    SEWERAGE INFRASTRUCTUREP ROCUREMENT M ETHODS

    C ONVENTIONAL VS DESIGN & BUILD

    1st MALAYSIA NATIONAL SEWERAGE CONFERENCE 2013

    JAB. PERKHIDMATAN PEMBENTUNGAN & MyWA

    Presented by:Sr Nik Zainal Alam Hasan

    Jabatan Kerja Raya

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    2/32

    1. G OVERNMENT P POCUREMENT P PRINCIPLE

    PUBLIC ACCOUNUTABILITY

    TRANSPARENT

    BEST VALUE FOR MONEY

    OPEN FAIR COMPETITION

    FAIR DEALING

    Sewerage 2013 2

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    3/32

    Sewerage 2013 3

    2. P POCUREMENT STRATEGY

    BESTOPTION

    ConventionalApproach

    Design & BuildApproach

    D e p e n

    d s

    O n

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    4/32

    Sewerage 2013 4

    3a. C ONCEPT C ONVENTIONAL

    4

    Procurement

    Conventional

    Design & Build

    1. Planning

    2. Design3. Supervision

    Construction,Completion,

    Testing &CommissioningContractor

    Appointment(SPP 2/2011)

    Designer(In-house)

    Responsibility

    COC JKR 203/203A

    Consultant

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    5/32

    Sewerage 2013 5

    3b. C ONCEPT DESIGN & BUILD

    Procurement

    Conventional

    Design & Build

    5

    1. Planning2. Controlling3. Auditing

    Design ;Construction;Supervision ;

    Fittings;

    Completion;Testing &

    Commissioning; &Maintaining

    Contractor

    HOPT/HODT

    COC PWD DB

    Consultant

    Responsibility

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    6/32

    Form theProject Team

    ProjectBrief

    Appointed byHead of Dept.

    PrepareTender Document

    COCDrawings

    OpenTender

    SelectiveTender

    SiteBriefing(If any)

    Pricing/Estimate

    Closing &Evaluation

    Financial

    TenderClarification

    (if any)

    > 21 da

    ys Validity = 90 days

    LOA

    1

    2

    3 4 5 6 7 8 TenderBoard/Nego

    9

    6

    4a. P ROCESS - C ONVENTIONAL

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    7/32

    Form theProject Team

    ProjectBrief

    Appointed byHead of Dept.

    PreparePre-bid Document

    COCGovernmentRequirement

    OpenTender

    SelectiveTender

    Pre-bidBriefing

    Pricing/Estimate

    Closing &Evaluation

    TechnicalFinancial

    TenderClarification

    > 60 da ys Validity = 120 days

    LOI

    Pre-Q

    Contractors Proposal

    1

    2

    3 4 5 6 7 8 TenderBoard/Nego

    LOA

    9

    Pre-awardClarification

    Meeting

    1011

    7

    4b. P ROCESS - DESIGN & BUILD

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    8/32

    PlanningD.O. Approval

    Design ProcurementMaterial/

    Labour

    Construction Testing &Commissioning

    Defects

    CPC

    Conventional

    Maintenance

    Design &Build

    Equipment &furniture

    8

    4c. P ROCESS - C ONTRAST

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    9/32

    Sewerage 2013 9

    4. C HARACTERISTIC DESIGN & BUILD

    i. Contractors Liability & Obligation

    PLANNING

    1 2

    DESIGN CONSTRUCTION TESTING &COMMISSION

    DEFECTS &MAINTENANCE

    MATERIAL WORKMANSHIP

    WARRANTY

    2 YEARS

    APPROVEDBANK

    DESIGN WARRANTY = 5 YERAS

    3 45

    6

    CPC

    COMPLETION &Fit For its Purpose

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    10/32

    Kes Graevtes & Co. Contractors vs. ByanhamMeikle & Partners

    The Engineer appointed by the Contractor todesign suspended floor sab under design &build contract.

    However, a failure to the slab theContractor & Engineer gave reason that allattention & diligently care especially on design& construction to complete the works.

    Court decided that: The Law does not usually imply a warranty that

    he will achieved a desired result but only a termthat he will use reasonable skill & care. Thesurgeon does not warrant that he will cure thepatient nor does the solicitor warrant that hewill win the case but when a dentist agrees tomake a set of false teeth for a patient, there isan implied warranty that they will fit his guns

    10

    Meaning of:Completion

    Fit For its Purpose

    Responsibility of theContractor:

    1. To use his highestskill and knowledge

    to fully comply toall requirementsand the obligationsas stipulated underthe Contract.

