Upload
xianda-feng
View
46
Download
6
Embed Size (px)
Citation preview
www.elsevier.com/locate/enggeo
Engineering Geology 71 (2004) 199–211
A case history of Tunnel Boring Machine jamming in an inter-layer
shear zone at the Yellow River Diversion Project in China
Yanjun Shanga,*, Jihong Xueb, Sijing Wanga, Zhifa Yanga, Jie Yangc
aKey Laboratory of Engineering Geomechanics, Institute of Geology and Geophysics, Chinese Academy of Sciences, Beijing 100029, ChinabDeputy Site Agent of CMC for Connecting Works—Lot 5 of Shanxi Wanjiazhai Yellow River Diversion Project,
Chaicun Town, P.O. Box 18, Taiyuan 030023, ChinacDepartment of Civil Engineering, Xi’an University of Science and Technology, Xi’an 710054, China
Received 10 July 2002; accepted 6 March 2003
Abstract
This is a case study of a Tunnel Boring Machine (TBM) jamming in a section of the Connection Works No. 7 tunnel of the
Yellow River Diversion Project (YRDP) in China. Analysis of tunnel lithology, rock convergence by shearing, rock strength and
ground stress, indicates that a high rate of convergence within an inter-layer shear zone in the lower part of an anticline was a
dominant factor in the jamming. In addition, the shield encountered unfavorable tunnelling conditions in the form of wet clay,
groundwater inflow, and cavities, coincident with tensile stresses in the lower part of an adjacent syncline. Based on these
diagnoses, economical and quick measures were adopted, including additional excavation outside of the shield leaving free
space to release the TBM. After 9 days of being jammed, the TBM was totally released and resumed normal excavation. This
example highlights lessons learned from folding and inter-layer shear zone in TBM tunnelling.
D 2003 Elsevier Science B.V. All rights reserved.
Keywords: TBM; Inter-layer shear zone; Fold; Marl
1. Introduction viewed case histories in the Opalinus Clayshale.
Jointed and fractured rock masses, fault zones,
cavities and groundwater inflow are frequently en-
countered and discussed with respect to engineering
geological conditions unfavorable to tunnelling. Most
of them have been included in case studies of TBM
tunnelling. Barton (2000) has modified his well-
known empirical rock mass classification for TBM
case histories, known as QTBM. Einstein (2000) re-
0013-7952/$ - see front matter D 2003 Elsevier Science B.V. All rights re
doi:10.1016/S0013-7952(03)00134-0
* Corresponding author. Fax: +86-10-62040574.
E-mail address: [email protected] (Y. Shang).
Alber (2000) evaluated advance rates of hard rock
TBMs and their effects on project economics. Barla
(1999) considered the protection of springs during
excavation of large diameter TBM tunnels. Hamza
et al. (1999) monitored and studied ground move-
ment due to the construction of cut-and-cover struc-
tures and a slurry shield TBM in the Cairo Metro.
Swoboda and Abu-Krisha (1999) used 3D numerical
modeling for analysis of TBM tunnelling in consol-
idated clay.
However, as a feature of geological settings, folds
have not received much attention. In large-scale hydro
projects for transferring water from southern to north-
served.
Y. Shang et al. / Engineering Geology 71 (2004) 199–211200
ern China, problems associated with geological struc-
tures including faulting and folding will be a common
occurrence (Fu, 1998). It has been found difficult to
construct consistent structural geological models for
TBM tunnelling sites, given the linear nature of tunnel
site investigations.
Therefore, detailed site investigation and probe
drilling are necessary in complex geological condi-
tions in order for TBMs to perform to specification
(Pelizza et al., 2001; Barton, 2000). For example, the
approaches to fault zones should integrate field inves-
tigation, bore drilling, probe-drilling, geological radar,
and daily logging (Zhang, 1999; Su et al., 2000, 2001;
Xu et al., 2000; Liu and Cheng, 2000).
Here, it should be noted again that typical case
histories of empirical or actual investigation results
require complete re-evaluation and retrospective study
(Bappler, 2001) for the construction of different
structural geological models. Obviously, these models
are significant in integrating exceptional conditions
encountered in tunnelling. Moreover, they will pro-
mote the advanced development of TBM techniques
(Voerckel and Peters, 2001).
