .§ ~ .§ U'J.
:S~ .....l §~ -~ ~ 0 0 ..........
~ ~.....l -~ ·~:: "-l:! 1il ·~:: 0
"' "' 0 IJ.< "' Q)~ IJ.<U'J. "' 0 <1) ~ ~u ~ u ~ 0 ~u o:l
Q) IJ.< ~ ~ u
1400 $28,000 $4,200 10 y N N y 1 51 1.15 1.15 67 8-20 Year Planning
-- Conceptual Cross Section ---
Segment D-4: Green Mountain Driye
J
1: Q)
....:l
1,100
J
.J
Segment D-5: PowerLine TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment D-5: Power Line
--- Segment Description ---Segment D-5 provides a shared use path along a utility right of way which makes a very direct link between
Nason Street and the downtown in the vicinity of Lower Weldon and Houghton Street. A graded stonedust path
built on a well drained base would be cost effective and an improvement to the informal path that now exists on
this route.
--- nont, conn!! P .. S D at a--
'"d"!;J "!iJ 12 c;l .... ca ~ ....
0 ~ = b.O $ Q) 0 0 ·-= 0
April2003
~~ u -~ _e. o ·m !$ .g 12 t;:~U u u =t) ...... ...... "§ "j .g 12 ~ Priority Ranking
. .§ ~ Sb 00 .g~ ~~ ....:l
§~ "§ ~ 0 0 ...... ..... ...... ~ . U!8 ca....:l 0 Cll 0 Cll ca
~ ~ ......
~u Q)
a:! u 0
$66,000 $9,900 10 y N N y
· ~:: . ~ Cll
Q)
0
0
1t Q)~ 0 ~ ~ u
48 1.15 1.05
Stone dust shared use path
· ~:: u ~00
58 8-20 Year Planning
- - Conceptual Cross Section -
Segment D-6: Power Line
Segment D-6: Lake Street (Town) TOWN OF ST. ALBANS
·~ Conrepwdl SidCl\•.Jfb
l'ropo<£>dCII)' Sitk>mr/S.
('JfY
Commmt.Jf tnrrvn!RI.'5
tifilllndw. fr;' l!fm.ylodu~ fr)'
SIDEWALK MASTER PLAN
Segment D-6: Lake Street (Town)
- Segment Description ---
April 2003
Segment D- 6 starts at the City line (at Adams Street) and extends to Bronson Road. Sidewalks recommended for both sides of
these three blocks will extend the urban setting of Lake Street, encourage pedestrian traffic to existing and future businesses and
improve the appearance of this commercial area. The typical roadway section below shows the sidewalk located to
J accommodate parallel parking that will serve neighborhood businesses. See Vl'rans guides for street tree planting in tree pits.
--- nont, onng P •. Sc • D at a--
.J
-o"til "til ~ ca .... ~ ~ bll ....
