Shaybah NGL Programme - Package 4. GOSP 2 &3 Mechanical Erection and GOSP 1, 2, 3 & 4 UG Piping
Project Schedule
S/No Description Start Finish Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec Jan Feb Mar A
Date Date
1 Mobilisation
i Initial for Setting-up 2/1/2012 3/12/2012
ii UG Fabrication Shop 2/15/2012 3/15/2012
iii Mechanical Works - Fab Shop and Temp Facilities 2/28/2012 3/30/2012
2 UG Fabrication GOSP 1, 2, 3 & 4
i Header 2/15/2012 4/23/2012
ii Ring Main 2/28/2012 7/7/2012
iii Branch Lines 5/10/2012 9/7/2012
UG Installation GOSP 1
i Road Crossing Area 3/15/2012 4/15/2012ii Ring Main Line 4/15/2012 6/15/2012
iii Branch Line 6/15/2012 9/15/2012
iv Penetration into Valve Box 9/15/2012 10/15/2012
v Hydrotest 8/15/2012 11/30/2012
vi Tie-In 11/30/2012
UG Installation GOSP 2
i Road Crossing Area 4/15/2012 5/15/2012
ii Ring Main Line 5/15/2012 7/15/2012
iii Branch Line 7/15/2012 10/15/2012
iv Penetration into Valve Box 10/15/2012 11/18/2012
v Hydrotest 9/10/2012 12/31/2012
vi Tie-In 12/31/2012
UG Installation GOSP 3
i Road Crossing Area 4/15/2012 5/15/2012
ii Ring Main Line 5/15/2012 6/30/2012
iii Branch Line 7/1/2012 8/30/2012
iv Penetration into Valve Box 9/1/2012 9/30/2012
v Hydrotest 9/1/2012 10/30/2012
vi Tie-In 10/30/2012
UG Installation GOSP 4
i Road Crossing Area 3/15/2012 4/15/2012
ii Ring Main Line 4/15/2012 8/20/2012
iii Branch Line 8/20/2012 12/30/2012
iv Penetration into Valve Box 12/15/2012 1/18/2013
v Hydrotest 9/20/2012 2/10/2013
vi Tie-In 2/10/2013
3 Mechanical Works - GOSP 2 & 3
i GOSP 2A Structure
a Pipe Rack
Protocol Inspection and Taking Over 4/7/2012 4/20/2012
Survey and Center Line Marking 4/20/2012 5/7/2012
Packer Plate Setting 5/7/2012 5/21/2012
Section 1 - Erection 5/21/2012 7/12/2012
Alignment and Inspection 7/12/2012 7/18/2012
Bolt Tightening 7/18/2012 8/4/2012
Final Inspection 8/4/2012
Grouting 8/4/2012 8/21/2012
Curing 8/21/2012 9/10/2012
Section 2 - Erection 6/20/2012 8/10/2012
Alignment and Inspection 8/10/2012 8/20/2012
Bolt Tightening 8/20/2012
Final Inspection 8/20/2012 9/7/2012
Grouting 9/7/2012 9/20/2012
Curing 9/20/2012 10/7/2012
Section 3 - Erection 6/20/2012 9/10/2012
Alignment and Inspection 9/10/2012 9/20/2012
Bolt Tightening 9/20/2012 10/6/2012
Final Inspection 10/6/2012
Grouting 10/6/2012 10/20/2012
Curing 10/20/2012 11/7/2012
De-Watering / De-Salter Area and Inlet-Outlet
Protocol Inspection and Taking Over 4/7/2012 4/20/2012
Survey and Center Line Marking 4/20/2012 6/10/2012Packer Plate Setting 5/15/2012 6/24/2012
De-Watering /De-Salter - Erection 6/24/2012 8/10/2012
Alignment and Inspection 8/10/2012 8/25/2012
2012
8/3/2019 Shaybah Schedule Level 3
2/4
Bolt Tightening 8/25/2012 9/3/2012
Final Inspection 9/3/2012
Grouting 9/3/2012 9/20/2012
Curing 9/20/2012 10/7/2012
GAS Compressor / Aux Eqpt - Erection 8/20/2012 10/13/2012
Alignment and Inspection 10/13/2012 10/20/2012
Bolt Tightening 10/20/2012 11/4/2012
Final Inspection 11/4/2012
Grouting 11/4/2012 11/18/2012
Curing 11/18/2012 12/12/2012
B Piping
Pipe Rack - Section 1
Scaffolding 12/12/2012 1/20/2013
Pipe Delivery to Site 12/25/2012 2/10/2013
Pipe moving into Pipe Rack - Level 1 2/10/2013 3/15/2013
Pipe moving into Pipe Rack - Level 2 2/27/2013 4/2/2013
Pipe moving into Pipe Rack - Level 3 3/7/2013 4/10/2013
Pipe Fit-up and Weld
Big Bore CS-Header lInes 2/10/2013 3/30/2013
Small Bore CS 3/1/2013 4/30/2013
Big Bore SS 4/30/2013 5/27/2013
Small Bore SS 5/27/2013 6/12/2013
Pipe Rack - Section 2
