21
www.purc.ufl.edu “Leadership in Infrastructure Policy” www.purc.ufl.edu “Leadership in Infrastructure Policy” Should Utilities Be Required to Bury Power Lines? Ted Kury Director of Energy Studies Public Utility Research Center University of Florida Presented at: 2013 EEI/NRECA Utility Siting Workshop Richmond, Virginia October 7, 2013

Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

  • Upload
    others

  • View
    1

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy” www.purc.ufl.edu “Leadership in Infrastructure Policy”

Should Utilities Be Required to Bury Power Lines?

Ted Kury Director of Energy Studies

Public Utility Research Center University of Florida

Presented at: 2013 EEI/NRECA Utility Siting Workshop Richmond, Virginia October 7, 2013

Page 2: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

2 www.purc.ufl.edu

Public Utility Research Center Research Expanding the body of knowledge in public utility regulation,

market reform, and infrastructure operations (e.g. benchmarking studies of Peru, Uganda, Brazil and Central America)

Education Teaching the principles and practices that support effective utility

policy and regulation (e.g. PURC/World Bank International Training Program on Utility Regulation and Strategy offered each January and June)

Service Engaging in outreach activities that provide ongoing professional

development and promote improved regulatory policy and infrastructure management (e.g. in-country training and university collaborations)

Page 3: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

3 www.purc.ufl.edu

The Body of Knowledge on Infrastructure Regulation

Page 4: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

4 www.purc.ufl.edu

Summary • Realities of utility regulation • Case studies in the costs and benefits of

undergrounding • Florida’s response to the storm seasons of

2004 and 2005 • Modeling the efficacy of undergrounding

Page 5: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

5 www.purc.ufl.edu

Mission Statement of Florida PSC GOALS FOR ECONOMIC REGULATION • To the extent possible, streamline regulatory requirements to provide an

open, accessible and efficient regulatory process that is fair and unbiased. • Provide a regulatory process that results in fair and reasonable rates while

offering rate base regulated utilities an opportunity to earn a fair return on their investments.

• Encourage efficiency and innovation among regulated utilities. • Encourage and facilitate responsible use of resources and technology in

the provision and consumption of utility services. GOALS FOR SERVICE REGULATION AND CONSUMER ASSISTANCE • Facilitate the provision of safe utility services at levels of quality and

reliability that comply with established industry standards and practices. • Inform utility consumers regarding utility matters. • Expedite resolution of disputes between consumers and utilities.

Page 6: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

6 www.purc.ufl.edu

Regulation and Utility Operation • Utility regulators (regardless of form) adhere to

the basic principle of safe and reliable service at just and reasonable rates

• Improving quality of service increases costs • Utilities typically have more information

regarding costs and benefits • Regulators determine what can be recovered

from ratepayers • Balance of interests is critical in meeting goals of

utility service

Page 7: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

7 www.purc.ufl.edu

State of North Carolina • Investigation following 2002 ice storm • Study focused on costs and benefits of undergrounding

existing infrastructure • Concluded that project would cost $41B (nearly six

times asset book value) and take 25 years • Electric bills would increase 125% • Recommended that each utility identify trouble areas

and develop plans to convert those facilities to underground

• Recommended that utilities continue current undergrounding practices regarding new construction

Page 8: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

8 www.purc.ufl.edu

Pepco Area in Washington, DC • Study in 2010 of the reliability implications, technical and

economic feasibility of undergrounding DC power lines • Reviewed 16 reports from 8 states from 2000 through 2009

and found that no study found quantifiable benefits for undergrounding existing facilities on a system-wide basis

• Did not model environmental impacts, business and tourist impacts of construction, resident’s inconvenience, or monetary value of aesthetics

• Concluded that 65% of outages could be avoided at a cost of $1.1B, but that an additional $4.7B would be necessary to avoid the remainder of outages

Page 9: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

9 www.purc.ufl.edu

2004 Atlantic Hurricane Season

Page 10: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

10 www.purc.ufl.edu

2005 Atlantic Hurricane Season

Page 11: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

Florida Storm Damage Year Named

Storm Damage (000$)

