Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

Embed Size (px)

Citation preview

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    1/20

    1 11 July 2011

    RE-ASSESSMENT OF FOUNDATION SETTLEMENTS FOR THE BURJ KHALIFA,

    DUBAI

    Gianpiero Russo1

    Harry G. Poulos2

    John C. Small3

    ABSTRACT: This paper deals with the re-assessment of foundation settlements for the Burj

    Khalifa Tower in Dubai. The foundation system for the tower is a piled raft, founded on deep

    deposits of calcareous rocks.Two computer programs, GARP and NAPRA have been used for the

    settlement analyses, and the paper outlines the procedure adopted to re-assess the foundation

    settlements, based on a careful interpretation of load tests on trial piles in which the interaction

    effects of the pile test setup are allowed for. It then examines the influence of a series of factors on

    the computed settlements. In order to obtain reasonable estimates of differential settlements within

    the system, it is found desirable to incorporate the effects of the superstructure stiffness which act to

    increase the stiffness of the overall foundation system. Values of average and differential

    settlements for the piled raft calculated with GARP and NAPRA were found to be in reasonableagreement with measured data on settlements taken near the end of construction of the tower.

    Key words: case history, footings and foundations, full-scale tests, piles, rafts, settlement.

    s 730

    1University of Naples, Italy2Coffey Geotechnics, Sydney, Australia

    3Coffey Geotechnics and University of Sydney

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    2/20

    2 11 July 2011

    INTRODUCTION

    The Burj Khalifa in Dubai was officially opened in January 2010, and at a height of 828m, is

    currently the worlds tallest building. The foundation system is a piled raft, a form of foundation

    that is being used increasingly to support tall structures where the loads are expected to be

    excessively large for a raft alone and where the raft and the piles are able to transfer load to the soil.The foundation design process for this building has been described by Poulos and Bunce (2008).

    An important component of the design of a piled raft foundation is the detailed assessment of the

    settlement and differential settlement of the foundation system, and their control by optimizing the

    size, location and arrangement of the piles, and the raft thickness. Many different methods of

    analysis have been devised in order to predict the behaviour of raft and piled raft foundations

    (Selvaduri, 1979; Clancy and Randolph, 1993; Poulos, 1994; Ta and Small, 1996; Russo and

    Viggiani, 1998; Viggiani, 1998; Hemsley, 1998; Hemsley, 2000), and these range from simple hand

    based methods to complex three-dimensional numerical analyses.

    In this paper, attention is focussed on two methods that model the raft as an elastic plate and the

    piles as interacting non-linear springs. The computer codes implementing these methods aredescribed very briefly and are then applied to the Burj Khalifa, currently the worlds tallest

    building, which is founded on a piled raft. The development of the ground modulus values is

    described using a combination of field test and laboratory data and the results of pile load tests. The

    method of interpreting the pile load test data is discussed, and the importance of allowing for

    interaction between the test pile and the surrounding reaction piles in emphasised. The two

    programs are then used to compare the computed settlements with available measurements of

    foundation settlements, and with the Class A predictions made by the foundation designers and

    the peer reviewers.

    An important objective of the paper is to explore how pile load test data should be used when

    predicting the settlement performance of piled and piled raft foundation systems, and to examine

    some factors that may have an important influence on predicted foundation settlements.

    COMPUTER ANALYSES

    The settlement analyses used in this paper for the Burj Khalifa have employed two computer

    programs, GARP and NAPRA, which idealize the piled raft foundation as a plate supported by non-

    linear interacting springs. A very brief description of these programs is given below.

    Program GARP

    The computer program GARP (Geotechnical Analysis of Raft with Piles, Small and Poulos, 2007)

    uses a simplified boundary element analysis to compute the behaviour of a piled raft when

    subjected to applied vertical loading, moment loading, and free-field vertical soil movements.

    The raft is represented by a thin elastic plate and is discretized via the finite element method, using

    8- noded elements. The soil is modelled as a layered elastic continuum, and the piles are represented

    by elasticplastic or hyperbolic springs, which can interact with each other and with the raft. Pile

    pile interactions are incorporated via interaction factors (Poulos and Davis, 1980). Simplifying

    approximations are utilized for the raft-pile and pile-raft interactions. Beneath the raft, limiting

    values of contact pressure in compression and tension can be specified so that some allowance can

    be made for nonlinear raft behaviour. The output of GARP includes the settlement at all nodes of

    the raft; the transverse, longitudinal, and torsional bending moments within each element of the raft;the contact pressures below the raft; and the vertical loads on each pile. In its present form, GARP

    can consider vertical and moment loadings, but not lateral loadings or torsion.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    3/20

    3 11 July 2011

    Program NAPRAThe computer program NAPRA (Non linear Analysis of Piled Rafts, Russo 1998; Russo &

    Viggiani, 1998) computes the behaviour of a raft subjected to any combination of vertical

    distributed or concentrated loading and moment loading. The raft is modelled as a two-dimensionalelastic body using the thin plate theory, and utilizing the finite element method, adopting a four or

    nine noded rectangular element.

    The piles and the soil are modelled by means of interacting linear or non-linear springs. It is

    assumed that the interaction between the raft and the soil (the piles) is purely vertical; accordingly,

    only the axial stiffness of the springs is required.

    The soil is assumed to be a layered elastic continuum. The Boussinesq solution for a point load and

    the closed form solution for a rectangular uniformly loaded area at the surface of an elastic half-

    space are used to calculate the soil displacements produced by the contact pressure developed at the

    interface between the raft and the soil. The layered continuum is solved by means of the

    Steinbrenner approximation (Russo, 1998; De Sanctis and Russo, 2002), and as such, invokes thesimple assumption that the stress distribution within an elastic layer is identical with the Boussinesq

    distribution for a homogeneous half-space (Russo, 1998).