In folding section with high ground stress, the
inter-layer shear zones are categorized as either being
under-developed or well developed according to the
shearing displacement being dominant and apparent
or not. Only the latter category affects the stability of
rock engineering works (Qu and Xu, 1979; Xiao et al.,
2000). Laboratory studies indicate that the two types
of inter-layer shear zone are differentiated from the
shearing function which the inter-layer zone experi-
enced (Morgensten and Tchaleko, 1967). We know
little about how the fold geometry adjustment affects
location of the inter-layer shear zone, except about the
evaluations of the effects of lithological properties on
fold geometry according to mechanical analysis and
modeling (Ramsay and Huber, 1987).
With an increase in the imposed stress, a large
displacement due to shearing will occur, which must
involve the movement of the heavy rock layers
overburden, in addition to localized stress concentra-
tion, as indicated by field evidences (Qu, 1985; Xiao
et al., 2000). This kind of phenomenon is widely
known in Daqing Petroleum Field, Northeast China,
where the convergence often results in borehole
failure during drilling to a large depth because of
secondary inter-layer shearing (Prof. Jiamo Xu, per-
sonal communications, 2001). When inter-layer shear
appears in the middle of a coal seam, it is traditionally
known as a bedding shear zone, or soft-coal band (Li,
2001). To perform analyses of shear zones and joints,
a simple contact–friction interface element for 2D
models is applied (Lei et al., 1995).
The contact zone (esp. inter-layer shearing zone)
between two beds (incompetent and competent) with
distinctive mechanical features generally deformed
and failed due to secondary shearing (Ramsay,
1967). The shearing displacement resulted from sim-
ple shearing usually occurs in the soft rocks or layers
adjacent to the contact zone (Qu, 1985). This move-
ment not only induces the disintegration of intact rock
masses, but also disturbs the original distribution of
ground stresses and results in convergence (Hudson
and Harrison, 1992). According to numerous case
examples of underground engineering in soft rocks,
when a project requires a depth of more than 200 m
and especially more than 300 m, the convergence
values are often large.
Pelizza et al. (2001) have discussed the instability
of the tunnel excavation faces and walls, fault zones,
and squeezing/swelling ground as typical limiting
ground conditions affecting the performance of
Tunnel Boring Machine (TBM). They noted that
‘‘jamming of rock TBMs for long periods of time
due to convergence problems has not been heard of, at
least recently’’. This case study of TBM jamming,
which occurred on 18 June 2001, in the Connection
Works No. 7 tunnel of Yellow River Diversion Project
(YRDP) (Fig. 1) provides an example of this kind of
problem.
With a total length of 13.52 km, the No. 7 tunnel
excavation of the YRDP (Fig. 1) started in December
2000. The final breakthrough to the TBM exit shaft
was achieved by the end of September 2001. A 1994
Robbins Double Shield TBM model 155-274 with a
4.8-m external diameter was used, together with a
complete backup system. It has a unit square cutting
power of 52 kW/m2 with two-speed motors. The
modified length of the backup line was 330 m; its
production rate was 2.4 m/cycle. Although four Rob-
bins Double Shield TBMs had been previously used
in the YRDP with great success (Martinis, 1995; Liu
et al., 2000; Cao et al., 2001), severe jamming initially
occurred in No. 7 tunnel. The lessons learned from
this are discussed below.
Fig. 1. Sketch map showing the alignment of No. 7 tunnel of the Yellow River Diversion Project (A–B cross-section shown in Fig. 3).
Y.Shanget
al./Engineerin
gGeology71(2004)199–211
201
Y. Shang et al. / Engineering Geology 71 (2004) 199–211202
Within one 1130-m section of No. 7 tunnel of the
YRDP, TBM encountered cavities and groundwater
inflow from 22 May to 3 June. After that, boring
advanced at a slow rate under unfavorable geological
conditions before jamming occurred. After jamming
took place on 18 June, it took 9 days to free the
machine. Then, the TBM was again advanced at a
normal rate. Backfilling with pea-gravel and grouting
for fractured rocks and cavities, enlargement excava-
tion outside of the shield with a jackhammer, were
carried out accordingly.