    2. To carry out thework with due care,diligently andworkmanlikemanner

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    11/32

    11

    Meaning of:Completion

    Fit For its Purpose

    Responsibility of theContractor:

    1. To use his highestskill and knowledge

    to fully comply toall requirementsand the obligationsas stipulated underthe Contract.

    2. To carry out thework with due care,diligently andworkmanlikemanner

    Kes Graevtes & Co. Contractors vs.Byanham Meikle & Partners (cont...)

    Judgment by the Court that theContractor & Engineer are :

    1. liable in their design through impliedwarranty; and

    2. Completion of the construction worksmust be FITNESS FOR PURPOSE .

    Therefore the Contractor is liable andmust comply as per the clientrequirement.

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    12/32

    Contractors Duty & Responsibility

    Before Award

    Appoint ConsultantsDesignSubmit the Proposal as per

    pre-bid document/ needstatement

    After AwardRevise DesignsDevelop details designs asapproval from P.D.Seeks Local Authority approvalManaging the Sub-Contractorsand/or SuppliesConstruct & CompleteSupervision & QualityAssuranceProgress Claim, VO s, EOTHanding Over, Cert. of FitnessDesign GuaranteeMaintenanceAs-built & manual

    Attend to Defects 12

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    13/32

    Sewerage 2013 13

    4. C HARACTERISTIC DESIGN & BUILD

    ii. Contractors Consultants

    Contractors responsible

    1

    Consultants

    2

    PlanningStage

    Supervision &Completion

    No replacementw ithout PDs Approval

    Government

    3Direct paymentthrough D.O.A

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    14/32

    Sewerage 2013 14

    4. C HARACTERISTIC DESIGN & BUILD

    iii. Project Director (P.D.)

    Known as ProjectDirector (P.D.);Conventional = S.O.

    As agent to theGovernment

    Responsible theGovernments interestespecially Best value

    for money

    Manage & Administer the Contract:

    Contractor comply with procedure &Contract obligation SCOPE, TIME & COST

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    15/32

    Before Award

    Form the Project TeamPrepare the estimateIssuance of LOI (nego)Preparation of Conceptdesign & need statementPrepare Pre-bid documentTender ExerciseTender Evaluation &Clarification before Award

    Issuance of LOACoordination with Employer

    After AwardApproved ContractDocument & SigningProject MonitoringValuation & Payment

    Managing the ChangesManaging the VO, EOT &ClaimsIssuances of CPC/CNCAccepts Handing Over

    Verify & Approved the FinalAccountContract Closing

    15

    P.D.s Duty & Responsibility

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    16/32

    Sewerage 2013 16

    4. C HARACTERISTIC DESIGN & BUILDContractors Duty & Responsibility

    iv. Discrepancies

    GovernmentRequirement (GR)

    Contractors Proposal (CP)

    1Discrepancyi

    GR prevail

    Technical & Quality >GR

    ii

    CP prevail without extra cost2

    GR discrepancies

    P.D.s decision & issueinstructions

    3

    CP discrepancies

    InformP.D.

    P.D. decide &Contractor to comply

    without extra cost

    Issue:Contractor not

    inform & amend &

    construct!!!

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    17/32

    5.

    Advantage -Design &

    Build

    SinglePoint

    Responsibility

    SimplifiedContractual

    Arrangement

    Speed ofProcurement

    Permits PriceCertainty

    Products FitFor Purpose

    Design Benefits

    BetterBuildability/Constructability

    ImprovedWorking

    Relationship

    17

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    18/32

    5. Advantage- Design& Build

    Only Contractor is responsible for alltasks from planning to completion

    Risk is transferred from theGovernment to the Contractor

    Major management responsibilities aretransferred to the Contractor including

    managing activities and ensuringbudgeting, scheduling and meetingsystem performance specifications

    1. Single PointResponsibility

    Only one party involve

    Should problems arise, Government willonly recognise a single party i.e. theD&B Contractor

    2. SimplifiedContractual

    Arrangement

    18

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    19/32

    Reduce total project time from planningto ultimate completion due tooverlapping design and constructionactivities

    3. Speed ofProcurement

    Lump sum price for all worksContractor shoulders the risk of hisestimate of the actual scope of workand the price quoted

    4. Permits PriceCertainty

    19

    5. Advantage- Design& Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    20/32

    Employer is guaranteed of the qualityand standards required of the finishedproducts