2004

Bonnie 100 Charley 5,533,680 Frances 5,602,120 Ivan 4,090,400 Jeanne 840,205

2005

Arlene 3,740 Cindy 300 Dennis 1,569,232 Katrina 208,600 Wilma 10,215,700

Total 28,064,077

Page 12: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

12 www.purc.ufl.edu

Aftermath of 2004 and 2005 Seasons • 10 named storms • $28 billion in damages • PSC convenes workshop for market

participants, commission staff, and policymakers on January 23, 2006

Page 13: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

13 www.purc.ufl.edu

FPSC Order PSC-06-035 1-PAA-E1 Florida would be better served by consolidating utility resources through a centrally coordinated

research and development effort with universities as well as research organizations. The purpose of such

effort would be to further the development of storm resilient electric utility infrastructure and

technologies that reduce storm restoration costs and outages to customers.

Page 14: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

14 www.purc.ufl.edu

Cooperative Initiatives • Model to assess the cost effectiveness of

relocating power lines under ground • Vegetation management workshops for

sharing best practices and discussing management issues

• Deployment of 50 high resolution wind monitoring stations throughout Florida

• Storm damage database

Page 15: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

Underground Model Flowchart

Page 16: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

Simulated Storm Frequency

Page 17: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

17 www.purc.ufl.edu

Model Output • Probability distribution of

– Restoration cost – Customer opportunity costs – Service interruptions

• Distribution generated before and after relocation of power lines

Page 18: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

Model Output Utility Annual Cost Before After Benefit

Equipment O&M $65,000.00 $29,000.00 $36,000.00Other O&M $1,653.72 $3,564.00 ($1,910.28)Lost Revenue (Storm) $15,011.14 $13,108.73 $1,902.41Lost Revenue (Non-Storm) $6,827.06 $2,730.19 $4,096.87Repairs (Storm) $2,679.56 $1,653.35 $1,026.21Repairs (Non-Storm) $14,240.00 $6,400.00 $7,840.00Others $0.00 $0.00 $0.00Total $105,411.48 $56,456.27 $48,955.21

Customer Opportunity CostStorm $296,847.74 $259,227.06 $37,620.68Non-Storm $135,005.95 $53,989.88 $81,016.08Total $431,853.70 $313,216.93 $118,636.76

Customer ReliabilityCMI (Storm) 5,956,809 5,201,883 754,926CMI (Non-Storm) 2,709,150 1,083,409 1,625,741Total 8,665,958 6,285,292 2,380,667

Page 19: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

Benefit Varies by Location Southeast (Ft. Lauderdale)

Northeast (Jacksonville)

Southwest (Naples)

Northwest (Pensacola)

Storms Affecting Project Area in 10,000 Hurricane Years

1,778 806 427 896

Average Annual Damage before Hardening

$2,700 $900 $1,000 $2,500

Average Annual Damage after Hardening

$1,700 $600 $600 $1,700

Average Storm Damage before Hardening

$16,000 $12,000 $23,000 $29,000

Average Storm Damage after Hardening

$10,000 $8,000 $14,000 $19,000

95th Percentile Storm Damage before Hardening

$67,000 $57,000 $96,000 $85,000

95th percentile Storm Damage after Hardening

$42,000 $38,000 $64,000 $60,000

Page 20: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

20 www.purc.ufl.edu

Conclusions • Regulator and utility need to work together to

determine the proper balance between price and service quality and reliability

• Modeling the effects of undergrounding power lines is highly technical

• Efficacy of underground relocation varies considerably with location

• Strategic undergrounding can provide benefits, but a blanket policy is almost certain to waste resources

Page 21: Should Utilities Be Required to Bury Power Lines? · • Study focused on costs and benefits of undergrounding existing infrastructure • Concluded that project would cost $41B (nearly

www.purc.ufl.edu “Leadership in Infrastructure Policy”

21 www.purc.ufl.edu

Thank You! • Ted Kury [email protected]