In this paper, the lithology, structural geology, and
ground stress behavior in the section with a distance
of 1130 m are analyzed. The approaches adopted
include site investigation, laboratory test and logging
data analysis, and conveyor-taken muck observations.
2. Engineering geological setting
The No. 7 tunnel, which is the subject of this case
history, is located in the southern flank of an anticline
(Fig. 2), in the western mountainous area of the
Meso–Cenozoic sedimentary basin of Taiyuan on
the North China Craton (Shanxi Bureau of Geology,
1989). In the section where the TBM became jammed,
the axis of a small-scale anticline trends about 50jNE,whereas the orientation of the tunnel is 71.7jNE(Fig. 2). The included angle, therefore, is about
20j. The dip angles of the southern and northern
limbs of the anticline are 20j and 16j, respectively,in the researched section (Fig. 2). To a larger area,
there are two dominant sets of folds. The first one
was formed earlier with an orientation of SN at the
eastern part of this area. The second set was formed
later with an orientation of NE at the western part of
this area.
Rocks surrounding the tunnel mainly include thick-
ly bedded dolomitic limestone (O2s2), marl with
breccia and marl intercalated with argillaceous lime-
stone, and gypsiferous limestone (O2s1), of Upper
Majiagou Group, Middle Ordovician System.
3. Exceptional events in No. 7 tunnel
As shown in Fig. 3, TBM excavation encountered
very bad geological conditions from May 21 to June
18, 2001, along a total length of 1130 m (chainages 49
km+ 321.21 m to 48 km+ 190.48 m). First, cavities,
wet clay and then groundwater inflow appeared in
sequence. Then on 18 June, the TBM was totally
jammed in squeezing ground.
From 21 to 27 May, TBM tunnelling advanced
slowly through strongly fractured rock masses in a
zone between O2s1 and O2s
2, soft rocks (marls) and
hard rocks (dolomitic limestone) appeared alternately
with high frequencies, together with the presence of
large fissures and karst cavities of various sizes. The
location with karst cavities is just 200 m deep from a
valley bed surface (Fig. 3). Surrounding rock masses
were very unstable and fallen stalactite in various size
of karst cavities were at chainage 49 km+ 167.06 m.
From 29 to 31 May, a karst cavity was encountered at
the upper-left side of the tunnel section. It was about
0.8–2.0 m wide and 2–4 m long along the perimeter
of tunnel, and it extended about 10–15 m along the
tunnel alignment (Fig. 3). This cavity was situated
partially in marl and partially in limestone. Rock
fragments of up to 1–2 m3 fell into the excavation
chamber.
About five wagons of muck comprising of marly
clay with high moisture content were taken from the
TBM excavation face and sent out on the last train of
the night shift of 2 June (at chainage 48 km+ 895.41).
From then until 5 June (reaching to chainage 48
km+ 829.64 m), groundwater seeping occurred local-
ly. After 6 June, the TBM slowly advanced more than
600 m forward through both dry and wet plastic marl
soils, but without encountering seeping water. How-
ever, at midnight of 17–18 June, the TBM became
totally jammed in squeezing ground. The total free
space between the shield of the TBM and surrounding
rocks with a width of 5–8 cm (Fig. 4) was closed in
about 2 h. Thus, the rate of convergence was about
20–40 mm/h.