Scaffolding 12/20/2012 2/12/2013
Pipe Delivery to Site 1/20/2013 3/12/2013
Pipe moving into Pipe Rack - Level 1 3/12/2013 4/15/2013
Pipe moving into Pipe Rack - Level 2 3/27/2013 5/2/2013
Pipe moving into Pipe Rack - Level 3 4/4/2013 5/12/2013
Pipe Fit-up and Weld
Big Bore CS-Header lInes 3/15/2013 4/27/2013
Small Bore CS 4/1/2013 5/30/2013
Big Bore SS 6/1/2013 6/20/2013
Small Bore SS 6/20/2013 7/7/2013
Pipe Rack - Section 3
Scaffolding 1/20/2013 3/12/2013
Pipe Delivery to Site 2/12/2013 3/30/2013
Pipe moving into Pipe Rack - Level 1 3/30/2013 5/1/2013
Pipe moving into Pipe Rack - Level 2 4/20/2013 6/1/2013
Pipe moving into Pipe Rack - Level 3 5/20/2013 6/30/2013
Pipe Fit-up and Weld
Big Bore CS-Header lInes 4/15/2013 5/28/2103
Small Bore CS 5/1/2103 6/30/2013
Big Bore SS 6/30/2013 8/15/2013
Small Bore SS 8/15/2013 9/15/2013
De-Watering / De-Salter Area and Inlet-Outlet
Scaffolding 11/15/2012 1/7/2013
Pipe Delivery to Site 12/1/2012 1/30/2013
Piping -Header to Equipment 1/6/2013 2/20/2013
Piping - Equipment to Equipment 2/20/2013 5/12/2013
Piping - Equipment to Piperack 5/12/2013 7/15/2013
Piping - CS Small Bore 7/15/2013 8/24/2013
Piping - SS Small Bore 8/24/2013 10/15/2013
GAS Compressor / Aux Eqpt - Erection
Scaffolding 1/15/2013 2/26/2013
Pipe Delivery to Site 2/1/2013 4/15/2013
Piping -Header to Equipment 3/6/2013 5/30/2013
Piping - Equipment to Equipment 3/18/2013 7/26/2013
Piping - Equipment to Piperack 7/26/2013 9/27/2013
Piping - CS Small Bore 9/27/2013 12/7/2013
Piping - SS Small Bore 12/7/2013 1/15/2014
C Hydrotest
Test Pack Preparation 4/24/2013 4/30/2013
Test Pressure 4/30/2013 2/27/2014
Pessivation 12/1/2013 3/30/2014
D Equipment Erection
Protocol Inspection and Taking Over 1/1/2013 3/30/2013
Survey and Center Line Marking 2/1/2013 4/25/2013
Packer Plate Setting 3/5/2013 5/12/2013
Anchor Bolt Setting 9/12/2013 5/27/2013
De-Watering /De-Salter - Erection
Alignment and Inspection 5/1/2013 6/30/2013
Bolt tightening 5/22/2013 7/27/2013
Final Inspection 6/20/2013 8/27/2013
Formwork for Grouting 8/1/2013 10/25/2013
8/3/2019 Shaybah Schedule Level 3
3/4
Grouting 8/15/2013 11/10/2013
Curing
GAS Compressor / Aux Eqpt - Erection
Alignment and Inspection 6/1/2013 7/30/2013
Bolt tightening 6/25/2013 8/27/2013
Final Inspection 7/18/2013 9/27/2013
Formwork for Grouting 9/1/2013 11/25/2013
Grouting 9/22/2013 12/13/2013
Curing 10/12/2013 12/30/2013
Flare Installation
Flare Structure
Flare Piping
Flare Burner / Tip and Gun
4 GOSP 3
A Structure
Pipe Rack
Protocol Inspection and Taking Over 4/7/2012 4/20/2012
Survey and Center Line Marking 4/20/2012 5/7/2012
Packer Plate Setting 5/7/2012 5/21/2012
Section 1 - Erection 5/21/2012 8/12/2012
Alignment and Inspection 8/12/2012 8/18/2012
Bolt Tightening 8/18/2012 9/4/2012
Final Inspection 9/4/2012
Grouting 9/4/2012 9/21/2012
Curing 9/21/2012 10/8/2012
Section 2 - Erection 6/20/2012 8/30/2012
Alignment and Inspection 8/30/2012 9/8/2012
Bolt Tightening 9/8/2012 9/21/2012
Final Inspection 9/25/2013
Grouting 9/25/2013 10/5/2012
Curing 10/5/2012 10/27/2012
Section 3 - Erection 7/20/2012 9/10/2012
Alignment and Inspection 9/10/2012 9/20/2012
Bolt Tightening 9/20/2012 10/6/2012
Final Inspection 10/6/2012
Grouting 10/6/2012 10/20/2012
Curing 10/20/2012 11/7/2012
De-Watering / De-Salter Area and Inlet-Outlet
Protocol Inspection and Taking Over 4/7/2012 4/20/2012
Survey and Center Line Marking 4/20/2012 6/10/2012
Packer Plate Setting 5/15/2012 6/24/2012