    The interaction factor method is used to model pile to pile interaction and a preliminary boundary

    element (BEM) analysis allows calculation of the interaction factors between two piles at various

    spacings. Interaction between axially loaded piles beneath the raft and the raft elements is

    accounted for via pile-soil interaction factors computed with a preliminary BEM procedure. The

    reciprocal theorem is used to maintain that the soil-pile interaction factor is equal to the pile-soil

    interaction factor.

    A stepwise incremental procedure is used to simulate the non-linear load-settlement relationship of

    a single pile, the total load to be applied is subdivided into a number of increments, and the diagonal

    terms of the pile-soil flexibility matrix are updated at each step. A computation of the nodal

    reactions vector is made at each step, to check for tensile forces between raft and soil and an

    iterative procedure is used to make them equal to zero. Basically, this procedure releases the

    compatibility of displacements between the raft and the pile-soil system in the node where tensile

    forces were detected, although the overall equilibrium is maintained by a re-distribution of forces.

    An iterative procedure is needed since after the first run some additional tensile forces may arise in

    different nodes. The output of the code is represented by the distribution of the nodal displacements

    of the raft and the pile-soil system, the load sharing among the piles and the raft, the bending

    moments and the shearin the raft, for each load increment.

    Abagnara et al (2011) have compared GARP and NAPRA analyses for a simple case, and have

    concluded that both programs give comparable results, but that some of the simplifying

    assumptions employed in each program give rise to differences in detail. For example, the

    difference in raft settlements may be due to the differences in the details of calculation of the soil

    layer stiffness using the Boussinesq/Steinbrenner approach. The difference in plate element types

    may also contribute to the differences. For the piled raft, the differences may arise because of

    differences in the methods used to compute the single pile stiffness values, the interaction factors

    and the pile-raft and raft-pile interactions.

    In this paper, attention will be focussed on analyses carried out with NAPRA, although acomparison will also be presented between the GARP and NAPRA analyses.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    4/20

    4 11 July 2011

    SETTLEMENT ASSESSMENT FOR THE BURJ KHALIFA TOWER, DUBAI

    Foundation layout

    The Burj Khalifa project in Dubai, United Arab Emirates (UAE), comprises a 160 storey high rise

    tower, with a podium development around the base of the tower, including a 4-6 storey garage. The

    Burj Khalifa is located on a 42000 m2site. The tower is founded on a 3.7m thick raft supported on

    194 bored piles, 1.5 m in diameter, extending 47.45m below the base of the raft; podium structures

    are founded on a 0.65 m thick raft (increased to 1m at column locations) supported on 750 bored

    piles, 0.9 m in diameter, extending 30-35 m below the base of the raft. A plan view of foundation is

    shown in Fig. 1.

    Figure 1. plan view of the Khalifa Tower foundation system

    Ground investigation and site characterization

    The investigations involved the drilling of 32 boreholes to a maximum depth of about 90 m below

    ground level and 1 borehole to a depth of 140 m under the tower footprint. Standpipe piezometers

    were installed to measure the ground water level which was found to be relatively close to the

    ground surface, typically at a level of 2.5m DMD. The ranges of measured SPT N values are

    summarised in Table 2. There was a tendency for N values to increase with depth, beyond anelevation of about -8m DMD.

    Table 2 Summary of Measured SPT Values

    Elevation m Range of SPT Values

    2.5 to -1 0-40

    -1 to -8 50-400

    -8 to -14 0-100

    -14 to -30 40-200

    -30 to -40 100-200-40 to -80 100-400

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    5/20

    5 11 July 2011

    The ground conditions at the site comprise a horizontally stratified subsurface profile which is

    complex and highly variable in terms of the strata thickness due to the nature of deposition and the

    prevalent hot arid climatic conditions. The main strata identified were as follows

    1. Very loose to medium dense silty sand (Marine Deposits).

    2. Weak to moderately weak calcarenite, generally unweathered with fractures close to mediumspaced interbedded with cemented sand. This material is generally underlain by very weak to

    weak sandstone which is generally unweathered with fractures close to medium spaced

    interbedded with cemented sand.

    3. Very weak to weak calcarenite, calcareous sandstone and sandstone; this formation is slightly tohighly weathered with fractures extremely close to closely spaced and interbedded with

    cemented sand. Bands of 1 to 5 m thickness are also present of medium dense to very dense,

    cemented, sand with sandstone bands and locally with bands of silt.

    4. Very weak to weak gypsiferous sandstone, gypsiferous calcareous sandstone occasionallygypsiferous siltstone. This material is generally unweathered to slightly weathered with

    fractures extremely close to closely spaced and interbedded with cemented sand. The formation

    is interbedded with dense to very dense, cemented, silty sand and occasionally silt withsandstone bands.

    5. Very weak to weak calcisiltite, conglomeritic calcisiltite and calcareous calcisiltite. Thismaterial is generally moderately to highly weathered, occasionally slightly and completely

    weathered with fractures extremely close to medium spaced. Calcareous siltstone was

    encountered in the majority of the deeper boreholes comprising very weak to weak occasionally

    moderately weak calcareous siltstone in bands with a thickness of 0.5 to 14.4 m generally

    slightly to moderately weathered occasionally highly to extremely weathered.

    6. Very weak to weak and occasionally moderately weak calcareous siltstone, calcareousconglomerate, conglomeritic sandstone and limestone. This material is generally slightly

    weathered and occasionally unweathered and moderately weathered to highly weathered.

    Occasionally encountered as calcisiltite interbedded with bands of siltstone and conglomerate.

    7. Very weak to moderately weak claystone interbedded with siltstone. This material is generallyslightly weathered with close to medium spaced fractures. Between -112.2 m and -128.2 m

    occasional bands of up to 500 mm thick gypsum were encountered. Below -128.2 m the stratum

    was encountered as weak to moderately weak siltstone with medium to widely spaced fractures.