The particular geological problems encountered as
wet clay, underground water, cavities and squeezing
ground are all in the upper part of the O2s1 formation
overlay by O2s2. Geographically, The former three
accidents occurred in a depth of 200 m beneath a
valley bed, the latter one happened at a depth of 300
m from the peak crest. In geology, the former three are
in the lower part of a syncline core, while the latter
one is near the limb and in the lower part of an
anticline core (Fig. 3). Therefore, the folding played a
Fig. 2. Geological map of the tunnel site in the western mountainous area of Taiyuan (A–B cross-section shown in Fig. 3) (according to Shanxi Bureau of Geology, 1979, 1989). (1)
Holocene alluvia; (2) Upper Pleistocene pluvial-talus series; (3) Middle Pleistocene pluvia; (4) Pliocene sediment series; (5) Sandy shale, sandstone of Upper Permian system; (6)
Sandstone, sandy shale, shale intercalated with coal seam of Lower Permian; (7) Sandstone, sandy shale, shale intercalated with coal seam, Shanxi Group of Upper Carboniferous
system; (8) Sandstone, sandy shale, shale, limestone with coal seam, Taiyuan Group of Upper Carboniferous system; (9) Allite, shale, limestone and iron deposit, Benxi Group of
Middle Carboniferous system; (10) Dolomitic marl with breccia, Limestone, gypsum, Fengfeng group of Middle Ordovician system; (11) Dolomitic limestone, marl with breccia,
limestone, Upper Majiagou Group of Middle Ordovician system; (12) Marl with breccia, dolomitic limestone, argillaceous dolomite, Lower Majiagou Group of Middle Ordovician
system; (13) Argillaceous dolomite, dolomite intercalated with shale, Lower Ordovician system; (14) Reversed fault; (15) Normal fault; (16) River; (17) Tunnel and researched
section (A–B).
Y.Shanget
al./Engineerin
gGeology71(2004)199–211
203
Fig. 3. Engineering geological problems encountered when the TBM excavated through the fold (including geological section and occurrence sequence of the accidents) (note that the
vertical scale is larger than the horizontal scale of the tunnel, which gives a false appearance of steeply dipping layers in the tunnel than the overlaying strata).
Y.Shanget
al./Engineerin
gGeology71(2004)199–211
204
Fig. 4. Free space left between shield of TBM and surrounding rocks before TBM jamming with orientation of principal ground stresses.
Y. Shang et al. / Engineering Geology 71 (2004) 199–211 205
major role in engineering geological conditions in this
case history.
4. Analysis of engineering geological conditions
4.1. Ground stresses and rock strength
The rock mass is generally in a dry state since the
groundwater table in this site is 40–80 m deeper than
the bottom of the tunnel. The limestone and dolomitic
limestone (O2s2) were in the form ofmassive thick beds
with high strength as hard rocks. For dolmitic lime-
stone with a natural moisture content, the uniaxial
compression strength (UCS) was about 60 MPa, and
the deformation modulus, between 300 and 1000 MPa.
In contrast, the marl (O2s1) was soft rock with lower
strength: its UCS was about 5 MPa (much lower when
saturated), and its deformation modulus, generally
about 300MPa in a dry condition (SHIDI, 1996). From
Fig. 3, it can be seen that in this section the rock mass
quality is Grade V (similar to those with a quality index
of rock mass by Barton Q < 0.1) (Li, 1999, Table 9-2).
From the results of hydraulic fracture tests aimed to
determine ground stresses, it was known that the
horizontal component comprising the major principal
stress increased with depth (Fig. 5). At a depth of
about 300 m, where the TBM jamming occurred, the
maximum horizontal major principal stress was larger
than the vertical major principal stress. The horizontal
deviatoric stress was about 5 MPa, which was similar
to the UCS value of the marl.
4.2. Fold and inter-layer shear zone
The exceptional events occurred at a position be-
tween two boreholes (Fig. 3). So, the initial geological
conditions had been inferred from the drill logging and
site investigation. On the lower part of the adjacent
syncline, extensive joints and small-scale fissures had
developed (Fig. 3), which were favorable for rock
fracture and groundwater movement. Dolomitic lime-
stone, the major part of O2s2, acts as a permeable
aquifer, whereas marl, the dominant part of O2s1,
constitutes impermeable strata. Thus, karst cavities in
various sizes and residual wet clay mainly from disso-
lution of limestone formed along the contact zone
between the two beds as illustrated in Fig. 3. As a
result, perched groundwater actively accumulated
there. After a long-term dissolution, stalactites formed
on the roof of karst cavities and wet clay accumulated
on the floor. Karst cavities, wet and plastic clay, and
groundwater inflow developed not only because of
lithology, but also because the tensile stress in the
lower part of the syncline affected the formation of
these unfavorable geological conditions (Engineering
Geomechanics Lab., Institute of Geology, CAS, 1976).