De-Watering /De-Salter - Erection 6/24/2012 9/10/2012
Alignment and Inspection 9/10/2012 9/20/2012
Bolt Tightening 9/20/2012 9/30/2012
Final Inspection 9/30/2012
Grouting 9/30/2012 10/10/2012
Curing 10/10/2012 10/30/2012
GAS Compressor / Aux Eqpt - Erection 9/10/2012 11/27/2012
Alignment and Inspection 11/27/2012 10/30/2012
Bolt Tightening 10/30/2012 12/4/2012
Final Inspection 12/4/2012
Grouting 12/4/2012 12/18/2012
Curing 12/18/2012 1/12/2013
B Piping
Pipe Rack - Section 1
Scaffolding 11/21/2012 1/20/2013
Pipe Delivery to Site 12/25/2012 3/15/2013
Pipe moving into Pipe Rack - Level 1 3/15/2013 5/15/2013
Pipe moving into Pipe Rack - Level 2 4/15/2013 5/30/2013
Pipe moving into Pipe Rack - Level 3 5/2/2103 6/29/2013
Pipe Fit-up and Weld
Big Bore CS-Header lInes 4/15/2013 7/8/2013
Small Bore CS 6/15/2013 8/15/2013
Big Bore SS 8/15/2013 9/5/2013
Small Bore SS 9/12/2013 10/4/2013
Pipe Rack - Section 2
Scaffolding 12/20/2012 2/12/2013
Pipe Delivery to Site 1/20/2013 4/30/2013
Pipe moving into Pipe Rack - Level 1 4/30/2013 5/30/2013
Pipe moving into Pipe Rack - Level 2 5/8/2013 6/15/2013
Pipe moving into Pipe Rack - Level 3 6/1/2013 7/8/2013
Pipe Fit-up and Weld
8/3/2019 Shaybah Schedule Level 3
4/4
Big Bore CS-Header lInes 6/5/2013 8/27/2013
Small Bore CS 7/15/2013 9/20/2013
Big Bore SS 9/20/2013 10/20/2013
Small Bore SS 10/20/2013 11/3/2013
Pipe Rack - Section 3
Scaffolding 4/1/2013 5/21/2013
Pipe Delivery to Site 5/21/2013 7/3/2013
Pipe moving into Pipe Rack - Level 1 7/3/2013 8/3/2013
Pipe moving into Pipe Rack - Level 2 4/20/2013 8/30/2013
Pipe moving into Pipe Rack - Level 3 8/20/2013 9/20/2013
Pipe Fit-up and Weld
Big Bore CS-Header lInes 4/15/2013 5/28/2103
Small Bore CS 5/1/2103 6/30/2013
Big Bore SS 6/30/2013 8/15/2013
Small Bore SS 8/15/2013 9/15/2013
De-Watering / De-Salter Area and Inlet-Outlet
Scaffolding 2/15/2013 4/7/2013
Pipe Delivery to Site 3/1/2013 4/30/2013
Piping -Header to Equipment 4/1/2013 5/20/2013
Piping - Equipment to Equipment 5/20/2013 8/12/2013
Piping - Equipment to Piperack 8/12/2013 10/15/2013
Piping - CS Small Bore 10/15/2013 11/24/2013
Piping - SS Small Bore 11/24/2013 1/15/2014
GAS Compressor / Aux Eqpt - Erection
Scaffolding 4/15/2013 5/26/2013
Pipe Delivery to Site 5/1/2013 7/15/2013
Piping -Header to Equipment 6/6/2013 8/30/2013
Piping - Equipment to Equipment 7/18/2013 10/26/2013
Piping - Equipment to Piperack 10/26/2013 12/27/2013
Piping - CS Small Bore 12/27/2013 2/27/2014
Piping - SS Small Bore 2/27/2014 4/15/2014
C Hydrotest
Test Pack Preparation 4/24/2013 6/30/2013
Test Pressure 6/30/2013 4/27/2014
Pessivation 1/21/2014 5/15/2014
D Equipment Erection
Protocal Inspection 1/1/2013 4/30/2013
Survey and Center Line Marking 3/1/2013 5/25/2013
Packer Plate Setting 4/5/2013 6/12/2013
Anchor Bolt Setting 5/1/2013 7/27/2013
De-Watering /De-Salter - Erection
Alignment and Inspection 6/1/2013 7/30/2013
Bolt tightening 6/22/2013 8/27/2013
Final Inspection 7/20/2013 9/27/2013
Formwork for Grouting 9/1/2013 11/25/2013
Grouting 9/15/2013 12/10/2013
Curing 10/12/2013 12/30/2013
GAS Compressor / Aux Eqpt - Erection
Alignment and Inspection 6/1/2013 7/30/2013
Bolt tightening 6/25/2013 8/27/2013
Final Inspection 7/18/2013 9/27/2013
Formwork for Grouting 9/1/2013 11/25/2013
Grouting 9/22/2013 12/13/2013
Curing 10/12/2013 12/30/2013
Flare Installation
Flare Structure 11/1/2013 1/21/2014
Flare Piping 11/2/2013 1/21/2014
Flare Tip / Gun Installation 1/21/2014 3/30/2014
Testing