    5. Products Fit ForPurpose

    Reaping the full benefits of Contractorsinnovative and economically optimaldesign expertise

    employer has a choice of options indesign

    6. Design Benefits

    20

    5. Advantage- Design& Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    21/32

    Since Contractor plays a majorrole in the design stage, hisexperience in buildability is put touse in realizing products that boastof innovation, efficiency inproduction and cost effectiveness

    increased creativity in areas ofdesign, methods and materials

    7. BetterBuildability /Constructability

    Simple line of communication with theContractor, i.e. confined officially to thePD / PD Rep. and the Contractor

    8. ImprovedWorkingRelationship

    21

    5. Advantage- Design& Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    22/32

    22

    6. Disadvantage-Design & Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    23/32

    X especially during post contract stage

    X any changes made by govt. shall be at

    cost and time premium

    X cost of making changes is relativelyhigh

    X no direct access to designers to issuechanges, all with Contractors consent

    1. Little flexibilityto change

    especially at tender stage

    difficult to evaluate the relative merits ofcompetitive bids

    may prolong tender evaluation

    2. Difficulty inEvaluation

    23

    6. Disadvantage-Design & Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    24/32

    o Contractors proposal requires:

    preparation of design,specification &

    financing proposals.

    o To achieve this end, the Contractorneeds to engage designers, advisors,specialists etc. in order to submit acompetitive bid.

    o These leads to high cost. It will be awaste if he is unsuccessful

    3. Uneconomic Useof Resources

    Some non-technical employer mayhave to appoint another set ofconsultants to take care of theirinterest, leading to pay anotherprofessional advisors

    4. HigherProfessionalOutlay

    24

    6. Disadvantage-Design & Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    25/32

    Some non-technical employer mayhave to appoint another set ofconsultants to take care of theirinterest, leading to pay anotherprofessional advisors

    25

    Not a technicaldepartment

    Conceptual DesignConsultant (e.g.

    Architect; Engineer(C&S; M&E), QS; etc.

    Govt.s Representative

    Design & BuiltContractor

    Sub-Contractor &Supplier

    Design Consultant(e.g. Architect;Engineer (C&S;M&E), QS; etc

    Legend:

    Day-to-day InterfaceContractual Relationship

    1

    2

    6. Disadvantage-Design & Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    26/32

    Precise & concise requirements willlead to a complete and effectiveproposal from Contractor

    may take longer time to prepare

    sketchy requirements may lead tolonger clarification time before award

    management responsibilities andOwners/Employers expectation mustbe explicitly outlined

    unclear / vague requirements maycause ambiguities which leads todisputes and claims especially afteraward

    5. EmployersRequirementsmust bepreparedcarefully

    26

    6. Disadvantage-Design & Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    27/32

    o Minimum control over how the works

    are done as works are concurrentlyongoing simultaneously with thedesign, more often than not Contractortend to practice `build first & designlater

    6. MinimumEmployersinvolvement

    Tendency of Contractor to ` design downto a cost or to do value engineeringwhich leads to changes with theintention to make as much profit as theycan, especially after award

    7. Changes withthe intention

    27

    6. Disadvantage-Design & Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    28/32

    Contractor has to face theconsequences if designers breach thedesign liability

    professional indemnity insurance doesnot cover for `fit for purpose, soContractor is deemed to compensatethe Govt.

    Employer will face more problems ifContractor ceased to exist

    8. Problems withDesign Liability

    leads to many misunderstanding andconfusion during implementation9. UnfamiliarisationTo Practitioners

    28

    6. Disadvantage-Design & Build

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    29/32

    Sewerage 2013 29

    7. Option - C ONVENTIONAL OR DB?

    Treasurys Circular Conventional

    tender

    Design & Buildtender

    SPP5/2012

    Meet Criteria?

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    30/32

    30

    No. Description Answer Approach

    1. Time for procurement &construction required shortertime period

    Design &Build

    2. Try to involve in during thedesign stage i.e. before the

    selection of the Contractor

    Conventional

    3. Involve specialist as theNominated Subcontractor Conventional

    4. Employer prefer to change theproject brief during designand/or construction stages

    Conventional

    5. Client & consultant able tosupervise project directly Conventional

    7. Option - C ONVENTIONAL OR DB?

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    31/32

    31

    No. Description Answer Approach

    6. The scope of work too complexand specialised expertise that isnot in the Department

    Design &Build

    7. Design of building / structure isdetermined by the equipmentsystem

    Design &Build

    8. Special projects to be completedin a short time due to the nationalinterest

    Design &Build

    9. Standard plan/design Conventional

    7. Option - C ONVENTIONAL OR DB?

  • 8/12/2019 Sewerage Infrastructure Procurement Methods Conventional vs Design Build

    32/32

    32