In a plane map, the TBM jammed section is on the
axis of the anticline (Fig. 2), and the anticlinal axis
plunges to the NE. In a cross-section, this part is in the
Fig. 5. Measured and computed ground stress components at different depth of two boreholes near No. 7 tunnel.
Y. Shang et al. / Engineering Geology 71 (2004) 199–211206
lower part of the anticline where compressional shear-
ing stress is dominant (Engineering Geomechanics
Lab., Institute of Geology, CAS, 1976). Stresses
concentration occurred at interface between the dolo-
mitic limestone and marls, known as an inter-layer
shear zone. Then shear convergence, taking the marls
as its dominant, took place (Figs. 3 and 6).
The TBM excavation at a depth of 300 m in soft
surrounding rocks with high ground stress concen-
trations caused the flow of marl at a rate of 20–40
mm/h in the inter-layer shear zone. The excavation of
TBM further disturbed the ground stress distribution,
Fig. 6. Plates taken outside of the shield windows showing geological cond
see Fig. 4). (A) Inter-layer shear zone between limestone and marl with sh
with breccia; (C) tensive longitudinal fissure in the tunnel roof; (D) local
scratches in marls.
and caused the TBM jamming. Observations outside
of the TBM opened windows (a square with side
length 80� 80 cm) on the two sides of the rear shield
(for their locations, see Fig. 4) in the jammed section,
provided the following information.
� The inter-layer shear zone between greyish black
limestone and greyish yellow marl, with a thickness
of 12f13 cm, and at 30jB20j, could be found on
the northern side. The intercalated shear zone
materials had geometries indicating levorotary shear
(Fig. 6A).
itions in TBM jammed location (for standpoint and view orientation,
eared and crept rock mass, small-scale fold developed in it; (B) marl
scratches implies secondary compressive shearing (E) old grouped
Y. Shang et al. / Engineering Geology 71 (2004) 199–211208
� On the northern side of the front shield, marl with
breccia with a higher strength (UCS = 13 MPa in
saturation) (SHIDI, 1996) was dominant (Fig. 6B).
It belongs to O2s1 and comprises the soft rocks.
� From the window on the roof of the front shield, a
longitudinal fissure was seen (Fig. 6C), which
implied differential shear stress on the walls and
roof, respectively. Mostly, it is parallel with the
axis of the anticline.� Outside of the window on the southern side of the
rear shield, both newly formed scratches from the
shearing and crushing action of marls could be
seen (Fig. 6D). Back of it is also soft marls with
early-formed scratches surrounding and tightly
crushing on the shield (Fig. 6E). These soft marls
presented more pushing force on the southern side
of the shield, and acted as a major part jamming the
TBM.
It should be noted here that the gypsum content in
O2s1 varies, although such gypsum could not be found
in the field profile. Its existence, however, obviously
affects groundwater discharge by reducing porosity
and permeability (Fig. 3). Certainly as a waterproof-
ing agent, gypsum prevents or hinders groundwater
seepage. The dissolution of gypsum, on the other
hand, produces cavities in the gypsiferous limestones.
But after observation at the tunnel site, it could be
seen that most of the gypsum has not been dissolved.
Thus, its effect on unfavorable geological conditions
at the TBM jamming site was not so important as that
of the ground stresses concentration and the low
strength of the marl at the inter-layer shear zone.
In brief, from site investigation and laboratory
tests, it is known that the combination of the following
four factors resulted in TBM jamming:
� Fold: The fractured rocks and karst cavities exist in
the lower part of the syncline, while the TBM
jamming site was in the lower part of the anticline.
The stress states are very different at these two
locations of the fold.� Inter-layer shear zone: It has soft marl and over-
laying hard dolomitic limestone as its two compo-
nents. The marl, mainly presenting in surrounding
rocks as soft rock layers, could not withstand the
shearing force compared with the limestone and
marl with breccia because of its lower strength.