"i Q) 0 0 0 "+=! 0
u •j ~~ ~ .co = ·~ ~ .s .g ~ ~u u u =t> "§ "! .g ~ u Priority Ranking IZl ;.:::l .....:l & ·~ ~ .@> :9~ ~E-< .s ..... u 0 "§ ~ 0 0
Q) ~ ~.....:l .~ ·c: "+=! §~ "til ·c: u .....:l <ll <ll8 ~ <ll Q)J:;L. ~IZl <ll 0 Q) ~
~ ~ u J:;L. 0 ~u ~
Q) ~ u Q Q
2,000 $180,000 $27,000 10 N y N y 2 34 1.15 1.0 39 Concept Planning
J
..J centertlne
· .···, ~-··::' ··r· · : ··:· ( · ·• ···'r·· .. · .. ·: ·.: ·• ··" ... ,,.,, .. i ...,, .. ,· j "' 1 11 n L " n 'Fe-nbelf. sideWalk parking f tr~l/a~· . - ~ travcl'ia-;,~·
Four Rod ROW= 66 IMt -·- . . .. ·----(---- - · I
Segment D-6: Lake Street (Town)
J
J
J
toning
Segment E-1: PeariStreet TOWN OF ST. ALBANS
l'll'"nd
Concxp!UJ!SklC!\\".tfks
l'ropo-«1 City Si<Ww.1/~
SIDEWALK MASTER PLAN
- -i (JJY
(0.'l'lmtW~II
<..nmm 1R~
l.}.ohlfmlr.blrr
llruvylmlu~l!y
1Wrdl ~riMii.d
KrJicknlid/ <Dmm<Jiion
\'t.J!IY
.. /t~lu>Sh<lfr'
Segment E-1: Pearl Street
--- Segment Description ---Segment E-1 would be built on Pearl Street between the City line and Brigham Road Though Pearl Street itself
is relatively undeveloped, this sidewalk would link neighborhood on Brigham Rd and Walnut Street and connect
to the City. The area is zoned Residential and Rural Residential. A curb, greenbelt and sidewalk is
recommended location for the north side of Pearl Street
--- nont, conn~ P .. S D at a---
'"01ii 1ii ~ ca ..... ~ !!l bO ..... Cl) 0 0 0 •.J:t 0 = .s
April 2003
i u -~ ~~ ~ 00 -~ lS .g ~ u .g ~ u taU u =t> ;..::::l ·s -~ ~ Priority Ranking . .§ ~ -~
00 ~~ ~E-< §~ -~ ~ 0 0 .......... Cl) 1)l ·c;jo ~~ -~ ·~::. 1ii ·~:: u ~ til Il-l Cl) Cl)~ ll-<00 til 0 Cl) ell ~u ~ u ~ 8 ~u 0 a:! 0 Il-l
2,100 $189,000 $28,350 10 N N N y 0 23 1.0 1.0 23 Concept Planning
--- Conceptual Cross Section ---
Segment E-1: Pearl Street
J
j
i Cl)
.....:l
Segment E -2: LowerNewton TOWN OF ST. ALBANS
l~nd
Concr;opWJl Sidl!lv.&.s
l'mpoS<>~.I Cilr S.~l('\\',1/~
OfY Comm(>td.!l
Comm.lffi.•s 1 /sfl !lntl~trr
SIDEWALK MASTER PLAN
--- Segment Description ---
Segment E-2: Lower Newton
Segment E-2 would serve residents on Lower Newton Street (VT Route 38). The new sidewalk would begin at the
City line and run west to North Elm Street. A thin strip of/and either side of Lower Newton Street is zoned
Rraiidmtial. The area behind the residential properties is zoned Commercial/Light Industrial to the north and
Comiiervation to the south. The sidewalk could be installed on either side ~{the road.
· --Pnont, S D conng ata---
"d~ ~ ~ ea '"' ~ bll '"' Cl) 0 0 0 = $
April2003
~ "-l=! 0 u •J
~ _e.o ·m ~ .g ~ ~u u ._g ~ u u =ts ;.::! s:S ..... "§ -~ rf: Priority Ranking .g ~ Sb r/.l :9~ ~£,-< .....:l
§~ -~ ~ 0 0 Cl)
C~:~.....:l -~ ·= ".::l ~ ;f~ ..... <n <n 0 <n 0 <n Cl:!
~ ~ <n Cl)J:l... 0
~u Cl) ~u u Cl) J:l... ~ ~ p:) ~ u
2000 $180,000 $27,000 10 N N N y 0 23 1.0 1.0 23 Concept Planning
--- Conceptual Cross Section ---
Segment E-2: l&wer Newton
)
1: v ...:I
J
1,500
J
Segment F-1: GeorgiaShore TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
Segment F-1: Georgia Shore
-- Segment Description ---Segment F-1 serves two blocks on the Georgia Shore Road from Lake St to Church Rd This sidewalk would serve
residents in the St A lbans Bay area and summer visitors. A sidewalk, curb and greenbelt are recommended for the
norlh .side of the road An existing culvert would need to be extended or replaced Although the walk would be close
to residential/awns, the sidewalk could be accommodated with a three rod right-of-way.