    Table 3 summarizes the stratigraphy adopted for the foundation settlement analyses.

    In situ and laboratory test results

    A comprehensive series of in situ tests was carried out, including pressuremeter tests, down-holeseismic, cross-hole seismic, and cross-hole tomography to determine compression (P) and shear (S)

    wave velocities through the ground profile. The vertical profile of P-wave velocity with depth gave

    a useful indication of variations in the nature of the strata between the borelogs.

    Conventional laboratory classification tests (moisture content of soil and rock, Atterberg limits,

    particle size distribution and hydrometer) and laboratory tests for determining physical properties

    (porosity tests, intact dry density, specific gravity, particle density) and chemical properties were

    carried out. In addition, unconfined compression tests, point load index tests, and drained direct

    shear tests were carried out. A considerable amount of more advanced laboratory testing was

    undertaken, including stress path triaxial tests, resonant column testing for small-strain shear

    modulus, undrained cyclic triaxial tests, cyclic simple shear, and constant normal stiffness (CNS)direct shear tests.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    6/20

    6 11 July 2011

    Table 3.Stratigraphic model adopted for settlement assessment.

    Stratum Description Level at the top

    of the stratum

    [m DMD]

    Thickness

    [m]

    Adopted

    Level at

    top of

    layer

    [m DMD]

    UCS

    qu

    [MPa]1 Marine

    deposits

    1.15 to 2.96 1.85 to 4.3 2.5

    2

    Calcarenite/

    Calcareous

    sandstone

    -0.27 to -1.95 2.87 to 10.75 -1.2 2

    3a Calcareoussandstone/

    Sandstone

    -4.13 to -12.06 10.5 to 21.43-7.3 -

    3b -13.5 1

    4 Gypsiferous

    sandstone

    -21.54 to -

    26.69

    1.7 to 7.75 -24 2

    5a

    Calcisiltite/

    Conglomeriticcalcisiltite -27.64 to -

    31.15

    39.2 to 46.75 -28.5 1.3

    5b Calcareous

    siltstone

    -50 1.7

    6

    Calcareous/

    Conglomeritic

    Strata

    -67.19 to -

    76.04

    31 (from 140m

    deep BH only) -68.5 2.5

    7

    Claystone/

    Siltstone

    interbedded

    with gypsumlayers

    -98.19 Proved to 39.6

    m thickness

    -90 -

    Some of the relevant findings from the in situ and laboratory testing are as follows:

    i. The cemented materials were generally very weak to weak; unconfined compressivestrength (UCS) values ranged mostly between about 0.16 MPa the average values for each

    layer being the ones reported in the table 3.

    ii. Values of the Youngs Modulus from pressuremeter tests (first and second reload cycle)were found to be in good agreement with values from correlation with shear waves

    velocities. From calcarenite (0 m to -7.5 m) to sandstone (-7.5 m to -24 m ) Youngs

    Modulus is approximately constant with depth; at greater depths the average values decrease

    in the gypsiferous sandstone (-24 to -28.5 m) then they slightly increase in the calcisiltite

    (from -28.5 to -68.5 m) and finally decrease in the siltstone (from -68.5 to -91 m).

    iii. Triaxial Stress Path Testing (at strain levels of 0.01% and 0.1%) was found to give resultsfor Youngs modulus that were in good agreement with pressuremeter and geophysics

    testing results.

    iv. Resonant Column Testing was found to give more conservative values for the YoungsModulus when compared with values from pressuremeter tests, geophysics tests and triaxial

    stress tests.

    v. Constant normal stiffness (CNS) tests were carried out on three samples taken from stratum5a to assess the ultimate skin friction values and the potential for cyclic degradation at the

    pile-soil interface. These tests indicated values of peak monotonic shear stress ranging from

    360 to 558 kPa, with only a little difference between the peak monotonic and the residual

    cyclic shear stress values.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    7/20

    7 11 July 2011

    Geotechnical Model

    The key parameters for the assessment of the settlement behaviour of the Khalifa Tower piled raft

    foundation system are the values of the Youngs modulus of the strata for both raft and pile

    behaviour under static loading. In a non-linear analysis, the values of ultimate skin friction of piles,the ultimate end-bearing resistance of the piles, and the ultimate bearing capacity of the raft would

    also be required, but in this paper, only linear elastic analyses have been undertaken using NAPRA

    and GARP analyses, having explored the little influence of non linearity up to the maximum

    observed load level. Attention has thus been focussed on evaluating relevant values of Youngs

    modulus for each stratum.

    As a first step in obtaining these values, the relative stiffness of the various soil layers was assessed

    considering values of the Youngs Modulus from the following data:

    1. Pressuremeter tests (initial loading, first reload, second reload cycles);2. Geophysics tests (correlation with shear wave velocities);

    3. Resonant column tests (Initial, 0.0001%, 0.001%, 0.01% strain levels);4. Triaxial Stress Path Tests (0.01% and 0.1% strain levels);

    Values of the various Youngs Modulusvalues are plotted in Fig. 2, and although inevitable

    scatter exists among the different values, there is a reasonably consistent general pattern of

    variation with depth.

    Layer 3b (see Table 3) has arbitrarily been chosen as the reference layer, and for each type of

    test, values of the Youngs Modulusfor a layer i, Ei, have been related to the value for layer 3b,

    E3b. The values of Ei/E3bhave then been averaged, using the following data: reload cycles from

    pressuremeter testing; seismic data; resonant column data at a strain level of 0.01%, and the

    triaxial stress path tests. Fig. 3 shows the different assessed relative stiffness profiles so

    obtained, andTable 4 summarises the average values of relative Youngs modulus that were

    adopted for the analyses and the interpretation of the pile load test data. The absolute values of

    Youngs modulus for each of the different layers have been then obtained by fitting the load

    settlement curves of the single piles obtained from the load tests, and the process of fitting the

    load-settlement curves to obtain the Youngs modulus values is described below.