� ground stress: The principal horizontal stress
components were high and locally concentrated at
the interface in the lower part of the anticline. It
induced the shearing stress playing roles in the inter-
layer shear zone and resulted in the movement of the
soft marls, and finally caused the TBM jamming.
While in the lower part of the synclinal core, the
ground stress transformed to tension state and
provided space for development of karst cavities.� TBM excavation: The TBM excavation unloaded
the stress confining the layered rocks, and made the
shearing stress activated in the jamming site. Thus,
it could be said that the TBM excavation was a
triggering force for the convergence at the inter-
layer shear zone.
Therefore, the inter-layer shearing directly caused
the lateral flow toward the free space around the TBM
shield, which finally induced the TBM jamming. That
is, the high rate of convergence is mostly due to the
concentration of ground stresses locally controlled by
the inter-layer shear zone in the lower part of the
anticline.
5. Treatment measures and the results
For the purpose of freeing the TBM from squeez-
ing ground, manual excavation with a jackhammer
was used to cut and remove the converged rock mass
behind the shield from the windows of the telescopic
shield. Meanwhile, two windows were opened on the
rear shields (for their locations, see Fig. 4), in order to
provide entrances for manual excavation. The space
left by removing squeezing soft rock via a jackham-
mer was just outside the shield of the TBM with a
width of about 1.0 m (Fig. 6).
In the unfavorable geological conditions with dif-
ferent kinds of exceptional events, some other meas-
ures were also adopted. These can be summarized
under four headings.
(1) Measures which were feasible and effective in
boring through small-size karst cavities:� slow down the TBM advance rate and drive
the TBM very carefully;� observe carefully any abnormal phenomena
seen during the excavation;
Y. Shang et al. / Engineering Geology 71 (2004) 199–211 209
� use grouting to backfill the gap between
segment extrados and the surrounding rock
as quickly and as completely as possible;� keep the cutterhead against the front face in
order to avoid any collapse or over-excavation.
(2) In order to minimize the bending of the telescopic
shield on the TBM, the extended length of the
thrust cylinders was reduced from 0.6 to 0.1 m.
Because the support from the surrounding rock
masses was insufficient and the segment joints
were not able to be closed, the installed segments in
the area of the karst cavity were bolted together
with steel plates. Meanwhile, the cavity was
backfilled with pea-gravel as soon as possible.
(3) In order not to interfere with or stop TBM
excavation because of the presence of big
fissures, fractures, karst cavities, and the unstable
surrounding rock masses, grouting was carried
out in two stages.� The first stage was completed during TBM
excavation to backfill the lower part of tunnel
with grouting;� The second stage grouting was performed after
TBM completion of the whole length of No. 7
tunnel, with some special treatment to fissures
and cavities before that time.
(4) In sections where the clay was sticking and
squeezing, the buckets, the hoppers and the
conveyor belt were manually cleaned. At the
same time, some cutters were removed in order to
increase the incoming crushed rocks. Water was
sprayed on the conveyor belt so as to reduce the
sticking clay.
Following the adoption of these measures, the
TBM advanced at a rate of 42 m/day under these
unfavorable geological conditions before the jam-
ming. After jamming, it took 9 days to release the
machine. After that, the TBM continued to advance at
an average rate of 60 m/day.
6. Discussion
(1) Rock loads as predicted by conventional empirical
methods are not applicable to TBM tunnelling in
squeezing ground, especially at large depths of
folds with ground stresses concentration where
high rate of convergence is mostly likely to be
triggered.
(2) The potential for rapid squeezing ground of marl
in areas of folding indicates that TBM excavation
may not be economic in these portions of the
tunnel. Difficult ground conditions can be
handled using various alternative tunnelling
techniques. It may be possible, for example, to
mine these difficult zones by drill and blast or
hand mining methods. With good quality geo-
logical information at the head of the tunnel face,
the need for such non-TBM techniques can be
anticipated in advance and preparations can be
made accordingly.
(3) In TBM tunnelling, substantial attention should
be given to prior engineering geological and
hydrogeological investigations and analyses,
especially as to the suitability of TBM excavation
under unexpected geological conditions in order
to assist the flexible design of TBM tunnelling.