-- nont, conn~?; a a---P .. S D t
'tjti.: t:: ~ ] l5 co:!
1:9 .....
~~ ~ = t:>O .9 v 0 0 0 0 .~ _e,O ·m l5 . .g ~ ~u u (.) =13 ~~
;.:s '§ 'i .g ~ ~ Priority Ranking .g ~ -~ 00 ~ v §~ -~ g 0 0 ........... v ...... ::::=
co:s...:l .8 ·t:: . t:: ·t:: (.) "' "' "' 0 p.. "' v~ p..I:Zl
"' 0 v co:! ~u ~ u ~ 8 ~u a:l v p.. Q Q
$135,000 $20,250 10 y N N N 1 38 0.9 1.05 36 Concept Planning
-- Conceptual Cross Section ---
Segment F- t: Georgia Shore
i Q)
.....:1
J
1500
J
Segment F-2: Lake street(bay) TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment F-2: Lake Street (Bay)
-- Segment Description ---Segment F-2 would be built on both sides of the St Albans Bay commercial block from Georgia Shore Road east
to for approximately 1500 feet in the village area. This sidewalk project would include the redesign of the Lake
S't#1PT 36/Georgia Shore Rd. intersection which is currently undefined and presents safoty issues for pedestrians.
It is recommended that parallel parking be incorporated into the Lake Street section o.fthe sidewalk
--- nonn conn~ a a--P . 't S D t
-o1il 1il ~ 'a 1-< CIS ~ bO
1-< 0 0 = .s
April2003
~~ ·-= 0 u .'d ~ ~ _e..O -~ :s ·E' ~ u (.) =t> ...... ·s ·a .g ~ ~ Priority Ranking 5h tZJ .g2 ~~ 0~ .....:1
§~ -~ ~ 0 0 ............ . ~ ...... Q) •t;j8 C~S....:l _e. ·~:: ·-= 1il ·~:: (.) Vl Vl ...... A. Vl Q)~ A-.00 Vl 0 Q) CIS
~ ~ u ~ 0 ll-lu a:l Q) A. u Q Q
$90,000 $13,500 10 y y N N 5 55 1.0 1.05 58 8-20 Year Planning
eentertlne
-I'- -----· - ··-·· -I
- Conceptual Cross Section -
Segment F-2: Lake street (ba0
J
J
1: Q)
H )
600
J
J
J
J
Segment F-3: Bay Park TOWN OF ST. ALBANS SIDEWALK MASTER PLAN
Segment F-3: Bay Park
--- Segment Description ---Segment F-3 would extend from Lake Street to the St Albans Bay Park Driveway. This sidewalk built on the east
side of VI' 36 would serve residents throughout the year and visitors in the summer when traffic volumes
increase.
--- Pnont' Sc ' D onng at a---
'O"!ii "iii ~ ~ ... c:s ~ 1;).0 ... 0 1=1 .9 Q) 0
April2003
~ :S u 0 ·-~:~ 0 (.) .~ _e.o .g ~ ·g !5 (.) ·€ ~ ~u (.) !=it$
~~ .s:S H "§ -~ & Priority Ranking .g ~ .§> !Zl ~2 §~ "§ ~ 0 0 Q) ...... - c:sH VI VI VI 0
VI 0 Q) c:s ~u ~ ~u Q ,:0
$5,400 $8,100 10 N N N
.-6' ·~::.
