Upload
beatrix-griffin
View
213
Download
1
Embed Size (px)
Citation preview
Shrinkage Forum 22 January 2014
Roy Malin
2
2014/15 Shrinkage Proposals
Initial proposals issued December 2013
Proposed Shrinkage Quantities calculated using two versions of
the leakage model:
V1.3 Original Model
V1.4 Includes LP Service Modification
As agreed at the 10 December 2012 Shrinkage Forum, National
Grid proposed and applied the revised model for 2013/14 in
anticipation of the model change being approved
Still expect model change to be approved
Need to agree the leakage model basis for 2014/15 proposals
3
2014/15 Shrinkage Proposals (GWh)
LDZ Using Leakage Model v1.3* Using Leakage Model v1.4* Difference
EA 232 217 15
EM 283 260 23
NT 282 256 26
NW 382 364 18
WM 310 307 3
NE 217.894.26*
NO 185.49
SC 230.14
13.5*SE 345.97
SO 235.43
SW 234.7 NG estimate based on data previously provided by WWU. Values to be confirmed
13.4WN 54.7
WS 124.4
* As published in initial proposals Total and estimated value 116 £2.6m
4
LP Service Modification
Consultation issued August 2013
Report on consultation sent to Ofgem for approval – October 2013
Concerns
NGN and WWU data not independently verified
Variance of impact between LDZS
NGN and WWU will be commissioning an independent review of their
leakage models and proposed baseline changes
Variance analysis
5
LP Service Modification Variance Analysis (1)
LP Service Modification Variance Analysis (2)
Published impact is the difference between v1.3 and v1.4 leakage
models using 2010/11 data
Necessary to normalise for:
Length of Metallic Main
Average System Pressure
Used an LDZ average
Actual impact will depend on the combination of the individual low pressure
networks’ ASP and metallic mains lengths
Calorific Value
6
7
LP Service Modification Variance Analysis (3)
8
AGI Venting IFI Update
Currently, National Grid procure 84GWh for AGI Venting
We were expecting a venting value of approximately 130GWh
Report Received January 2014
National Grid venting from pneumatic control equipment
17+/-5.1 GWh
Concerns over robustness of site/equipment inventory
Intention to commission DNV GL carryout a site inventory of National
Grid’s pneumatic control equipment
9
Review of SLM Review Consultations
Consultations issued by each DN November/December
2013
Two responses – British Gas and Scottish Power
Intend to issue a Joint DN Report on the consultation
Subject to agreement, future SLM Reviews and
Consultations to be a joint DN process
Agree with stakeholders and Ofgem
10
Outcome of SLM Review Consultations
Issues/areas for development
The level of detail included within the SLM Review;
The requirement to review the low pressure leakage rates, and in
particular whether this would be cost-effective;
Continued development of Theft of Gas detection and resolution;
Further clarification of the Own Use Gas estimation;
How the industry deals with CSEP Shrinkage;
The level of detail provided regarding the ‘activity factors’ driving the
shrinkage estimation, e.g. mains replacement and pressure
management.