(4) When facing exceptional events, the design
schedule may require modification to fit the
new conditions.
(5) The high rate of tunnel wall convergence should
be further researched in detail, which influences
the TBM excavation more directly than the total
convergence value in soft rock masses to a large
extent.
(6) A general structural geological model is required
before tunnel boring begins, in order to system-
atically tackle complicated geological conditions
at different depth of folds without the benefits of
detailed site investigation and logging data.
7. Conclusions
The existence of an inter-layer shear zone in the
lower part of the anticlinal core, together with local
concentration of ground stresses caused a high rate of
convergence of marls in the tunnel wall, which
directly brought about TBM jamming.
The trough of the syncline under tension stresses
controls the development of fractured and jointed
rocks and cavities. Differential dissolution between
marl and limestone at this location made the formation
of karst cavities and wet clay and groundwater inflows
possible.
Y. Shang et al. / Engineering Geology 71 (2004) 199–211210
Enlargement excavation with a jackhammer out-
side of the shield is both feasible and economical to
free the blocked TBM in time.
Acknowledgements
The authors would like to thank Prof. Bingjun Fu,
the former General Secretary of Chinese ISRM, and
Prof. Jiamo Xu, for their constructive advice on
revision of this paper. Field investigation was assisted
by the staffs of the Shanxi Wanjiazhai Yellow River
Diversion Project, CMC Company, Italy. Language
(English) correction was provided by Prof. Gregory
Davis, Department of Earth Sciences, University of
Southern California. Thanks should also be extended to
the two anonymous reviewers for their helpful
suggestions and comments. The authors would like to
acknowledge the financial support by the National
Natural Science Foundation of China (Project No.:
40102024).
References
Alber, M., 2000. Advance rate of hard rock TBMs and their effects
on project economics. Tunnelling and Underground Space Tech-
nology 15 (1), 55–64.
Bappler, D.I.K., 2001. Learning from experience. Tunnels and Tun-
nelling International 33 (10), 25–27.
Barla, G., 1999. Larger diameter TBM tunnel excavation in weak
environmental conditions. News Journal, International Society
for Rock Mechanics 5 (3), 48–54.
Barton, N., 2000. TBM Tunnelling in jointed and faulted rock.
Balkema, the Netherlands, pp. 3–104, 147–149.
Cao, C.C., Meng, J.Z., Fan, A.S., Guo, Y.F., 2001. Development of
TBM at home and abroad and application in YRDP. Water Re-
sources and Hydropower Engineering 32 (4), 27–30 (in
Chinese).
Einstein, H.H., 2000. Tunnels in Opalinus Clayshale—a review of
case histories and new developments. Tunnelling and Under-
ground Space Technology 15 (1), 13–29.
Engineering Geomechanics Lab., Institute of Geology, Chinese
Academy of Sciences, 1976. Basement and approaches for re-
searches on the engineering geomechanics of rock masses. In:
Institute of Geology (Ed.), Problems of the Engineering Geo-
mechanics of Rock Masses. Science Press, Beijing, pp. 1–45
(in Chinese).
Fu, B.J., 1998. Mega Hydro Projects for transferring water from
Southern to Northern China. News Journal, International Soci-
ety for Rock Mechanics 5 (2), 25–30.
Hamza, M., Ata, A., Roussin, A., 1999. Ground movements due to
the construction of cut-and-cover structures and slurry shield
tunnel of the Cairo Metro. Tunnelling and Underground Space
Technology 14 (3), 281–289.
Hudson, J.A., Harrison, J.P., 1992. A new approach to studying
complete rock engineering problems. Quarterly Journal of En-
gineering Geology 25, 93–105.
Lei, X.Y., Swoboda, G., Zenz, G., 1995. Application of contact–
friction interface element to tunnel excavation in faulted rock.
Computers and Geotechnics 17, 349–370.
Li, S.H., 1999. A new concept of tunnel support design—applica-
tion and theory of precedent type analysis. Science Press,
Beijing, pp. 312–318 (in Chinese).