    Table 4. Relative Values of Youngs Modulus Used in Pile Load Test Interpretation

    Stratum Youngs Modulus, Relative to Value for Layer 3b

    2

    3a

    3b

    3c

    4

    5a

    5b

    6

    2.3

    0.6

    1.0

    1.0

    0.8

    0.7

    0.8

    0.7

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    8/20

    8 11 July 2011

    Fig. 2. Summary of Youngs modulus values.

    Fig. 3. Assessed soil relative stiffness.

    Pile Load TestsA program of pile load testing was undertaken which involved the installation of seven test piles in

    the podium area near the location of the Khalifa Tower. All the test piles and reaction piles were

    bored cast in-situ and constructed under polymer fluid. A permanent casing, 6m long, was installed

    from the top of each pile to just above the highest strain gauge level for all the trial piles tested in

    compression and tension. Five piles, designated as P1, P2, P3, P4 and P5, were tested in

    compression; two, P3 and P5, were shaft grouted. Test pile P6 was tested in tension and test pile P7

    was laterally loaded.

    Only the compression load tests on trial piles P1, P2 and P4 have been considered for the presentpaper. Table 5 summarizes the main features of these piles. Figure 4a shows the load test

    arrangements for piles P1 and P2, which consisted of the test pile and six reaction piles, while

    -90

    -80

    -70

    -60

    -50

    -40

    -30

    -20

    -10

    0

    0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

    Young's Modulus [MPa]

    Depth[m]

    Press Init AVE

    Press First AVE

    Press Second AVE

    Seismic (x 0.2)

    TRXL 0.01%

    TRXL 0.1%

    RC Initial

    RC 0.0001%

    RC 0.001%

    RC 0.01%

    adopted profile for drained modulus E'

    -90

    -80

    -70

    -60

    -50

    -40

    -30

    -20

    -10

    0

    0 1 2 3 4

    Relative Stiffness E/E3b[-]

    Depth[m]

    Press Init AVE

    Press First AVE

    Press Second AVE

    Seismic (x 0.2)

    TRXL 0.01%

    TRXL 0.1%

    RC Initial

    RC 0.0001%

    RC 0.001%

    RC 0.01%

    ALL

    NO INITIAL PRESS

    NO INITIAL PRESS & NO TRXL0.01%

    Poulos & Davids 2005

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    9/20

    9 11 July 2011

    Figure 4b shows the set-up for pile P4, which consisted of the test pile and four reaction piles. Steel

    load distribution plates were grouted to the top of the test piles and hydraulic jacks were placed

    between the steel plates and the reaction beams. Steel reaction beams were used to transfer the load

    from the hydraulic jacks to the installed reaction piles. Macalloy bars were used as reaction anchors

    to transfer the load from the beams to the reaction piles. Six cycles of loading were applied to trial

    piles P1 and P2 while nine cycles of loading were applied to trial pile P4, which was the piledesignated to be tested cyclically.

    Table 5.Summary of pile load tests.

    Trial

    Pile

    Diam.

    [m]

    Cut-off

    level

    [m DMD]

    Toe

    level

    [m DMD]

    Length

    [m]

    Load Test

    layout

    DWL*

    [t]

    DML**

    [t]

    No. of cycles

    1 1.5 -4.85 -50 45.15

    6 RP

    circle with a

    4.5 m radius

    3000 6000 6

    (50%-150% DWL)

    2 1.5 -4.85 -60 55.15

    6 RP

    circle with a4.5m radius

    3000 6000 6(50%-150% DWL)

    4 0.9 -2.90 -50 47.1

    4 RP

    square with a 9

    m side

    1000 3500 9

    (100%-150% DWL)

    *designated working load;** designated maximum test load.

    Four main types of instrumentation were used in the compression test piles:

    1. Concrete embedment vibrating wire strain gauges, to allow measurement of axial strains atsix levels along the pile shafts and hence estimation of the axial load distribution;

    2. Extensometers, to measure change in length of the piles, and installed at the same levels asthe vibrating wire strain gauges to provide back-up information on axial load distribution

    with depth;

    3. Displacement transducers at the top of piles, to measure the vertical movement at the pileheads.

    4. Load cells, to monitor the load applied to the pile via the jacks.

    Back-Analysis interpretation of load tests to obtain Youngs Modulus Values

    The computer program NAPRA was used to carry out the back-analyses of compression tests on the

    three test piles considered. Since a detailed soil profile at each trial pile location was not available,

    the same geotechnical model was adopted for all three piles.

    For comparison purposes the three load tests were back-analysed both taking and not taking into

    account interaction between test piles and reaction piles. It is now well-recognised that ignoring

    interaction between the test pile and the reaction piles can lead to an overestimation of the pile head

    stiffness (Poulos & Davis, 1980; Poulos, 2000; Kitiyodom et al., 2004).

    Both linear elastic (LE) and non-linear analyses (NL) were carried out. In all analyses, Youngs

    modulus for the piles, Ep, was assumed to be 31.8 GPa. For the linear analyses, the theoretical

    behaviour was fitted to the observed load-settlement behaviour at pile head displacements of about

    0.08% of diameter and 0.2 % of diameter.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    10/20

    10 11 July 2011

    In the non-linear analyses, in order to assess the sensitivity of the back-calculated values of soil

    stiffness to the value of ultimate capacity, Qlim, three different values were adopted in the analyses:

    1) Qlim was estimated as the asymptote to a hyperbola fitted to the whole measuredload-settlement curve (HYP);

    2) Qlimwas based on the load transfer deducedby strain gauges readings (SG);3) Qlimwas based on the load transfer deducedby extensometer readings (EX).

