10-Day Public Notice: Water & Sewer Main Replacement and Pavement Renovation Project - Jackson, Sacramento, Washington, Davis and Drumm Streets ……………………………………………………………………………………………………………………… March 12, 2015 Workdays & Hours (Weather Permitting) Monday – Friday 8:00 a.m. to 6:00 p.m. Weekends (Only required for sewer work on Sacramento) 8:00 a.m. to 6:00 p.m. . . . . . . . . . . . . . . . . . . . . . . . . . . Contact: Steve Kech SFPUC Communications 1-415-551-4569 [email protected] After hours: Empire Engineering & Construction – 1-415-786-9019 or SFWD at 1-415-550-4911 . . . . . . . . . . . . . . . . . . . . . . . . . . For more information visit: sfwater.org/construction 如果您需要中文協助、請致電1-415-554- 3289Si necesita asistencia en español llame 1-415-554-3289 What: The San Francisco Public Utilities Commission (SFPUC) will begin the installation of a new water main pipe on Jackson St from Stockton St to Grant & Sansome to Front; Washington St from Davis to Drumm; Davis St from Sacramento to Market; and Drumm St from Jackson to California. Crews will replace the sewer main on Sacramento St from Battery to Drumm. This project will replace pipes in the street that are approaching the end of their useful life. Who: Empire Engineering & Construction is the contractor working for the SPFUC. When: The project re-started March 12, 2015 with completion scheduled for January 11, 2016. Weather and/or construction issues may impact the schedule. How: • Cut trench in pavement; remove pavement and soil • Install water main pipe; install sewer main pipe • Backfill trench & install temporary asphalt as work moves forward • Make service connections to new pipe • Final trench paving and street restoration There may be periods of inactivity within construction schedule. What to expect during construction: • There will be noise, vibration, dust, parking and traffic impacts in work zone and disruption to normal neighborhood activity. • Businesses and residents in the work zone will maintain access to their garages, although there may be temporary delays. • Parking will be prohibited in the work zone during work hours. Please see posted signs for exact details. • A city construction inspector will be on-site during work hours and may be able to assist you with construction concerns. Inspectors typically wear a yellow safety vest and hard hat. • A short interruption of water service when crews are making connections to new pipe. Advance notice will be given.

SFPUC FiDi water main, 3.12.15

Embed Size (px)

DESCRIPTION

Public notice regarding water main repair in the northern Financial District

Citation preview

  • 10-Day Public Notice: Water & Sewer Main Replacement and Pavement Renovation Project - Jackson, Sacramento, Washington, Davis and Drumm Streets

    March 12, 2015

    Workdays & Hours (Weather Permitting)

    Monday Friday 8:00 a.m. to 6:00 p.m.

    Weekends (Only required for sewer work on Sacramento) 8:00 a.m. to 6:00 p.m. . . . . . . . . . . . . . . . . . . . . . . . . . .

    Contact: Steve Kech SFPUC Communications 1-415-551-4569 [email protected]

    After hours: Empire Engineering & Construction 1-415-786-9019 or SFWD at 1-415-550-4911 . . . . . . . . . . . . . . . . . . . . . . . . . .

    For more information visit: sfwater.org/construction 1-415-554-3289 Si necesita asistencia en espaol llame 1-415-554-3289

    What: The San Francisco Public Utilities Commission (SFPUC) will begin the installation of a new water main pipe on Jackson St from Stockton St to Grant & Sansome to Front; Washington St from Davis to Drumm; Davis St from Sacramento to Market; and Drumm St from Jackson to California. Crews will replace the sewer main on Sacramento St from Battery to Drumm. This project will replace pipes in the street that are approaching the end of their useful life.

    Who: Empire Engineering & Construction is the contractor working for the SPFUC.

    When: The project re-started March 12, 2015 with completion scheduled for January 11, 2016. Weather and/or construction issues may impact the schedule.

    How: Cut trench in pavement; remove pavement and soil Install water main pipe; install sewer main pipe Backfill trench & install temporary asphalt as work moves forward Make service connections to new pipe Final trench paving and street restoration There may be periods of inactivity within construction schedule.

    What to expect during construction: There will be noise, vibration, dust, parking and traffic impacts in work zone

    and disruption to normal neighborhood activity. Businesses and residents in the work zone will maintain access to their

    garages, although there may be temporary delays. Parking will be prohibited in the work zone during work hours. Please see

    posted signs for exact details. A city construction inspector will be on-site during work hours and may be

    able to assist you with construction concerns. Inspectors typically wear a yellow safety vest and hard hat.

    A short interruption of water service when crews are making connections to new pipe. Advance notice will be given.

  • 10-Day Public Notice Jackson, Sacramento, Washington, Davis & Drumm Sts - Water & Sewer Main Replacement and Pavement Renovation Project