u ~ Q)
N
Stonadu1t ahated ... .,.Itt
Q
2
"iii £~ Q)r... r... 8 ~
16 1.15 1.05 19 Concept Planning
\
-- Conceptual Cross Section -
Segment F-3: Bay Park
Appendix c: Prioritized Sidewalk Corridors TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April 2003
SegmentiD Description Planning Horizon Estimated Design and
Construction Cost
B-1 Congress Street 1-7 Years Planning $134,550
B-4 Fairfield Street 1-7 Years Planning $93,150
C-1 Upper Welden 1-7 Years Planning $134,550
C-3 Fairfax Street 1-7 Years Planning $486,450
C-4 Colins Perley
8-20 Year Planning $20,700 Access
D-3 Nason Road City
8-20 Year Planning $124,200 Link
D-4 Green Mountain
8-20 Year Planning $32,200 Drive
D-5 Power Line 8-20 Year Planning $75,900
F-2 Lake Street (Bay) 8-20 Year Planning $103,500
A-1 Main Street Concept Planning $362,250
A-2 Route 7 - Exit 20 Concept Planning $434,700
B-2 Hardack Concept Planning $82,800 )
B-3 Fisher Pond Road Concept Planning $186,300
B-5 Vermont 104
Concept Planning $69,000 North
C-2 Vermont 104 Concept Planning $158,700
C-5 Interstate Access
Concept Planning $414,000 Road
C-6 Vermont 104
Concept Planning $207,000 South .J
D-1 Industrial Park Concept Planning $80,500
J D-2 Nason Street Concept Planning $331,200
D-6 Lake Street
Concept Planning $207,000 (Town)
J E-1 Pearl Street Concept Planning $217,350
E-2 Lower Newton Concept Planning $207,000
F-1 Georgia Shore Concept Planning $155,250
F-3 Bay Park Concept Planning $62,100
Total $4,380,350
Appendix c: Prioritized Sidewal_k Corridors
j
j
Appendix B: Data and Analysis TOWN OF ST. ALBANS SIDEWALK MASTER PLAN April2003
I hetn /o i·ing lirJJUJdi. · co1, m; ti.r> .v>read\·heei tl.ar
detuil\ t/;e dura and I'( W't makinl! '"f"itaiu r wf li ert
i'en,'rctled r). i · thi.\ ;; ··ojcct I h ., <'I -'(()\I in t 17L' rn r , on'r
of the i"tjl()f f 'rmraiw t digrtul cnJ> • rf tlil , . . \f)J ectd\h .'e
Appendix B: Data and Analysis
L .
L_
L .
St Alb • ans own I ewa lkPl ann1ng Dtb a a ase Prioritization
Step 1 Step 2 Step 3 Step 4 . Segement ID Segment Name Description Is it Built? In Planning? Coordinate With City? Facility Type Cost Per lF Length in FT Construction Cost Design Cost Total Cost Base Score !-Res Colt Pub Tran A to A City Lfnk Pri Dest Step 2 Score Permit Cost Step 3 Score !-Priority Score Priority Ranking Recomended Action
L A-1 Main Street From City/Town line to Parah Road n n y s $90 3500 $315,000 $47,250 $362,250 10 n y n n 2 21 -1.05 1 1.05 22 3 Concept Planning A-2 Route 7 - Exit 20 VT 7 from Parah Road through Interstate Acess Road n n n s $90 4200 $378,000 $56,700 $434,700 TO n y n y 3 .. 