    Ultimate skin friction values inferred from the axial load distribution and from the extensometer

    readings were employed to assess pile shaft capacity up to depths above -30m, -38m and -30m for

    piles P1, P2 and P4 respectively. From pilesoil interface load-strain curves at various depths along

    the shafts, these values were found to be representative of the ultimate values in the upper (cased)

    part of the shaft. Below these depths, ultimate values of shaft friction were estimated from

    correlations with the unconfined compressive strength (UCS) of the rock.

    Table 6 summarises the values of Qlimobtained from these three procedures. As might be expected,

    the hyperbolic extrapolation procedure gives the largest values, and probably over-estimates thecapacity. There is some difference between the values assessed on the basis of the strain gauge and

    extensometer readings, but from the point of view of settlement prediction, such differences are not

    very significant.

    Figures 5 and 6 show typical fits (for Pile P2) of the computed non-linear load-settlement behaviour

    and the observed load-settlement behaviour. Figure 5 is for the interpretation taking account of

    interaction, while Figure 6 shows the corresponding fit with interaction between the test pile and

    reaction piles being ignored. In both cases, very reasonable fits are obtained with the measured data.

    Table 6. Assessed pile capacity with different methods.

    Pile

    Qlim

    [kN]

    Hyperbolic Extrapolation

    (HYP)

    Strain Gauge Readings

    (SG)

    Extensometer Readings

    (EX)

    TP1 108,800 93,800 73,200

    TP2 115,900 97,300 100,200

    TP4 82,600 50,500 59,900

    (a)Piles P1 and P2. (b) Pile P4

    Fig. 4 Set-up for pile load tests

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    11/20

    11 11 July 2011

    Fig. 5Predicted and measured loadsettlement Fig. 6Predicted and measured loadsettlement

    for pile P2(interaction considered). for pile P2 (interaction ignored).

    Back-calculated values of the Youngs Modulusfor stratum 3b, E3b, are reported in Table 7. In the

    linear elastic analyses the first point on the measured load-settlement curve has been considered. Inthis way back-calculated values of soil stiffness in linear analyses are affected by the loading

    procedure adopted in the load tests. In the cases of piles P2 and P4, values of back-calculated soil

    stiffness are in close agreement with values back-calculated in the non linear analysis (values of

    w/D are 0.0008 - 0.0009) while in the case of pile P1, the first point is at a higher displacement

    (0.21%), and so the back-calculated value is lower. It should be noted that had the interaction

    between the test pile and the reaction piles not been taken into account, the back-calculated values

    of pile-soil relative stiffness would have been considerably larger.

    Table 7.Youngs Modulusvalues derived from load tests.

    TESTPILE

    E3b[MPa] with interaction accounted for E3b[MPa] with interaction not accounted for

    Linear Analysis(w/D=0.0008)

    Linear Analysis(w/D=0.002)

    Non-linear Analysis Linear Analysis(w/D=0.0008)

    Non-linear Analysis

    P1- 350 650 (HYP)-850 (SG) - 900 (HYP)-1100 (SG)

    P2 700 6501000 (HYP)-1200 (SG-

    EX)1200

    1500 (HYP)-1700 (SG-

    EX)

    P4850 550 650(EX)-850(SG) 1100 850(EX)-1100(SG)

    Notes: HYP denotes values derived from hyperbolic extrapolationEX denotes values derived from extensometer readingsSG denotes values derived via strain gauges

    From Table 7, the following points can be noted:

    1. The consideration of interaction between the test pile and the reaction piles results inbackfigured modulus values which are considerably less than those for which interaction has

    been ignored. Thus, there would be a tendency to under-estimate foundation settlements if

    interaction effects are ignored.

    2. The back-calculated values from the three tests are scattered.

    In order to partially overcome the described limitation in the back-analysis of load tests, and to

    show its effects on the average settlement assessment, sensitivity analyses have been carried out

    with NAPRA by adopting two different values of soil stiffness assessed to be representative oflower and upper bound values.

    0

    5

    10

    15

    20

    0 10000 20000 30000 40000 50000 60000 70000

    Q [kN]

    w

    [mm]

    measured

    E3b=1000 Mpa (NL)HYP

    E3b=1200 Mpa (NL)SG

    E3b=1200 Mpa (NL)EX

    0

    5

    10

    15

    20

    0 10000 20000 30000 40000 50000 60000 70000

    Q [kN]

    w

    [mm

    ]

    measured

    E3b=1500 Mpa (NL)HYP

    E3b=1700 Mpa (NL)SG

    E3b=1700 Mpa (NL)EX

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    12/20

    12 11 July 2011

    In the GARP and NAPRA analyses described below, for the assessment of the average and

    differential settlements, the values of E3bshown in Table 8 were adopted, on the basis of the non-

    linear analysis of the load test results.

    Table 8. Values of Youngs Modulus (E3b) of Layer 3b Adopted for Foundation Analyses

    CaseYoungs Modulus of Layer 3b (E3b) MPa

    Best Estimate Upper Bound Value Lower Bound Value

    Reaction pile

    interaction considered900 1000 650

    Reaction pile

    interaction ignored1200 1500 900

    PROCEDURE FOR FOUNDATION SETTLEMENT RE-ASSESSMENT

    The majority of the foundation settlement re-assessment was carried out using linear elasticanalyses with the computer program NAPRA. The mesh adopted for the NAPRA analyses is shown

    in Figure 7, and in this mesh, the columns were spaced 1.7 m apart. Preliminary analyses indicated

    that using a finer mesh than this produced no change in the results. The actual shape of the raft was

    modelled by adopting a piecewise approximation.

