Project Task PlanTelematics-Health Monitoring Application
TASK ID TASK FROM DATE TO DATE
1 Project Planning 20-Jan-09 24-Jan-09
1.1 Application Goal 20-Jan-09 21-Jan-091.2 External References 22-Jan-09 24-Jan-09
2 Requirement Definition 27-Jan-09 9-Feb-09
2.1 Functional Requirement Analysis 27-Jan-09 30-Jan-092.2 Non-functional Requirement Analysis 2-Feb-09 3-Feb-092.3 Document Preparation 4-Feb-09 9-Feb-09
3 Designing 10-Feb-09 27-Feb-09
3.1 Data Flow Diagram 10-Feb-09 11-Feb-093.2 Architecture Design 12-Feb-09 13-Feb-093.3 System Design 16-Feb-09 17-Feb-093.4 User Interface Design 18-Feb-09 23-Feb-093.5 Database Design 24-Feb-09 27-Feb-09
4 Coding and Unit testing 2-Mar-09 3-Apr-09
4.1 Developing Source Code 2-Mar-09 30-Mar-094.2 Module Testing 31-Mar-09 3-Apr-09
5 Testing 6-Apr-09 18-Apr-09
5.1 Test Plan 6-Apr-09 7-Apr-095.2 Test Development 8-Apr-09 9-Apr-095.3 Test Execution 10-Apr-09 10-Apr-095.4 Test Reporting,Result Analysis 13-Apr-09 14-Apr-095.5 Retesting the Resolved Defects 15-Apr-09 16-Apr-095.6 Regression Testing 17-Apr-09 17-Apr-095.7 Test Closure 18-Apr-09 18-Apr-09
6 Installation and Acceptance 20-Apr-09 28-Apr-09
6.1 Acceptance Plan 20-Apr-09 21-Apr-096.2 Deployment 22-Apr-09 28-Apr-09
Project Task PlanTelematics-Health Monitoring Application
NO OF HOURS
40
1624
96
321648
112
1616163232
208
17632
88
16168161688
56
1640