37 1 1 1.00 37 3 Concept Planning B-1 Congress Street From City/Town Line to Vermont 104 n n y s $90 1300 $117,000 $17,550 $134,550 10 y y n y 2 59 1.15 1.05 1.21 71 1 1-7 Years Planning B-2 Han:iack Atong Hardack Access Road n n n p $60 1200 $72,000 $10,800 $82,800 10 n n n n 1 13 1.15 1.05 1.21 16 3 Concept Planning B-3 Fisher Pond Road From Fairfield Street to Congress Street n n n p $60 2700 $162,000 $24,300 $186,300 10 n n n n 2 16 0.9 1 0.90 14 3 Concept Planning B-4 Fairfield Street From City/Town Line to Vermont 104 n n y s $90 900 $81,000 $12,150 $93,150 10 y y n y 2 59 1.15 1.05 1.21 71 1 1-7 Years Planning B-5 Vermont 104 North From Upper Welden to Farifield Street n n n p $60 1000 $60,000 $9,000 $69,000 10 n y y n 3 29 1.15 1.05 1.21 35 3 Concept Planning C-1 Upper Welden From City/Town Line to Vermont 104 "' n y s $90 1300 $117,000 $17,550 $134,550 10 y y n y 3 62 1.15 1.05 1.21 75 1 1-7 Years Planning C-2 Vermont 104 From Interstate Access Road to Upper Welden n n n
' p $60 2300 $138,000 $20,700 $158,700 10 n y n n 1 18 1 1.05 1.05 19 3 Concept Planning
I C-3 Fairfax Street From Main Street to Vermont 104 n y y s $90 4700 $423,000 $63,450 $486,450 10 y y y y 3 67 1 .15 1 1.15 77 1 1-7 Years Planning LJ C-4 Colins Perley Access From Meadow Brook to Collins-Perley Access n n n p $20 900 $18,000 $2,700 $20,700 10 y n n n 1 38 1.15 1.15 1.32 50 2 8-20 Year Planning
C-5 Interstate Access Road From Main Street to Vermont 104 n n y s $90 . 4000 $360,000 $54,000 $414,000 10 n n n y 2 29 0.9 1 0.90 26 3 Concept Planning C-6 Vermont 104 South From Fairfax Street to Vermont 104 n n n s $90 2000 $180,000 $27,000 $207,000 10 n y n n 0 15 0.9 1 0.90 14 3 Concept Planning D-1 Industrial Park From Main Street to Nason Street n n y sr $20 3500 $70,000 $10,500 $80,500 10 n y y n 1 23 1.15 1.05 1.21 28 3 Concept Planning D-2 Nason Street From Green Mountain Drive to Bronson Road n n n s $90 3200 $288,000 $43,200 $331,200 10 y n n n 1 38 1 1 1.00 38 3 Concept Planning 0-3 Nason Road City Link From City/Town Line to Green Mountain Drive n n y s $90 1200 $108,000 $16,200 $124,200 10 y n n y 1 51 1.15 1.05 1.21 62 2 8-20 Year Planning 0-4 Green Mountain Drive From Nason Street to Russell Street n n y sr $20 1400 $28,000 $4,200 $32,200 10 y n n y 1 51 1.15 1.15 1.32 67 2 8-20 Year Planning · 0-5 Power Line From Nason Street along ROW to Town/City line n n y p $60 1100 $66,000 $9,900 $75,900 10 y n n y 0 48 1.15 1.05 1.21 58 2 8-20 Year Planning D-6 Lake Street (Town) From City/Town· line to Bronson Road n n n s $90 2000 $180,000 $27,000 $207,000 10 n y n y 2 34 1.15 1 1.15 39 3 Concept Planning E-1 Pearl Street From City/Town Line to Brigham Road n n y s $90 2100 $189,000 $28,350 $217,350 10 n n n y 0 23 1 1 1.00 23 3 Concept Planning E-2 Lower Newton From City/Town line to limit of Development (1/4 mile) n n y s $90 2000 $180,000 $27,000 $207,000 10 n n n y 0 23 1 > 1 1.00 23 3 Concept Planning F-1 Georgia Shore From lake Road to little Country Road n n n s $90 1500 $135,000 $20,250 $155,250 10 y n n n 1 38 0.9 1.05 0.95 36 3 Concept Planning
. F-2 Lake Street (Bay) From Georgia Shore Road to limit of Developemtn (1/4 mile) n n n s $90 1000 $90,000 $13,500 $103,500 10 y y n n 5 55 1 1.05 1.05 58 2 8-20 Year Planning F-3 Bay Park Along Lake Road from Georgia Shore Road to Bay Park n n n s $90 600 $54,000 $8,100 $62,100 10 n n n n 2 16 1.15 1.05 1.21 19 3 Concept Planning
L
L..
L