    Only long-term conditions have been considered, and for the majority of the early analyses, an

    average load per pile of 23.21 MN has been used (this is representative of the design dead plus live

    loading) and has been applied as a point load on each of the 194 piles. This load corresponds to a

    uniformly distributed load on the tower raft of about 1250 kPa.

    The majority of analyses were undertaken using the best-estimate modulus value of 900 MPa

    derived from the proper interpretation of the load test data (see Table 8).

    A series of sensitivity analyses was undertaken to examine the following issues:

    1. The influence of non-linear pile response;2. The influence of the range of back-figured values of Youngs modulus;3. The influence of using correct and incorrect back-figured values of Youngs modulus;4. The effect of not considering the raft in the foundation settlement analysis;5. The differences between analyses using NAPRA and GARP;

    6. The influence of the assumed loading pattern;7. The effect of incorporating the stiffness of the superstructure;8. The effect of including the podium loading.

    The results of these sensitivity studies are described below.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    13/20

    13 11 July 2011

    Fig.7 Model adopted in NAPRA analyses

    RESULTS OF SENSITIVITY STUDIES

    Influence of Non-Linear Pile Response

    For the non-linear NAPRA analyses, the ultimate axial capacity of each pile has been assumed to be

    112.5MN. Table 9 compares the computed maximum (S max) and central settlements (S centre),

    and the maximum differential settlement (DS max), from the linear and non-linear analyses. There

    is very little difference between the two analyses in this case, as it could be expected being the

    global safety factor on each pile in the range 3 to 5. Thus the comparison indicates that the

    foundation response is essentially elastic under the dead plus live loadings. Accordingly, only linear

    analyses have been employed for the remainder of the sensitivity studies.

    Table 9. Computed Settlements (mm) from Linear and Non-Linear Analyses

    Linear Analysis Non-Linear Analysis

    S max S centre DS max S max S centre DS max

    52 51 27 53 53 27

    The influence of the range of back-figured values of Youngs modulus

    Table 10 summarises the computed settlements from the NAPRA analysis, using the range of

    values of Youngs modulus back-figured from the correct interpretation of the pile load tests (see

    Table 8). As would be expected, the computed settlement for the lower-bound modulus value is

    considerably greater than that for the upper-bound modulus value, although the ratio of the

    computed settlement values is less than the ratio of the modulus values. This may be explained by

    the non linearity source provided by the iterative check on the tensile forces at the raft-soil

    interface.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    14/20

    14 11 July 2011

    Table 10. Influence of Using Upper and Lower Bounds of Backfigured Modulus Values

    Modulus Value for Layer 3b S max S centre DS max

    Lower bound (E3b= 650 MPa) 81 68 50

    Upper bound (E3b=1000 MPa) 56 46 35

    The influence of using correct and incorrect back-figured values of Youngs modulus

    Table 11 shows the influence on the computed settlements of using the best-estimate modulus

    values for Layer 3b obtained from the correct interpretation (considering test pile-reaction pile

    interaction) and the incorrect interpretation (ignoring this interaction). The settlements computed

    using the incorrect modulus interpretation are about 21% less than those using the correctinterpretation, and it is therefore important to properly interpret the test pile load-settlement data to

    avoid the tendency to under-estimate the foundation settlements and differential settlements.

    Table 11. Influence of Modulus Value on Computed Settlements

    Modulus Value Used

    Computed Settlements

    mm

    S max S centre DS max

    Correct Interpretation

    E3b= 900 MPa

    52 51 27

    Incorrect Interpretation

    E3b=1200 MPa41 40 22

    Effect of Not Considering the Raft in the Analysis

    NAPRA has been used to analyse the foundation system, both as a piled raft, and as a pile group inwhich there is no raft joining the piles. The correct best-estimate modulus of Layer 3b of 900

    MPa has been used. Table 12 shows the computed settlements for both these cases. The difference

    between the computed central settlements is negligible, but there is a considerable difference

    between the computed maximum settlements and differential settlements. In this case, the

    conservatism introduced by ignoring the raft would lead to a 17% increase in the computed

    maximum settlement but a 40% increase in the maximum differential settlement. Therefore it is

    desirable to incorporate the effect of the raft when computing the settlement distribution within the

    foundation system.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    15/20

    15 11 July 2011

    Table 12. Influence of Ignoring Pile Cap on Computed Settlements

    Case Analysed Computed Settlements mm

    S max S centre DS max

    Pile Group (no raft)61 51 38

    Piled Raft52 51 27

    Analyses Using NAPRA and GARP

    Similar meshes have been used for both the NAPRA and GARP analyses and identical analysis

    assumptions have been made in both cases. Figure 8 shows the computed profile of settlement along

    Wing C from both analyses, and reveals that they are almost identical. Thus, pleasingly, for the

    same input, each program is capable of giving very similar results.

    Figure 8 Calculated settlements along wing C from NAPRA and GARP

    The Influence of the Loading Pattern

    The preceding results have all been obtained assuming that the average design load (23.21 MN) has

    been applied to each pile location. In reality, the loads will be applied via wall and column

    locations, and consequently, NAPRA has been used to examine the influence of the loading pattern

    on the computed settlement profile for two cases:

    a. Equal loads on all the piles;b. The actual design loadings are applied at the wall and column locations.

    The computed settlement profiles along Wing C in Figure 9 show a difference in the computed

    settlement patterns, with the equal load assumption giving smaller maximum settlement than the

    other case. Thus, it would appear desirable to employ the actual load pattern in design calculations.