Li, H.Y., 2001. Major and minor structural features of a bedding
shear zone along a coal seam and related gas outburst, Pingding-
shan coal field, Northern China. International Journal of Coal
Geology 47, 101–113.
Liu, L.P., Cheng, B.C., 2000. Harm of defects in TBM construction
to hydraulic tunnel. Shanxi Hydrotechnics (3), 27–29 (in
Chinese).
Liu, L.P., Jin, Z.Y., Sun, W.N., 2000. Wide application of full-faced
TBM, probable problems in tunnelling. Shanxi Hydrotechnics
(2), 30–32 (in Chinese).
Martinis, A., 1995. Yellow River Diversion. World Tunnelling Oct.,
299–302.
Morgensten, N.R., Tchaleko, J.S., 1967. Microscopic structure in
kaolin subject to direct shear. Geotechnique 17 (4), 307–328.
Pelizza, S., Grasso, P., Xu, S.L., 2001. Tunnelling by TBM—an
overview of international issues relevant to China. Workshop
‘‘Tunnel Boring Machines and Related Engineering Practice’’,
Beijing, Sept. Unpublished.
Qu, Y.X., 1985. Engineering geological prediction of inter-layer
shear zones. Institute of Geology, Chinese Academy of Scien-
ces, Research on Engineering Geomechanics. Geological Pub-
lishing House, Beijing, pp. 87–97 (in Chinese).
Qu, Y.X., Xu, R.C., 1979. Study on the inter-layer shear zone at the
Gezhouba Dam site in the Yangtze River. Institute of Geology,
Chinese Academy of Sciences, Problems in Research of Rock
Engineering Geomechanics, 1–10 (in Chinese).
Ramsay, J.G., 1967. Folding and fracturing of rocks. McGraw-Hill,
London, pp. 266–288.
Ramsay, J.G., Huber, M.I., 1987. The techniques of modern struc-
tural geology, Vol. 2: Folds and Faults. Academic Press, H.B.
Jovanovich, London, pp. 106–174.
Shanxi Bureau of Geology, 1979. Regional geological investigation
report (1:200,000): Yuci Section (J-49-XXIII) (Geology Part).
Shanxi Bureau of Geology, Taiyuan (in Chinese).
Shanxi Bureau of Geology, 1989. Shanxi regional geology. Geo-
logical Publishing House, Beijing (in Chinese).
SHIDI, 1996. Engineering investigation report on the South Main
Exit to Taiyuan of the YRDP. Shanxi Hydroelectric Investiga-
tion and Design Institute of MWRC, Taiyuan, Shanxi Province
(in Chinese).
Su, S., Zan, Z.B., He, J.P., 2000. TBM construction in fault zone.
Shanxi Hydrotechnics (4), 31–32 (in Chinese).
Su, S., Du, C.Q., Cheng, X.M., 2001. Geological problems and
construction measures of the tunnels constructed by TBM in
Y. Shang et al. / Engineering Geology 71 (2004) 199–211 211
YRDP. Water Resources and Hydropower Engineering 32 (4),
15–17 (in Chinese).
Swoboda, G., Abu-Krisha, A., 1999. Three-dimensional numerical
modelling for TBM tunnelling in consolidated clay. Tunnelling
and Underground Space Technology 14 (3), 327–333.
Voerckel, M., Peters, M., 2001. Tunnelling with TBM-state of the
art and future development. Workshop ‘‘Tunnel Boring Ma-
chines and Related Engineering Practice’’, Beijing, Sept. Un-
published.
Xiao, Y.X., Lee, C.F., Wang, S.J., 2000. Spatial distribution of inter-
layer shear zones at Gaobazhou dam site, Qingjiang River, Chi-
na. Engineering Geology 55, 227–239.
Xu, J.Y., Liang, J.P., Jin, Y.J., Wang, W.B., 2000. Geological doc-
umentation during TBM tunnel construction. Hydrogeology and
Engineering Geology (6), 35–38 (in Chinese).
Zhang, J.J., 1999. The application and some problems of TBM and
its prospects. Chinese Journal of Rock Mechanics and Engineer-
ing 18 (3), 363–367 (in Chinese).