    0

    10

    20

    30

    40

    50

    60

    0 10 20 30 40 50 60 70

    Distance along wing cross section [m]

    w

    [mm]

    GARP AV 23210 kN NAPRA AV 23210 kN

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    16/20

    16 11 July 2011

    Figure 9 Influence of Assumed Loading Pattern on Computed Settlement Profile

    The Influence of the Podium Structure on the Tower Settlement

    The podium structure was assumed to be founded at the same depth of the tower raft, but the two

    rafts were assumed to be unconnected. The length of the podium piles was taken to be 30m, and the

    columns and rows in the NAPRA mesh were spaced at 3m up to a distance of 30 diameters and 4 m

    at larger distances. An average load per pile of 23.21 MN was applied as a point load on each of the

    194 tower piles while the loads acting on the low-rise area were modelled as point loads of between

    2 and 8 MN acting on the podium piles, depending on their location.

    The maximum computed settlement was 54mm which was only 2mm larger than the valuecomputed for the tower only. The effect of the 750 piles of the podium was thus very small in this

    case, primarily because of the significant distance of many of the podium piles from the tower, and

    the relatively small loads that they carried.

    The Influence of Superstructure Stiffness

    In order to investigate the effect on the computed settlement and differential settlement, and to try

    and obtain a more accurate estimate of the pattern of settlement, the stiffening effect exerted by the

    superstructure on the raft was taken into account, in various ways, by increasing the bending

    stiffness of the raft in each wing (estimated by the structural designers to be equivalent to an

    increase of 25200 kNm2per wing). Six alternative methods of incorporating this increased bendingstiffness were adopted:

    a. Increasing the thickness of the whole raft to reflect the bending stiffness of the entire tower(Model 1).

    b. Increasing the raft thickness over the central part of the wings and on the core, as shown inFigure 10, to reflect the bending stiffness of the entire tower. This is denoted as Model 2.

    c. Increasing the raft thickness only below the shear walls (see Figure 11), to reflect thebending stiffness of the entire tower; this case is denoted as Model 3.

    d. Model 1, with only 10% of the stiffness of the tower considered (Model 1M).e. Model 2, with only 10% of the stiffness of the tower considered (Model 2M).f. Model 3, with only 10% of the stiffness of the tower considered (Model 3M).

    0

    10

    20

    30

    40

    50

    60

    70

    80

    0 10 20 30 40 50 60 70

    w

    [mm]

    d [m]

    Averagepile loadsapplied

    Loadsapplied atwall &columnlocations

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    17/20

    17 11 July 2011

    In each case, the actual pattern of loading via the columns and walls was applied, with only the dead

    load component considered.

    Figure 12 compares the various computed profiles of settlement across the tower, together with

    those in which no account is taken of superstructure stiffness. Also shown is the design profile

    developed by Poulos and Bunce (2008), which was for combined dead plus live load, and thereforenot directly comparable. Clearly, there is a considerable difference between the extreme profiles,

    those taking all the superstructure stiffness into account, and that in which no account is taken of the

    superstructure stiffness. It would appear reasonable to assume that the profiles from Models 1M,

    2M and 3M may be more reasonable approximations to reality, and this appears to be borne out by

    the comparisons with the measured settlements, as described below.

    Fig.10. Raft model 2. Fig.11. Raft Model 3.

    Figure 12 Comparison Between Various Calculated Settlement Profiles

    Comparisons Between Calculated and Measured Settlements

    Detailed settlement measurements were only available up to February 2008, before the end of

    construction and well before the commissioning and occupation of the building in January 2010.Nevertheless, anectodal evidence indicated that the additional settlements between February 2008

    and January 2010 were relatively small, of the order of 1-2mm.

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    0 20 40 60

    Settlement[mm]

    Distance along wing [m]

    NAPRA Model 1

    NAPRA Model 2

    NAPRA Model 3

    NAPRA Model 1M

    NAPRA Model 2M

    NAPRA Model 3M

    NAPRA-No Structure StiffnessAllowanceDesign Values (Poulos & Bunce(2008)

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    18/20

    18 11 July 2011

    Figure 13 shows comparisons between the latest available measured profile of settlement in

    February 2008, and the calculated settlement profiles from Models 1M, 2M and 3M. The following

    observations are made from an examination of Figures 12 and 13:

    1. Without allowance for superstructure stiffness, the calculated maximum final differentialsettlement is about 35mm which is considerably larger than the measured value of about

    14mm. The computed maximum settlement is also larger than the measured value, although

    some additional settlement would be expected after the building has been in operation for

    some years.

    2. When allowance is made for the superstructure stiffness, the computed maximum settlementis similar in magnitude to the measured value. However, for Models 1, 2 and 3, in which the

    full superstructure stiffness is incorporated (albeit approximately), the computed settlement

    pattern differs somewhat from the measured pattern, and the computed differential

    settlements are significantly smaller than those measured. It seems clear that it is not

    appropriate to allow for the bending stiffness of the entire structure when trying to modify

    the foundation stiffness.3. When the allowance for superstructure stiffness is reduced by a factor of 10 (Models 1M,

    2M and 3M), there is better agreement between the computed and measured profiles, with a

    computed maximum differential settlement ranging between 15 and 21 mm for the three

    models, similar to the measured value. In this case, the stiffness of the raft is approximately

    53 times its original value, and this latter value is much larger than the value of 10 times

    adopted by Hooper (1973) for the Hyde Park Barracks in London and by Sales et al. (2010)

    for the Skyper Building in Frankfurt. Interestingly, and almost certainly coincidentally, the

    profile for this case is rather similar to that obtained for the case when the average load is

    imposed on each pile.

    4. There remain some differences between the measured and computed settlement profiles inthe vicinity of the edge of the wing. There may well be scope to refine the method by which

    the superstructure is incorporated into the geotechnical foundation analysis.

    5. The calculated settlements from the design phase are considerably greater than thoseobtained from the analyses in this paper. The main reason for these larger settlements is that

    the settlements were for both dead and live load acting, and in addition, conservative values

    of Youngs modulus were used in these analyses, with a somewhat different distribution of

    ground stiffness with depth being adopted in those calculations. Once again, this comparison

    emphasises the importance of appropriate selection of the ground stiffness values if accurate

    foundation settlement predictions are to be made.

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    19/20

    19 11 July 2011

    Figure 13 Measured and Computed Settlement Profiles along Wing C

    CONCLUSIONS

    1. The case history of the Burj Khalifa Tower in Dubai has been re-assessed for the prediction

    of average and differential settlement of the piled raft foundation system. Thecomprehensive ground investigation and pile testing program carried out for this project has

    enabled the site to be characterized in some detail. The pile load tests is particular have been

    an important factor in enabling reasonable settlement prediction to be made.

    2. The ground stiffness or modulus is a key factor in the prediction of foundation settlements.If this is to be derived from pile load test data, then the interpretation of the load-settlement

    should take into account interaction effects with the reaction system, otherwise the ground

    stiffness is likely to be over-estimated and the foundation settlements subsequently under-

    predicted.

    3. Sensitivity studies have been carried out to explore the effects of a number of factors onpredicted settlement behaviour of the Burj Khalifa tower. In addition to the ground stiffness

    or modulus, the consideration of the effects of the raft and superstructure stiffness may be

    important factors in influencing both the maximum settlement and the maximum differential

    settlement.

    4. The assessment of the differential settlementof the Khalifa tower foundation has been byexplored by adopting three different models to account for the stiffening effect of the

    superstructure, and they have been found to give reasonably similar results. However, if the

    foundation, or parts of it, are stiffened to represent the bending stiffness of the entire

    structure, the consequent foundation response is too rigid, and the differential settlements

    tend to be under-predicted considerably. For the Burj Khalifa tower, an additional stiffnessequivalent to about 10% of the entire bending stiffness has been found to give improved, but

    0

    10

    20

    30

    40

    50

    60

    0 20 40 60

    Settlement[mm]

    Distance along wing [m]

    NAPRA Model 1M

    NAPRA Model 2M

    NAPRA Model 3M

    Measured (February 2008)

  • 8/10/2019 Settlement Assessment for the Burj Khalifa, Dubai-HGP-6 (1)

    20/20

    20 11 July 2011

    by no means perfect, results when compared with measured settlement profiles. This result

    suggests that there is a limit to the stiffness that the structure can provide to the foundation

    system, and so the full structure should not be taken into account when calculating the

    effective increase of stiffness.

    5. In this case at least, consideration of the low-rise podium structure leads to only a smallincrease in the settlement under the tower footprint.

    6. The method of analysis may be a less significant factor in the prediction of piled raftssettlements, provided the method is sound. For the same input data, the computer programs

    GARP and NAPRA produced similar settlementsof the tower.

    REFERENCES

    Abagnara, V., Poulos, H.G. and Small, J.C. (2012). Comparison of two piled raft analysis programs.

    Submitted for 12thAustralia- New Zealand Conf. Geomechanics, Melbourne.

    Clancy, P. & Randolph, M.F. 1993. An approximate analysis procedure for piled raft foundations.Int. Journ. For Num. and Anal. Meth. in Geomech, 17(12): 849-869.

    De Sanctis, L., Russo, G. and Viggiani, C. 2002. 21.Piled raft on layered soils. Proc. Ninth

    International Conference on Piling and Deep Foundations, ___ -___Nice 2002

    Hemsley, J.A. 1998.Elastic Analysis of Raft Foundations. Thomas Telford, London.

    Hemsley, J.A. (ed) 2000.Design Applications of Raft Foundations. Thomas Telford, London.

    Kitiyodom, P., Matsumoto, T. and Kanefusa, N. 2004. Influence of reaction piles on the behaviour

    of a test pile in static load testing. Canadian Geotechnical Journal, 41, 408420

    Poulos, H.G. & Davis, E.H. 1980.Pile foundation analysis and design. New York, John Wiley.

    Poulos, H.G. 1994. An approximate numerical analysis of pile-raft interaction.

    Int. Journ. For Num. and Anal. Meth. in Geomech., 18, 73-92.

    Poulos, H.G. 2000. Pile testingFrom the designers viewpoint.Statnamic Loading Test 98,

    Balkema, Rotterdam, 3-21.

    Poulos, H.G. and Bunce, G. (2008). Foundation design for the Burj Dubaithe worlds tallest

    building. Proc. 6thInt. Conf. Case Histories in Geot. Eng., Arlington, Virginia, Paper 1.47 CD

    volume.

    Russo, G. 1998. Numerical analysis of piled rafts.Int. Journ. For Num. and Anal. Meth. In

    Geomech., 22, No 6, 477-493.

    Russo, G. And Viggiani, C. 1998. 15.Factors controlling soil-structure interaction for piled rafts.

    Proc. International Conference on Soil-Structure Interaction in Urban Civil Engineering, Ed. R.

    Katzenbach & U. Arslan, Darmstadt,___ - ___.

    Sales. M.M., Small, J.C., Poulos, H.G. 2010. Compensated piled rafts in clayey soils: behaviour,measurements, and predictions. Can. Geotech. J.47, 327-345.

    Selvaduri, A.P.S. 1979.Elastic Analysis of Soil-Foundation Interaction. Elsevier Publishing Co.,

    New York.

    Small, J.C. and Poulos, H.G. (2007). Nonlinear analysis of piled raft foundations. Geotech. Special

    Publication GSP158, ASCE, CD Volume, GeoDenver 2007.

    Ta, L.D. & Small, J.C. 1996. Analysis of piled raft systems in layered soils. Int. Journ. For Num.

    and Anal. Meth. inGeomech. 20: 57-72.

    Viggiani, C. 1998. Pile groups and piled rafts behaviour.Proc. 3rdInt. Geot. Seminar on Deep

    Foundations on Bored and Auger Piles, Ghent, 77-94